Proposed Tech Spec Changes Revising Sections 6.5.2 & 6.2.3 to Require Minutes of Safety Review Committee Meetings Be Approved within 6 Wks Following MeetingML20064N917 |
Person / Time |
---|
Site: |
Waterford |
---|
Issue date: |
02/11/1983 |
---|
From: |
LOUISIANA POWER & LIGHT CO. |
---|
To: |
|
---|
Shared Package |
---|
ML20064N902 |
List: |
---|
References |
---|
NUDOCS 8302160378 |
Download: ML20064N917 (8) |
|
|
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20217K9011999-10-18018 October 1999 Proposed Tech Specs 3.6.2.2 Loc,Allowing Plant to Operate with Two Independent Trains of Containment Cooling, Consisting of One Fan Cooler Per Train,Operable During Modes 1,2,3 & 4 ML20211F3701999-08-24024 August 1999 Proposed Tech Specs,Revising Efas,Originally Submitted on 980702 as TS Change Request NPF-38-207 ML20211F5501999-08-24024 August 1999 Proposed Tech Specs Page Xviii, Index Administrative Controls, Originally Submitted with TS Change Request NPF-38-220 ML20210M9681999-08-0404 August 1999 Existing & Proposed marked-up TS Pages Modifying TS 3.5.2 by Extending AOT to Seven Days for One LPSI Train Inoperable & AOT of 72 Hours Imposed for Other Conditions ML20210M9861999-08-0404 August 1999 Existing & Proposed TS Pages Modifying TS 3.5.2 by Extending AOT to Seven Days for One HPSI Train Inoperable & TS 3.5.3, Changing end-state to Hot Shutdown with at Least One Operable Shutdown ML20210H2371999-07-29029 July 1999 Proposed Tech Specs 3.6.2.1 Extending Allowable Outage Time to Seven Days for One Containment Spray Sys Train Inoperable ML20210H1771999-07-29029 July 1999 Proposed Tech Specs 3.8.1.1 Re EDG AOT Increase from 72 H to Ten Days ML20210B3411999-07-19019 July 1999 Proposed Tech Specs 4.5.2.f.2,increasing Performance Requirement for LPSI Pumps ML20209H3191999-07-15015 July 1999 Proposed Tech Specs Pages Modifying TS 3/4.4.8.1,Figures 3.4-2 & 3.4-3 to Extend RCS Pressure Temperature Curves to 20 EFPY ML20210D0521999-07-15015 July 1999 Proposed Tech Specs Creating New TS for Feedwater Isolation Valves ML20210D1071999-07-15015 July 1999 Proposed Tech Specs Adding TS Bases Control Program to TS Administrative Controls Section & Correcting Editorial Error Identified in TS Following Issuance of Amend 146,dtd 981019 ML20209D4091999-07-0707 July 1999 Proposed Tech Specs,Revising Actions 19 & 20 for Table 3.3-3 for Functional Unit 7 Emergency Feedwater, Items B & C,Per 980702 TS Change Request NPF-38-207 ML20195B1811999-05-20020 May 1999 Proposed Tech Specs Changes to Bases B 3/4.3.1 & 3/4.3.2, B 3/4.6.3,B 3/4.7.1.2 & B 3/4.7.12 ML20203C4891999-02-0505 February 1999 Proposed Revised Tech Specs Pages 3/4 3-12a & B 3/4 3-1a Re Reactor Trip Circuit Breaker Surveillance Interval Extension ML20199E0861999-01-12012 January 1999 Proposed Tech Specs Re Rev 1 for TS Change Request NPF-38-174 ML20199D9851999-01-12012 January 1999 Proposed Tech Specs,Adding Requirement That CR Intake Monitors Be Operable & SRs Be Applicable During Movement of Irradiated Fuel ML20198G2401998-12-23023 December 1998 Proposed Tech Specs,Modifying LCO for 3.3.3.7.1 for Chlorine Detection Sys by Changing Alarm/Trip Setpoint from 3 Ppm to 2 Ppm ML20196D2181998-11-30030 November 