ML15282A072

From kanterella
Jump to navigation Jump to search

Duke Energy Presentation in Support of October 13, 2015, Public Meeting with NRC Staff Pre-Application Meeting for LAR to Support Khu Stator Replacement
ML15282A072
Person / Time
Site: Oconee  
Issue date: 10/09/2015
From: Shingleton B
Duke Energy Carolinas
To:
Office of Nuclear Reactor Regulation
Whited, Jeffrey, NRR/DORL/LPLII-1
References
CAC MF6762, CAC MF6763, CAC MF6764
Download: ML15282A072 (26)


Text

Oconee Nuclear Station Pre-Application Meeting - October 13, 2015 LAR to Support Keowee Stator Replacement

Duke Participants

 Doug Phelps, Critical Systems Engineering Director, Oconee Nuclear Station

 Chris Wasik, Regulatory Affairs Manager, Oconee Nuclear Station

 Darla King, Keowee Electrical System Lead Engineer, Oconee Nuclear Station

 Boyd Shingleton, Licensing Lead Engineer for Stator LAR, Oconee Nuclear Station For Information Only 2

Agenda

 Introduction/Background Chris Wasik

 Proposed Technical Specification Change Chris Wasik

 Keowee Outage Timeline Doug Phelps

 Diverse Backup Power for Emergency Power System Doug Phelps

 Risk Reduction Measures Doug Phelps For Information Only 3

Introduction Chris Wasik Regulatory Affairs Manager, Oconee Nuclear Station For Information Only 4

Keowee Generator Stator Project

 Keowee Hydro Station commissioned in 1971

 2008 - 2009 preventative maintenance inspections identified aging mechanisms in rotor pole assemblies

 2009 Duke Energy started planning efforts to refurbish/overhaul both Keowee generators

 First phase refurbished/replaced all 56 generator field poles on each KHU

  • KHU-2 performed January 2014
  • KHU-1 performed July 2014

 Second phase is to replace stator for each KHU

  • KHU-1 scheduled January 2018
  • KHU-2 scheduled January 2019 5

For Information Only

Keowee Generator Stator Project 6

For Information Only

Keowee Generator Stator Project Licensing Background

 NRC approved LAR for one-time extended TS Completion Time to allow KHU rotor pole rewind work on January 8, 2014

 ONS plans to request a one-time extended TS Completion Time to allow stator on each KHU to be replaced

 Similar justification will be provided for stator LAR 7

For Information Only

Proposed Technical Specification Change

 Current TS 3.8.1 C - KHU aligned to the overhead path inoperable Cumulative 45 day Completion Time to restore inoperable KHU over a 3 year period

 The License Amendment Request (LAR) will request a one-time 55 day Completion Time for each KHU to allow stator replacement 8

For Information Only

Keowee Generator Stator Project Doug Phelps Critical Systems Engineering Director Oconee Nuclear Station 9

For Information Only

Keowee Generator Stator Project 10 For Information Only

 Implementation Strategy

 Original strategy was a standard rewind, estimated to require a 100-120 day Technical Specification (TS) Allowed Outage Time (AOT)

 Alternate strategy was developed based on benchmark trip

 Benchmark plant strategy was to pre-build stator remote to unit

 Feasibility study was conducted to determine if a pre-build strategy was viable for Keowee

 Study concluded pre-build stator strategy was feasible and reduces the required TS AOT by ~50%

 ONS selected option to pre-build the stator in an assembly building to minimize required TS AOT

 As a result, the scope of the project expanded to include:

New Frames Stator Assembly Building Powerhouse Modifications Heavy hauling from the assembly facility to the powerhouse and haul path evaluation

Keowee Generator Stator Outage Timeline 11 For Information Only Start Finish 55 Days - Total Work Window 2 days - Dewater Dual KHU Outage 24 days physical work, generator restoration & testing with contingency 25 days physical work with contingency 2 days - Dewater Dual KHU Outage 2 days - Generator Isolation & Prep for Rotor/Stator Lifts

Oconee Nuclear Station Pre-Application Meeting - October 13, 2015 LAR to Support Keowee Stator Replacement

Duke Participants

 Doug Phelps, Critical Systems Engineering Director, Oconee Nuclear Station

 Chris Wasik, Regulatory Affairs Manager, Oconee Nuclear Station

 Darla King, Keowee Electrical System Lead Engineer, Oconee Nuclear Station

 Boyd Shingleton, Licensing Lead Engineer for Stator LAR, Oconee Nuclear Station For Information Only 2

