ML14356A006
ML14356A006 | |
Person / Time | |
---|---|
Site: | Oconee |
Issue date: | 12/03/2014 |
From: | Duke Energy Carolinas |
To: | Division of Operating Reactor Licensing |
Hall V, NRR/JLD, 415-2915 | |
References | |
Download: ML14356A006 (19) | |
Text
Jocassee Dam Breach Analysis NRC Technical Presentation Rockville, MD December 3, 2014 For Information Only
Dave Baxter, GM, Oconee Regulatory Project Completion Ed Burchfield, GM, Oconee Nuclear Station Engineering Dean Hubbard, Eng. Director, Fukushima External Flooding Benjamin Zoeller, Water Resources Engineer, AMEC Brian Stevens, Water Resources Engineer, AMEC Chris Ey, HDR Civil Engineering Manager Adam Johnson, Oconee Fukushima Engineering 2
For Information Only
Agenda Purpose & Scope
Background
Request for Additional Information - Scope Breach Analysis JLD-ISG 2013-01 Conformance Key assumptions Breach Results 2D Modeling - TUFLOW FV TUFLOW FV Selection TUFLOW FV Validation Summary 3
For Information Only
Background / Timeline Fukushima 50.54(f) Requires reevaluation of all flooding hazards using present-day guidance and methodologies Deterministic failure of upstream dams required.
Fukushima Hazard Reevaluation Submitted March 12, 2013 Request for Additional Information, September 15, 2014 - Resubmit dam failure analysis applying alternate breach-parameter estimations Jocassee Dam failure reanalyzed using JLD-ISG-2013-01 On schedule to meet submittal of revised FHRR by 2/13/15 Initial results to be discussed today 4
For Information Only
NRC Request for Additional Information September 15, 2014 Reanalyze and resubmit the dam failure analyses for the ONS, Units 1, 2 and 3 FHRR after applying alternate breach-parameter estimations.
The staff requests that the model results not rely on a single methodology Instead, the staff requests comparison of results for several models judged appropriate.
Although the Oconee FHRR was submitted before JLD-ISG-2013-1 which was completed in July, 2013, this JLD-ISG may provide useful guidance regarding application of breach models the NRC staff find appropriate for use.
Justification should be provided for the selection of the candidate breach models used as well as the selected value(s) used in the hydraulic model.
Parameter uncertainty as well as parameter sensitivity in the final model results should be explicitly addressed in the response.
5 For Information Only
JLD-ISG-2013-01 Conformance JLD-ISG 2013-01 Dam Failure Guidance Sunny Day Failure - deterministic failure assumed Hydrologic Failure - not credible Seismic Failure - not credible (separate RAI response)
JLD-ISG 2013-01 7.2 Breach Modeling of Embankment Dams Uses multiple common regression equations for breach parameters sensitivity studies and to predict parameters Uses multiple common regression equations for peak outflow sensitivity studies Multiple modeling methods used including regression, physics based and historical failure comparative analysis Hierarchical hazard assessment (HHA) used with conservative plausible assumptions consistent with available data 6
For Information Only
Key Assumptions Starting reservoir elevation 1100 msl (maximum operating level)
Sunny day piping failure initiating at 1020 msl at the West Abutment Breach starts at West Abutment and expands toward dam center Formation in one direction limits the breach size (w/ rock abutment)
Peak outflow occurs prior to full breach based on decreasing head differential and resulting water velocities Breach time recognizes time required to empty the reservoir Bottom of breach at 800 ft msl based on Keowee reservoir full pool elevation. Note the 800 ft msl, the distance from the upstream face to the downstream face of the dam is 1324 feet 7
For Information Only
