Other: CP-201600814, And ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)), CP-201600932, & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201600933, And Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201600934, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)), CP-201600936, Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201601011, Submittal of Amendment No. 13 to Indemnity Agreement No. B-96, CP-201700082, Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, ML15351A050, ML15351A053, ML16032A349, ML16076A163
|
MONTHYEARCP-201501062, ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments2015-11-12012 November 2015 ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request CP-201501130, ISFSI - Transmittal of Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2015-12-0909 December 2015 ISFSI - Transmittal of Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request ML15348A0182015-12-14014 December 2015 NRR E-mail Capture - Acceptance Review - Application for Order Approving Transfer of Licenses and Conforming License Amendments - CACs MF7075 and MF7076 Project stage: Acceptance Review ML15351A0572016-01-19019 January 2016 Request for Withholding Information from Public Disclosure, Affidavit Dated 12/9/15 Executed by T. Mccool, Luminant Generation Company LLC Balance Sheets (CAC MF7075-MF7076) Project stage: Withholding Request Acceptance ML15351A0502016-01-27027 January 2016 Independent Spent Fuel Storage Installation - Letter, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendment, and Opportunity for a Hearing Project stage: Other ML15351A0532016-01-27027 January 2016 Independent Spent Fuel Storage Installation - FRN, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendment, and Opportunity for a Hearing Project stage: Other ML16032A3492016-02-0202 February 2016 Independent Spent Fuel Storage Installation - Correction Letter, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for a Hearing (CAC MF7075-MF7076) Project stage: Other CP-201600092, Guarantees of Payment of Deferred Premiums2016-02-0404 February 2016 Guarantees of Payment of Deferred Premiums Project stage: Request ML16034A1962016-02-0808 February 2016 Independent Spent Fuel Storage Installation - Request for Additional Information, Application for Order Approving Transfer of Facility Operating Licenses and Conforming Amendment Project stage: RAI ML16076A1632016-03-14014 March 2016 Balance Sheets Project stage: Other CP-201600136, And Independent Spent Fuel Storage Installation (Isfsi), Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2016-03-14014 March 2016 And Independent Spent Fuel Storage Installation (Isfsi), Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request CP-201600328, Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-03-29029 March 2016 Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Request ML16085A1482016-04-0606 April 2016 Request for Withholding Information from Public Disclosure - 3/14/16 Affidavit Executed by T. Mccool, Luminant Generation Company LLC Balance Sheets (Proprietary) Project stage: Withholding Request Acceptance CP-201600411, And Independent Spent Fuel Storage Installation - Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2016-04-20020 April 2016 And Independent Spent Fuel Storage Installation - Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request ML16096A2662016-05-0606 May 2016 Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments Project stage: Draft Approval ML16096A2642016-05-0606 May 2016 Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments Project stage: Draft Other ML16096A2552016-05-0606 May 2016 Order Approving Transfer of Licenses and Approving Conforming Amendments Project stage: Request ML16130A6492016-05-0606 May 2016 ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments Project stage: Draft Other NRC-2016-0020, ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments (CAC Nos. MF7075 and MF7076)2016-05-0606 May 2016 ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments (CAC Nos. MF7075 and MF7076) Project stage: Draft Other CP-201600814, And ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-08-16016 August 2016 And ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Other CP-201600932, & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-09-16016 September 2016 & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201600933, And Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-09-21021 September 2016 And Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201600934, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-09-29029 September 2016 Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Other CP-201600936, Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-10-13013 October 2016 Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201601011, Submittal of Amendment No. 13 to Indemnity Agreement No. B-962016-10-19019 October 2016 Submittal of Amendment No. 13 to Indemnity Agreement No. B-96 Project stage: Other CP-201700082, Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2017-01-30030 January 2017 Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other 2016-02-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Ken J. Peters Senior Vice President and Chief Nuclear Officer (Acting)
Attention: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043 lp:"il 6, 2016
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (CAC NOS. MF7075 AND MF7076)
Dear Mr. Peters:
By letter dated March 14, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16076A162), Luminant Generation Company LLC (Luminant Power) submitted an affidavit executed by Mr. Thomas P. McCool, Site Vice President (Acting),
Luminant Generation Company LLC, dated March 14, 2016, requesting that information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
Balance Sheets (Labeled as Enclosure 4 (Proprietary))
A nonproprietary version of the document has been placed in the U.S. Nuclear Regulatory Commission's (NRC's) Public Document Room and added to ADAMS in the NRC Library at Accession No. ML16076A163.
The affidavit stated that the information sought to be withheld is considered to be proprietary for the reasons below:
- a.
This information is and has been held in confidence by Luminant Power and its affiliates;
- b.
This information is of a type that is held in confidence by Luminant Power and its affiliates, and there is a rational basis for doing so because the information contains sensitive financial competitive information concerning Luminant Power affiliates' anticipated revenues and operating expenses.
- c.
This information is being transmitted to the NRC in confidence.
- d.
This information is not available in public sources and could not be gathered readily from other publically available information.
K. Peters
- e. Public disclosure of this information would create substantial harm to the competitive position of Luminant Power by disclosing its internal financial pro form[a] statements and the commercial terms of a unique transaction to other parties whose commercial interests may be adverse to those of Luminant Power.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavits, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at (301) 415 -1233 or via e-mail at Margaret.Watford@nrc.gov.
Docket Nos. 50-445 and 50-446 cc: Distribution via Listserv Sincerely, Margaret M. Watfor, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
ML16085A148 Sincerely, IRA/
Margaret M. Watford, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrPMComanchePeak Resource RidsNrrLAJBurkhardt Resource RidsRgn4MailCenter Resource ETabakov, NRR/DIRS/IFIB OFFICE NRR/DORULPL4-1/PM NRR/DORULPL4-1 /LA NRR/DIRS/IFIB/BC NRR/DORULPL4-1/BC NAME MWatford JBurkhardt A Bowers RPascarelli DATE 3/28/2016 3/28/2016 3/31/2016 4/06/2016