Other: ML110872079, ML11145A064, ML11256A057, ML11256A058, ML11256A059, ML12011A188, ML12086A081, ML12264A642, ML13029A497, ML13032A074, ML13063A071, ML13198A056, ML13253A163, ML16118A311, NOC-AE-12002780, Clarification of Information in Support of the Review of the License Renewal Application, NOC-AE-13002945, Update to License Renewal Application - Environmental Permits
|
MONTHYEARML1030102572010-10-25025 October 2010 Transmittal of License Renewal Application Project stage: Request ML1108720792011-04-0505 April 2011 Project Manager Change for the License Renewal of South Texas Project, Units 1 and 2 Project stage: Other ML11145A0642011-06-21021 June 2011 Plan for the Environmental Related Regulatory Audit Regarding the South Texas Project, Units 1 and 2, License Renewal Application Review Project stage: Other ML11193A0162011-07-0505 July 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application Project stage: Response to RAI ML11193A0742011-07-0505 July 2011 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI NOC-AE-11002687, Response to Request for Additional Information for the South Texas Project License Renewal Application2011-07-0505 July 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application Project stage: Response to RAI NOC-AE-11002691, Response to Request for Additional Information for the Review of the License Renewal Application2011-07-0505 July 2011 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML11154A0132011-07-0606 July 2011 Summary of Telephone Conference Call Held on May 23, 2011, Between the NRC and STPNOC, Concerning Requests for Additional Information Pertaining to the South Texas Project, LRA-Future Consideration of Operating Experience Project stage: RAI ML11201A0622011-08-0404 August 2011 Request for Additional Information for the Review of the South Texas Project, License Renewal Application Project stage: RAI ML1123000162011-08-18018 August 2011 License Renewal - Errata in AMP RAI Package Project stage: RAI ML11214A2072011-08-18018 August 2011 RAI for the Review of the STP, License Renewal Application (TAC No. ME4938 and ME512) Project stage: RAI ML11250A0672011-08-23023 August 2011 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI NOC-AE-11002711, Response to Request for Additional Information for License Renewal Application2011-08-23023 August 2011 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI ML11256A0572011-08-31031 August 2011 Documents to Support Review of the South Texas Project License Renewal Application, List of Transmitted Documents Including Copy of Each Document, Enclosure to NOC-AE-11002720 Project stage: Other ML11256A0582011-08-31031 August 2011 Documents to Support Review of the South Texas Project License Renewal Application, WR-5, TCEQ Id No. 1610103/1610051 (Operation of Public Potable Water System) Project stage: Other ML11256A0562011-08-31031 August 2011 Transmittal of Documents to Support Review of the South Texas Project License Renewal Application Project stage: Request ML11256A0592011-08-31031 August 2011 Documents to Support Review of the South Texas Project License Renewal Application, WR- 11, a Summary of Historic and Current (Past 5 Years) Total Dissolved Solids (Tds) Data for Groundwater Produced by STP Production Wells from the Deep Ch Project stage: Other ML1123601142011-09-0101 September 2011 Request for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: RAI ML11255A2112011-09-0606 September 2011 Response to Request for Additional Information for the License Renewal Application Project stage: Response to RAI NOC-AE-11002719, Response to Request for Additional Information for the License Renewal Application2011-09-0606 September 2011 Response to Request for Additional Information for the License Renewal Application Project stage: Response to RAI ML11259A0312011-09-12012 September 2011 Transmittal of Document to Support Review of the License Renewal Application Project stage: Request NOC-AE-11002723, Response to Requests for Additional Information for the License Renewal Application2011-09-12012 September 2011 Response to Requests for Additional Information for the License Renewal Application Project stage: Response to RAI NOC-AE-11002734, Transmittal of Document to Support Review of the