Jocassee Breach Modeling Multiple Methods Applied Regression equations used for sensitivity input Von Thun and Gillette (1990)
Froehlich (1995)
Froehlich (2008)
USBR (1982)
Costa (1985)
McDonald Langridge-Monopolis (1984)
Physics based model sensitivity input NWS Breach Model Routing Methodologies HEC-RAS, V4.1 Historical failure comparison to empirical breach equations Hell Hole Teton Dam Oros Dam 8
For Information Only
Breach Analysis Summary (Draft)
Final Jocassee Dam Breach Parameters Top Width 959 ft Bottom Width 634 ft Side Slopes 0.5 H: 1V Final Bottom Elevation 800 ft Breach Development Time 2.1 hrs Full Formation Time 10.2 hrs Time to Empty Reservoir 19.2 hrs Computed Peak Outflow at Jocassee Dam 2,846,010 cfs 9
For Information Only
Jocassee Dam Breach Progression and Hydrographs Jocassee Dam Breach Progression and Hydrographs 1.20 6,000,000 Elevation (ft/1,000) and Fraction of Breach 1.00 5,000,000 0.80 4,000,000 Flow (cfs) 0.60 3,000,000 Progression 0.40 2,000,000 0.20 1,000,000 0.00 0 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 22.00 24.00 Time (Hours)
Headwater Tailwater Breach Progression Breach Discharge 10 For Information Only
Jocassee HEC-RAS Breach Progression A Time to Empty Reservoir = 19.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> B Full Formation Time as Defined by Froehlich = 10.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> C Breach formation to peak outflow = 2.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> D Breach formation limited to 70% at the point of peak outflow 11 For Information Only
Peak Outflow Sensitivity Peak Breach Outflow Peak Breach Peak Flow Predictors (m3/sec) Outflow (cfs)
USBR 1982 (envelope) 94,069 3,322,010 Froehlich 1995 90,999 3,213,590 Jocassee Outflow 80,590 2,846,010 Costa 1985 (Dam Height) 56,692 2,002,060 Costa 1985 (Dam Factor) 47,376 1,673,070 MLM 1984 44,209 1,561230 Costa 1985 (Reservoir Volume) 31,438 1,110,220 12 For Information Only
Jocassee Dam Peak Outflow vs. Empirical Peak Flow Predictors and Historical Data Jocassee Dam Peak Outflow vs. Empirical Peak Flow Predictors and Historical Data Historical Dams 3500000 Jocassee Peak Outflow with Recommended Breach 3000000 Parameters Froehlich 1995 2500000 USBR 1982 Peak Outflow (cfs) 2000000 Costa 1985 (Dam Factor) 1500000 Costa 1985 (Volume) 1000000 Costa 1985 (Dam Height) 500000 MLM 1984 0 Linear (Historical Dams) 0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 Breach Height (ft) 13 For Information Only
Comparison of Empirical Breach Equations to Historical Failures
- Prediction of Embankment Dam Breach Parameters- USBR, states that Froehlich (1995) is the best predictor of breach width for cases with observed breach widths less than 50 meters.
- The largest dam included in the database used to develop the Froehlich equations is La Fruta Dam in Texas, with a volume of water above breach of 64,000 acre-feet.
- By comparison, Oros Dam had a reservoir storage volume of approximately 535,000 acre-feet and Jocassee Dam has a reservoir storage volume of 1,160,298 acre-feet.
- Breach parameters computed using Von Thun and Gillette, Froehlich (1995), and Froehlich (2008) were compared to observed parameters for three of the largest historical dam failures to date where breach data was collected (Hell Hole Dam, Teton Dam, and Oros Dam).
- Von Thun and Gillette equations estimated breach parameters provide the best representation for the three historical dam failures, particularly the largest volume dam, Oros Dam. The empirical predicted breach widths with the breach widths of twelve historical dam failures as a function of reservoir volume were compared.
14 For Information Only
Linear Trend of Historic Breach Width vs.
Reservoir Volume Historical and Empirical Breach Widths as a Function of Volume 1600 1400 Database reservoir volume vs.