Agenda

 Introduction/Background Chris Wasik

 Proposed Technical Specification Change Chris Wasik

 Keowee Outage Timeline Doug Phelps

 Diverse Backup Power for Emergency Power System Doug Phelps

 Risk Reduction Measures Doug Phelps For Information Only 3

Introduction Chris Wasik Regulatory Affairs Manager, Oconee Nuclear Station For Information Only 4

Keowee Generator Stator Project

 Keowee Hydro Station commissioned in 1971

 2008 - 2009 preventative maintenance inspections identified aging mechanisms in rotor pole assemblies

 2009 Duke Energy started planning efforts to refurbish/overhaul both Keowee generators

 First phase refurbished/replaced all 56 generator field poles on each KHU

  • KHU-2 performed January 2014
  • KHU-1 performed July 2014

 Second phase is to replace stator for each KHU

  • KHU-1 scheduled January 2018
  • KHU-2 scheduled January 2019 5

For Information Only

Keowee Generator Stator Project 6

For Information Only

Keowee Generator Stator Project Licensing Background

 NRC approved LAR for one-time extended TS Completion Time to allow KHU rotor pole rewind work on January 8, 2014

 ONS plans to request a one-time extended TS Completion Time to allow stator on each KHU to be replaced

 Similar justification will be provided for stator LAR 7

For Information Only

Proposed Technical Specification Change

 Current TS 3.8.1 C - KHU aligned to the overhead path inoperable Cumulative 45 day Completion Time to restore inoperable KHU over a 3 year period

 The License Amendment Request (LAR) will request a one-time 55 day Completion Time for each KHU to allow stator replacement 8

For Information Only

Keowee Generator Stator Project Doug Phelps Critical Systems Engineering Director Oconee Nuclear Station 9

For Information Only

Keowee Generator Stator Project 10 For Information Only

 Implementation Strategy

 Original strategy was a standard rewind, estimated to require a 100-120 day Technical Specification (TS) Allowed Outage Time (AOT)

 Alternate strategy was developed based on benchmark trip

 Benchmark plant strategy was to pre-build stator remote to unit

 Feasibility study was conducted to determine if a pre-build strategy was viable for Keowee

 Study concluded pre-build stator strategy was feasible and reduces the required TS AOT by ~50%

 ONS selected option to pre-build the stator in an assembly building to minimize required TS AOT

 As a result, the scope of the project expanded to include:

New Frames Stator Assembly Building Powerhouse Modifications Heavy hauling from the assembly facility to the powerhouse and haul path evaluation

Keowee Generator Stator Outage Timeline 11 For Information Only Start Finish 55 Days - Total Work Window 2 days - Dewater Dual KHU Outage 24 days physical work, generator restoration & testing with contingency 25 days physical work with contingency 2 days - Dewater Dual KHU Outage 2 days - Generator Isolation & Prep for Rotor/Stator Lifts

ONS Electrical Distribution System 12 For Information Only A

HPSWP B

PSWP

ONS Transmission Lines 13 For Information Only Oconee Nuclear Station Oconee Nuclear Station

Defense-in-Depth - Multiple Diverse Backup Power Sources 14 For Information Only

  • commercial power feed during dual KHU outage, Keowee or commercial power feed during single KHU outage

Backup Power for Emergency Power System

 Proposed LAR will credit the following backup power sources:

Underground Keowee Hydro Unit Dedicated Lee Combustion Turbine energizing both Standby Buses during extended completion time Remaining LCT available and capable of energizing the Standby Buses within one hour Required offsite power sources available SSF capable of mitigating SBO for at least 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Two dedicated Jocassee Hydro Units available either of which has capacity of powering ONS shutdown loads in approximately one hour Temporary diesel generator at Keowee capable of restoring unwatered Underground KHU within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> PSW power system capable of powering SSF FLEX equipment available 15 For Information Only

Alternate Methods of Maintaining Safe Shutdown

 The following systems/equipment can be used to maintain all three Oconee units in a safe shutdown condition:

  • SSF operable and capable of providing alternate shutdown capability
  • PSW System operable and capable of providing alternate shutdown capability
  • FLEX equipment available

 One or more of the following power sources can be used to place all three Oconee units in cold shutdown:

  • One LCT energizing ONS standby buses prior to outage start
  • Underground KHU
  • A second LCT can be started and aligned to the standby buses within one hour
  • Two Jocassee Hydro Units available, either of which can be aligned to the Oconee 230kV Yellow Bus in approximately one hour
  • Any of multiple offsite power sources 16 For Information Only

