MONTHYEARCP-201201212, Spent Fuel Pool Criticality Analysis2012-10-0909 October 2012 Spent Fuel Pool Criticality Analysis Project stage: Request CP-201300257, License Amendment Request (LAR) 13-01, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.3, Fuel Storage, and 5.5 Programs & Manuals2013-03-28028 March 2013 License Amendment Request (LAR) 13-01, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.3, Fuel Storage, and 5.5 Programs & Manuals Project stage: Request ML13175A2252013-06-27027 June 2013 Supplemental Information Needed for Acceptance of Application to Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: Acceptance Review CP-201300826, Supplemental Information Supporting LAR 13-01, Spent Pool Criticality Analysis2013-07-16016 July 2013 Supplemental Information Supporting LAR 13-01, Spent Pool Criticality Analysis Project stage: Supplement ML13253A0052013-09-11011 September 2013 Acceptance Review Following Supplement, Amendment Request to Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: Acceptance Review ML13253A0062013-09-26026 September 2013 Request for Withholding Information from Public Disclosure, 3/18/13 Affidavit Executed by J. Gresham, Westinghouse Regarding WCAP-17728-P, Revision 0 Project stage: Withholding Request Acceptance CP-201301215, License Amendment Request (LAR) 13-01 Supplement Spent Fuel Pool Criticality Analysis Removal Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.32013-10-22022 October 2013 License Amendment Request (LAR) 13-01 Supplement Spent Fuel Pool Criticality Analysis Removal Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.3 Project stage: Supplement ML13309A0272013-10-31031 October 2013 WCAP-17728-NP, Rev. 1, Comanche Peak Nuclear Power Plant Units 1 and 2 Spent Fuel Pool Criticality Safety Analysis Project stage: Other ML13301A6452013-11-0505 November 2013 Redacted, Request for Additional Information, Amendment Request to Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: RAI ML13317B7032013-11-19019 November 2013 Non-proprietary, Request for Additional Information Round 2, Amendment Request to Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: RAI CP-201301332, License Amendment Request (LAR) 13-01 Supplement Spent Fuel Pool Criticality Analysis Removal Technical Specifications 3.7.17, Spent Fuel Assembly Storage,4.3, Fuel Storage, and 5.5 Programs and Manuals2013-11-26026 November 2013 License Amendment Request (LAR) 13-01 Supplement Spent Fuel Pool Criticality Analysis Removal Technical Specifications 3.7.17, Spent Fuel Assembly Storage,4.3, Fuel Storage, and 5.5 Programs and Manuals Project stage: Supplement ML14016A1242013-12-17017 December 2013 License Amendment Request (LAR) 13-01 Spent Fuel Pool Criticality Analysis, Response to Requests for Additional Information Round 2 Project stage: Response to RAI ML14027A7052013-12-17017 December 2013 Responses to LAR 13-01 Request for Additional Information (RAI) - Round 2 Project stage: Request CP-201301411, Response to Requests for Additional Information Round 2, on License Amendment Request (LAR) 13-01 Spent Fuel Pool Criticality Analysis,2013-12-17017 December 2013 Response to Requests for Additional Information Round 2, on License Amendment Request (LAR) 13-01 Spent Fuel Pool Criticality Analysis, Project stage: Response to RAI ML14015A5472014-01-15015 January 2014 NRR E-mail Capture - Request for Additional Information - License Amendment Request 13-01 to Revise Technical Specifications 3.7.16, 3.7.17, 4.3 and 5.5 - TACs MF1365 and MF1366 Project stage: RAI CP-201400074, License Amendment Request (LAR) 13-01 Spent Fuel Pool Criticality Analysis, Response to Request for Additional Information2014-01-16016 January 2014 License Amendment Request (LAR) 13-01 Spent Fuel Pool Criticality Analysis, Response to Request for Additional Information Project stage: Response to RAI ML14007A0392014-02-0606 February 2014 Request for Withholding Information from Public Disclosure - 11/22/13 Affidavit Executed by J. Gresham, Westinghouse Responses to 11/5/13 NRC Requests for Additional Information Project stage: RAI ML14058A0892014-02-27027 February 2014 Request for Additional Information Round 3, Amendment Request to Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: RAI ML14022A0462014-03-19019 