|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217K1051999-10-19019 October 1999 Ack Receipt of Ltr Dtd 990707,which Transmitted Rev 29 to Callaway Plant Physical Security Plan,Under Provisions of 10CFR50.54(p).Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML20217G2071999-10-14014 October 1999 Forwards Insp Rept 50-483/99-10 on 990913-16.No Violations Noted.Insp Was to Review Emergency Plan & Procedures During Biennial Emergency Preparedness Exercise ML20217B5901999-10-0505 October 1999 Informs That Staff Concludes That Licensee Responses to GL 97-06 Provides Reasonable Assurance That Condition of Util SG Internals in Compliance with Current Licensing Bases for Callaway Plant,Unit 1 ML20217B5711999-10-0505 October 1999 Discusses GL 98-01 Issued by NRC on 980511 & Uec Responses for Callaway NPP Unit 1 ,990224 & 990628.Informs That Staff Reviewed Responses & Concluded That All Requested Info for GL 98-01 Provided ML20212G0221999-09-22022 September 1999 Forwards Insp Rept 50-483/99-11 on 990812-20.No Violations Noted.Team Found,Weakness in flow-accelerated Corrosion Monitoring Program Resulted in No Previous Insp of Pipe Segment Which Failed ML20212D9341999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Callaway Plant.In Area of Ep,C/As Taken in Response to Problems Identified During Previous Exercises Warrant More in-dept Review.Details of Insp Plan Through March 2000 Encl ML20217D5791999-09-15015 September 1999 Provides Formal Documentation of Reviews & Discussions Re Technical Ltr Rept for Proprietary Info.Review of Ltr Was Discussed in Telcon & Via e-mail Messages. Summary of Telcons as Documented on 990708,included ML20212A4921999-09-13013 September 1999 Forwards Insp Rept 50-483/99-08 on 990725-0904.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy ML20212A4701999-09-10010 September 1999 Rssponds to NRC 990709 RAI Re Util Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection Iwe. Acceptance Criteria for Liner Plate Pressure Boundary Thickness Will Be Limited to 10% Nominal Thinning ML20212B1521999-09-10010 September 1999 Forwards Insp Rept 50-483/99-07 on 990809-13.No Violations Noted.Inspectors Used Annual Licensed Operator Requalification Exams to Assess Licensed Operator Performance ML20211N0321999-09-0202 September 1999 Forwards SE Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20211B0241999-08-18018 August 1999 Ack Receipt of Ltr Dtd 990714,transmitting Scenario for Licensee Upcoming Biennial Exercise.Based on Review,Nrc Determined That Exercise Scenario Sufficient to Meet Emergency Plan Requirements & Exercise Objectives ML20210T9121999-08-13013 August 1999 Forwards Insp Rept 50-483/99-06 on 990613-0724.One Severity Level 4 Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20210R7241999-08-12012 August 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for 990101-990630,IAW 10CFR26.71(d) ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ULNRC-04085, Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power1999-08-11011 August 1999 Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power ML20210P0371999-08-10010 August 1999 Forwards SE Granting Licensee 980710 Requests for Relief (ISI-13 - ISI-18) from Requirements of Section XI of 1989 Edition of ASME B&PV Code for Second 10-year Interval ISI at Plant,Unit 1 ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ULNRC-04079, Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal1999-08-0202 August 1999 Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ML20210H6381999-07-30030 July 1999 Forwards SE Accepting Relief Request for Approval for Use of Alternate Exam Requirement for Plant Inservice Insp Program A93443, Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves1999-07-28028 July 1999 Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves