Other: CP-201600814, and ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)), CP-201600932, & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201600933, and Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201600934, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)), CP-201600936, Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, CP-201601011, Submittal of Amendment No. 13 to Indemnity Agreement No. B-96, CP-201700082, Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments, ML15351A050, ML15351A053, ML16032A349, ML16076A163
|
MONTHYEARCP-201500264, Decommissioning Report2015-03-31031 March 2015 Decommissioning Report Project stage: Request CP-201501062, ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments2015-11-12012 November 2015 ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request CP-201501130, ISFSI - Transmittal of Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2015-12-0909 December 2015 ISFSI - Transmittal of Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request ML15348A0182015-12-14014 December 2015 NRR E-mail Capture - Acceptance Review - Application for Order Approving Transfer of Licenses and Conforming License Amendments - CACs MF7075 and MF7076 Project stage: Acceptance Review ML15351A0572016-01-19019 January 2016 Request for Withholding Information from Public Disclosure, Affidavit Dated 12/9/15 Executed by T. Mccool, Luminant Generation Company LLC Balance Sheets (CAC MF7075-MF7076) Project stage: Withholding Request Acceptance ML15351A0502016-01-27027 January 2016 Independent Spent Fuel Storage Installation - Letter, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendment, and Opportunity for a Hearing Project stage: Other ML15351A0532016-01-27027 January 2016 Independent Spent Fuel Storage Installation - FRN, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendment, and Opportunity for a Hearing Project stage: Other ML16032A3492016-02-0202 February 2016 Independent Spent Fuel Storage Installation - Correction Letter, Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for a Hearing (CAC MF7075-MF7076) Project stage: Other ML16034A1962016-02-0808 February 2016 Independent Spent Fuel Storage Installation - Request for Additional Information, Application for Order Approving Transfer of Facility Operating Licenses and Conforming Amendment Project stage: RAI CP-201600136, and Independent Spent Fuel Storage Installation (Isfsi), Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2016-03-14014 March 2016 and Independent Spent Fuel Storage Installation (Isfsi), Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request ML16076A1632016-03-14014 March 2016 Balance Sheets Project stage: Other CP-201600328, Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-03-29029 March 2016 Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Request ML16085A1482016-04-0606 April 2016 Request for Withholding Information from Public Disclosure - 3/14/16 Affidavit Executed by T. Mccool, Luminant Generation Company LLC Balance Sheets (Proprietary) Project stage: Withholding Request Acceptance CP-201600411, and Independent Spent Fuel Storage Installation - Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments2016-04-20020 April 2016 and Independent Spent Fuel Storage Installation - Additional Information Regarding Application for Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Request ML16130A6492016-05-0606 May 2016 ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments Project stage: Draft Other ML16096A2552016-05-0606 May 2016 Order Approving Transfer of Licenses and Approving Conforming Amendments Project stage: Request ML16096A2642016-05-0606 May 2016 Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments Project stage: Draft Other ML16096A2662016-05-0606 May 2016 Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments Project stage: Draft Approval NRC-2016-0020, ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments (CAC Nos. MF7075 and MF7076)2016-05-0606 May 2016 ISFSI - FRN, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming License Amendments (CAC Nos. MF7075 and MF7076) Project stage: Draft Other CP-201600814, and ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-08-16016 August 2016 and ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Other CP-201600932, & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-09-16016 September 2016 & ISFSI - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201600933, and Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-09-21021 September 2016 and Independent Spent Fuel Storage Installation, Submittal of Additional Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201600934, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))2016-09-29029 September 2016 Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) Project stage: Other CP-201600936, Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2016-10-13013 October 2016 Independent Spent Fuel Storage Installation, Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other CP-201601011, Submittal of Amendment No. 13 to Indemnity Agreement No. B-962016-10-19019 October 2016 Submittal of Amendment No. 13 to Indemnity Agreement No. B-96 Project stage: Other CP-201700082, Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments2017-01-30030 January 2017 Independent Spent Fuel Storage Installation (Isfsi), - Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other 2016-02-08
[Table View] |
|
---|
Category:Letter type:CP
