Summary of Telephone Conference Call Held on July 16, 2013, Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Concerning a Schedule Change for the Review of the South Texas Project, License Renewal Applicatio
ML13200A140
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 08/08/2013
From: Tam Tran
Division of License Renewal
To:
South Texas
Tam Tran 301-415-3617
References
TAC ME4938, TAC ME4939, TAC ME5122, TAC ME5123
Download: ML13200A140 (5)


Text

\\..~,..I\\ R£GIJ~

UNITED STATES

~v(,

"'01' NUCLEAR REGULATORY COMMISSION

(;

. ~

WASHINGTON, D.C. 20555-0001 0

Ii) f

\\

I August 8, 2013

'f,<?

~o LICENSEE:

STP Nuclear Operating Company FACILITY:

South Texas Project

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JULY 16,2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND STP NUCLEAR OPERATING COMPANY, CONCERNING A SCHEDULE CHANGE FOR THE REVIEW OF THE SOUTH TEXAS PROJECT, LICENSE RENEWAL APPLICATION (TAC. NOS. ME4938, ME4939, ME5122, AND ME5123)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of STP Nuclear Operating Company held a telephone conference call on July 16, 2013, to discuss and clarify about the change of the issuance of the final Supplemental Environmental Impact Statement milestone from July 2013 to September 2013, related to the review of the South Texas Project license renewal application. The telephone conference call was useful in clarifying the reason for the schedule change and the new milestone. The applicant had an opportunity to comment on this summary. provides a listing of the participants and Enclosure 2 contains a summary of the discussion with the applicant.

~fi~

Tam Tran, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499

Enclosures:

1. List of Participants
2. Summary of the discussion cc: Listserv

ML13200A140 OFFIC~RPB1 :DLR PM:RPB2:DLR BC:RPB2:DLR NAME Edmonds ITran ASimmons DATE 18/02/13 815/13 8/8/13

SUBJECT:

Summary of Telephone Conference Call conducted on August 8, 2013.

DISTRIBUTION:

HARDCOPY:

DLRRF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter JDaily TIran DMclntyre, OPA BSingal, DORL Vl/Walker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NOKeefe, RIV AVegel, RIV SGraves, RIV

PARTICIPANT A. Simmons T. Tran A Aldridge K. Taplett M. Murray Rob Engen TELEPHONE CONFERENCE CALL SOUTH TEXAS PROJECT LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AFFILIATION Nuclear Regulatory Commission (NRC)

NRC STP Nuclear Operating Company (STPNOC)

STPNOC STPNOC STPNOC ENCLOSURE 1

SUMMARY

OF DISCUSSION LICENSE RENEWAL APPLICATION SOUTH TEXAS PROJECT The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of STP Nuclear Operating Company held a telephone conference call on July 16, 2013, to discuss and clarify about the change of the issuance of the final Supplemental Environmental Impact Statement milestone from July 2013 to September 2013, concerning the review of the South Texas Project license renewal application.

Discussion

  • The need for the schedule change NRC issued the newly revised Generic Environmental Impact Statement (GElS) on June 20, 2013. The staff needs additional time for the environmental review of STP license renewal to take into consideration the information presented in the newly revised GElS.
  • Reasons for the change of the final Supplemental Environmental Impact Statement (FSEIS) milestone from July 2013 to September 2013 The additional times would allow the staff to update the information in the FSEIS to be consistent with the newly revised GElS (e.g., cumulative impacts for socio economic, consistent descriptions of the baseline conditions of the affected environment, etc.)
  • Sensitivity to project schedule for the completion of the FSEIS The staff is aware of the STPNOC needs for an efficient review and will keep STPNOC informed early if there are any changes to the FSEIS review. The staff will make every effort to meet the September milestone.

ENCLOSURE 2