|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20205B9601999-03-24024 March 1999 Seventh Partial Response to FOIA Request for Documents. Records in App N Already Available in Pdr.App O Records Being Released in Entirety & App P Records Being Withheld in Part (Ref FOIA Exemptions 7C,2 & 5) ML20205A2771999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Vogtle PPR on 990208.PPR for Plant Involved Participation of All Technical Divs in Evaluating Insp Results & Safety Performance Info for Period of Dec 1997 - Jan 1999 ML20207L8281999-03-0808 March 1999 Forwards Partially Withheld Insp Repts 50-424/99-01 & 50-425/99-01 & Notice of Violation ML20207J0431999-03-0303 March 1999 Forwards Insp Repts 50-424/98-10 & 50-425/98-10 on 981227- 990213.No Violations Noted.Licensee Conduct of Activities at Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices ML20203G5691999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Ltr Indicating No Candidates or Ltr Listing Names of Candidates for Exam ML20202H9691999-01-29029 January 1999 Forwards Safety Evaluation Authorizing Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant, Unit 1 ML20199J7931999-01-20020 January 1999 Forwards Insp Repts 50-424/98-09 & 50-425/98-09 on 981115-1226 at Vogtle Units 1 & 2.No Violations Were Identified.Conduct of Activities at Vogtle Was Generally Characterized by safety-conscious Operations ML20199K1381999-01-12012 January 1999 Informs That on 990117,Region II Implemented Staff Reorganization as Part of agency-wide Streamlining Effort, Due to Staffing Reductions in FY99 Budget.Organization Charts Encl ML20198S1601998-12-31031 December 1998 Forwards SER of Licensee Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Vogtle Electric Generating Plant Submitted on 970529. INEEL/EXT-98-01007 Rept Also Encl ML20199E4741998-12-23023 December 1998 Provides Summary of 981105 Training Managers Conference Held in Atlanta,Georgia.Conference Agenda,List of Conference Attendees,Presentation Slides & Preliminary Schedule for FY99 & FY00 Encl ML20199J9781998-12-22022 December 1998 Responds to 981209 Meeting Re Installation of Seismic Clips on Cutler Hammer Electrical Circuit Breakers.Forwards List of Attendees & Handouts ML20198F6711998-12-11011 December 1998 Forwards Insp Repts 50-424/98-08 & 425/98-08 on 980927-1114. No Violations Identified ML20198N9431998-12-10010 December 1998 Ack Receipt of Response, to NOV Issued on 980112 Re Surveillance Testing of Reactor Trip Sys P-4 Interlock Feature at Licensee Facility.Nrc Agrees That Surveillance Testing Not Required ML20196J2181998-12-0101 December 1998 Advises of Planned Insp Effort Resulting from 981102 Insp Planning Meeting.Historical Listing of Plant Issues Called Plant Issues Matrix & Insp Plan,Including Specific Insps Such as in Security & Radiological Protection Areas Encl ML20196J2581998-12-0101 December 1998 Confirms Arrangements Made Between J Bailey & B Holbrook, Re Info Meeting Scheduled for 990210 to Discuss Licensee Performance,New Initiatives & Other Regulatory Issues Pertaining to Listed Facilities ML20196B1231998-11-23023 November 1998 Confirms Telephone Conversation Between J Bailey & P Skinner on 981120 Re Info Meeting Which Has Been Scheduled for 981209 in Atlanta,Ga,To Discuss Issues Re Seismic Retainer Clips ML20196D4981998-11-13013 November 1998 Informs That on 981007,NRC Administered Gfes of Written Operator Licensing Examination.Copy of Answer Key & Master Bw/Pwr GFE Encl,Even Though Facility Did Not Participate in Exam.Without Encl ML20195B3391998-11-0909 November 1998 Forwards Partially Withheld Insp Repts 50-424/98-12 & 50-425/98-12 on 981005-09 (Ref 10CFR73.21).No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations & Sound Engineering ML20155H2501998-10-21021 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-424/98-05 & 50-425/98-05 Issued on 980723.Concluded for Reasons Stated That Example 2 Violation Occurred as Stated in NOV ML20155A7491998-10-15015 October 1998 Forwards Insp Repts 50-424/98-07 & 50-425/98-07 