Average Breach Width (ft) 1200 avg width Von Thun Avg Width 1000 NWS BREACH Width 800 600 Froehlich 1995 400 Froehlich 2008 200 Linear (Database reservoir volume vs. avg width) 0 0 500000 1000000 1500000 2000000 2500000 Volume (acre-ft)
Average Reservoir Average Reservoir Dam Breach Dam Volume (acre- Breach Width Volume (acre-ft)
Width (ft) ft) (ft)
Taum Sauk 4,600 680 Lower Otay 40,000 436 Zhugou 14,900 443 Shimantan 94,900 1,204 Johnsontown, PA 15,300 310 Nanaksagar 170,000 500 Longtun 24,300 392 Teton Dam 251,300 495 Hell Hole Dam 24,800 397 Banqiao 492,500 955 Jiahezi 34,000 392 Oros Dam 535,000 541 15 For Information Only
2D Modeling - TUFLOW FV TUFLOW FV Selection SRH-2D used in previous analysis (finite-volume numerical scheme)
TUFLOW FV (Finite Volume) represents state of the practice model includes time-varying bed elevation solutions Logic controls provide for dynamic response (automated breach initiation)
Stable platform solving shallow water equations, active development, ability to handle large models Enhanced numerical solution speed (hours vs weeks)
Ability to solve equations using high speed parallel processors 16 For Information Only
2D Modeling - TUFLOW FV cont.
TUFLOW FV Validation Model has been in development since 2008 Model developed for in-house professional use prior to releasing as a commercial product (similar to SRH2D)
UK Environment Agency Benchmarking S&L Validation for OPPD (Appendix B application)
SRH-2D / TUFLOW FV comparison with Oconee data 17 For Information Only
Summary Von Thun Gillette breach equations are best suited for the analysis of Jocassee Dam based on a linear trendline of average breach widths vs. reservoir volume The key to a conservative and realistic peak outflow lies in the breach progression pattern used in the HEC-RAS The breach development was limited to 70% during the breach development phase based on sensitivity analysis on breach development time which allows the peak outflow to align with historical data The breach width was limited to 80% of the total width predicted by the Von Thun and Gillette where the breach is assumed to initiate at one of the abutments and growth would be limited by the abutment in one direction. This is supported by the historic Teton Dam failure where the piping failure and subsequent breach occurred against the abutment Full formation time using Froehlichs definition is 10.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (including part of the 2.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to reach the peak outflow value)
The time to empty reservoir was calculated to be 19.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to account for the continuation of breach growth until the reservoir is fully drained. The rate of breach formation after the development time is proportional to the depth of water in the reservoir at each time step in relation to the final pool level The breach analysis is a refined analysis based on conservative but plausible assumptions based on multiple and diverse methods that are consistent with historical failure data 18 For Information Only
Questions or Comments?
19 For Information Only
Jocassee Dam Breach Analysis NRC Technical Presentation Rockville, MD December 3, 2014 For Information Only
Dave Baxter, GM, Oconee Regulatory Project Completion Ed Burchfield, GM, Oconee Nuclear Station Engineering Dean Hubbard, Eng. Director, Fukushima External Flooding Benjamin Zoeller, Water Resources Engineer, AMEC Brian Stevens, Water Resources Engineer, AMEC Chris Ey, HDR Civil Engineering Manager Adam Johnson, Oconee Fukushima Engineering 2
For Information Only
Agenda Purpose & Scope
Background
Request for Additional Information - Scope Breach Analysis JLD-ISG 2013-01 Conformance Key assumptions Breach Results 2D Modeling - TUFLOW FV TUFLOW FV Selection TUFLOW FV Validation Summary 3
For Information Only
Background / Timeline Fukushima 50.54(f) Requires reevaluation of all flooding hazards using present-day guidance and methodologies Deterministic failure of upstream dams required.
Fukushima Hazard Reevaluation Submitted March 12, 2013 Request for Additional Information, September 15, 2014 - Resubmit dam failure analysis applying alternate breach-parameter estimations Jocassee Dam failure reanalyzed using JLD-ISG-2013-01 On schedule to meet submittal of revised FHRR by 2/13/15 Initial results to be discussed today 4
For Information Only
NRC Request for Additional Information September 15, 2014 Reanalyze and resubmit the dam failure analyses for the ONS, Units 1, 2 and 3 FHRR after applying alternate breach-parameter estimations.
The staff requests that the model results not rely on a single methodology Instead, the staff requests comparison of results for several models judged appropriate.
Although the Oconee FHRR was submitted before JLD-ISG-2013-1 which was completed in July, 2013, this JLD-ISG may provide useful guidance regarding application of breach models the NRC staff find appropriate for use.