1998 Proposed Tech Specs Pages 3/4 8-8,3/4 9-8,3/4 9-9 & B 3/4 9-2,revised for Consistency Between Action Statements & NUREG-1432,Rev 1, Std Tech Specs for CE Plants ML20154E4171998-10-0606 October 1998 Proposed Tech Specs Pages Re TS Change Request NPF-38-212, Modifying Requirement to Perform Mtc Test Near End of Each Cycle ML20154E1141998-10-0101 October 1998 Proposed Tech Specs Modifying TS 3.3.3.7.3 & SR 4.3.3.7.3 for Broad Range Gas Sys ML20153D5771998-09-23023 September 1998 Proposed Tech Specs Revising Description Re Reactor Power Input Used by Operating Bypass Permissive & Trip Enable of 10-4% Bistable ML20153B4441998-09-18018 September 1998 Proposed Tech Specs Modifying Notes in Tables 2.2-1 & 3.3-1 Re Reactor Protective Instrumentation ML20151W5971998-09-11011 September 1998 Proposed Tech Specs Re Notes in Table 2.2-1 Re Reactor Protective Instrumentation Trip Setpoints Limits & Table 3.3-1 Re Reactor Protective Instrumentation ML20237A7921998-08-12012 August 1998 Proposed Tech Specs,Increasing Max Boron Concentration in SITs & Rwsp from 2300 Ppm to 2900 Ppm ML20236U7361998-07-29029 July 1998 Proposed Tech Specs Pages Revising TS 6.9.1.11.1 to Replace Ref to Abb Combustion Engineering SBLOCA ECCS Performance Evaluation Model ML20236H1501998-07-0202 July 1998 Proposed Tech Specs Section 3/4.3.2,adding Restriction on Period of Time Channel of Efas Instrumentation Can Remain in Tripped Condition ML20249C8321998-06-29029 June 1998 Proposed Tech Specs 3.7.6.1,3.7.6.2,3.7.6.3,3.7.6.4 & 3.7.6.5,revising Control Room Ventilation to Be Consistent w/NUREG-1432 ML20249C7901998-06-29029 June 1998 Proposed Tech Specs Adding Footnote to Action Statements to Allow CR Ventilation Sys to Be Unisolated Periodically Under Administrative Controls ML20249A3101998-06-12012 June 1998 Proposed Tech Specs Pages,Adding Footnote to TS Refueling Operations,Surveillance Requirements 4.9.7.2,to Effect Limited Deviation to Allow Crane Main Hook Electrical Interlocks to Be Replaced W/Administrative Controls ML20248B7611998-05-28028 May 1998 Proposed TS Pages Supporting Change to TS 3.7.1.2, Surveillance Requirement 4.7.1.2 & Bases for Emergency Feedwater Sys ML20247P2431998-05-21021 May 1998 Proposed Tech Specs Re Design Feature Suppl ML20217P8411998-05-0101 May 1998 Rev TS Pages Changing Actions Required Should Channel of Recirculation Actuation Signal (RAS) Be Placed in Tripped Condition,Replacing TS Pages Submitted in 970603 Submittal ML20217D5181998-03-25025 March 1998 Proposed TS 3.9.8.1,3.9.8.2,TS Action 3.9.8.2a,3.8.1.2 & Bases 3/4.9.8 ML20198R1251998-01-21021 January 1998 Corrections to Proposed Tech Spec 3/4.1 Re Reactivity Control Sys ML20198R3081998-01-21021 January 1998 Errata to Proposed TS Change Request NPF-38-196 Which Changed TS 3.1.1.1,3.1.1.2,3.10.1 & Figure 3.1.