on 980816-0926 & Nov.Insp Generally Characterized by Safety Conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20155B7771998-10-0909 October 1998 Extends Invitation to Attend Training Manager Conference on 981105 in Atlanta,Georgia.Conference Designed to Inform Regional Training & Operations Mgt of Issues & Policies That Effect Licensing of Reactor Plant Operators ML20155B4621998-09-25025 September 1998 Discusses OI Investigation Which Completed on 980728. Investigation Reviewed Circumstances Surrounding Apparent Disabling of Fire Computer Trouble Alarm by Unit Shift Supervisor.Concludes Enforcement Discretion Warranted ML20153B0401998-09-17017 September 1998 Responds to 980904 e-mail Message Making Certain Observations Re Apparent Increase in Reactor Trips at Plant, Units 1 & 2.NRC Concluded That Licensee post-trip Reviews Adequately Conducted & That No Adverse Trends,Apparent ML20153B9311998-09-16016 September 1998 Forwards RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations, Responses for Plant,Units 1 & 2 ML20153F7081998-09-11011 September 1998 Provides Summary of 980909 Meeting Held to Discuss TS & Other Regulatory Issues Re Vogtle Electric Generating Plant. List of Meeting Attendees & Copy of Presentation Slides Encl ML20154C4871998-09-10010 September 1998 Forwards Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815 & Nov.One Violation Involved Failure to Implement Adequate C/As for Repeated Failures to Enter Applicable TS Limiting Conditions for Operation ML20151U7901998-09-0909 September 1998 Discusses 980615 Request for Exemption from Requirement of 10CFR73.55(e)(1) & (f)(1) to Provide Continuous Staffing of Plant CAS During Contingency Events.Request Denied ML20151S7291998-09-0202 September 1998 Discusses Evaluation of Util Response to GL 97-05 for Plant, Units 1 & 2.NRC Did Not Identify Any Concerns W/Sg Tube Insp Techniques Employed at Plant ML20239A4251998-08-27027 August 1998 Informs of Change Being Implemented by Region II Re Administrative Processing of Licensee Responses to Nov.Nov Responses Will Be Formally Ack as Part of Periodically Issued Integrated Insp Repts 1999-09-01
[Table view] |
See also: IR 05000424/1990019
Text
. . - -
.- ,
-
, !
'
)
4
'
.
d
Docket No. 50-424
License No. NPF-68 information in this record as deleted
EA 93-304, EA 94-036, in accordance with theJJeedom " 01 Infom
,
EA 94-037, and EA 94-052 Act, exem -
Georgia Power Company
ATTN: Mr. H. Allen Franklin
,
- President and Chief Executive Officer
Post Office Box 1295
, Birmingham, Alabama 35201
-
SUBJECT: NOTICE OF VIOLATION
-
's s 'FND s' ci s i'f- s'
s, UE
-
( C Office o nvestigations Report No. 2-90-020 and NRC
Inspection Report No. 50-424,425/90-19, Supplement I)
This refers to the investigation conducted by the Nuclear Regulatory
' Commission's Office of Investigations (01) at Georgia Power Company's (GPC or ,
Licensee) Vogtle Electric Generating Plant (VEGP) which was completed on l
December 17, 1993. The investigation was initiated as a result of information l
received in June 1990 by Region II alleging, in part, that material false I
statements were made to the NRC by senior officials of GPC regarding the
reliability of the Diesel Generators (DGs). The pertinent events involved in
- this matter are described below.
,
On March 20, 1990, during a refueling outage at VEGP Unit 1, GPC declared a
l Site Area Emergency (SAE) when offsite power was lost concurrent with the
failure of the only Unit 1 DG that was available (1A). The other Unit 1 DG
4
(IB) was unavailable due to maintenance activities.
<
The NRC immediately responded to the SAE at the VEGP site with an Augmented
Inspection Team (AIT). The NRC effort was upgraded to an Incident
Investigation Team (IIT) on March 23, 1990. The IIT was composed of NRC
Headquarters technical staff and industry personnel. The results of this
investigation are documented in NUREG-1410, " Loss of Vital AC Power and the
Residual Heat Removal System During Mid-loop Operations at Vogtle Unit 1 on
March 20, 1990."