License Renewal Application2011-09-12012 September 2011 Transmittal of Document to Support Review of the License Renewal Application Project stage: Request ML11259A0142011-09-12012 September 2011 Response to Requests for Additional Information for the License Renewal Application Project stage: Response to RAI ML11270A0602011-09-22022 September 2011 Response to Requests for Additional Information for License Renewal Application Project stage: Response to RAI ML11269A0022011-09-28028 September 2011 Requests for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: RAI ML11298A0852011-10-18018 October 2011 Response to Requests for Additional Information for License Renewal Application Project stage: Response to RAI NOC-AE-11002761, Clarification to Response to Request for Additional Information for License Renewal Application (TAC No. ME4938 & ME5122)2011-11-17017 November 2011 Clarification to Response to Request for Additional Information for License Renewal Application (TAC No. ME4938 & ME5122) Project stage: Response to RAI ML11333A0942011-11-17017 November 2011 Clarification to Response to Request for Additional Information for License Renewal Application (TAC No. ME4938 & ME5122) Project stage: Supplement NOC-AE-12002780, Clarification of Information in Support of the Review of the License Renewal Application2012-01-10010 January 2012 Clarification of Information in Support of the Review of the License Renewal Application Project stage: Other ML12011A1882012-01-10010 January 2012 Clarification of Information in Support of the Review of the License Renewal Application Project stage: Other NOC-AE-110027, Supplemental Response to Requests for Additional Information for the South Texas Project License Renewal Application - SAMA2012-01-19019 January 2012 Supplemental Response to Requests for Additional Information for the South Texas Project License Renewal Application - SAMA Project stage: Supplement NOC-AE-120027, Clarification to Supplemental Response to Request for Additional Information for the South Texas Project License Renewal Application - SAMA2012-02-16016 February 2012 Clarification to Supplemental Response to Request for Additional Information for the South Texas Project License Renewal Application - SAMA Project stage: Supplement ML12017A1282012-02-29029 February 2012 RAI for the Review of the STP LRA Project stage: RAI ML12047A2852012-02-29029 February 2012 January 17, 2012, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission & STP Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the South Texas Project License Renewal Project stage: RAI ML12079A0142012-03-12012 March 2012 Response to Requests for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Response to RAI NOC-AE-12002818, Response to Requests for Additional Information for the Review of the South Texas Project License Renewal Application2012-03-12012 March 2012 Response to Requests for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Response to RAI ML11290A2262012-03-19019 March 2012 Revision of Schedule for the Conduct of Environmental Review of the South Texas Project License Renewal Application Project stage: Approval ML12128A0612012-05-0404 May 2012 NRR E-mail Capture - NEPA Consultation - Waterborne Outbreak Project stage: Request ML12142A0022012-05-18018 May 2012 NRR E-mail Capture - Environmental Permit Updated Status Project stage: Request ML12144A4432012-06-25025 June 2012 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application- Aging Management, Set 20 TAC Nos. ME4939 and ME4937) STP-RAIs-Set 20-RAI Project stage: RAI ML12171A4832012-08-10010 August 2012 Revision of Schedule for the Conduct of Environmental Review of the South Texas Project License Renewal Application Project stage: Approval ML11153A0822012-11-14014 November 2012 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by STP Nuclear Operating Company for Renewal of the Operating License for South Texas Project, Units 1 and 2 Project stage: Approval ML12264A6422012-11-14014 November 2012 STP Scoping Report_Paula Cooper Project stage: Other ML12086A0812012-11-14014 November 2012 Environmental Impact Statement Scoping Process Summary Report for South Texas Project, Units 1 and 2 Project stage: Other ML12324A0492012-11-30030 