-1 by Removing Cycle Dependent B Concentration & Boration Flow Rate from Action Statements ML20197C6431997-12-22022 December 1997 Proposed Tech Specs Page Supplementing TS Change Request NPF-38-186,by Retaining Operations Superintendent in Paragraph 6.2.2.f of Administrative Controls Section ML20199A1101997-11-13013 November 1997 Proposed Tech Specs,Modifying 6.8.4.a, Primary Coolant Sources Outside Containment to Add Portions of Containment Vacuum Relief Sys & Primary Sampling Sys to Program ML20199A0011997-11-13013 November 1997 Errata to Proposed Tech Specs Change Request NPF-38-193, Replacing Pages 13 Through 21 ML20217G2421997-10-0707 October 1997 Proposed Tech Specs Modifying 3.3.3.7.3 & Surveillance Requirement 4.3.3.7.3 for Broad Range Gas Detection Sys ML20211F8141997-09-25025 September 1997 Proposed Tech Specs Pages Modifying LCO 3.6.1.2, Containment Leakage, Associated Action & SR 4.6.1.2 ML20141G7131997-07-0707 July 1997 Proposed Tech Specs Expanding Applicability of TS 3.7.1.3 to Include Mode 4 Operational Requirements & Maintains 91 Percent Minimum Condensate Storage Pool Level Previously Requested for Modes 1,2 & 3 ML20141D8551997-06-26026 June 1997 Proposed Tech Specs Revising TS Tables 3.7-1 & 3.7-2 by Changing MSSVs Orifice Size from 26 Inches to 28.27 Inches & Relocating Orifice Size from TS to TS Bases ML20140B1671997-06-0303 June 1997 Proposed Tech Specs,Modifying Action Requirements for TS 3/4.3.2 for SI Sys Sump Recirculation Actuation Signal ML20148G6631997-06-0303 June 1997 Proposed Tech Specs,Requesting Minimum Required Level in Condensate Storage Pool Be Increased from 82% to 91% to Account for Vortexing & Instrumentation Measurement Uncertainties ML20141K1741997-05-24024 May 1997 Proposed Tech Specs 3.1.1.1,3.1.1.2,3.10.1 & Figure 3.1-1, Removing Cycle Dependent Boron Concentration ML20141K1951997-05-24024 May 1997 Proposed Tech Specs 3/4.7.4 Modifying Ultimate Heat Sink, Table 3.7-3,by Incorporating More Restrictive Dry Cooling Tower Fan Requirements & Changes Wet Cooling Tower Water Consumption in TS Bases ML20140H0831997-05-0606 May 1997 Proposed Tech Specs Modifying Wording of SR 4.5.2.j by Replacing Venting ECCS Pump Casings & Discharge Piping High Points, with Verifying ECCS Piping Is Full of Water ML20140C8881997-04-17017 April 1997 Proposed Tech Specs,Replacing Attachment to Waterford 3 Submittal W3F1-97-0067,dtd 970407,correcting Oversight ML20137T4051997-04-11011 April 1997 Proposed Tech Specs,Modifying TS 3.3.3.7.3 & SR 4.3.3.7.3 for Broad Range Gas Detection Sys ML20137T4541997-04-11011 April 1997 Proposed Tech Specs Making TS 3.6.2.2 & Surveillance Requirement 4.6.2.2 Consistent W/Containment Cooling Assumptions in Waterford 3 Containment Analysis 1999-08-04
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20217K9011999-10-18018 October 1999 Proposed Tech Specs 3.6.2.2 Loc,Allowing Plant to Operate with Two Independent Trains of Containment Cooling, Consisting of One Fan Cooler Per Train,Operable During Modes 1,2,3 & 4 ML20211F5501999-08-24024 August 1999 Proposed Tech Specs Page Xviii, Index Administrative Controls, Originally Submitted with TS Change Request NPF-38-220 ML20211F3701999-08-24024 August 1999 Proposed Tech Specs,Revising Efas,Originally Submitted on 980702 as TS Change Request NPF-38-207 ML20210M9681999-08-0404 August 1999 Existing & Proposed marked-up TS Pages Modifying TS 3.5.2 by Extending AOT to Seven Days for One LPSI Train Inoperable & AOT of 72 Hours Imposed for Other Conditions ML20210M9861999-08-0404 August 1999 Existing & Proposed TS Pages Modifying TS 3.5.2 by Extending AOT