MONTHYEARML0713003582007-05-11011 May 2007 Notice of Meeting with Txu Generation Company LP, Regarding Proposed Transition to Westinghouse Methodology and Other Methodologies Specific to Comanche Peak Steam Electric Station (CPSES) and Power Uprate Application Project stage: Meeting CPSES-200701076, Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2007-08-28028 August 2007 Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Other ML0727001092007-10-0909 October 2007 Acceptance Review of License Amendment Request 07-004, Revision to the OL and TS 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power (TAC MD6615/MD6616) Project stage: Acceptance Review CP-200700016, Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage2007-10-24024 October 2007 Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage Project stage: Supplement ML0728200122007-11-0606 November 2007 Request for Withholding Information from Public Disclosure Proprietary Request for Stretch Power Uprate Information (Tac Nos. MD6615 and MD6616) Project stage: Withholding Request Acceptance ML0728200252007-11-0606 November 2007 Request for Withholding Information from Public Disclosure WCAP-16827-P (Tac Nos. MD6615 and MD6616) Project stage: Withholding Request Acceptance ML0731101282007-11-14014 November 2007 LAR 07-004, Revision to OL and TS 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt (Tac Nos. MD6615 & MD6616) Project stage: Approval ML0731300292007-11-20020 November 2007 Request for Withholding Information from Public Disclosure Power Stretch Uprate (C. Savage, Westinghouse 10/23/07 Affidavit) Project stage: Withholding Request Acceptance ML0734402082007-12-11011 December 2007 Request for Additional Information, License Amendment Request 07-004, Changes to Technical Specifications to Revise Thermal Power from 3458 Mwt to 3612 Mwt (TACs MD6615 & MD6616) Project stage: RAI ML0736203732008-01-0707 January 2008 Request for Additional Information, License Amendment Request 07-004, Changes to Technical Specifications to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: RAI CP-200800053, Submittal of Annual Report of Changes in Peak Cladding Temperature for Comanche Peak Steam Electric Station (CPNPP) Units 1 and 22008-01-10010 January 2008 Submittal of Annual Report of Changes in Peak Cladding Temperature for Comanche Peak Steam Electric Station (CPNPP) Units 1 and 2 Project stage: Request CP-200800057, Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-01-10010 January 2008 Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement CP-200800123, Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to LAR Associated with Methodology Used to Establish Core Operating Limits and LAR 07-004 Revision to Operating License2008-01-29029 January 2008 Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to LAR Associated with Methodology Used to Establish Core Operating Limits and LAR 07-004 Revision to Operating License Project stage: Supplement CP-200800124, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-01-31031 January 2008 Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement ML0800401822008-02-0101 February 2008 Correction Letter Regarding Safety Evaluation for Audit of Licensees Management of Regulatory Commitments Project stage: Approval ML0803108692008-02-0808 February 2008 Request for Additional Information, Iolb, Emcb, Eeeb Tech Branches, License Amendment Request 07-004, Changes to Technical Specifications to Revise Rated Thermal Power from 3458 Mwt to 3612 MWT.(MD6615/MD6616) Project stage: RAI CP-200800263, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-02-21021 February 2008 Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement CP-200800213, Response to Request for Additional Information2008-02-26026 February 2008 Response to Request for Additional Information Project stage: Response to RAI CP-200800125, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-02-28028 February 2008 Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement CP-200800357, Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-03-0606 March 2008 Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement ML0806602512008-03-12012 March 2008 Request for Withholding Information from Public Disclosure (Re 2/20/08 Affidavit Executed by J. Gresham, Westinghouse) (Tac Nos. MD6615 and MD6616) Project stage: Withholding Request Acceptance ML0807905452008-03-31031 March 2008 Request for Additional Information, License Amendment Request 07-004, Changes to Technical Specifications to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt (De/Eeeb Follow-up RAI) Project stage: RAI CP-200800560, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-04-17017 April 2008 Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement ML0811300992008-04-24024 April 2008 Letter Enclosing Draft Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate Project stage: Draft Other ML0811301112008-04-24024 April 2008 Draft Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate Project stage: Draft Other CP-200800645, Supplement to License Amendment Request Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2008-05-14014 May 2008 Supplement to License Amendment Request Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt Project stage: Supplement ML0815102472008-06-16016 June 2008 Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate Project stage: Other ML0815102412008-06-16016 June 2008 Letter to Licensee Enclosing Copy of Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate Project stage: Other ML0816905832008-06-18018 June 2008 Public Transmittal Letter for Draft Safety Evaluation for Stretch Power Uprate, License Amendment Request 07-004, Revision to the Operating License & TS 1.0, Use and Application, to Revise Thermal Power from 3458 to 3612 Mwt Project stage: Draft Approval ML0815101752008-06-27027 June 2008 License, Appendix B, and Technical Specification Pages, Amendment Nos. 146 and 146, Stretch Power Uprate, Revision to TS 1.0, Use and Application, to Revise Rated Thermal Power from 3458 to 3612 Mwt Project stage: Other ML0815101732008-06-27027 June 2008 Issuance of Amendment Nos. 146 and 146, Stretch Power Uprate, Revision to TS 1.0, Use and Application, to Revise Rated Thermal Power from 3458 to 3612 Mwt Project stage: Approval 2008-02-01