ULNRC-04075, Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves1999-07-28028 July 1999 Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves ULNRC-04076, Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs1999-07-28028 July 1999 Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs ULNRC-04070, Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power1999-07-27027 July 1999 Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power 05000483/LER-1998-008, Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved1999-07-27027 July 1999 Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved ULNRC-04071, Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-021999-07-27027 July 1999 Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-02 ML20210B5611999-07-20020 July 1999 Forwards Review of Ltr & Encl Objectives for Plant,Unit 1,1999 Emergency Plan Exercise Scheduled for 990914 ML20210B4021999-07-19019 July 1999 Ack Receipt of Facility Emergency Plan Implementing Procedure EIP-ZZ-00101, Classification of Emergencies, Rev 23,issued on 990513,under Provisions of 10CFR50,App E, Section V ML20210B4401999-07-19019 July 1999 Ack Receipt of Revs to Facility Radiological Emergency Response Plan,Chapters 8.0 & 4.0,issued Respectively on 990512-14,under Provisions of 10CFR50,App E,Section V ML20212A3291999-07-15015 July 1999 Forwards Scenario Manual Containing Description of Callaway Plant 1999 Biennial Emergency Response Plan Exercise to Be Conducted 990914.Correspondence to Satisfy 60-day Submittal Requirement ML20209F3471999-07-0909 July 1999 Forwards Response to NRC 990624 RAI to Complete NRC Review of Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection IWE ML20209E5591999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2.TAC MA0531 Closed ML20209H2471999-07-0707 July 1999 Forwards Rev 29 to Physical Security Plan,Per 10CFR50.54(p). Rev Withheld,Per 10CFR73.21 ML20196J9501999-07-0202 July 1999 Ack Receipt of Plant Ep,Rev 22,received on 981207 & Submitted Under Provision of 10CFR50,App E,Section V.Changes Does Not Decrease Effectiveness of EP & Continues to Meet Stds of 10CFR50.47(b).NRC Approval Not Required ML20209B6851999-06-28028 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Nuclear Power Plants. Disclosure Rept Encl ML20209C0171999-06-28028 June 1999 Forwards Special Rept 99-01 Re Fifteenth Year Inservice Containment Bldg Tendon Surveillance Failure.Observed Voids in Sheathing Filler Grease Do Not Indicate Degradation of post-tensioning Sys,Based on Encl Evaluation ML20196F8101999-06-25025 June 1999 Informs That J Donohew Will Assume Project Manager Responsibilities,Effective 990621 ML20196H2521999-06-25025 June 1999 Forwards Insp Rept 50-483/99-05 on 990502-0612.Two Violations Occurred & Being Treated as Noncited Violations, Consistent with App C of Enforcement Policy ML20196F8181999-06-24024 June 1999 Forwards RAI Re 990111 Request for Relief from Certain ASME Code ISI Requirements for Containment Liners.Response Requested within 30 Days from Date of Agreement ML20196G5621999-06-21021 June 1999 Informs NRC of Implementation of Amend 132 to Callaway License NPF-30 to Allows Installation of Electrosleeves for Steam Generator Tube Repair for Two Cycles Following Installation of First Electrosleeve IR 05000483/19990041999-06-18018 June 1999 Refers to GL 96-05 Issued by NRC on 960918,UE Responses & 970313 & NRC Insp Rept 50-483/99-04,dtd 990427. Forwards Request for Addl Info Re GL 96-05 Program at Callaway Plant,Unit 1 ML20212J2441999-06-18018 June 1999 Submits Request for Alternate Exam Requirements for Plant Re ISI Program Plan.Plant Does Not Torque Bolted Connections to Stress Values Greater than 100 Ksi ML20195H0971999-06-14014 June 1999 Discusses Une 990407 Request That Proprietary Document Entitled, Thermal Stability Assessment - Electrosleeved Tubes, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207H3751999-06-14014 