Lee Combustion Turbines

 Two LCTs (7C, 8C) available to power Oconee standby buses

 Dedicated line electrically separated from the system grid and offsite loads

 Capacity to supply ONS shutdown loads

 Routinely operated/tested, demonstrating reliability

 Black start capable, tested annually

 Included in the ONS Normal and Emergency Operating Procedures

 Verified available each shift

 Staffed continuously 17 For Information Only

Lee Combustion Turbines 18 For Information Only

Jocassee Hydro Station

 Two of the four Jocassee Hydro Units can be separated from the grid and dedicated to ONS in approximately one hour

 Each Jocassee Hydro Station unit is rated at 195 MVA

 Two transmission lines, north of ONS, directly connect the Jocassee 230 kV switchyard to the Oconee 230 kV switchyard

 Capacity to supply ONS shutdown loads

 Routinely operated/tested, demonstrating reliability

 Black start capable, tested annually

 Included in the ONS Emergency Operating Procedures

 Verified available each shift

 Staffed continuously 19 For Information Only

Jocassee Hydro Station 20 For Information Only

Temporary DG located at Keowee for restoring U/G KHU

 Onsite DG supplies backup power to KHS during dual KHU outage when unwatered

 Adequate capacity to restore the underground KHU

 Allows for rapid restoration of the underground KHU during loss of all power ( 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />)

 Black start capable

 Use approved Keowee operating procedures

 Operated and tested prior to outage

 Verified available each shift

 Keowee Hydro Station continuously staffed 21 For Information Only

Standby Shutdown Facility and Protected Service Water System Standby Shutdown Facility



Provides an alternate means to achieve and maintain the ONS units in safe shutdown conditions



Provides additional defense in depth protection by serving as a backup to existing safety systems



Includes a dedicated power system including a diesel generator



Credited to mitigate Station Blackout, and other non design basis events



Mission time is 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />



Staffed continuously during dual KHU outages Protected Service Water



Provides an alternate means to achieve and maintain the ONS units in safe shutdown conditions



Provides additional defense in depth protection by serving as a backup to existing safety systems



Alternate power path to connect the SSF switchgear, with sufficient capacity to operate SSF equipment in the event of a failure of the SSF diesel generator 22 For Information Only

Risk Reduction Measures - Regulatory Commitments Duke Energy will commit to the following:

 ONS will not start the extended single KHU outage or a dual KHU outage if severe weather conditions are forecast within the next two days.

 ONS will contact the system load dispatcher once per day to ensure no significant grid perturbations (high grid loading not able to withstand a single contingency of line or generation outage) are expected during extended TS completion time.

 ONS will avoid component testing or maintenance of safety systems and important non safety equipment in the offsite power systems that can increase the likelihood of a plant transient (unit trip) or LOOP. In addition, no discretionary switchyard maintenance will be performed.

 ONS will verify that TS required systems, subsystems, trains, components, and devices that depend on the remaining power sources are operable and preclude subsequent nondiscretionary testing or maintenance activities on these systems, subsystems, trains, components, and devices during the extended TS completion time.

 ONS will control the steam-driven emergency feedwater pump(s) as protected equipment during the extended TS completion time.

 ONS will continuously staff the SSF during the dual KHU outages in which the intake is de-watered.

23 For Information Only

Other Risk Reduction Measures Critical Activity Plan, approved by the Plant Operations Review Committee prior to implementation, used for risk management. Plan will include the following risk reduction measures:

 LCT and Central Switchyard protected

 2nd LCT protected and available within one hour

 Two Jocassee Hydro Units available either of which can be aligned to the Oconee 230kV Yellow Bus in approximately one hour

 Temporary DG located at Keowee Hydro Station with capability to restore available KHU unit to operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from dual KHU outage

 Reduced RCS Inventory not permitted during dual KHU outage

 PSW available to backup SSF

 FLEX equipment available 24 For Information Only

Summary

 Stator replacement is needed and will improve equipment reliability for emergency power system

  • Stator replacement outages scheduled for January 2018 and January 2019

 Additional diverse backup power sources result in electrical system defense-in-depth that provides level of protection equivalent with Branch Technical Position guidelines

 Additional risk reduction measures will be implemented and managed by critical activity plan

 Staff approval of LAR is essential to allow Duke Energy to implement KHU reliability improvements 25 For Information Only

26