to Seven Days for One HPSI Train Inoperable & TS 3.5.3, Changing end-state to Hot Shutdown with at Least One Operable Shutdown ML20210H1771999-07-29029 July 1999 Proposed Tech Specs 3.8.1.1 Re EDG AOT Increase from 72 H to Ten Days ML20210H2371999-07-29029 July 1999 Proposed Tech Specs 3.6.2.1 Extending Allowable Outage Time to Seven Days for One Containment Spray Sys Train Inoperable ML20210B3411999-07-19019 July 1999 Proposed Tech Specs 4.5.2.f.2,increasing Performance Requirement for LPSI Pumps ML20210D0521999-07-15015 July 1999 Proposed Tech Specs Creating New TS for Feedwater Isolation Valves ML20210D1071999-07-15015 July 1999 Proposed Tech Specs Adding TS Bases Control Program to TS Administrative Controls Section & Correcting Editorial Error Identified in TS Following Issuance of Amend 146,dtd 981019 ML20209H3191999-07-15015 July 1999 Proposed Tech Specs Pages Modifying TS 3/4.4.8.1,Figures 3.4-2 & 3.4-3 to Extend RCS Pressure Temperature Curves to 20 EFPY ML20209D4091999-07-0707 July 1999 Proposed Tech Specs,Revising Actions 19 & 20 for Table 3.3-3 for Functional Unit 7 Emergency Feedwater, Items B & C,Per 980702 TS Change Request NPF-38-207 ML20196E9971999-05-24024 May 1999 Rev 3 to NTP-203, Emergency Plan Training ML20195B1811999-05-20020 May 1999 Proposed Tech Specs Changes to Bases B 3/4.3.1 & 3/4.3.2, B 3/4.6.3,B 3/4.7.1.2 & B 3/4.7.12 ML20204H2591999-03-16016 March 1999 Rev 0 to STD-100-237, Procedure for Modification of RCS Pressure Boundary for Installation of Mechanical Nozzle Seal Assemblies (Mnsa) for Waterford Nuclear Generating Station Unit 3 ML20204H2511999-03-16016 March 1999 Rev 1 to C-NOME-EP-0189, Engineering Procedure for Installation of Mechanical Nozzle Seal Assemblies for Waterford 3 ML20203C4891999-02-0505 February 1999 Proposed Revised Tech Specs Pages 3/4 3-12a & B 3/4 3-1a Re Reactor Trip Circuit Breaker Surveillance Interval Extension ML20199D9851999-01-12012 January 1999 Proposed Tech Specs,Adding Requirement That CR Intake Monitors Be Operable & SRs Be Applicable During Movement of Irradiated Fuel ML20199E0861999-01-12012 January 1999 Proposed Tech Specs Re Rev 1 for TS Change Request NPF-38-174 ML20198G2401998-12-23023 December 1998 Proposed Tech Specs,Modifying LCO for 3.3.3.7.1 for Chlorine Detection Sys by Changing Alarm/Trip Setpoint from 3 Ppm to 2 Ppm ML20196D2181998-11-30030 November 1998 Proposed Tech Specs Pages 3/4 8-8,3/4 9-8,3/4 9-9 & B 3/4 9-2,revised for Consistency Between Action Statements & NUREG-1432,Rev 1, Std Tech Specs for CE Plants ML20154E4171998-10-0606 October 1998 Proposed Tech Specs Pages Re TS Change Request NPF-38-212, Modifying Requirement to Perform Mtc Test Near End of Each Cycle ML20154E1141998-10-0101 October 1998 Proposed Tech Specs Modifying TS 3.3.3.7.3 & SR 4.3.3.7.3 for Broad Range Gas Sys ML20153D5771998-09-23023 September 1998 Proposed Tech Specs Revising Description Re Reactor Power Input Used by Operating Bypass Permissive & Trip Enable of 10-4% Bistable ML20153B4441998-09-18018 September 1998 Proposed Tech Specs Modifying Notes in Tables 2.2-1 & 3.3-1 Re Reactor Protective Instrumentation ML20151W5971998-09-11011 September 1998 Proposed Tech Specs Re Notes in Table 2.2-1 