ML20133C005

From kanterella
Jump to navigation Jump to search
Final Rept,Connecticut Yankee Plant Design Change External Review Group
ML20133C005
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 09/06/1985
From: Harrington W, Poindexter C, Vandenburgh D
BALTIMORE GAS & ELECTRIC CO., BOSTON EDISON CO., YANKEE ATOMIC ELECTRIC CO.
To:
Shared Package
ML20133B997 List:
References
NUDOCS 8510070193
Download: ML20133C005 (10)


Text

. .

FINAL REPORT CONNECTICUT YANKEE PLANT DESIGN CHANGE EXTERNAL REVIEW GROUP SEPTEMBER 6, 1985 A , , Chairman D. E. Vandenburgh, Sr. V President Yankee Atomic Electric C ny D , Member W. D. HarringtoG, Sr. Vice President-Nuclear Boston Edison Company

, Member C. H'. P~oindexterf Vice President -

Engineering & fonstruction Baltimore Gas & Electric 8510070193 850906 PDR ADOCK 05000213 P PDR

t

?

I

+

CONTENTS i

l Summary...................................... 1 .

Evaluation of Task Groups Screening of Plant Design Changes......... 2 I

' Evaluation of Task Groups Review of Plant Design Changes............

3 1

[ Evaluation of.the Plant Design l

Change Process............................ 4 i

g '. Conclusions.................................. 5 I

Appendix..................................... 6 t

i i

I I

I l

i i

SUMMARY

Connecticut Yankee Atomic Power Company's response to the NRC's order for modification of their license is contained in a Program Plan, dated January 1985. Included in the plan was the creation of a three-member Plant Design Change External Review Group, the charter of which was included in the plan as Enclosure III. As indicated in the charter, this group is responsible to provide a Final Report to the Vice President, Nuclcar and Environmental Engineering, at Northeast Utilities Service Company and to the NRC - Region I.

The External Review Group (ERG) was charged with the responsibility to provide an independent oversight of the Plant Design Change Task Group (Task Group). In carrying out these responsibilities, the ERG was charged with the tasks of deter-mining the adequacy of the reviews, the effectiveness and sufficiency of the Task Group's activities and recommendations, and the completeness of the corrective actions to improve the design change process.

The oversight by the ERG took several forms as follows:

1. Development of the Charter and Procedures for ERG activities.
2. Review and approval of working prccedures for the Task Group.

, 3. Four day-long meetings with the Task Group.

4. Independent review by the staffs of ERG members of various documents and reports produced by the Task Group.

Based on the ERG's oversight of the Task Group's activities during the last six months, the ERG concludes that an effective multi-disciplined approach was taken to the review of all design changes at the Connecticut Yankee plant covering the period January 1979 through December 1984. The ERG was very much impressed with the thoroughness of the review conducted. During the six-year period in question, 355 Plant Design Change Requests (PDCR) were processed for Connecticut Yankee. About 10% of these were found by the screening process to require detailed evaluation. In addition, the Impell Corporation was retained by the Task Group to review 20,294 Work Permits / Orders to determine if any involved design changes of potential safety significance.

The subsequent detailed evaluation determined that the imple-mentation of only one PDCR raised an immediate safety concern.

The prompt notification of Northeast Utilities Service Company management resulted in a thorough review and a filing with the Nuclear Regulatory Commission of a Justification for Continued Operation. A detailed listing of the other deficiencies has been provided to the Northeast Utilities Service Company Senior Vice President who will provide an action plan to the NRC which will address the resolution of the deficiencies.

It is gratifying to verify that design changes for Connecticut Yankee were handled in an appropriate manner in the past, but it is even more gratifying to determine that an improved process has evolved since the fuel pool seal failure incident. Recommendations to improve further the plant design change process have been made by the Task Group, and the addition of these process modifications should provide a standard of excellence for the industry.

EVALUATION OF TASK GROUPS SCREENING OF PLANT DESIGN CHANGES The Plant Design Change Task Group performed a preliminary evaluation of all plant design changes approved during the period January 1, 1979 through December 31, 1984, to determine if any public safety concerns had been introduced with imple-mentation of the changes. This preliminary evaluation was termed

" screening."

Plant design changes had been initiated in one of three ways:

. through the use of Plant Design Change Requests

. through the use of jumpers, lifted leads and bypasses, and

. through the use of Work Permits and Automated Work Orders without approval under a PDCR.

The screening process was carried out by the six member Task Group working under the guidance provided in their Procedure 1.02 - Pland Design Change Screening. The Task Group used three

. screening criteria to evaluate the design changes as follows:

1) Potential loss of a boundary designed to contain radioactivity,
2) Thoroughness of the change package for safety related changes, and 3) Adequacy of the safety evaluation. Documentation of reviews was provided by completion of a form which included reviewer's evaluations, independent review questions and comments, a summary of the Task Group's discussion and the basis for the final deter-mination. For those design changes requiring additional review, the appropriate concerns which arose during the screening process were documented on the screening form to ensure their resolution during detailed evaluation.