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report CP-202300139, (CPNPP) - Property Damage Insurance2023-03-30030 March 2023 (CPNPP) - Property Damage Insurance CP-202300098, (Cpnpp), Annual Report of Changes in Peak Cladding Temperature2023-03-16016 March 2023 (Cpnpp), Annual Report of Changes in Peak Cladding Temperature CP-202200481, Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST)2022-12-0707 December 2022 Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST) CP-202200454, (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 .2022-12-0101 December 2022 (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 . CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200450, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2022-11-16016 November 2022 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202200435, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2022-11-0808 November 2022 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report CP-202200358, (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46)2022-09-14014 September 2022 (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46) CP-202200246, Evacuation Time Estimate Analysis2022-08-25025 August 2022 Evacuation Time Estimate Analysis CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200276, (CPNPP) - Relief Request Application P-1, Inservice Testing (IST)2022-07-20020 July 2022 (CPNPP) - Relief Request Application P-1, Inservice Testing (IST) CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 2024-01-31
[Table view] |
Text
II Thomas P. McCool Luminant Power Site Vice President P 0Box1002 Thomas.McCool@Luminant.com 6322 North FM 56 Glen Rose, TX 76043 Luminant T 254 897 6042 c 817 776 0308 F 254 897 6652 CP-201700082 Ref: 10 CFR50.80 TXX-17010 10 CFR50.90 10 CFR 72.50 January 30, 2017 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Director, Office of Nuclear Reactor Regulation Washington, DC 20555-0001
SUBJECT:
Comanche Peak Nuclear Power Plant (CPNPP) and Independent Spent Fuel Storage Installation (ISFSI), Docket Nos. 50-445, 50-446, 72-74 Information Regarding NRC Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) (CAC NOS. MF7075 and MF7076)
REFERENCES:
- 1. Comanche Peak Nuclear Power Plant, Unit Nos. 1 And 2 And Independent Spent Fuel Storage Installation - Order Approving Transfer of Licenses And Conforming Amendments (CAC NOS. MF7075 AND MF7076), dated May 6, 2016 (ML16096A255)
- 2. Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2 And Independent Spent Fuel Storage Installation - Issuance of Conforming Amendments RE: Transfer of Licenses (CAC NOS. MF8398 AND MF8399), dated October 3, 2016 (ML16266A005) 3.' Luminant Power Letter logged TXX-16105 from Thomas P. McCool to the NRC dated September 21, 2016, Application for Order Approving Transfer of Licenses and Conforming License Amendments (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))
Dear Sir or Madam:
Vistra Operations Company LLC ("Vistra OpCo") hereby submits additional information in connection with the transfer of licenses approved by References 1 and 2.
Reference 1 required the applicants to notify the NRC no later than 120 days after the transfer (i.e.,
October 3, 2016) of any changes to the directors, officers, or executive positions of Reorganized TCEH and its subsidiaries during the first 90 days following the transfers.
During the first 90 days following the transfers there have been no changes to the directors, officers, or executive positions identified in Enclosure 2 of Reference 3. This letter satisfies condition 1 of NRC order in Reference 1 and closes item (9) of regulatory commitment 5178508.
U. S. Nuclear Regulatory Commission TXX-17010 Page 2 of 2 01 /30/2017 of this letter provides an updated status of regulatory commitment 5178508 to reflect the additional information provided by this letter.
If you have any questions regarding this submittal, please contact Carl B. Corbin at (254) 897-0121 or carl.corbin@luminant.com.
I state under penalty of perjury that the foregoing is true and correct.
Executed on January 30, 2017.
Sincerely, Vistra Operations Company LLC
~ol Site Vice President Updated Regulatory Commitment c -.
William M. Dean, Director, Office of Nuclear Reactor Regulation Kriss Kennedy, Region IV Margaret M. Watford, NRR Resident Inspectors, Comanche Peak Mr. Robert Free Environmental Monitoring & Emergency Response Manager Texas Department of State Health Services Mail Code 1986 P. 0. Box 149347 Austin TX, 78714-9347 to TXX-17010 Page 1of2 Updated Regulatory Commitment (Number 5178508)
(1) Luminant Power will notify the NRC if at any time prior to the NRC consent to the requested transfer, the following item changes: Any entity of the Reorganized TCEH acquires greater than 15% of the First Lien Claims;
- a. Schedule Completion Date: Upon NRC consent of the requested transfer
- b. Status / Comments: Closed / The ownership percentages of the First Lien Creditors identified in the table at page 17 of TXX-15146 were updated by Enclosure 2 to TXX-16028. All entities remain below 15%.
(2) Luminant Power will notify the NRC if at any time prior to the NRC consent to the requested transfer, the following item changes: Any member of the First Lien Creditor Committee, other than those already identified in the Application, is expected to own 10% of the voting power of Reorganized TCEH.
- a. Schedule Completion Date: Upon NRC consent of the requested transfer
- b. Status / Comments: Closed / consent provided by NRC Order dated May 6, 2016.
(3) Luminant Power will also provide to the NRC: The names of the principal officers and directors of each of the subsidiary companies of the Reorganized TCEH, after they have been identified;
- a. Schedule Completion Date: As soon as they have been identified but no later than 7 days prior to consummation of the transfer
- b. Status/ Comments: Closed/ Information provided by Enclosure 2 of TXX-16105 (4) Luminant Power will also provide to the NRC: The names and citizenship of the initial members of the Reorganized TCEH Board, when that information becomes available. All or substantially all of the Reorganized TCEH Board members will be U.S. citizens. Three of the initial seven members have been identified (2 U.S. citizens and 1 Canadian citizen) and the remaining four members will be U.S. citizens;
- a. Schedule Completion Date: As soon as available but no later than 7 days prior to consummation of the transfer
- b. Status/ Comments: Closed/ TXX-15146 identified three board member, Geoffrey Strong (U.S. citizen), Cyrus Madon (Canadian citizen), and Jennifer Box (U.S. citizen). TXX-16098 identified four board members, Curt Morgan (U.S. citizen/ new CEO), Jeff Hunter (U.S. citizen), Gavin Baiera (U.S. citizen), and Michael Liebelson (U.S. citizen) .