Re Reactor Protective Instrumentation Trip Setpoints Limits & Table 3.3-1 Re Reactor Protective Instrumentation ML20237A7921998-08-12012 August 1998 Proposed Tech Specs,Increasing Max Boron Concentration in SITs & Rwsp from 2300 Ppm to 2900 Ppm ML20236U7361998-07-29029 July 1998 Proposed Tech Specs Pages Revising TS 6.9.1.11.1 to Replace Ref to Abb Combustion Engineering SBLOCA ECCS Performance Evaluation Model ML20236H1501998-07-0202 July 1998 Proposed Tech Specs Section 3/4.3.2,adding Restriction on Period of Time Channel of Efas Instrumentation Can Remain in Tripped Condition ML20249C8321998-06-29029 June 1998 Proposed Tech Specs 3.7.6.1,3.7.6.2,3.7.6.3,3.7.6.4 & 3.7.6.5,revising Control Room Ventilation to Be Consistent w/NUREG-1432 ML20249C7901998-06-29029 June 1998 Proposed Tech Specs Adding Footnote to Action Statements to Allow CR Ventilation Sys to Be Unisolated Periodically Under Administrative Controls ML20249A3101998-06-12012 June 1998 Proposed Tech Specs Pages,Adding Footnote to TS Refueling Operations,Surveillance Requirements 4.9.7.2,to Effect Limited Deviation to Allow Crane Main Hook Electrical Interlocks to Be Replaced W/Administrative Controls ML20248B7611998-05-28028 May 1998 Proposed TS Pages Supporting Change to TS 3.7.1.2, Surveillance Requirement 4.7.1.2 & Bases for Emergency Feedwater Sys ML20248H7871998-05-25025 May 1998 Rev 1 to Waterford Unit 3 Second Interval ISI Plan ML20247P2431998-05-21021 May 1998 Proposed Tech Specs Re Design Feature Suppl ML20217P8411998-05-0101 May 1998 Rev TS Pages Changing Actions Required Should Channel of Recirculation Actuation Signal (RAS) Be Placed in Tripped Condition,Replacing TS Pages Submitted in 970603 Submittal ML20217L9971998-04-30030 April 1998 Small Break LOCA ECCS Performance Analysis Using Abb/Ce Suppl 2 Model ML20217D5181998-03-25025 March 1998 Proposed TS 3.9.8.1,3.9.8.2,TS Action 3.9.8.2a,3.8.1.2 & Bases 3/4.9.8 ML20198R3081998-01-21021 January 1998 Errata to Proposed TS Change Request NPF-38-196 Which Changed TS 3.1.1.1,3.1.1.2,3.10.1 & Figure 3.1.-1 by Removing Cycle Dependent B Concentration & Boration Flow Rate from Action Statements ML20198R1251998-01-21021 January 1998 Corrections to Proposed Tech Spec 3/4.1 Re Reactivity Control Sys ML20197C6431997-12-22022 December 1997 Proposed Tech Specs Page Supplementing TS Change Request NPF-38-186,by Retaining Operations Superintendent in Paragraph 6.2.2.f of Administrative Controls Section ML20202C2911997-12-0101 December 1997 Rev 0 to Pump & Valve Inservice Test Plan for Second 10-Yr Interval. Page 23 of Incoming Submittal Not Included ML20199A0011997-11-13013 November 1997 Errata to Proposed Tech Specs Change Request NPF-38-193, Replacing Pages 13 Through 21 ML20199A1101997-11-13013 November 1997 Proposed Tech Specs,Modifying 6.8.4.a, Primary Coolant Sources Outside Containment to Add Portions of Containment Vacuum Relief Sys & Primary Sampling Sys to Program ML20217M0221997-10-28028 October 1997 Rev 8 to RW-001-210, Process Control Program ML20217H5931997-10-14014 October 1997 Revised Page of App B of FOL, Environ Protection Plan (Nonradiological) ML20217G2421997-10-0707 October 1997 Proposed Tech Specs Modifying 3.3.3.7.3 & Surveillance Requirement 4.3.3.7.3 for Broad Range Gas Detection Sys ML20211F8141997-09-25025 September 1997 Proposed Tech Specs Pages Modifying LCO 3.6.1.2, Containment Leakage, Associated Action & SR 4.6.1.2 ML20141G7131997-07-0707 July 1997 Proposed Tech Specs Expanding Applicability of TS 3.7.1.3 to Include Mode 4 Operational Requirements & Maintains 91 Percent Minimum Condensate Storage Pool Level Previously Requested for Modes 1,2 & 3 ML20141D8551997-06-26026 June 1997 Proposed Tech Specs Revising TS Tables 3.7-1 & 3.7-2 by Changing MSSVs Orifice Size from 26 Inches to 28.27 Inches & Relocating Orifice Size from TS to TS Bases 1999-08-04
[Table view] |
Text
.
i 6.2.3 ONSITE SAFETY REVIEW SUBGROUP (OSRS)
FUNCTION 6.2.3.1 The Independent Safety Engineering Group (ISEG) section of OSRS shall function to examine plant operating characteristics, NRC issuances, industry advisories, Licensee Event Reports and other sources of plant design and operating experience information, including plants of similar design, which may indicate areas for improving plant safety.
The Operations' Assessment Section (OAS) of OSRS shall function to identify risks which are/or may be too high by performing independent review of the activities listed in 6.2.3.3.b. , including the areas of:
- a. nuclear power plant operation
- b. nuclear engineering
- c. chemistry and radiochemistry
- d. metallurgy
- e. instrumentation and contror
- f. radiological safety
- g. mechanical and electrical engineering
- h. quality assurance practices COMPOSITION 6.2.3.2 The OSRS is composed of two sections, the ISEG and OAS. The ISEG includes at least five full-time engineers located on site. Each member of ISEG shall have a bachelor's degree in engineering or related science and at least two years professional level experience in his field. The OAS, supplemented through outside consultants or organiza-tions, includes sufficient expertise for reviews of operational phase activities.
RESPONSIBILITIES 6.2.3.3.
- a. The ISEG shall be responsible for the following:
- 1. Reviewing and assessing plant activities to identify areas with significant risk potential.
7002160378 930211 PDR ADOCK 05000382 A PDR
- 2. Evaluating the technical adequacy and clarity of selected plant procedures and.their consistency with related proce-dures.
- 3. Evaluating the effectiveness of Quality Assurance activities
~to meet 0A program objectives and. commitments.
4 '. Reviewing snplanned plant transients, personnel errors and safety-related equipment failures to idertify root causes and potential risks'and to make recommendations, if appropriate to reduce risks.
- b. The OAS shall be responsible for the following:
- 1. Reviewing safety evaluations for 1) changes to procedures, equipment or systems, and 2) tests or experiments completed under the provision of section 50.59, 10CFR, to verify that such actions did not involve an unreviewed safety question.
- 2. Reviewing proposed changes to procedures, equipment or systems
.which. involve an unreviewed safety question as defined in section 50.59, 10CFR.
- 3. Reviewing proposed tests or experiments which involve an un-reviewed safety question as defined in section 50.59, 10CFR.
