January 24, 2017, Summary of NRC Public Meeting on the Proposed License Transfer of Vermont Yankee for Decommissioning
ML17031A277
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 02/01/2017
From:
Office of Nuclear Material Safety and Safeguards
To:
J. Parrott NMSS/DUWP/RDB 415-6634 T-8E47
References
Download: ML17031A277 (4)


Text

February 1, 2017 MEETING REPORT MEETING DATE: January 24, 2017 TIME: 10:00 am - 11:30 am EST PLACE: U.S. Nuclear Regulatory Commission Three White Flint North Building 11601 Landsdown Street, Room 1C03 Rockville, Maryland PURPOSE: To discuss a proposal to transfer the Vermont Yankee Nuclear Power Station 10 CFR Part 50 license and decommissioning trust fund from Entergy Nuclear (Entergy) to NorthStar Group Services, Inc. (NorthStar).

The meeting announcement is publicly available in NRCs Agencywide Documents Access and Management System (ADAMS) at accession number ML17006A204.

ATTENDEES: See Enclosure 1 DISCUSSION: Entergy and NorthStar provided a presentation on the proposal to transfer the license and decommissioning trust fund of the permanently shutdown Vermont Yankee Nuclear Power Station (VYNPS), from Entergy to NorthStar for the purposes of decommissioning. The presentation covered the current status of the VYNPS and current approach to decommissioning, a timeline for decommissioning under the proposed approach, gave an overview of the NorthStar approach, their teaming partners, their technical qualifications, financial assurance, plan for spent fuel management and other topics such as foreign ownership and control, insurance coverage. The decommissioning strategy would go from the currently planned SAFSTOR method to an immediate DECON method thus shortening the decommissioning period by as much as 43 years.

The decommissioning trust fund, site property, and title to the spent fuel would transfer to NorthStar upon successful transfer of the NRC license, successfully obtaining a certificate of public good from the Vermont Public Service Board, and successful transfer of the spent fuel to dry cask storage. NorthStar would retain ownership of the site property and spent fuel after the completion of decommissioning. The NorthStar presentation is in ADAMS at ML17019A145.

NRC gave a presentation on the process for reviewing license transfer requests, the review criteria, and the fact that the NRC safety, security, and financial assurance oversight continues for the site before, during and after the license transfer review process. The NRC presentation is in ADAMS at ML17024A106.

ACTIONS: The licensee intends to submit a formal request for the license transfer at by the end of February 2017. NRC will consider holding a public meeting

after the request for license transfer is submitted. NRC will also establish a web page to post links to licensing documents related to this license transfer.

Docket No./

License No.: 05000271/DPR-28

DISTRIBUTION:

cc: Vermont Yankee ListServ JTappert AKock BWatson JParrott ABowers, NRR VWilliams, NSIR JWachutka, OGC RPowell, RI JWeil, OCA DMcIntyre, OPA JKim, NRR DTiftt, RI ML17031A277 OFFICE DUWP/RDB/PM DUWP/RDB/BC NAME JParrott BWatson DATE 02/01/2017 02/01/2017

Attendees for January 24, 2017 Meeting Between NRC and Entergy/NorthStar John Tappert NRC Andrea Kock NRC Bruce Watson NRC Jack Parrott NRC Anthony Bowers NRC Mike Dusaniwskyj NRC Eric Olvera NRC Ruth Murray NRC Jim Kim NRC Jenny Weil NRC Jeremy Wachutka NRC Dave McIntyre NRC Vince Williams NRC Steve Hammann NRC Steven Scheurich Entergy Paul Paradis Entergy Andrew Rosenlieb Entergy John Gordon Entergy Phil Couture Entergy Susan Raimo Entergy Scott State NorthStar Scott LaBuy NorthStar Billy Reid NorthStar Gregory DiCarlo NorthStar Frederic Bailly Areva Rod Baltzer WCS John Neises Burns & McDonnell Thomas Magette PwC John Matthews Morgan Lewis Willis Bixby Energy Solutions David Lewis Pillsbury Tim Judson NIRS Diane DArrigo NIRS Kevin Kamps Beyond Nuclear Enclosure 1