June 1999 Discusses 990407 Une Request That Proprietary Version of Document Entitled, Evaluation of Severe Accident Simulation, Dtd April 1999,be Withheld from Public Disclosure.Determined Info Proprietary & Will Be Withheld ML20195H9731999-06-11011 June 1999 Forwards Requested Addl Info Related to Relief Request ISI-16,encountered During Refuel 9 ML20195J9301999-06-0808 June 1999 Informs That Refuel 9 OAR-1 Owners Data Rept for ISI & Summary Rept for Interval 2 Was Submitted with Typographical Error,In That Commercial Service Date Should Be 841219,vice 941219.Please Substitute Encl Corrected Document ML20207G3201999-06-0707 June 1999 Ack Receipt of Change Notice 98-008 Dtd 980918,which Transmitted Changes to Callaway Plant Ep,Rev 21,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required.No Violations Identified ML20207G3151999-06-0707 June 1999 Ack Receipt of Callaway Plant EP Implementing Procedure EIP-ZZ-001001M,Classification of Emergencies,Rev 22,issued on 981222 Under 10CFR50,App E,Section V Provisions.No Violations Identified ML20195C5131999-05-28028 May 1999 Forwards Revs to Sections 3.9 & 5.6 of Its,Based on Resolution Telcons Held Between NRC Staff & Util on 990526 & 27 A98803, Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS1999-05-27027 May 1999 Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS 1999-09-22
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217D5791999-09-15015 September 1999 Provides Formal Documentation of Reviews & Discussions Re Technical Ltr Rept for Proprietary Info.Review of Ltr Was Discussed in Telcon & Via e-mail Messages. Summary of Telcons as Documented on 990708,included ML20212A4701999-09-10010 September 1999 Rssponds to NRC 990709 RAI Re Util Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection Iwe. Acceptance Criteria for Liner Plate Pressure Boundary Thickness Will Be Limited to 10% Nominal Thinning ML20210R7241999-08-12012 August 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for 990101-990630,IAW 10CFR26.71(d) ULNRC-04085, Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power1999-08-11011 August 1999 Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power ULNRC-04079, Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal1999-08-0202 August 1999 Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ULNRC-04075, Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves1999-07-28028 July 1999 Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves A93443, Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves1999-07-28028 July 1999 Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves ULNRC-04076, Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs1999-07-28028 July 1999 Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs 05000483/LER-1998-008, Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved1999-07-27027 July 1999 Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved ULNRC-04070, Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power1999-07-27027 July 1999 Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power ULNRC-04071, Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-021999-07-27027 July 1999 Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-02 ML20212A3291999-07-15015 July 1999 Forwards Scenario Manual Containing Description of Callaway Plant 1999 Biennial Emergency Response Plan Exercise to Be Conducted 990914.Correspondence to Satisfy 60-day Submittal Requirement ML20209F3471999-07-0909 July 1999 Forwards Response to NRC 990624 RAI to Complete NRC Review of Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection IWE ML20209H2471999-07-0707 July 1999 Forwards Rev 29 to Physical Security Plan,Per 10CFR50.54(p). Rev Withheld,Per 10CFR73.21 ML20209C0171999-06-28028 June 1999 Forwards Special Rept 99-01 Re Fifteenth Year Inservice Containment