- 4. Reviewing proposed changes to Technical Specifications or the Operating License.
- 5. Reviewing violations of codes,' regulations, orders, Technica,l' Specifications, license requirements, or of internal procedures or instructions, having nuclear safety significance.
- 6. Reviewing all recognized indications of an unanticipated de-ficiency in some aspect of design or operation of structures, systems, or components that could. affect nuclear safety.
- 7. Reviewing significant operating abnormalities or deviations from normal and expected performance of unit equipment that affect nuclear safety.
AUTHORITY 6.2.3.4 The OSRS shall make detailed recommendations for revised procedures, equipment modification, maintenance activities, operations activities or other means of improving plant safety to the Nuclear Project Support Group Manager. In addition, the OAS shall report identified risks which it determines to be significant to the-SRC.
l'
. ~ , - _ _ _ _ _ . _ , , , - - - .-
a 6.5.2 SAFETY REVIEW COMMITTEE (SRC)
FUNCTION 6.5.2.1 The SRC is responsible to the Senior Vice President-Op rations, for identifying and evaluating significant risks which contribute to the potential for nuclear accidents and radiation exposure. For risks which are judged by it to be too high or too uncertain, the SRC will recommend what steps should be taken to further evaluate and/or to reduce them to acceptable levels.
The SRC will examine and judge the effectiveness of the overall Waterford 3 system for controlling risks, including the effec-tiveness of PORC, the Onsite Safety Review Subgroup and quality assurance activities.
COMPOSITION 6.5.2.2 The Senior Vice President-Operations shall appoint, and may remove, the Chairman of the Sac. The Chairman shall appoint, and may remove, the Vice Chairman, SRC memoers and a permanent SRC Secretary, and shall establish a plan for implementing SRC functions.
The SRC will have no less than 9, nor more than 12, members. No more than a minority of the members will have direct line responsibility for operation of the Waterford 3 SES. The Waterford 3 SES Plant Manager-Nuclear, Project Support Manager-Nuclear, Quality Assurance Manager, Training Director-Nuclear, and the Onsite Safety Review Subgroup Engineering Supervisor
will be members of the SRC. At least 2 members shall be from outside the LP&L employee group, or that of its parent or sister organizations. Other members will be selected from within LP&L or its parent or sister organizations.
Tho objective of member selection shall be to encourage compe-tant critical review of Waterford 3 safety. Minimum qualifica-tions of SRC members who are in line positions in LP&L will be those of their respective line positions. Members other than those in line positions must have a Bachelor's degree or equivalent in engineering, science, or the discipline he repre-sents, plus at least eight years of related professional exper-ionce, five of which have been in connection with nuclear power plants. The Chairman may make exceptions if he determines a potential member has equivalent skills, knowledge, and training.
ALTERNATES l
6.5.2.3 In the interest of preserving member continuity and contact, and recognizing the overview stature of the Committee, no alternate members shall be appointed.
CONSULTANTS 6.5.2.4 The SRC Chairman has the authority to engage the services of others, inside and outside of LP&L; to conduct
! investigations needed to carry out SRC responsibilities.
l MEETING FREQUENCY j 6.5.2.5 The SRC shall meet at least once per calendar quarter l
during the initial year of unit operation following fuel loading and at least once every six months thereafter.
cm-6.5.2.6 Ths praccnca of tho Chairman or Vice Chairman is required at'any m3ating of the SRC. ThD quorum required to constitute a echeduled meeting is the physical presence in the same place of half of the members plus one. .
REVIEW 6.5.2.7 The SRC shall:
- a. Review:
- 1. Those operating abnormalities or deviations from normal and expected performance of unit equipment determined to be significant by the OSRS.
- 2. Events requiring 24-hour written notification to the Commission determined to be significant by the PORC.
- 3. Reports forwarded to the SRC by the PORC.