Justification should be provided for the selection of the candidate breach models used as well as the selected value(s) used in the hydraulic model.
Parameter uncertainty as well as parameter sensitivity in the final model results should be explicitly addressed in the response.
5 For Information Only
JLD-ISG-2013-01 Conformance JLD-ISG 2013-01 Dam Failure Guidance Sunny Day Failure - deterministic failure assumed Hydrologic Failure - not credible Seismic Failure - not credible (separate RAI response)
JLD-ISG 2013-01 7.2 Breach Modeling of Embankment Dams Uses multiple common regression equations for breach parameters sensitivity studies and to predict parameters Uses multiple common regression equations for peak outflow sensitivity studies Multiple modeling methods used including regression, physics based and historical failure comparative analysis Hierarchical hazard assessment (HHA) used with conservative plausible assumptions consistent with available data 6
For Information Only
Key Assumptions Starting reservoir elevation 1100 msl (maximum operating level)
Sunny day piping failure initiating at 1020 msl at the West Abutment Breach starts at West Abutment and expands toward dam center Formation in one direction limits the breach size (w/ rock abutment)
Peak outflow occurs prior to full breach based on decreasing head differential and resulting water velocities Breach time recognizes time required to empty the reservoir Bottom of breach at 800 ft msl based on Keowee reservoir full pool elevation. Note the 800 ft msl, the distance from the upstream face to the downstream face of the dam is 1324 feet 7
For Information Only
Jocassee Breach Modeling Multiple Methods Applied Regression equations used for sensitivity input Von Thun and Gillette (1990)
Froehlich (1995)
Froehlich (2008)
USBR (1982)
Costa (1985)
McDonald Langridge-Monopolis (1984)
Physics based model sensitivity input NWS Breach Model Routing Methodologies HEC-RAS, V4.1 Historical failure comparison to empirical breach equations Hell Hole Teton Dam Oros Dam 8
For Information Only
Breach Analysis Summary (Draft)
Final Jocassee Dam Breach Parameters Top Width 959 ft Bottom Width 634 ft Side Slopes 0.5 H: 1V Final Bottom Elevation 800 ft Breach Development Time 2.1 hrs Full Formation Time 10.2 hrs Time to Empty Reservoir 19.2 hrs Computed Peak Outflow at Jocassee Dam 2,846,010 cfs 9
For Information Only
Jocassee Dam Breach Progression and Hydrographs Jocassee Dam Breach Progression and Hydrographs 1.20 6,000,000 Elevation (ft/1,000) and Fraction of Breach 1.00 5,000,000 0.80 4,000,000 Flow (cfs) 0.60 3,000,000 Progression 0.40 2,000,000 0.20 1,000,000 0.00 0 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 22.00 24.00 Time (Hours)
Headwater Tailwater Breach Progression Breach Discharge 10 For Information Only
Jocassee HEC-RAS Breach Progression A Time to Empty Reservoir = 19.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> B Full Formation Time as Defined by Froehlich = 10.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> C Breach formation to peak outflow = 2.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> D Breach formation limited to 70% at the point of peak outflow 11 For Information Only
Peak Outflow Sensitivity Peak Breach Outflow Peak Breach Peak Flow Predictors (m3/sec) Outflow (cfs)
USBR 1982 (envelope) 94,069 3,322,010 Froehlich 1995 90,999 3,213,590 Jocassee Outflow 80,590 2,846,010 Costa 1985 (Dam Height) 56,692 2,002,060 Costa 1985 (Dam Factor) 47,376 1,673,070 MLM 1984 44,209 1,561230 Costa 1985 (Reservoir Volume) 31,438 1,110,220 12 For Information Only
Jocassee Dam Peak Outflow vs. Empirical Peak Flow Predictors and Historical Data Jocassee Dam Peak Outflow vs. Empirical Peak Flow Predictors and Historical Data Historical Dams 3500000 Jocassee Peak Outflow with Recommended Breach 3000000 Parameters Froehlich 1995 2500000 USBR 1982 Peak Outflow (cfs) 2000000 Costa 1985 (Dam Factor) 1500000 Costa 1985 (Volume) 1000000 Costa 1985 (Dam Height) 500000 MLM 1984 0 Linear (Historical Dams) 0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 Breach Height (ft) 13 For Information Only
Comparison of Empirical Breach Equations to Historical Failures
- Prediction of Embankment Dam Breach Parameters- USBR, states that Froehlich (1995) is the best predictor of breach width for cases with observed breach widths less than 50 meters.