The Task Group's screening of 355 design changes resulted in 35 being selected for detailed evaluation. The ERG's exami-nation of six screening packages (4 which had been dispositioned "yes" - indicating further review was required due to potential safety significance and 2 which had been dispositioned "no" -

but which had been considered borderline as to whecher further evaluation should be conducted) resulted in the Group's con-currence-that the assessments made by the Task Group had been made correctly.

t .

l

}

j The ERG also audited the screening packages for 2 of 12 l

design changes involving jumpers, lifted leads or bypasses which were still in effect as of April 15, 1985. The ERG agreed with the Task Group's assessment.

l The Impell Corporation's review of 9101 work permits and

! 11,193 automated work orders revealed that safety evaluations j

had to be done for 65 work permits / orders which were safety significant. The ERG verified that the Task Group worked in close cooperation with the contractor throughout the task, thereby auditing their work from time to time. During the course of ERG's meeting with Impell representatives, the methodology used, the detailed findings, suggested generic guidelines and their observations and recommendations were all reviewed to the Group's satisfaction. It is obvious the task was a formidable one yet it was performed in a thorough, probing and unbiased manner. Based on ERG's discussions with the Task Group and discussions with Impell, we believe their work was complete and good judgement was exercised. Although several work permits / orders have been identified for further evaluation, none have resulted in a changa which is known to adversely affect plant safety.

Based on ERG's review of selected design change screening packages and Impell's evaluations, ERG members have concluded that the screening process has been executed in an objective, complete and thorough manner. This is based on the premise that in those design change packages audited it was found that a broad spectrum of concerns had been considered, concerns such as testing requirements, failure modes, specification adequacy, impact on other systems, adequacy of operation, adequacy of safety evalu-ations, seismic requirements, safety analysis, accident conse-quences, faulty operation of equipment and adequacy of procedures were all assessed in the Task Group's review. The ERG believes that the Task Group has conducted a very complete and thorough screening review.

EVALUATION OF TASK GROUP'S REVIEW OF PLANT DESIGN CHANGES Working under the guidance provided in their Procedure 1.03 - Plant Design Change Evaluation, the Task Group undertook detailed evaluations of the 35 PDCR's which were found to have potential safety significance. Detailed evaluations of 11 of the 35 resulted in no identified deficiencies. The remaining 24 resulted in 39 deficiencies requiring further evaluation or corrective action.

A scope review was first conducted to outline the areas requiring detailed evaluation. The review considered three primary

phases for evaluation:

. Impact on the plant design basis

. Confirmation of proper implementation

. Provisions for continued safe operation.

The detailed evaluations were then performed based on the concerns identified in the screening, scoping reviews, and on-site inspections and walkdowns. Documentation of the evaluations was provided by completion of a Summary Evaluation form which provided each member of the Task Group an opportunity to review the findings for completeness and accuracy. Questions and resolutions were also documented. All six members of the Task Group had to concur with evaluation results before approval could be reached.

The Task Group findings on the 39 deficiencies showed 3 which needed to be addressed; one of immediate concern (PDCR "380")

which was addressed in a notification to the Vice President of Nuclear and Environmental Engineering and two major areas which could require extensive evaluation and corrective action. These involved 1) an evaluation necessary to clearly identify components and system boundaries necessary to allow cold shutdown following a design basis earthquake, and 2) an evaluation of the contain-ment isolation system. Further, deficiencies were categorized into five classifications; seismic, procedural, design, testing and safety analysis. This revealed that 66% of the deficiencies were in the engineering and design areas and in particular, seismic qualification of components. Eleven of the 39 deficiencies had been identified through other programs in process at Northeast Utilitiet and therefore only 28 deficiencies could require new studies or projects.

Based on ERG's audit of 10 evaluation packages, ERG members have concluded that the evaluation process has been conducted in a most thorough and professional manner. The audits have indi-cated a genuine concern for addressing all possible issues even though remotely applicable. The methodical manner in which the Task Group has conducted their evaluations gives the ERG a high level of confidence that the task was executed in a most competent and complete manner.

EVALUATION OF THE PLANT DESIGN CHANGE PROCESS Throughout the screening and detailed evaluation phases of the design review effort, the Task Group identified potential design change process deficiencies. The ERG provided additional process improvement suggestions. At the meeting of the ERG with the Task Group on August 8, 1985, eighteen recommendations for process corrections and improvements were discussed.

The ERG, on the basis of their oversight, concludes that there has been a concern for safety and quality at Connecticut Yankee throughout the six-year period, 1979-1984. As expected, the process was not perfect and improvements have been continually made. In fact, a number of process improvements were initiated by the Northeast Utilities Service Company independent of the Task Group's work.

The ERG believes that the recommendations made by the Task Group will further improve the process.- They include a more integrated review, enhanced identification of and control over design basis information, and improved ongoing training for engineering personnel responsible for the design changes. The Northeast Utilities Service Company would do a service to the nuclear utility industry by sharing the lessons learned as a result of this review.