March 2014 Request for Withholding Proprietary Information from Public Disclosure Project stage: Other ML13318A0292014-03-19019 March 2014 Request for Withholding Information from Public Disclosure, 10/14/13 Affidavit Executed by J. Gresham, Westinghouse Regarding WCAP-17728-P, Revision 1 Project stage: Withholding Request Acceptance ML14097A5132014-04-0707 April 2014 NRR E-mail Capture - Request for Additional Information - License Amendment Request for Spent Fuel Pool Criticality Analysis - TACs MF1365 and MF1366 Project stage: RAI CP-201400503, Response to Requests for Additional Information on License Amendment Request 13-01 Spent Fuel Pool Criticality Analysis2014-04-17017 April 2014 Response to Requests for Additional Information on License Amendment Request 13-01 Spent Fuel Pool Criticality Analysis Project stage: Response to RAI CP-201400619, License Amendment Request (LAR) 13.01, Spent Fuel Pool Criticality Analysis, Supplemental Information to Requests for Additional Information2014-05-0101 May 2014 License Amendment Request (LAR) 13.01, Spent Fuel Pool Criticality Analysis, Supplemental Information to Requests for Additional Information Project stage: Supplement ML14150A1382014-06-30030 June 2014 Request for Withholding Information from Public Disclosure - 7/12/13 Affidavit Executed by B. Maurer, Westinghouse; Supplemental Information Supporting Amendment Request Question 1, 2, and 4 (TAC MF1365-MF1366) Project stage: Withholding Request Acceptance ML14150A1422014-06-30030 June 2014 Request for Withholding Information from Public Disclosure - 4/17/14 Affidavit Executed by J. Gresham, Westinghouse; Responses to Request for Additional Information SFP Configuration Interfaces (TAC MF1365-MF1366) Project stage: RAI ML14160A0352014-07-0101 July 2014 Redacted, Issuance of Amendment No. 162, Revise TS 3.7.16, Fuel Storage Pool Boron Concentration, TS 3.7.17, Spent Fuel Assembly Storage, and TS 5.5, Programs and Manuals Project stage: Approval 2013-09-11
[Table View] |
Text
Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 6, 2014 Attention: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2-REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NOS. MF1365 AND MF1366)
Dear Mr. Flores:
By letter dated November 26, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13346A175), Luminant Generation Company LLC (Luminant) submitted an affidavit dated November 22, 2013, executed by J. A. Gresham, Manager, Regulatory Compliance, Westinghouse Electric Company (Westinghouse), requesting that information designated proprietary in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR), Part 2, Section 2.390:
Comanche Peak Responses to LAR [License Amendment Request]
13-01 Request for Additional Information (Proprietary)
The proprietary version of the document is Attachment 1 and the Westinghouse affidavit is the Enclosure to the letter dated November 26, 2013, from Luminant to the U.S. Nuclear Regulatory Commission (NRC), for the Comanche Peak Nuclear Power Plant, Units 1 and 2.
A non-proprietary copy of the document, provided as Attachment 2 to the letter dated November 26, 2013, has been placed in the NRC's Public Document Room and added to the NRC Library at ADAMS Accession No. ML13346A175.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a)
The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.
(c)
Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.
We have reviewed your application and the material in accordance with the requirements of 1 0 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the information sought to be withheld in the submittal, contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 1 03(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at (301) 415-3016.
Docket Nos. 50-445 and 50-446 cc:
J. A. Gresham, Manager Regulatory Compliance Westinghouse Electric Company Suite 310 1000 Westinghouse Drive Cranberry Township, PA 16066 Additional Distribution via Listserv Sincerely,
~-T-t-SJ""-~
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
- NAME BSingal JBurkhardt DATE 1/13/14 1/10/14 Sincerely, IRA/
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrLAJBurkhardt Resource RidsRgn4MaiiCenter Resource KWood, NRR/DSS/SRXB APatel, NRR/DSS/SRXB EWong, NRR/DE/ESGB