ML14058A074

From kanterella
Jump to navigation Jump to search
Slides on Oconee Ssf Flood Barrier Breach SDP - Lessons Learned
ML14058A074
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/04/2014
From: Jeff Circle
NRC/NRR/DRA/APOB
To:
Shared Package
ML14055A421 List: ... further results
References
FOIA/PA-2012-0325
Download: ML14058A074 (18)


Text

(.

Oconee SSF Flood Barrier Breach SDP - Lessons Learned Jeff Circle NRR/DRAIAPOB 1

[2U. US.NRC UrE DSTATES NUR nUIATRY COMMON Proteetin People and Mea Enviromment

Purpose s To brief the RMT of the lessons learned from the disposition of the Oconee Standby Shutdown Facility (SSF) wall SDP finding, s To discuss potential regulatory actions considered to ensure safety.

Po)ýýý-

SQnsifivýeýf 2

U S.-NRC UNITE STATES N1ZWUR REGVLATORY COMMISON Protactin5 People and the Environment

Discussion Topics Background of finding.

Technical lessons learned.

s Process lessons learned.

s Actions taken to date.

s Considered draft action plan.

\\jfi ýsevernIerniio~r!!i n'

3

,USNRC WqrTE STAM S NWLW REGMTUOR&Y CO'4MLSSION Prolecing Peopke and the Epwironment

Importance of the SSF at Oconee

  1. The SSF contains the only means to shut all three units down following a station blackout induced by catastrophic flood, fire, or other external events.

s The Oconee site does not have emergency diesel generators.

- On-site emergency ac power is provided by two hydro-electric generators at the Keowee dam, Catastrophic flooding to the site can render all the switchyards and Keowee dam unavailable thus blacking out all three units.

Under these conditions, the additional failure of the SSF function results in core damage.

.r_

NY

'1 nU

,S.N R C

--_______________UNIID STATES KUC"A RWLrLTORT COMWSSIGN Protecting People and the Environment

Aerial View Showing The Relationship of the Oconee Site Environment and Lake Keowee 5

ý2U.S.NRC UNIhJTED STATES NU~CLEAR REGULATORY COMMSSION Protecting People and the Environment

Aerial View of the Oconee Site Use 6

US.NRC UrotMTATESNUCLnARg UkoLpe tEvir oe ha61ProetiSepk and the Entvironment

The Flood Barrier Finding U

U I

U U

o Licensee opened an access cover uncovering a previously cut hole in the wall on August 13, 2003.

Should have done a 10CFR50.65 (a)(4) assessment immediately.

Should have done a 10CFR50.59 evaluation after 90 days.

  • Licensee opportunities to identify issue June 2, 2005 NRC inspectors notified the licensee of condition.

Licensee issued PIP (condition report in their corrective action system). Corrective action not taken.

August 3, 2005 NRC inspectors questioned lack of corrective action and licensee issued a further PIP.

. Opening sealed on August 3, 2005.

Five-foot flood wall protecting the doorway.

~~aeSs eaII~al in 7

U.S.NRjC UNIMhSTAME NLTLLO1 REGq.TO~

CmJ1 Protectinag People and the Environment

Interior and Exterior Walls of SSF 1~

(ý6Zdi My Seifi allI rm 8

'US.NRC UNITED STATES NbCLLAR REGULATORY COMMISSION Protecting People and the Environment

The Flood Scenario Rupture of Jocassee Dam

+*i 7V

'Lake Jocassee

- S+,

+.

Nimmnmas Os, Kea.wee I

~

.Nir' Times Six MlWe 0

Cute Oconee It d

+
  • Oconee Site

+

Pickens effiýse ýOniy 4ensitiWnterýinfoýafioW 9

US.NRC UNITED STATE NCLEAR UaTLATORT CMISO protectig people altd the EnVironMen4

Aerial View of Jocassee Dam. Upstream of the Oconee Site Jrn or-1

? S.NRC UNTDSTATES N1JcIFR REGJL&.TURY OMMISSiON

~Protecting People and the Environment

SSF Catastrophic Flood Heights Given Rupture of Jocassee Dam Licensee study in 1980s established a resultant flood height of approximately 5 feet.

- Justification for erection of the 5-ft wall around the doorway.

- Study is unavailable.

- Flood height almost matches that of overtopping of Keowee dam.

@ Licensee commissioned additional study by FERC in 1992.

- Established a higher resultant flood height range of 12-16 feet.

- Licensee still used the 5-ft height for their IPEEE submittal developing a 20% split fraction apportioning the Jocassee Dam rupture frequencies to account for these higher FERC flood heights.

