UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 June 3, 2014 MEETING

SUMMARY

LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY: VERMONT YANKEE NUCLEAR POWER STATION

SUBJECT:

SUMMARY

OF PUBLIC MEETING On May 28, 2014, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public meeting/open-house at the Brattleboro High School in Brattleboro, VT. The NRC conducted the open house and question and answer portion to discuss its assessment of the safety performance at Vermont Yankee Nuclear Power Station for 2013.

A notice of the public meeting/open-house was issued on May 7, 2014, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML14127A345.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented fact sheets and reading material, and was available to discuss its assessment of the safety performance of Vermont Yankee for the period of January 1 through December 31, 2013, as documented in our letter dated March 4, 2014 (ADAMS Accession No. ML14059A297). The NRC fact sheets and reading material included background on the Reactor Oversight Process. Additional information relative to the NRC's annual assessment process and the safety performance of Vermont Yankee can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, Local officials, State officials, and members of the media attended the public meeting/open-house and were offered the opportunity to question the NRC regarding Vermont Yankees performance and the role of the agency in ensuring safe plant operations.

/RA/

Raymond R. McKinley, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

1. Attendee List (ML14154A151)
2. NRC Presentation (ML14154A252)

ML14059A297). The NRC fact sheets and reading material included background on the Reactor Oversight Process. Additional information relative to the NRC's annual assessment process and the safety performance of Vermont Yankee can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, Local officials, State officials, and members of the media attended the public meeting/open-house and were offered the opportunity to question the NRC regarding Vermont Yankees performance and the role of the agency in ensuring safe plant operations.

/RA/

Raymond R. McKinley, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

1. Attendee List (ML14154A151)
2. NRC Presentation (ML14154A252)

Distribution: (via email)

R. McKinley, DRP S. Rich, DRP, RI S. Shaffer, DRP A. Rancourt, DRP, AA J. DeBoer, DRP RidsNRRPMVermontYankee Resource S. Rutenkroger, DRP, SRI DOC NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2013 EOC\Meeting Summaries\Annual Assessment Meeting Summary Vermont Yankee.docx ADAMS Accession No. ML14154A442 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SShaffer/SWS RMcKinley/RRM DATE 6/3/2014 6/3/2014