[Response to NRC RAI, statement in NRC Order Safety Evaluation, and NRC Order condition (1)]
(5) Luminant Power will also provide to the NRC: The final legal entity names, and updated proposed operating license revision pages, when final names for Reorganized TCEH, Intermediate Holding Company LLC, Operating Company LLC, Asset Company LLC, Preferred Stock Company Corp., and Comanche Peak LLC are selected;
- a. Schedule Completion Date: No later than 7 days prior to consummation of the transfer
- b. Status / Comments: Closed / Information provided by Enclosures 1, 3, and 4 of TXX-16105 (6) Luminant Power will also provide to the NRC: The name of the new CNO, when a successor to current CNO Rafael Flores is selected; and
- a. Schedule Completion Date: No later than 7 days prior to consummation of the transfer
- b. Status/ Comments: Closed/ Update provided by TXX-15166 (Ken Peters is acting CNO) and closed by TXX-16057 (Ken Peters is new CNO) to TXX-17010 Page2 of2 (7) Luminant Power will also provide to the NRC: Notification that the Bankruptcy Court has confirmed the "Fifth Amended Joint Plan of Reorganization of Energy Future Holdings Corp., et al., Pursuant to Chapter 11 of the Bankruptcy Code," upon receipt of a final order of the Bankruptcy Court.
- a. Schedule Completion Date: Upon consent of the requested transfer
- b. Status / Comments: Closed / Completed by submittal of Enclosures 1 and 2 of letter TXX-15166.
(8) At the first meeting of the Reorganized TCEH Board of Directors emergence, the Board will adopt resolutions that non-U.S. citizens or foreign appointed U.S. citizens serving as either directors or executive officers of Reorganized TCEH, the ultimate parent, and intermediate parents of CP LLC and OpCo LLC shall not seek access to any classified informati9p or to special nuclear material in the custody of the Comanche Peak licensees and shall not participate in or seek to influence operational decisions by the licensees regarding nuclear safety or security matters. Also, at the first meeting a Nuclear Oversight and Advisory Board will be formed to assist in the oversight of the safety and quality of nuclear operations.
- a. Schedule Completion Date: First meeting of Reorganized TCEH Board of Directors
- b. Status/ Comments: Closed/ TXX-16108 provided notification that actions were completed [Updated to reflect 151 sentence of NRC Order condition (3)]
(9) The applicants will notify the NRC of any changes to the directors, officers, or executive positions of Reorganized TCEH and its subsidiaries during the first 90 days following the transfers
- a. Schedule Completion Date: No later than 120 days after the transfers
- b. Status/ Comments: Closed/ TXX-17010 dated January 30, 2017 [Identified by TXX-16028 and NRC Order condition (1)]
(10) A letter will be issued to the NRC by the new licensee within 30 days that" adopts and endorses" all outstanding items on the docket, including, but not limited to requests for license amendments, exemptions, relief requests, etc. The letter will be submitted under oath or affirmation.
- a. Schedule Completion Date: No later than 30 days after the transfers
- b. Status/ Comments: Closed/ TXX-16108 dated October 4, 2016 (11) Provide satisfactory documentary evidence to the Director of the Office of Nuclear Reactor Regulation that the licensees reflected in the amended licenses have obtained the appropriate amount of insurance required of a licensee under 10 CFR Part 140 and 10 CFR 50.54(w)
- a. Schedule Completion Date: On the license transfer date
- b. Status / Comments: Closed / Documentary Evidence of Insurance provided by TXX-16106 dated September 29, 2016 [Added to reflect NRC Order condition (4)]
(12) After receipt of all required regulatory approvals of the proposed transfer action, inform the Director of Nuclear Reactor Regulation in writing of such receipt.
- a. Schedule Completion Date: Within 5 business days of after all regulatory approvals
- b. Status/ Comments: Closed/ Notification to Director of Nuclear Reactor Regulation provided by TXX-16106 dated September 29, 2016 [Added to reflect NRC Order requirement]
(13) Notify the Director of the Office of Nuclear Reactor Regulation in writing of the date of the closing of the direct transfer.
- a. Schedule Completion Date: 7 business days before the date of closing
- b. Status/ Comments: Closed/ Targeted date of October 3, 2016 provided by TXX-16109 dated September 16, 2016 [Added to reflect NRC Order requirement]