On March 23, 1990, the NRC issued a Confirmation of Action Letter (CAL) to GPC
that, among other things, confirmed that GPC had agreed not to return VEGP
Unit 1 to criticality until the Regional Administrator was satisfied that
appropriate corrective actions had been taken, and that the plant could safely
return to power operations.
On April 9, 1990, GPC made a presentation to the NRC in the Region II offices
in support of GPC's request to return VEGP Unit 1 to power operations. As
part of this presentation, GPC provided information on DG starts in response
to a specific NRC request that GPC address DG reliability in its April 9
9610090009 960827
PDR FOIA
WILHOTH95-81 PDR
-- _ _ . _ . . ~ . _ _ _ _. _ ._ . -_ ._ _ _ _ . . _ _ _ . . _ _ _ _ _
l*
4
i = ,
l
- ,
i Georgia Power Company 2
'
!
I presentation. GPC submitted a written summary of its April 9 presentation in '
an April 9,1990 letter, "Vogtle Electric Generating Plant Confirmation of'
Action Letter." ;
'
On April 12, 1990, the NRC formally granted permission for VEGP Unit I to '
j return to criticality and resume power operations.
4
- On April 19, 1990, pursuant to 10 CFR 50.73, GPC submitted Licensee Event
Report (LER) 50-424/90-006, " Loss of Offsite Power Leads to Site Area '
i
' Emergency."
4
On June.29, 1990, GPC submitted a revised LER, 50-424/90-006-01. The purpose
, .of the submittal was to clarify information related to successful DG starts
t that were discussed in the April 9,1990 letter and the April 19, 1990 LER,
and to update the status of corrective' actions in the original LER.
,
From August 6 through August 17, 1990, the NRC conducted a Special Ter
Inspection at VEGP, as a result of NRC concerns about, and allegations altted
to, VEGP operational activities. This inspection examined the technica:
validity and safety significance of the allegations, but did not investigate
alleged wrongdoing. The Special Team informed GPC that the June 29, 1990
submittal failed to address the April 9,1990 data and requested that GPC
clarify DG starts reported on April 9,1990. Results of this inspection are
documented, in part, in NRC Inspection Report No. 50-424,425/90-19,
Supplement 1, dated November 1,1991. t
,
On August 30, 1990, GPC submitted a letter, " Clarification of Response to
Confirmation of Action Letter." The purpose of the submittal was to clarify
the diesel start information that was addressed in the April 9, 1990
submittal.
The NRC has carefully reviewad the evidence associated with these events,
submittals, and representations to the NRC. Specifically, the NRC reviewed
information gathered as part of the 01 investigation, information gathered
during the IIT, NUREG-1410, Supplement 1 of NRC Inspection Report 90-19,
discovery responses in the Vogtle operating license amendment proceeding
(pocket Nos. 50-424 OLA-3, 50-425 OLA-3),'and other related information.
I
I
j
4
-
h
.... __ _ . . _ _ _ _ _ _ . _ _ _ - _ _ _ _ _ _. _ _ _ _ _
!-
!.
I
!
' The VEGP Gsheral Man'ager was
,
personally inv 6 1on of the data regarding the DG
- reliability and tasked the Unit Superintendent with co ti the
number of successful DG starts for th nd IB DGs.
l
In fact, che VEGP General Manager stated no criteria for successful
starts, a term not formally defined, when he directed the Unit
Superintendent to gather successful DG starts. The Unit Superintendent
collected DG start data from the Control Room to and the Shift
Supervisor's Log
ora y cony
Mana er for the 1A and 18 di
ormation
( was t en presente in an pri , 1990 ora resentation by
( the VEGP f:eneral Manager and in an April 9, 1990 letter that since
i March 20. 1990, there were 18 and 19 successful consecutive starts on
i the 1A ano IB DGs, respectively, without problems or failures.
