Annual Assessment Meeting Presentation
ML23087A297
Person / Time
Site: Oconee, Mcguire, Catawba, McGuire  Duke Energy icon.png
Issue date: 04/17/2023
From:
Division Reactor Projects II
To:
References
Download: ML23087A297 (28)


Text

CATAWBA CATAWBA CATAWBA Reactor Oversight Process Nuclear Regulatory Commission - Region II MCGUIRE MCGUIRE OCONEE OCONEE OCONEE 2022 ANNUAL ASSESSMENT

PURPOSE Discuss licensee performance in 2022 Address findings and Performance Indicators Information Meeting with a Q&A Session

AGENDA

  • Introductions
  • Review Reactor Oversight Process
  • Annual Assessment Summary
  • Catawba Nuclear Station
  • McGuire Nuclear Station
  • Oconee Nuclear Station
  • Closing Remarks
  • NRC available for public questions

Introductions

  • Regional Personnel
  • Catawba Nuclear Station Resident Inspectors
  • Amber Donley, Ph.D. - Acting Senior Resident Inspector
  • David Rivard - Resident Inspector

Introductions

  • McGuire Nuclear Station Resident Inspectors
  • Chris Safouri-Senior Resident Inspector
  • Frank Young - Resident Inspector
  • Oconee Nuclear Station Resident Inspectors
  • Nick Smalley - Resident Inspector

NRC REACTOR OVERSIGHT PROCESS Implemented in each of the NRCs four regions Involves inspection and assessment activities Executed by regional and resident inspectors 1

2 3

4 NRC NRC

Reactor Oversight Framework

Reactor Oversight Inputs and Oversight INCREASING SAFETY SIGNIFICANCE Performance Indicators Performance within an expected level; Cornerstone objectives are met Performance outside expected range; Cornerstone objectives are still being met Related cornerstone objectives are being met; Minimal reduction in the safety margin Signals a significant reduction in safety margin in the area measured Findings Very low safety or security significance Low to moderate safety or security significance Substantial safety or security significance High safety or security significance Oversight Baseline Inspection Requires additional NRC oversight Requires more NRC oversight Requires most NRC oversight WHITE GREEN YELLOW RED INCREASING NRC OVERSIGHT

RESIDENT INSPECTOR PROGRAM

  • Resident inspectors live in the communities they serve
  • Perform inspections at Catawba, McGuire, &

Oconee Nuclear Stations

  • Provide daily oversight of plant activities

NRC Annual Assessment Summary

NRC Annual Assessment Summary CATAWBA NUCLEAR STATION Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment All findings associated with Catawba Nuclear Station in 2022 were Green

Findings and Performance Indicators CATAWBA NUCLEAR STATION

3 - non-cited violations identified in 2022 2 - Green 1 - traditional enforcement All Performance Indicators were Green

NRC Annual Assessment Summary CATAWBA NUCLEAR STATION Catawba Units 1 and 2 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2022 NRC plans to conduct routine baseline inspections at the Catawba Nuclear Station for 2023

QUESTIONS?

NRC Annual Assessment Summary

NRC Annual Assessment Summary MCGUIRE NUCLEAR STATION

  • Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
  • All findings associated with McGuire Nuclear Station in 2022 were Green

Findings and Performance Indicators MCGUIRE NUCLEAR STATION

  • 4 - Green non-cited violations identified in 2022
  • All Performance Indicators were Green

NRC Annual Assessment Summary MCGUIRE NUCLEAR STATION

  • McGuire Units 1 and 2 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2022
  • NRC plans to conduct routine baseline inspections at the McGuire Nuclear Station for 2023

QUESTIONS?

NRC Annual Assessment Summary

NRC Annual Assessment Summary OCONEE NUCLEAR STATION

  • Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
  • All findings associated with Oconee Nuclear Station in 2022 were Green

Findings and Performance Indicators OCONEE NUCLEAR STATION

  • 14 - non-cited violations identified in 2022 13 - Green 1 - traditional enforcement
  • All Performance Indicators were Green

NRC Annual Assessment Summary OCONEE NUCLEAR STATION

  • Oconee Units 1, 2, and 3 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2022
  • NRC plans to conduct routine baseline inspections at the Oconee Nuclear Station for 2023

QUESTIONS?

CONTACT THE NRC Web: https://www.nrc.gov Report an Emergency - 301-816-5100 Safety Concern or Allegations 800-695-7403 l allegation@nrc.gov Questions/Information - OPA2.Resource@nrc.gov or 404-997-4417

CONTACT THE RESIDENT INSPECTORS Catawba NRC resident inspectors

  • Phone (404) 997-5134
  • Phone (404) 997-5131 McGuire NRC resident inspectors
  • Phone (404) 997-5171
  • Phone (404) 997-5173 Oconee NRC resident inspectors
  • Phone (404) 997-5211
  • Phone (404) 997-5213
  • Phone (404) 997-5214

NRC ON SOCIAL MEDIA Twitter: https://twitter.com/nrcgov Facebook: https://www.facebook.com/nrcgov/

YouTube: https://www.youtube.com/user/NRCgov Flickr: https://www.flickr.com/photos/nrcgov/sets LinkedIn: https://www.linkedin.com/company/u-s--nuclear-regulatory-commission/

GovDelivery: https://service.govdelivery.com/accounts/USNRC/subscriber/new

FEEDBACK/COMMENTS/QUESTIONS Public Meeting Feedback Form:

1) Navigate to the Public Meeting Schedule (recently held)
2) click the Meeting Feedback link or the [more] link for this meeting
3) click the Meeting Feedback link on the Meeting Details page Nuclear Regulatory Commission l Region II April 17, 2023