Bldg Tendon Surveillance Failure.Observed Voids in Sheathing Filler Grease Do Not Indicate Degradation of post-tensioning Sys,Based on Encl Evaluation ML20209B6851999-06-28028 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Nuclear Power Plants. Disclosure Rept Encl ML20196G5621999-06-21021 June 1999 Informs NRC of Implementation of Amend 132 to Callaway License NPF-30 to Allows Installation of Electrosleeves for Steam Generator Tube Repair for Two Cycles Following Installation of First Electrosleeve ML20212J2441999-06-18018 June 1999 Submits Request for Alternate Exam Requirements for Plant Re ISI Program Plan.Plant Does Not Torque Bolted Connections to Stress Values Greater than 100 Ksi ML20195H9731999-06-11011 June 1999 Forwards Requested Addl Info Related to Relief Request ISI-16,encountered During Refuel 9 ML20195J9301999-06-0808 June 1999 Informs That Refuel 9 OAR-1 Owners Data Rept for ISI & Summary Rept for Interval 2 Was Submitted with Typographical Error,In That Commercial Service Date Should Be 841219,vice 941219.Please Substitute Encl Corrected Document ML20195C5131999-05-28028 May 1999 Forwards Revs to Sections 3.9 & 5.6 of Its,Based on Resolution Telcons Held Between NRC Staff & Util on 990526 & 27 A98803, Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS1999-05-27027 May 1999 Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS ML20196L2911999-05-19019 May 1999 Forwards Responses to NRC 990315 RAI Concerning GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves A36791, Forwards Response to NRC 990510 RAI Re GL 96-06 with Respect to Analysis of Water Hammer & two-phase Flow Issues. Supporting Calculation Also Encl1999-05-17017 May 1999 Forwards Response to NRC 990510 RAI Re GL 96-06 with Respect to Analysis of Water Hammer & two-phase Flow Issues. Supporting Calculation Also Encl ULNRC-04034, Forwards Amerenues Risk Evaluation Summary & Provides Listing of Other Documents Which Have Been Previously Provided to Support Evaluation of Electrosleeves at High Temp Severe Accident Conditions1999-05-17017 May 1999 Forwards Amerenues Risk Evaluation Summary & Provides Listing of Other Documents Which Have Been Previously Provided to Support Evaluation of Electrosleeves at High Temp Severe Accident Conditions 05000483/LER-1998-003, Forwards LER 98-003-01 Re Inadvertent Actuation of ESFAS Due to 'A' SG High Level During Refuel 9.Rept Is Submitted to Report Change in C/A from That Reported in Original Rept1999-05-12012 May 1999 Forwards LER 98-003-01 Re Inadvertent Actuation of ESFAS Due to 'A' SG High Level During Refuel 9.Rept Is Submitted to Report Change in C/A from That Reported in Original Rept ML20206Q9551999-05-12012 May 1999 Responds to NRC Re Violations Noted in Insp Rept 50-483/99-04.Corrective Actions:Une Commits to Make Available for NRC Review,Action Plan Outlining Scope & Completion Dates of Project ULNRC-04027, Forwards Comments on Draft SE Re Proposed Conversion to Improved Tss.Copy of ITS & ITS Bases Will Be Provided by 990524,to Support Issuance of License Amend on or About 9905281999-05-0404 May 1999 Forwards Comments on Draft SE Re Proposed Conversion to Improved Tss.Copy of ITS & ITS Bases Will Be Provided by 990524,to Support Issuance of License Amend on or About 990528 ML20206E3211999-04-28028 April 1999 Forwards Special Rept 98-03 Re Inservice Insp of CP Sgs,Per Plant TS 4.4.5.5.b.Insp Was Performed in Apr 1998 During Plant Ninth Refueling Outage.Rept Is Being Resubmitted Due to Typos in Original Rept ML20206E5781999-04-23023 April 1999 Informs That R Schukai Is No Longer Employed with Amerenue & Info Sent Is No Longer Required.Name Should Be Removed from Mailing Lists.Mailing Label Used by Company Which May Assist in Matter,Submitted ULNRC-04018, Submits follow-up Items Re Proposed Conversion to ITS Sections 1.0,3.3,3.4,3.6,3.7 & 3.9.Suppl to Ltr