! 9
ro ree s e pr n W on
and_1_etter inIluded three starts with problems that occurre during DG'
(overhaul / maintenance activit'ies'(a high lube oil temperature trip on
la 6 22, 1990; a low jacket w'ater pressure /turba lube oil pressure low
~
-
.
trip on March 23, 1990; and a failure to trip on a high jacket water
! temperature alarm occurring on March 24, 1990). The correct number of
l consecutive successful starts was 12 for the 18 DG--a number l
l han that re rted by GPC to the NRC on April 9,
<
In considering a restart decision,
l the NR was especially interes in the reliability of the DGs and
specifically asked that GPC address the matter in its presentation on
restart. The NRC relied, in part, upon this information presented by
GPC on April 9, 1990 in the oral presentation and in the GPC letter in
,
reaching the NRC decision to allow Vogtle Unit I to return to power l
l
operation.
'
i
he air or s arting a 8 = opera ing 1 s1 e - 5 and con ro s is
derived from the starting air system. The starting air system contains
I
i
)
1
1
.;.___...___,__._____....____m_._.m_ _ - . _ . . . - - _ _ _ . _ _ . .-
- -
~ _ - _ - - - - . - - - - - - - - - - - - - - - - - - - - - - -
i
!
j.
,
1
!
!
,
l Georgia Power Company 4
!
I
'f dryers designed to ntain moisture content (i.e., dew poin
acceptable levels.
eficiency cards
associated wi nit I would have revealed that high dew points were
also attributable to system air dryers occasionally being out of service
l for extended periods and to system repressurization following
maintenance, as documented in NRC Inspecti No. 50-424,425/90-
19, Supplement I dated Nov
'
In consi ering a resta ecision, the N was especia y interested in
the reliability of the DGs and specifically asked that GPC address the
,
matter in its presentation on restart. The NRC relied, in part, upon
i this information presented by GPC in its letter of April 9,1990 in
! reaching the decision to allow Vagtle Unit I to return to power
l operation.
l
,
e
1
i
l
1
i
LER 90-006, submitted to the NRC on April 19, 1990, was based, in part,
on information presented to.the NRC on April 9, 1990. During the
preparation of the LER, the Acting VEGP Assistant General Manager -Plant
Support questioned the accuracy of the April 9, 199 en that
there were trips on the IB DG after Mar
iscussions regar ing the draft LER, the Genera Manager,
Technical Support Manager and Acting VEGP Assistant General Manager -
Plant Support acknowledged that they could not identify the specific DG
start that represented the starting point for the count presented to the
__ _ - -
. . - - . . _ . - _ - - . . . . - _ . . _ - . ~ . . - _ . - - - . - . - - - . . ._ . _ . - . - . - - - _ _ . . _ .
l
'
.
l
.
l
l
Georgia Power Company 5
NRC, i.e., the first start following completion of the CTP. The General
Manager - Plant Support (Vogtle Project), the VEGP Technical Support
Manager, and the Acting VEGP Assistant General Manager - Plant Support
were aware that the VEGP General Manager had earlier stated that his
April 9 count began after instrument recalibration. The Acting VEGP
Assistant General Manager - Plant Support stated that his understanding
of the CTP was that it woul
tore rabili
In ct, Unit
uperin o co e origina pri th data advised the
Acting VEGP Assistant General Manager - Plant Support and the VEGP
Technical Support Manager that he started his cou on March 20, rior
to the time when a CTP could have been completed.
an
1 OG start coun s reported on pri , overs the actual
, countsbyincludingstartsthatwerepartofthetestprogram.ll ERB
.
d
a
A
1
A
3
.d
-
- - . - - - . _ - - - - - . . . . - . - _ _ - - - _ . - - _ _ . _ _ _ _ _ - _ _ _ _ - . - _ _ _ _ _ _ _ - -
1.
1
1
- -
!
1
i
i
!
!
i
i
!
,
1
l dii' April 36,1990, the Acting VEGP Assistant General Ma er - Plant
i gave the VEGP General Mana er a listing of IB DG starts
l
l
!
After being informed that the April 15 DG start counts were in error, the
i
!
l
l
<
'
l
J
4
i
j
,
! ._. . . _ . . _ _ . _ . _ _
_ _ _ _ _ _ _ _ __ _ _.___ _ _ _ _ ___ _ __. - - _ _
.
!-
t
l Georgia Power Company 7
Senior Vice President - Nuclear Operations informed the Regional Administrator
that a revision to the April 19 LER would be submitted, in part, to correct
the DG start counts. After being provided conflicting data for the second
time, the Senior Vice President - Nuclear Operations again notified the
l Regional Administrator. He also requ a ted that an audit be conducted by GPC's
l Safety Audit and Engineering Review (SAER) group to establish the correct data
j
'
and to determine why the errors were made. The audit, completed June 29,
narrowl focused on a review of diesel records (Test ' Data Sheets, Shift
rvisor's Log, and Diesel Generator Start Log) to verify the number of DG
s starts. The audit did not identify any specific cause for the error in the
j number reported in the LER. The audit stated, however, that the error
i appeared to result from incomplete documentation. The audit also noted that
there apparently was som confusion about the s ecific oin at which the est
rogram was completed.
?
On June 29, 1990, the draft cover letter for the LER revision was being
reviewed at the site. The draft had originated in GPC corporate headquarters
and included language personally developed by the Senior Vice President -
Nuclear Operations and the Vice President - Vogtle Project. During the site
review, a VEGP Technical Assistant (TA) (formerly the Acting VEGP Assistant
'
General Manager - Plant Support) noted that the letter was incomplete and
challenged the accuracy of the reasons stated in the draft cover letter in
conversations with the Supervisor - SAER, the VEGP Assistant General Manager -
Plant Support, the VEGP Manager - Engineering Support, and a Licensing
Engineer - Vogtle Project. The VEGP TA stated that: (1) the letter failed to
, clarify the DG starts reported on April 9, (2) DG record keeping practices
I
i
were not a cause of the difference in the DG starts reported in the April 19
LER because adequate information was available when the counting errors were
made, and (3) the err us ts resulted from
devel the coun
!
The Licensing Engineer - Vogtle Project had staff responsibility for preparing
the cover letter for the LER revision and was specifically instructed by the
- Senior Vice President - Nuclear Operations to work cl with the site to
j ensure that the submittal was accurate and co ete.
!
I
i
1
l The VEGP Manager - Engineering Support was responsible for the Diesel Start
i
Logs and agreed with the audit. report findings regarding deficiencies in their
i
-- - . - - - - - - . . -_ . _ _ - - .. _. - - _ _ . - . - -
- . - - - - . . - . - . - - - - . - . - - . . - - . . . . - . _ _ _ . - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ -
-
\
l Georgia Power Company 8
condition. Given thar. his logs had not been used to collect the DG start
data, he pointed out that it was wrong t( state that the conditi his logs
caused errors in the information initially provided to the NRC.
!
l
I
l the Supervisor - SAER'was made aware by the
EGP TA on June 12, 1990 t a , to identify the root cause of the error in the
l April 19, 1990 LER (i.e., personnel errtirs), the audit scope would need to
include an assessment of the performanco of the Unit Superintendent and the
VEGP General Manager, the individuals taat developed the initial count. Yet,
the audit report did not include either of these individuals in the list of
persons contacted during the audit. Or June 29, 1990, the Supervisor - SAER
f was again made a r TA ths.t the root cause for the difference was
ersonnel error.
The VEGP Assistant General Manager war apprised of concerns regarding the
June 29, 1990 letter by the VEGP TA (an individual who had been involved in
preparing the April 19, 1990 LER and had been involved in developing an
accurate DG start count). The VEGP Tu identified to him the failure of the
~'
June 29, 1990 draft cover lett he inaccuracies in the A ril 9,
j etter
l The Vice President - Vogtle
j Project and the Senior Vice President - Nuclear Operations were actively
j involved in the preparation of the June 29 cover letter. The VEGP General
'
i Manager and Vice President - Vogtle Project reviewed, and th. Senior Vice
President - Nuclear Operations signed, the June 29 cover letter which stated
that its ur ose was, in art to 1 tion rovided to the NR
A ril 9.
l
I
. .-- - - - . - - - ._ _ . - - - . _ . _ . - _ _ _ _ . _ -
t
, %k me:m x
l* ..
1
I
i
!
il 9
- letter and presentation and the April 19 LER were caused, in part, by
i
confus in the tinction between a successful start and a valid
- test.