CONCLUSIONS Based on ERG's audit of the Task Group's conduct of investigations, data produced, findings and follow-up actions, the ERG concludes that the task has been conducted and completed

- in a very thorough and effective manner. These conclusions are supported by the detailed information presented in the Connecticut '

Yankee Plant Design Change Task Group's Final Report, a copy of which is enclosed, and by the record of ERG's communication and involvement with the Task Group as found in the Appendix to this report.

We further believe that the Northeast Utilities Service Company has made available all the necessary resources to' allow completion of this task in a most competent and professional manner, as evidenced by the fact that approximately 11,700 man-hours of highly experienced engineering professionals were assigned and carried the project to completion.

t t

1 i

t . .

APPENDIX CHRONOLOGY OF THE ERG /CYPDCTG INTERFACE Date - Form Subject Feb. 1 Letter from W.G. Counsil Program background to D.E. Vandenburgh information WGC-85-CY-ll l Feb. 13 Telecon between R.J. Schmidt Method for procedure

& D.E. Vandenburgh development Feb. 15 Letter from C.F. Sears to Draft ERG Procedures D.E. Vandenburgh, CFS85-050 Feb. 20 Telecon between R.J. Schmidt Procedures, Audit / Review and D.E. Vandenburgh Feb. 21 Letter from R.J. Schmidt to CYAPCO letter to NRC of D.E. Vandenburgh, CYPDCTG-012 Feb. 6, 1985.

. Feb. 21 Letter from R.J. Schmidt to Transmit CYPDCTG Procedures D.E. Vandenburgh, CYPDCTG-Oll 1.01, 1.02, 1.03, 1.04 i

Comment on CYPDCTG March 1 Telecon between R.J. Schmidt

, . and D.E. Vandenburgh procedures i March 1 Letter from D.E. Vandenburgh Comments on CYPDCTG l ,

to R.J. Schmidt procedures March 5 Telecon between R.J. Schmidt Comments on CYPDCTG and D.E. Vandenburgh procedures March 6 Memo from R.J. Schmidt to February Monthly Report C.F. Sears (CYPDCTG-017),

with copies to ERG

March 7 Letter from R.J. Schmidt to Procedure 1.01, 1.02 CYPDCTG Procedures Manual l Copy Holders, CYPDCTG-021 L March 7 Letter from R.J. Schmidt to Procedures 1.03, 1.04, 1.05

[ D.E. Vandenburgh, CYPDCTG-022 March 12 Meeting ERG and CYPDCTG Status / Audit

March 21 Letter from C.H. Poindexter to Comments on Procedures j D.E. Vandenburgh March 27 Letter from D.E. Vandenburgh Approval of 1.01, 1.02, to R.J. Schmidt 1.03, 1.04, 1.05

Date Form Subject April 4 Memo from R.J. Schmidt to March Monthly Report C.F. Sears (CYPDCTG-037) with copies to ERG April 8 Letter from R.J. Schmidt to Procedures 1.01, 1.03, 1.04, CYPDCTG Procedures Manual 1.05, 2.01, 2.02 Copy Holders, CYPDCTG-046 April 11 Letter from D.E. Vandenburgh ERG first status report to T.E. Murley .

~

April 25 Meeting - ERG and CYPDCTG Status / Audit May 7 Memo from R.J. Schmidt to April Monthly Report C.F. Sears (CYPDCTG-064),

with copies to ERG May 8 Letter from R.J. Schmidt Screoning Milestone Report to C.F. Sears, CYPDCTG-069 May 20 Letter from W.D. Harrington Review Design Change to D.E. Vandenburgh May 21 Letter from R.J. Schmidt Procedure 1.04, Rev. 1 to D.E. Vandenburgh, CYPDCTG-074 May 31 Meeting - CYPDCTG and ERG Status / Audit

~

May 31 Letter from D.E. Vandenburgh Approval of Procedure to R.J. Schmidt 1.04, Rev. 1 June 7 Memo from R.J. Schmidt to May Monthly Report C.F. Sears (CYPDCTG-078),

with copies to ERG June 13 Leuter from R.J. Schmidt Procedures 1.04, Rev. 1, to CYPDCTG Procedure 2.01, 2.03 Manual Copy Holders, CYPDCTG-083 June 21 Letter from D.E. Vandenburgh ERG 2nd status report to C.F. Sears July 2 Letter from R.J. Schmidt Evaluation of ERG to D.E. Vandenburgh, comments on screening CYPDCTG-091 and process improvement July 3 Memo from R.J. Schmidt to June Monthly Report C.F. Sears (CYPDCTG-090),

with copies to ERG.

)

l l

f .. .

l ,

Date Form Subject July 24 Letter from R.J. Schmidt Milestone reports: Plant to-D.E. Vandenburgh Design Change Evaluations, Review of the Design Change l Process

l. July 26 Letter from R.J. Schmidt Draft Final Report

' to D.E. Vandenburgh Aug. 5 Memo from R.J. Schmidt to July Monthly Report to C.F. Sears (CYPDCTG-106),

with copies to ERG l

f *

+

+

9

+

I i

l _-

8-f-

t - --. _ - - - _ _ _ _ _ _ _ _ _ _ ___ _ _ -- __________