Will Be Submitted at Later Date1999-04-21021 April 1999 Submits follow-up Items Re Proposed Conversion to ITS Sections 1.0,3.3,3.4,3.6,3.7 & 3.9.Suppl to Ltr Will Be Submitted at Later Date ML20205Q7751999-04-16016 April 1999 Forwards Special Rept 98-03 Concerning ISI of Callaway SGs Performed in Apr 1998 During Callaway Plants Ninth Ro. Rept Documents Final SG Insp Results ULNRC-04015, Forwards Cash Flow Projection & Certification to Satisfy Guarantee of Payment of Retrospective Premiums,Per 10CFR140.211999-04-15015 April 1999 Forwards Cash Flow Projection & Certification to Satisfy Guarantee of Payment of Retrospective Premiums,Per 10CFR140.21 ULNRC-04005, Forwards Proprietary & non-proprietary White Paper Entitled, Evaluation of Severe Accident Simulation, as Addl Info to Facilitate Approval of Requested Amend to Revise TS to Use Repair SG Tubes.Proprietary Info Withheld,Per 10CFR2.7901999-04-0707 April 1999 Forwards Proprietary & non-proprietary White Paper Entitled, Evaluation of Severe Accident Simulation, as Addl Info to Facilitate Approval of Requested Amend to Revise TS to Use Repair SG Tubes.Proprietary Info Withheld,Per 10CFR2.790 ULNRC-04004, Forwards Proprietary Thermal Stability Background Data Along with Time/Temp Graph Requested in 990402 Telcon with NRC & Contractor,Argonne Natl Lab.Proprietary Info Withheld1999-04-0707 April 1999 Forwards Proprietary Thermal Stability Background Data Along with Time/Temp Graph Requested in 990402 Telcon with NRC & Contractor,Argonne Natl Lab.Proprietary Info Withheld ULNRC-04007, Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6 & 3.7.Encl Includes mark-ups of ITS Sections 3.5,3.6 & 3.8.Suppl to Ltr Will Be Provided at Later Date1999-04-0707 April 1999 Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6 & 3.7.Encl Includes mark-ups of ITS Sections 3.5,3.6 & 3.8.Suppl to Ltr Will Be Provided at Later Date ULNRC-04000, Forwards Rept Re Present Level of Insurance & Sources of Insurance Applicable to Callaway Plant,Per 10CFR50.54(w)1999-04-0101 April 1999 Forwards Rept Re Present Level of Insurance & Sources of Insurance Applicable to Callaway Plant,Per 10CFR50.54(w) ULNRC-03998, Forwards Required Financial Info Re Decommissioning Callaway Nuclear Plant,Per 10CFR50.751999-03-30030 March 1999 Forwards Required Financial Info Re Decommissioning Callaway Nuclear Plant,Per 10CFR50.75 ML20205G2211999-03-25025 March 1999 Submits Rev 28A to Callaway Plant Physical Security Plan, Incorporating Addendum Re Security Sys Replacement Transition Plan,Per 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20205R5251999-03-25025 March 1999 Forwards Special Rept 98-03 Re Results of Tenth SG Tube Inservice Insp,Per Requirements of Plant TS 4.4.5.5.b.Insp Was Performed in Apr 1998 During Plant Ninth Refueling Outage ULNRC-03988, Requests Approval of Alternative Exam ISI-12A Per 10CFR50.55a(a)(3)(i) & (II) for 1989 Edition of ASME Section IX,IWA-5242(a) for Class I Bolted Connections Inside Bioshield for RFO 101999-03-19019 March 1999 Requests Approval of Alternative Exam ISI-12A Per 10CFR50.55a(a)(3)(i) & (II) for 1989 Edition of ASME Section IX,IWA-5242(a) for Class I Bolted Connections Inside Bioshield for RFO 10 ULNRC-03991, Forwards 1998 Annual Rept of Individual Monitoring Results, Per 10CFR20.2206.Rept Provided in Electronic Format on Diskette IAW Gudiance of Reg Guide 8.7.Without Diskette1999-03-19019 March 1999 Forwards 1998 Annual Rept of Individual Monitoring Results, Per 10CFR20.2206.Rept Provided in Electronic Format on Diskette IAW Gudiance of Reg Guide 8.7.Without Diskette ML20204F7211999-03-17017 March 1999 Forwards Amended Fitness for Duty Program Performance Data for Six Month Period Beginning Jul-Dec 1998 ML20204E1331999-03-17017 March 1999 Responds to NRC Re Violations Noted in Insp Rept 50-483/99-02 on 990208-12.Corrective