Schedule Revisions for the Subsequent License Renewal Application Review
ML19206A651
Person / Time
Site: Surry  
Issue date: 07/31/2019
From: Eric Oesterle
NRC/NRR/DMLR/MRPB
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
Tran T, NRR-DMLR 415-3617
References
EPID L-2018-RNW-0024
Download: ML19206A651 (5)


Text

July 31, 2019 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Blvd Glen Allen, VA 29060

SUBJECT:

SURRY POWER STATION, UNIT NOS. 1 AND 2 - SCHEDULE REVISION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NO.

L-2018-RNW-0024)

Dear Mr. Stoddard:

By letter dated October 15, 2018 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML18291A842), as supplemented by letters dated January 29, 2019 (ADAMS Accession No. ML19042A137), and April 2, 2019 (ADAMS Accession No. ML19095A666), and June 10, 2019 (ADAMS Accession No. ML19168A028) the Virginia Electric and Power Company (Dominion Energy Virginia or Dominion) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-32 and DPR-37 for the Surry Power Station, Units 1 and 2 (Surry). Dominion submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

The purpose of this letter is to inform you of a change in the environmental review schedule for the Surry subsequent license renewal application. The scheduled date for Issue Draft SEIS

[Supplemental Environmental Impact Statement] is revised from September 2019 to October 2019 to support workload priorites and resource constraints. Also, a determination on whether to hold a public meeting on the DSEIS will be made based on the level of public interest and comments received. The overall schedule for issuance of the renewed license is currently not impacted. Enclosure 1 of this letter provides the staffs revised review schedule for the Surry subsequent license renewal application.

If you have any questions related to this review schedule, please contact Emmanual Sayoc at 301-415-4084 or by e-mail at Emmanuel.Sayoc@nrc.gov for the safety review or Tam Tran at 301-415-3617 or by e-mail at Tam.Tran@nrc.gov, for the environmental review of the Surry subsequent license renewal application.

Sincerely,

/RA/

Eric. R. Oesterle, Chief License Renewal Project Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281

Enclosure:

Revised Review Schedule cc w/encl: Listserv

ML19206A651

  • concurred by email OFFICE PM:MRPB:DMLR PM:MRPB:DMLR* LA:MRPB:DMLR PM:MRPB:DMLR*

NAME TTran ESayoc YEdmonds AWu DATE 7/29/19 7/29/19 7/30/19 7/26/19 OFFICE BC:MENB:DMLR (A) D:DMLR BC:MRPB:DMLR NAME BBeasley JDonoghue EOesterle DATE 7/31/19 7/31/19 7/31/19

Enclosure SURRY POWER STATION, UNIT NOS. 1 AND 2 Revised Subsequent License Renewal Application Review Schedule Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 10/2018 10/15/2018 Publish Federal Register Notice (FRN) - LRA Availability 11/2018 11/01/2018 Publish FRN - Docketing Acceptance/Rejection and Opportunity for Hearing 12/2018 12/10/2018 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 12/2018 12/20/2018 Public Meeting - Overview of Subsequent License Renewal Process and Environmental Scoping 1/2019 1/8/2019 Environmental Scoping Period Ends 2/2019 1/22/2019 Deadline for Filing Hearing Requests and Petitions for Intervention 2/2019 2/15/2019 Issue Draft Supplemental Environmental Impact Statement (DSEIS) 10/2019 Public Meeting - Draft SEIS Meeting, If Needed TBA*

End of DSEIS Comment Period 11/2019 Issue Safety Evaluation Report (SER) 11/2019 Advisory Committee on Reactor Safeguards (ACRS)

Subcommittee Meeting 2/2020 Issue Final SEIS 4/2020 U.S. Environmental Protection Agency FRN Published

- Availability of Final SEIS 4/2020 ACRS Full Committee Meeting 4/2020 Decision - Director, NRR 6/2020

(*) to be assessed based on the level of public interest and comments received.