- 4. Selected results of reviews included in 6.5.2.7.b for the purpose of carrying out its responsibilities under that section.
- b. Maintain cognizance o.f, evaluate the adequacy of, and recommend improvements (as appropriate) in the LP&L processes for review of the following:
- 1. The safety evaluations for (1) changes to pro-
! cedures, equipment, or systems; and (2) tests t
i or experiments completed under the provision of
! Section 50.59, 10 CFR, to verify that such l
actions did not constitute an,unreviewed safety ,
l question; 2.
Proposed changes to procedures, equipment, or systems which involve an unreviewed safety question as defined in Section 50.59, 10 CFR;
- 3. Proposed tests or experiments which involve an unreviewed safety question as cefined in Section 50.59, 10 CFR;
- 4. Proposed changes to Technical Specifications or this Operating License;
- 5. Violations of codes, regulations, orders, Tech-nical Specifications, license requirements, or of internal procedures or instructions having nuclear safety significance;
- 6. Significant operating abnormalities or deviations from normal and expected performance of unit equip-ment that affect nuclear safety, except as noted in 6.5.2.7.a;
- 7. Events requiring 24-hour written notification to the Commission,except as noted in 6.5.2.7.a;
- 8. All recognized indications of an unanticipated deficiency in some aspect of design or operation of structures, systems, or components that could affect nuclear safety; and
- 9. Reports and meeting minutes of the PORC.
AUTHORITY 6.5.2.8 The SRC shall report to, and advise, the Senior Vice i Presideht-Operations in accordance with responsibility specified in Sectionc 6.5.2.1 and 6.5.2.7.
RECORDS 6.5.2.9 Summary minutes will be prepared for each meeting and will be approved by the SRC within six (6) weeks after the meeting.
=
In each instance where the SRC perceives that action should be taken to reduce a risk'or to improve the Waterford 3 risk control process, it will make a formal written recommendation to this offect. Formal SRC recommendations will be addressed to the SVP-O and the VP-NO.
6.543 Quality Assurance AUDITS 6.5.3.1 The Quality Assurance Organization audits plant activities for conformance with regulations, programs, plans, procedures, codes and other specified requirements. Results shall be reported to the line manager responsible for the area audited. Signifi-cant non-conformance shall be reported to the Senior Vice President-Operations and the SRC. These audits shall include:
- a. The conformance of unit operation to provisions contained within the Technical Specifications and applicable license conditions at least once per 12 months.
- b. The performance, training and qualifications of the entire unit staff at least once per 12 months.
- c. The results of actions taken to correct deficiencies occurring in unit equipment, structures, systems or method of operation that affect nuclear safety at least once per 6 months.
- d. The performance of activities required by the Opera-tional Quality Assurance Program to meet the criteria of Appendix "B", 10 CFR 50, at least once per 24 months.
~
- e. Any other area of unit operation considered appro-priate by the SRC or the Senior Vice President-Operations.
The Firs Protection Program and implementing procedures at least once per 24 months.
- f. An independent fire protection and loss prevention inspection and audit shall be performed annually utilizing either qualified offsite licensee personnel or an outside fire protection firm.
- g. An inspection and audit of the fire protecticn and loss prevention program shall be performed by an outside qualified fire consultant at intervals no greater than 3 years. ' ~
- h. The radiological environmental monitoring program and the results thereof at least once per 12 months.
- i. The Offsite Dose Calculation Manual (ODCM) and imple-I menting procedures at least once per 24 months.
l l
J. The Process Control Program and implementing procedures l
l for solidification of radioactive wastes at least once I
per 24 months.
- k. ,The performance of activities required by the Quality Assurance Program to meet the criteria of Regulatory Guide 4, 15, December 1977 at least once per 12 months.
6.5.3.2 The SRC will review the results of the annual management l
l audit of the Waterford 3 QA Program which is performed by a manage-m:nt audit group appointed by the SVP-O and is independent of the LP&L QA section.