Met JSKVRUS,NRC

'\\UMED $TAM I"*hUAR REGULATORY COMASS Protecting PeopIe and the Environment

Background Summary

, August 17, 2006 - SERP meeting assessed as preliminary WHITE based on a blended qualitative and quantitative risk-informed approach (pre-IMC 0609 App M).

, August 31, 2006 -Choice letter sent to licensee.

, October 5, 2006 - Licensee provided written response to choice letter and waived regulatory conference.

, Nov. 22, 2006 -Final significance determination issued. WHITE based on qualitative erosion of defense-in-depth, but includes quantitative CDF based on apportioning flood frequency to flood height.

, December 20, 2006 -Licensee appeals the final significance determination.

Requests NRC to accept incomplete, un-docketed new information on Jocassee dam seismic failure.

Appeal panel convened on January 9, 2007.

  • Licensee contractor seismic fragility analysis of Jocassee issued January 29, 2007.
  • March 1, 2007-Appeal panel upheld the WHITE finding.
  • May 3, 2007 - Licensee requests reassessment of final significance determination.

June, 2007 - Assembled a team to review new information. Flooding expert review of data on random dam failure.

  • June 28, 2007 -Follow up telecom with Licensee on dam failure questions and
comments,
  • July 17, 2007 -Licensee response to analysis questions by email.
  • September 5, 2007 - Final SERP split vote forces upper management resolution.
  • November 20, 2007 -Final determination letter released to licensee.

12 0

US.NRC UNrTED Sr&TE NtCLL&R REGqATORY CONM ION Protecting PeopLe and the Environment

Jocassee Dam Random Failure Frequency Licensee developed random dam failure frequency for IPEEE submittal based on rockfill dam failures per population of earthen, rockfill, and composite dams.

- Severely underestimated frequency by an order of magnitude at 1,4E-5 per year.

As part of the second appeal, James Vail of NRR/

DRA/APOB investigated the derivation of this frequency.

(b)(7)(F) 7-,-

Offiial Uco Only Scn~ti~e lntern~l liifuniwtiofl' 13 itUS.NRi&0 UJIrrED slATES NMjCLEAE REGULATORY OWSN Sprotecting People and the Envirnmment

Process Lessons Learned

  • Process did not account for situations where licensee did not communicate to the regional office and waived participation in a regulatory conference.

. Process did not accept new information prior to final determination.

Without a regulatory conference, communication was impacted to program office and regional management of potential greater-than-green SDP findings.

a~.......6U.S.NRC

--rficiai use unly.- Sensitive irnernai info.iiiaL,,1.

16 U

R UNITlED STATES NUCtAR REGULATOE COMMISSION Protecting Peopile and the Environmient

Actions Taken I

IMC0609 in draft revision to account for:

- Licensees may present new information provided that they informed the agency either during a regulatory conference or in writing before the final significance determination is made.

- New information has to be submitted within the 30-day appeal period.

- Using best available information to determine final significance in a timely manner.

- NRR concurrence with regional management on accepting an appeal.

,, rllil.I. Only.-S.*

jju n*t~ ra lfrmtei-1

/

IJNI'D STATES 1htCL1AR MIGLATORY COMMISSION

Actions Taken (cont'd)

, Training conducted to regional Senior Reactor Analysts (SRAs) in October 2007 counterparts meeting.

, Met with NSIR to inform DHS on potential dam and other outside infrastructure vulnerability.

/( orr~;aI U3c OnI~' - Scncitivc Internal Information 18 1CU~SNRC UNYI1D STATES NU1XIAR REGLUITORY COMMISSION Protecting People and the Envnirnment

Draft Action Plan to Consider Future Actions

, NRR Program Office Director and/or Deputy Director should be informed of all greater-thanogreen findings.

, Exploration of licensing and potential backfit requirement for protection against most likely flood.

, Generic communication to licensees on flooding.

QfI.-M J Use-0Unly -Sensitiv-e iWfMnTe-rMnall-rmd 19 U, R i2USSNRC

__UNITED STATES

'UCLEA REGULATORY COMMISSION Protecting People and the Environment

Draft Action Plan to Consider Future Actions (Cont'd)

  • Update of RASP manual for additional external flood guidance, s Consider an update to NUREG/CR-6928 to include rupture frequencies, s NRO Licensing and Design Bases Review for New Reactor Licensing to incorporate lessons learned on new applications.

e Develop a Temporary Instruction to assess licensee performance in this area.

ensi ive n ernai norma ion 20

.. UNIT E ESvTATE NCLEA REGULATORY COM eISSON Protectng Peop& and the Envimoment