[Table View] |
Text
November 20, 2007 Mr. M. R. Blevins Executive Vice President
& Chief Nuclear Officer Luminant Generation Company LLC ATTN: Regulatory Affairs P.O. Box 1002 6322 North FM 56 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NOS. MD6615 AND MD6616)
Dear Mr. Blevins:
By letter dated October 24, 2007, Mr. Fred W. Madden, Director, Oversight and Regulatory Affairs, TXU Generation Company LP, subsequently renamed Luminant Generation Company LLC, (the licensee), submitted an affidavit, executed by Mr. C. Savage, Director, Systems and Safety Analysis, for Westinghouse Electric Company LLC (Westinghouse), dated October 23, 2007, requesting that the information designated as proprietary in WPT-17046, Power Uprate Project Response to NRC [U.S. Nuclear Regulatory Commission] Request for Transmittal of Information, for the Comanche Peak Steam Electric Station (CPSES), Units 1 and 2, be withheld from the public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390. The "Power Uprate Project Response to NRC Request for Transmittal of Information" (WPT-17046) and the Westinghouse letter are Attachment 2 and, respectively, to the licensees letter dated October 24, 2007. Attachment 1 to the letter provided as the non-proprietary version of the above document contains no information because all the GOTHIC input data files are designated as proprietary.
The October 23, 2007, affidavit by Mr. C. Savage (supplemented by Westinghouse letter dated November 6, 2007) stated that the submitted information should be considered exempt from the mandatory public disclosure pursuant to 10 CFR 2.390(b)(4)(ii) for the following reason:
(c)
Use by our competitor would put Westinghouse at a competitive disadvantage by reducing its expenditure of resources at our expense.
We have reviewed the affidavits and the material designated as proprietary in accordance with the requirements of 10 CFR 2.390. Although the proprietary version of the document does not identify the reasons for which the information should be withheld from public disclosurein the future, each page containing proprietary information should indicate specifically the applicable reasons for withholding the information from the public disclosurethe supplemental Westinghouse letter dated November 6, 2007, stated that it should be withheld from public disclosure for reason (c) stated above. Therefore, on the basis of the statements in the affidavit, the NRC staff has determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore,
M. R. Blevins the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
A non-proprietary copy of the document designated as WPT-17046, and provided as to the letter dated October 24, 2007, has been placed in the NRCs Public Document Room and added to the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at (301) 415-3016.
Sincerely,
/RA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page
M. R. Blevins the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
A non-proprietary copy of the document designated as WPT-17046, and provided as to the letter dated October 24, 2007, has been placed in the NRCs Public Document Room and added to the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at (301) 415-3016.
Sincerely,
/RA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page DISTRIBUTION:
PUBLIC LPLIV Reading RidsAcrsAcnwMailCenter RidsNrrDorlDpr RidsNrrDorlLpl4 RidsNrrPMBSingal RidsNrrLAJBurkhardt RidsOgcRp RidsRgn4MailCenter RidsNrrDssScvb (Dennig)
NKaripineni, NRR/DSS/SCVB ADAMS Accession No.: ML073130029
- Concurrence via e-mail OFFICE NRR/LPL4/PM NRR/DSS/SCVB/BC NRR/LPL4/LA NRR/LPL4/BC NAME BSingal RDennig*
JBurkhardt THiltz, JND for DATE 11/20/07 11/8/07 11/20/07 11/20/07 OFFICIAL AGENCY RECORD
Comanche Peak Steam Electric Station cc:
Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 2159 Glen Rose, TX 76403-2159 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Mr. Fred W. Madden, Director Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043 Timothy P. Matthews, Esq.
Morgan Lewis 1111 Pennsylvania Avenue, NW Washington, DC 20004 County Judge P.O. Box 851 Glen Rose, TX 76043 Environmental and Natural Resources Policy Director Office of the Governor P.O. Box 12428 Austin, TX 78711-3189 Mr. Richard A. Ratliff, Chief Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 Mr. Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Ms. Susan M. Jablonski Office of Permitting, Remediation and Registration Texas Commission on Environmental Quality MC-122 P.O. Box 13087 Austin, TX 78711-3087 Anthony P. Jones Chief Boiler Inspector Texas Department of Licensing and Regulation Boiler Division E.O. Thompson State Office Building P.O. Box 12157 Austin, TX 78711