- The largest dam included in the database used to develop the Froehlich equations is La Fruta Dam in Texas, with a volume of water above breach of 64,000 acre-feet.
- By comparison, Oros Dam had a reservoir storage volume of approximately 535,000 acre-feet and Jocassee Dam has a reservoir storage volume of 1,160,298 acre-feet.
- Breach parameters computed using Von Thun and Gillette, Froehlich (1995), and Froehlich (2008) were compared to observed parameters for three of the largest historical dam failures to date where breach data was collected (Hell Hole Dam, Teton Dam, and Oros Dam).
- Von Thun and Gillette equations estimated breach parameters provide the best representation for the three historical dam failures, particularly the largest volume dam, Oros Dam. The empirical predicted breach widths with the breach widths of twelve historical dam failures as a function of reservoir volume were compared.
14 For Information Only
Linear Trend of Historic Breach Width vs.
Reservoir Volume Historical and Empirical Breach Widths as a Function of Volume 1600 1400 Database reservoir volume vs.
Average Breach Width (ft) 1200 avg width Von Thun Avg Width 1000 NWS BREACH Width 800 600 Froehlich 1995 400 Froehlich 2008 200 Linear (Database reservoir volume vs. avg width) 0 0 500000 1000000 1500000 2000000 2500000 Volume (acre-ft)
Average Reservoir Average Reservoir Dam Breach Dam Volume (acre- Breach Width Volume (acre-ft)
Width (ft) ft) (ft)
Taum Sauk 4,600 680 Lower Otay 40,000 436 Zhugou 14,900 443 Shimantan 94,900 1,204 Johnsontown, PA 15,300 310 Nanaksagar 170,000 500 Longtun 24,300 392 Teton Dam 251,300 495 Hell Hole Dam 24,800 397 Banqiao 492,500 955 Jiahezi 34,000 392 Oros Dam 535,000 541 15 For Information Only
2D Modeling - TUFLOW FV TUFLOW FV Selection SRH-2D used in previous analysis (finite-volume numerical scheme)
TUFLOW FV (Finite Volume) represents state of the practice model includes time-varying bed elevation solutions Logic controls provide for dynamic response (automated breach initiation)
Stable platform solving shallow water equations, active development, ability to handle large models Enhanced numerical solution speed (hours vs weeks)
Ability to solve equations using high speed parallel processors 16 For Information Only
2D Modeling - TUFLOW FV cont.
TUFLOW FV Validation Model has been in development since 2008 Model developed for in-house professional use prior to releasing as a commercial product (similar to SRH2D)
UK Environment Agency Benchmarking S&L Validation for OPPD (Appendix B application)
SRH-2D / TUFLOW FV comparison with Oconee data 17 For Information Only
Summary Von Thun Gillette breach equations are best suited for the analysis of Jocassee Dam based on a linear trendline of average breach widths vs. reservoir volume The key to a conservative and realistic peak outflow lies in the breach progression pattern used in the HEC-RAS The breach development was limited to 70% during the breach development phase based on sensitivity analysis on breach development time which allows the peak outflow to align with historical data The breach width was limited to 80% of the total width predicted by the Von Thun and Gillette where the breach is assumed to initiate at one of the abutments and growth would be limited by the abutment in one direction. This is supported by the historic Teton Dam failure where the piping failure and subsequent breach occurred against the abutment Full formation time using Froehlichs definition is 10.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (including part of the 2.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to reach the peak outflow value)
The time to empty reservoir was calculated to be 19.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to account for the continuation of breach growth until the reservoir is fully drained. The rate of breach formation after the development time is proportional to the depth of water in the reservoir at each time step in relation to the final pool level The breach analysis is a refined analysis based on conservative but plausible assumptions based on multiple and diverse methods that are consistent with historical failure data 18 For Information Only
Questions or Comments?
19 For Information Only