Actions:Will Revise Security Plan to Increase Min Staffing by Three Armed Security Force Response Personnel Per Shift ML20207C3631999-03-12012 March 1999 Forwards Exam Matl & Associated QA Checklist for Written Exam to Support Plant RO Retake Exam Scheduled for 990423. Exam Matls Requested to Be Withheld from Public Disclosure Until After Exam Completion 05000483/LER-1998-001, Forwards LER 98-001-01,being Submitted to Clarify Scope of Original Reviews Performed for Corrective Action Number 3 in LER 98-001-00.Reviews Have Identified Case of Failure to Properly Establish Equipment Operability1999-03-10010 March 1999 Forwards LER 98-001-01,being Submitted to Clarify Scope of Original Reviews Performed for Corrective Action Number 3 in LER 98-001-00.Reviews Have Identified Case of Failure to Properly Establish Equipment Operability ULNRC-03979, Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6,3.7,3.8,3.9 & 5.0.Suppl to Ltr Dtd 970515,will Be Provided at Later Date1999-03-0909 March 1999 Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6,3.7,3.8,3.9 & 5.0.Suppl to Ltr Dtd 970515,will Be Provided at Later Date ULNRC-03975, Informs of No Reportable ECCS Evaluation Model Revs for Callaway During Time Period from Mar 1998 to Mar 1999,IAW 10CFR50.46.ECCS Evaluation Model Margin Assessment Encl1999-03-0505 March 1999 Informs of No Reportable ECCS Evaluation Model Revs for Callaway During Time Period from Mar 1998 to Mar 1999,IAW 10CFR50.46.ECCS Evaluation Model Margin Assessment Encl ULNRC-03971, Forwards Annual Personnel Exposure & Monitoring Rept for 1998, Per TS Sections 6.9.1.4 & 6.9.1.5.Rept Includes One Incident of Specific Activity Analysis of RCS in Which Limits of TS 3.4.8 Were Exceeded1999-02-26026 February 1999 Forwards Annual Personnel Exposure & Monitoring Rept for 1998, Per TS Sections 6.9.1.4 & 6.9.1.5.Rept Includes One Incident of Specific Activity Analysis of RCS in Which Limits of TS 3.4.8 Were Exceeded ML20207A4311999-02-17017 February 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for Period of 980701-981231 1999-09-15
[Table view] |
Text
- . - . . . . - . - . . . - . _ - . .. -- - - _ - - . . -. .. -- - .- -
-.. ( .who#
4
~f;,?0" e5:nI49
~
. , , *;* %+ 1 } Y(
, . Qyy),y oor,anii sesnen
-Euicnuc '
33 September 6, 1941 ,
U.S.-Nuclear Regulatory Commission Attn:- Docus.ent Control Desk ,
Mail btation Pl-137 Washington, DC 20555
. Gentlemen:- ULNRC- 2479 DOCKET NO.-50-483
. RESPONSE TO GENERIC' LETTER 91-06,
" RESOLUTION OF GENERIC: ISSUE A-30,
' ADEQUACY OF= SAFETY-RELATED-DC-POWER SUPPLIES,'
._ PURSUANT'TO 10 CFR 50.54(f)"
Attachment:
~ Responses to queGtions listed in Enclosure 1 of NRC Generic L6tter 91-06.
The subject.NRC_ Generic Letter requested additional _information regarding the adequacy of safety-related DC. power. supplies at the Callaway-Plant..
Union Electric Company's-responses to questions' listed in Enclosure 1 of'the subject =NRC Generic. Letter are attached.
Eased'on our responses.to these questions, no.
further action is required to resolve Generic Issue A-30
-for the callaway Plant.
If additional *information concerning this- ,
L Generic Letter'is required, please-contact us.
Very truly y urs, lL. 'f. fiZA2/che-h'w[
Donald F.-Schnell GAC/p1h '
n l J_ ,
l- 9109152061f 910906 -
P DR - ADOCK 05000403 p PDR
,Y
-] !
s l1 1201M
\
,~
r t
.. I-
- -. = _ _ - - _ . _- - - . . _ - .
4 STATE OF MISSOURI )
) S S-CITY OF ST. LOUIS )
Alan C. Passwater, of. lawful age, being first duly sworn upon oath says that he is Manager, Licensing and Fuels (Nuclear) for Union Electric Company; that he has read the foregoing document and knows the content--thereof; that he has executed the same for and on behalf of said company with full power and authority to do so; and -
that the facts therein stated are true and correct to the best of his knowledge, information and belief.
