SVPLTR 16-0027, 2016 Dresden Nuclear Station Initial License Examination Proposed Exam Files - Licensee Letter Transmitting the Proposed Examination/Test to the NRC

From kanterella
(Redirected from ML16336A812)
Jump to navigation Jump to search
2016 Dresden Nuclear Station Initial License Examination Proposed Exam Files - Licensee Letter Transmitting the Proposed Examination/Test to the NRC
ML16336A812
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 12/01/2016
From: Karaba P
Exelon Generation Co
To: Palagi B
NRC/RGN-III
Shared Package
ML16257A679 List:
References
SVPLTR 16-0027
Download: ML16336A812 (2)


Text

Dresden Generating Station

,£J7F 6500 North Dresden Road Exelon Generation Morris. IL 60450 www.exeloncorp.com June 13, 2016 SVPLTR: #16-0027 Regional Administrator, Region Ill U.S. Nuclear Regulatory Commission 2443 Warrenville Road Lisle, IL 60532-4352 Dresden Nuclear Power Station, Units 2 and 3 Facility Operating License Nos.DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

Submittal of Integrated Initial License Training Examination Materials Enclosed are the examination materials, which Dresden Nuclear Power Station is submitting in support of the initial license exam scheduled for the weeks of August 08, 2016, through August 19, 2016, at the Dresden Nuclear Power Station.

This submittal includes the Senior Reactor Operator and Reactor Operator Written Examinations, Job Performance Measures, and Integrated Plant Operation Scenario Guides.

These examination materials have been developed in accordance with NUREG-1 021, "Operator Licensing Examination Standards for Power Reactors," Revision 10. Please note that reference materials are attached to each individual examination question or item.

Some minor modifications have been made to the Integrated Examination Outline with regards to the operational scenarios in order to improve balance and content. These changes improve examination quality and are in compliance with NUREG-1 021, Revision 10, "Operator Licensing Examination Standards."

Some modifications or adjustments to the examination material may be required due to procedural changes.

In accordance with NUREG-1 021, Revision 10, Section ES-201, please ensure that these materials are withheld from public disclosure until after the examinations are complete.

Should you have any questions concerning this letter, please contact Bruce Franzen at 815 416-2800. For questions concerning examination materials, please contact Wayne Cope at 815 416-4053.

Respectfully, l<J~

.::::;-:..A,._~ c<< -P. ~&> lo ..__

P Karaba Site Vice President Dresden Nuclear Power Station

Enclosures:

(Hand delivered to Bruce Palagi, NRC Region Ill)

RO/SRO Composite Examination with references attached Control Room Systems and Facility Walk-Through Job Performance Measures with references attached Administrative Topic Job Performance Measures with references attached Integrated Plant Operation Scenario Guides Completed Checklists:

Operating Test Quality Checklist (Form ES-301-3)

Simulator Scenario Quality Checklist (Form ES-301-4}

Transient and Event Checklist (Form ES-301-5)

Competencies Checklist (Form ES-301-6)

BWR Examination Outline (Forms ES-401-1 and ES-401-3)

Written Exam Quality Checklist (Form ES-401-6)

Examination Security Agreements (Form ES-201-3)

Record of Rejected K/As (Form ES-401-4) cc: (without attachments)

Chief, NRC Operator Licensing Branch NRC Senior Resident Inspector- Dresden Nuclear Power Station Bee: Station Project Manager, NRR Site Vice President - Dresden Regulatory Assurance Manager - Dresden Vice President - Licensing and Regulatory Affairs Director, Licensing Exelon Document Control Desk Licensing (Electronic Copy)

Human Resources - Dresden Station Training Manager - Dresden Station