,
uring ugust 29, 1990 P view Board (PRB)
mee ing, e VEGP Manager - Technical Support questioned if the Unit
Superintendent (the individual who originally collected the DG start
data) was confused in the distinction between a successful start and a
valid test. The VEGP General Manager admitted that the Unit
l
Superintendent was not confused about the distinction when he collected
the data which was use'd to prepare the April 9 letter, but stated that
the sentence was not in error because other people were confused. The
VEGP General Manager acknowledged that there was confusion among
individuals after April 9, but admitted that the t Superintendent was
not confused when he developed the information.
l
u
j $,,
l
,
!
! E ~ The August 30 letter states that the
I error in the Apri 9 e er an i
lresentation and the April 19 LER were
f caused, in part, by n error made b the individual who performed the
{
count of DG starts.
~
s
!
4
f
!
.
_ _ _ _ . . . .___ ._ .._ .._ __ __-__ _ __. _. _ _. ____._ _ __ _ _ _ . . _ .__ _ _ _ _ _ _ _ _ _ .. _ ___ _ ___ _ _ __ _ . _ . _..__ _. _ _ _.
.
4
4
i
The' Senior ~Vice President-Nuclear Operations ano
e ce resident - Vogtle Project rectl invol
development of the June 29 letter.
C re ted
su ressi he ril 9 letter
ice
resi -
ect commit ng ugus meeting with
+he NRC special inspection team to rovide clarification to th> RC
arding the ril 9 letter.
<
GPC forwarded a submittal regar ing t pri
letter on August that was drafted at corporate head uarters under the
direction of the Vice President - Vootle Pro.ie'ct.
1
i
. _ . . . - . . ._ -. .
i
,
[
4
I
l
l
Georgia Power Company 11
,
I
,
i
!
l
)
- - . . ._. -. . .. .. - - . . - _ . - . _ . . . . __. . - . -
,
e
Georgia Power Company g
,
4
i
!
,
l
4
1
..-_____.___ _ _--- - _ _ . . - . - . - - - . . - - . _ _ _ _ - _ _ - - - - - - . -
,
i l
I
I
I
The responses directed by this letter and the enclosed Notice are not subject l
6 to the clearance procedures of the Office of Management and Budget as required i
by the Paperwork Reduction Act of 1980, Pub. L. No.96-511.
l
l
Sincerely,
!
l James L. Milhoan
Deputy Executive Director
for Nuclear Reactor Regulation,
Regional Operations,and Research
l
'
Enclosures-
2.
l
,
i
(
l
. _ . _ _ _ _ _ _ . .. - . _ _ . . _ . .. __ . _ _ . . _ . . _ _
i
(
,
<
!
J :
,
Georgia Power Company -
!
5
DISTRIBUTION:
PDR
SECY
CA
JTaylor, EDO I
JMilhoan, DEDR *
f
JLieberman, OE
SEbneter, RII i
LChandler, OGC
JGoldberg, OGC .
WRussell, NRR
EReis, OGC
Enforcement Coordinators ;
RI, RII, RIII, RIV, RV l
!
FIngram, GPA/PA
EJordan, AEOD l
BHayes, 01
EA File
DCS
Vogtle Coordinating Group:
D. Matthews, Chairman
R. Pedersen, OE
P. Skinner, RII-
D. Hood, NRR
D. Wheeler, NRR l
D. Hoefling, OGC !
M. Young, OGC .l
l
)
I
~
I
l
!
_ .----.-.. - - - - - - - - - - - - - - -
'
.
3
GEORGE BOCKNOLD, JR.
O
General Manager at Vogtle during March - August 1990 time-
frame.
o
o Sent to INPO for approximately 1 or 2 years. l
o Currently serving as the General Manager of Nuclear.
Technical Services for Southern Nuclear (promotion from
Vogtle General Manager).
l o Has held current position for approximately 1 or 2 years.
t
'
i o CU.rrent position considered licensed activities.
t
o Current position impacts operations at Vcgtle, Hatch, and
{
-
Farley (currently conducting overview of work request
j process at all three facilities).
!
j o Five supervisors report to him. l
1
l l
,
l
- 1
}
i
i
!.
i
!
!
i
1
l
j
i
i
4
1
i
l
Information in this record was deleted
- ! in accordance with thje Fr edom of information
' Act, exemptions.
FolA- W "X/-. -
I