/ ., /n N"
.I
/ / ,
f By- '
[ NT h '
Alan C. Passwater Manager, Licensing and Fuels Nuclear SUBSCl3IBED and sworn to before me this _ [ ^ day of ./ m 7/ n'/ 4 -
i
, 1991.
,.g . i. . .. at tA.
gy e ffAYY BARBARA J. PFAFF NOTARY PUBUC, STATE 08 Ml!5OURI Mf COMMISSION EXPlRES APRIL 22. 1993 ST. LOUIS COUNTY 1
w , - - s...,. ..,e, c., . -
i
~
ce s. T. A. Baxter,-Esq.
Shaw,_Pittman, Potts.& Trowbridge 2300 N. Street, N.W.
Washington,-D.C. 20037 Dr. J. 0. Cermak CFA, Inc.
18225-A Flower 11111 Way ,
~
.Gaithersburg, MD 20879-5334 R. C. Knop Chief, Reactor Project _ Branch l U,S. Nuclear Regulatory Commission Region III >
799' Roosevelt Road
~
Glen Ellyn, Illinois 60137 Bruce Bartlett Callaway Besident Office
-U.S. Nuclear Regulatory Commission RR41 Steedman, Missouri 65077 IM. Dr Lynch (2)
-Office of Nuclear Reactor Regulation
-U.S. Nuclear-Regulatory Commission 1 White Flint,-North, Mail Stop 13E21 '
-11555 Rockville Pike
.-Rockville, MD 20852
' Manager,. Electric Department
' Missouri--Public Service Commission ,
P.O. Box 360 Jefferson City, MO 65102 P
i l
l-
. . . - . . . . . . .< , - . +- , - , , . , , . - . . , . ,. . . . - - , . ,
ULNRC-2479
' ~
ENCLOSURE 1 10 CFR 50.54(f) REQUEST - GENERIC ISSUE (GI) A-30 " ADEQUACY OF SAFETY-RELATED DC POWER SUPPLIES"
_Bac_
k ground The specific area of concern of GI A-30 " Adequacy of Safety-Related DC Power Supplies" is the adequacy of the safety-related de power in operating nuclear power plants, particularly with regard to multiple and comon cause f ailures.
Risk analysis and past plant experience support conclusions that failure of the de power supplies could repre:;ent a significant contribution to the unreliability of shutdown cooling. Analysis indicates that intdequate maintenance and surveillance and failure to detect battery unavailability are the prime contributors to f ailure of the de power systems.
During the development of plans to resolve G1 A-30, it was observed that several previously issued regulatory notices (IENs), bulletins (IEBs) and letters (GLs) submitted to licensees include recomendations similar to those that have been identified to resolve G1 A-30. More specifically, it has been determined that recomendations contained in notifications IEN 85-74, " Station Battery Problems", IEB 79-27 " Loss of Non-Class 1E Instrumentation and Control Power System Bus during Operation," and separate actions being taken to resolve GI 49, " Interlocks and LCOs for Class 1E Tie Breakers" include the elements necessary to resolve GI A-30. It is therefore concluded that licensees that have implemented these recomendations and actions will have resolved 61 A-30.
The response to the questions that follow is necessary to provide the staff with information to determine whether any further action is required for your facility.
Questions The following information is to be provided for each unit at each site:
- 1. Unit _ _callaway
- 2. a. The number of independent redundant divisions of Class 1E or safety-related de power for this plant is __ _ 2 . (Include any separate Class IE or safety-related de, such as any oc dedicated to the diesel generators.)
- b. The number of functional safety-related divisions of de power necessary to attain safe shutdown for this unit is t .
- 3. Does the control room at this unit have the following separate, independent 1.y annunciated alarms and_ indications for each division of de power?
- a. alarms
- 1. Battery disconnect or circuit breaker open? yes
- 2. Battery charger disconnect or circuit breaker open (both input ac and output dt)? yes
~ .