November 2012 NUREG-1437 Supp 48 Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding South Texas Project, Units 1 and 2 (Draft for Comment) Project stage: Draft Other ML12339A2652012-12-0505 December 2012 Notice of Availability of the Draft Plant-Specific Supplement 48 to the GEIS for License Renewal of Nuclear Plants Regarding South Texas Project, Units 1 and 2, Project stage: Draft Other ML12195A0852012-12-0505 December 2012 Notice of Availability of the Draft Plant-Specific Supplement 48 to the GEIS for License Renewal of Nuclear Plants Regarding South Texas Project, Units 1 and 2, Project stage: Draft Other ML13029A4972013-01-15015 January 2013 Slides - Preliminary Site-Specific Results of the Environmental Review for South Texas Project License Renewal Project stage: Other ML13029A7552013-01-15015 January 2013 Transcript of South Texas Project License Renewal Public Meeting: Afternoon Session, January 15, 2013, Pages 1-34 Project stage: Meeting 2011-09-28
[Table View] |
Text
UNITED STATES*
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 February ii, 2013 Mr. D. W. Rencurrel Senior Vice President, Technical Support and Oversight STP Nuclear Operating Company P.O. Box 289 Wadsworth,TX 77483
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE SOUTH TEXAS PROJECT LICENSE RENEWAL APPLICATION (TAC NOS. ME5122, ME5123, ME4938, AND ME4939)
Dear Mr. Rencurrel:
By letter dated October 25, 2010, STP Nuclear Operating Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54), to renew operating licenses NPF-76 and NPF-80 for the South Texas Project (STP), Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you about a schedule change in the STP license renewal review.
On August 10, 2012, the NRC revised the environmental review schedule showing future environmental dates as "to be determined" in order to allow the staff to determine the impacts of a United States Court of Appeals for the District of Columbia decision on the NRC waste confidence rule update (10 CFR 51.23). The NRC has completed its evaluation and subsequently issued the draft supplemental environmental impact statement for STP license renewal. The enclosed schedule has been updated to reflect updates to future environmental review milestones.
If you have any questions on the revised schedule, please contact Tam Tran by telephone at 301-415-3617 or bye-mail at tam.tran@nrc.gov.
Sincerely, John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
As stated cc w/encl: Listserv
I SOUTH TEXAS PROJECT LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 10/26/10 10/28/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 12/09/10 12/09/10 Publish FRN -LRA acceptability, environmental scoping period, and opportunity for hearing 01/13/11 01/13/11 Publish FRN -intent to conduct environmental scoping i Publi,c Meeting -license renewal process and environmental scoping 01/31/11 03/02/11
~11 2111 i Deadline for filing hearing requests and petitions for intervention 03/14/11 03/14/11 Environmental scoping periods ends 04/01/11 04/01/11 Audit - scoping and screening methodology 05/16/11 05/20/11 Audit - aging management programs (AMPs) 06/13/11 06/24/11 Audit - environmental 07/11/11 07/11/11 Inspection - scoping, screening, and AMPs 08/2011 08/07/11 Issue draft supplemental environmental impact statement (SEIS) 12/05/12 12/5112 Public Meeting - draft SEIS 01/15/13 01/15/13 Issue safety evaluation report (SER) with open item{s)
TBD*
End of comment period for the draft SEIS 02/22/13 ACRS subcommittee meeting on SER with open item(s)
TBD Issue final SEIS 07/13 Issue SER TBD ACRS full committee meeting on SER TBD NRR decision TBD
ENCLOSURE
ML13011A131
- concurred via email OFFICE PM:DLR/RF LA:DLR/RPB2*
OGC BC:DLR/RPB1 NAME TTran IKing LSubin DMorey DATE 1/18/13 1/18/13 2/4113 1/24/13 OFFICE BC:DLR/RP D:DLR NAME DWrona JLubinski (MAGalioway fort DATE 1128/13 2/11/13
Letter to D. Rencurrel from J. Lubinski dated February 11, 2013
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE SOUTH TEXAS PROJECT LICENSE RENEWAL APPLICATION (TAC NOS. ME5122, ME5123, ME4938, AND ME4939)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter
~IDaily TTran ICouret, OPA BSingal, DORL NO'Keefe GPick, RIV JDixon, RIV VDricks, RIV WMaier, RIV AVegel, RIV