4 Enclosure 1
- 3. de system ground? Yes
- 4. de bus undervoltage? Yes
- 5. de bus overvoltage? Yes
- 6. Battery charger f ailure? Yes
- 7. Batt cy discharge? Yes __
- b. Indicatiens
- 1. Battery float charge current? _Yes
- 2. E 'tery circuit output current? __ Yes
- 3. Battery discharge? Yes
- 4. - Bus voltage? Yes
- c. Does the unit have written procedures for response to the above alarms and indications? , yes j
- 4. Does this unit have indication cf bypassed and inoperable status of circuit breakers or other devices that can be used to disconnect the
' battery and battery charger from its de bus and the battery charger from its ac power source during maintenance or testing? Yes
- 5. If the answer to any part of question 3 or 4 is no, then provide information justifying the existing design features of the'f acility's safety-related
, de systems. _ *See note below.
- 6. (1) Have you conducted a review of maintenance and testing activities to minimize the potential for human error causing more than one de division to be unavailable? _Yes _ and (2) do plant procedures prohibit maintenance or testing on redundant de divisions at the same time? ;
Yes If the facility Technical Specifications have provisions equivalent to those found in the Westinghouse and Combustion Engineering Standard Technical Specifications ,
. for maintenance and surveillance, then question 7 may be skipped and a statement to that effect may be inserted here. ca11avev pi,nt 7,ckn4 m e ~ 4fications have D provisims equilvalent to bestinghouse standard technical specifications. l
- 7. Are maintenance, surveillance and test procedures regarding station t
batteries conducted routinely at this plant? Specifically:
- a. At least once per 7 days are the following verified to be within acceptable limits:
- 1. Pilot cell electrolyte level?
. 2 ULNRC-2479 Enclosure 1
2.- Specific' gravity or charging current?
3.. Float voltage?
4 Total bus voltage on float charge?
- 5. Physical condition of all cells?
b.- At least once_ per 92= days, or within 7 days after a battery discharge, overcharge, or if the pilot cell readings are outside the 7-day-surveillance requirements are the following verified to be within acceptable limits:
f
- 1. - Electrolyte level of each cell?
2.- The average' specific gravity of all cells?
- 3. _The specific; gravity of each cell?
4 The average electrolyte temperature-of a representative number of cells?
- 5. The float voltage of each cell?
- 6. Visually inspect or measure resistance of terminals and connectors-(including the connectors at the de bus)?
- c. -At least every?l8 months are the following verified:
- 1. Low resistance of each connection (by test)? _ _
- 2. Physi _ cal condition of the battery?
3.- Battery charger capability to deliver rated ampere output to the de bus?
4 -The capability of the battery to deliver its design duty cycle.to the de bus?
- 5. Each individual cell voltage is within acceptable-limits.
during the service test?
.d; , At least every 60 months, is capacity of each battery verified by performance of a. discharge. test?
- e. At least annually, _is the battery capacity verified by performance discharge test,- if the battery shows signs of degradation or has reached 85% of the expected service life?
Lnclosure 1
-4
- 8. Does this plant have operational features such that following loss of one safety-related de power supply or bus: -
- a. Capability is maintained for ensuring continued and adequate reactor cooling? Yes
- b. Reactor coolant system integrity and isolation capability are maintained?
Yes
- c. Operating procedures, instrumentation (including indicators and annunciators), and control functions are adequate to initiate systems as required to maintain adequate core cooling? Yes
- 9. If the answer to any part of question 6, 7 or 8 is no, then provide your basis for not performing the maintenance, surveillance and test procedures described and/or the bases for not including the operational features cited. *See note below.
- Note: For questions involving supporting type information (question numbers 5 and 9) instead of developing and supplying the information in response to this letter, you may ommit to further evaluate the need for such provisions during the performance of your individual plant examination for severe accident vulnerabilities (IPE). If you select this option, you are required to:
(1) So state in response to these questions, and (2) Commit to explicitly address questions 5 and 9 in your IPE submittal per the guidelines outlined in NUREG-1335 (Section 2.1.6, Subitem 7),
" Individual Plant Examination: Submittal Guidance."
l l
____ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _