ML12132A067
Letter Sequence Draft RAI | |
---|---|
Initiation Administration | |
MONTHYEARML1011601822010-04-16016 April 2010
[Table View]St. Lucie Unit 1 License Amendment Request for Extended Power Uprate Project stage: Request L-2010-181, Withdrawal of Extended Power Uprate License Amendment Request2010-08-13013 August 2010 Withdrawal of Extended Power Uprate License Amendment Request Project stage: Withdrawal ML1035604192010-11-22022 November 2010 St. Lucie, Unit 1 - Transmittal of Affidavits from Westinghouse, Areva and Caldon Ultrasonica Technology Center Re License Amendment Request for Extended Power Uprate Project stage: Request L-2010-302, License Amendment Request for Extended Power Uprate2010-12-15015 December 2010 License Amendment Request for Extended Power Uprate Project stage: Request ML1107301162011-02-25025 February 2011 St. Lucie, Unit 2 - License Amendment Request for Extended Power Uprate Project stage: Request ML1107302822011-02-25025 February 2011 St. Lucie, Unit 2 - License Amendment Request for Extended Power Uprate, Attachment 2; Supplemental Environmental Report Project stage: Supplement ML1105906632011-03-0909 March 2011 Acceptance for Review of License Amendment Request for Extended Power Uprate Project stage: Acceptance Review ML1110100982011-04-19019 April 2011 Request for Additional Information Regarding License Amendment Request for Extended Power Uprate Project stage: RAI ML1113200042011-05-12012 May 2011 EPU - Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Project stage: Acceptance Review ML11153A0482011-05-27027 May 2011 St. Lucie Plant, Unit 1 - Information Regarding Areva LOCA and Non-LOCA Methodologies Provided in Support of the License Amendment Request for Extended Power Uprate Project stage: Request NRC-2011-0128, St. Lucie, Unit 1 - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Documents Access to Sensitive Unclassified Nonsafeguards Information2011-06-0202 June 2011 St. Lucie, Unit 1 - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Documents Access to Sensitive Unclassified Nonsafeguards Information Project stage: Approval ML11119A0852011-06-0202 June 2011 Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Documents Access to Sensitive Unclassified Nonsafeguards Information Project stage: Other ML11119A0842011-06-0808 June 2011 Transmittal Letter - Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing and Order Imposing Procedures for Document Access to Sensitive Unclassified Non Safeguards Information Project stage: Other ML11173A1042011-06-23023 June 2011 Acceptance for Review of License Amendment Request for Extended Power Uprate Project stage: Acceptance Review ML12037A1472011-07-21021 July 2011 NRR E-mail Capture - Efh Species for St. Lucie Project stage: Request L-2011-273, Information Regarding Anticipated Transients Without Scram (ATWS) Provided in Support of the Extended Power Uprate License Amendment Request2011-07-22022 July 2011 Information Regarding Anticipated Transients Without Scram (ATWS) Provided in Support of the Extended Power Uprate License Amendment Request Project stage: Request L-2011-314, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-08-12012 August 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request NRC-2011-0190, St. Lucie Nuclear Plant, Units 1 and 2 - Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI2011-08-26026 August 2011 St. Lucie Nuclear Plant, Units 1 and 2 - Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Info Project stage: Approval ML11208B6442011-08-26026 August 2011 Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Information Project stage: Other ML11208B6422011-09-0101 September 2011 Transmittal Letter - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Information Project stage: Other ML1123602302011-09-0202 September 2011 Request for Concurrence on List of Species with Essential Fish Habitat in the Vicinity of the St. Lucie Plant, Units 1 and 2 Project stage: Other L-2011-360, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-0202 September 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-397, Unusual or Important Environmental Event - Reportable Fish Kill2011-09-20020 September 2011 Unusual or Important Environmental Event - Reportable Fish Kill Project stage: Request L-2011-389, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-22022 September 2011 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-383, Response to NRC Containment and Ventilation Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-22022 September 2011 Response to NRC Containment and Ventilation Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-410, Environmental Protection Plan Report 316(b) Related Documentation2011-09-30030 September 2011 Environmental Protection Plan Report 316(b) Related Documentation Project stage: Request L-2011-422, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information and Supplemental Information Regarding Extended Power Uprate License Amendment Request2011-10-10010 October 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information and Supplemental Information Regarding Extended Power Uprate License Amendment Request Project stage: Supplement L-2011-450, Submittal of Final Revised Industrial Wastewater Facility Permit No. FL0002208, and Environmental Protection Plan Report2011-10-20020 October 2011 Submittal of Final Revised Industrial Wastewater Facility Permit No. FL0002208, and Environmental Protection Plan Report Project stage: Request L-2011-448, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-10-31031 October 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-466, Revision to Extended Power Uprate License Amendment Request Proposed Technical Specification 5.6, Design Features - Fuel Storage - Criticality2011-11-0404 November 2011 Revision to Extended Power Uprate License Amendment Request Proposed Technical Specification 5.6, Design Features - Fuel Storage - Criticality Project stage: Request L-2011-467, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-11-14014 November 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-493, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-11-23023 November 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-524, Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-12-27027 December 2011 Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request ML11332A0202011-12-28028 December 2011 Transmittal Letter - Draft Environmental Assessment and Draft Finding of No Significant Impact Related to the Proposed Extended Power Uprate Project stage: Draft Other ML11332A0212011-12-28028 December 2011 Federal Register Notice - Draft Environmental Assessment and Draft Finding of No Significant Impact Related to the Proposed Extended Power Uprate Project stage: Request L-2011-533, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-12-29029 December 2011 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-565, Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-532, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-566, Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-441, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-18018 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-534, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-18018 January 2012 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-009, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-21021 January 2012 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-012, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-21021 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-043, Comment (1) of Richard L. Anderson, on Behalf of Florida Power & Light, Regarding Draft Environmental Assessment and Draft Finding of No Significant Impact Related the Proposed Extended Power Uprate2012-01-30030 January 2012 Comment (1) of Richard L. Anderson, on Behalf of Florida Power & Light, Regarding Draft Environmental Assessment and Draft Finding of No Significant Impact Related the Proposed Extended Power Uprate Project stage: Draft Other ML12044A1272012-02-13013 February 2012 Comment (2) from Edward W. Johnson Opposing Ncr Permit Approval for St. Lucie 1 & 2 Project stage: Request L-2012-059, Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-02-29029 February 2012 Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-075, Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0606 March 2012 Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-100, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0606 March 2012 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-094, Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0808 March 2012 Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-106, Response to Nuclear Performance and Code Review Branch Request for Additional Information Identified During an Audit of Analyses Supporting the Extended Power Uprate License Amendment Request2012-03-15015 March 2012 Response to Nuclear Performance and Code Review Branch Request for Additional Information Identified During an Audit of Analyses Supporting the Extended Power Uprate License Amendment Request Project stage: Request 2011-06-23 |
ML12132A067 | |
Person / Time | |
---|---|
Site: | Saint Lucie |
Issue date: | 05/02/2012 |
From: | Orf T Division of Operating Reactor Licensing |
To: | Travers A Division of License Renewal |
References | |
TAC ME5091, TAC ME5843 | |
Download: ML12132A067 (9) | |
Similar Documents at Saint Lucie | |
---|---|
Category:E-Mail
MONTHYEARML24281A1592024-10-0707 October 2024
[Table view]Acceptance Review for FPL LAR - St. Lucie Unit 2 - Fuel Methodology Changes in Support of Transition to 24- Month Fuel Cycles ML24254A2562024-09-0606 September 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for August 2024 ML24248A2422024-09-0404 September 2024 Acceptance Review for St. Lucie, Unit 2 - Relief Request (RR) 14: Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval ML24246A0152024-08-12012 August 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for July 2024 ML24194A1222024-07-11011 July 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for June 2024 ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24176A1612024-06-15015 June 2024 NRR E-mail Capture - (External_Sender) May 2024 FPL Marine Turtle Removal Monthly Report ML24150A2192024-05-29029 May 2024 (E-Mail) St. Lucie, Unit 2 - License Amendment Request, Updated Spent Fuel Pool Criticality Analysis - Acceptance Review ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24134A0142024-05-10010 May 2024 NRR E-mail Capture - (External_Sender) Pasl Monthly Turtle Report for April 2024 ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML24113A0372024-04-22022 April 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 and St. Lucie 2 - Request to Use Later Code of ASME (L-2024-LLR-0024) ML24101A2202024-04-0808 April 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for March 2024 ML24074A4262024-03-12012 March 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for February 2024 ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24036A2152024-02-0505 February 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for January 2024 ML24031A5472024-01-13013 January 2024 NRR E-mail Capture - (External_Sender) December 2023 FPL Marine Turtle Removal Monthly Report ML24002A7272023-12-16016 December 2023 NRR E-mail Capture - (External_Sender) November 2023 FPL Marine Turtle Removal Monthly Report ML23332A0352023-11-27027 November 2023 Conversion to Improved Technical Specifications Change in Estimated Review Schedule ML23326A0252023-11-20020 November 2023 NRR E-mail Capture - (External_Sender) October 2023 FPL Marine Turtle Removal Monthly Report ML24008A1582023-11-14014 November 2023 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for October 2023 ML23254A2852023-09-11011 September 2023 NRR E-mail Capture - (External_Sender) August 2023 FPL Marine Turtle Removal Monthly Report ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9182023-08-31031 August 2023 NRR E-mail Capture - Re Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23228A1482023-08-16016 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PSL2-I5-RR-01 (L-2023-LLR-0038) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23226A0692023-08-12012 August 2023 NRR E-mail Capture - (External_Sender) July 2023 FPL Marine Turtle Removal Monthly Report ML23223A0152023-08-11011 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PR-10 (L-2023-LLR-0039) ML23191A1952023-07-10010 July 2023 NRR E-mail Capture - (External_Sender) June 2023 FPL Marine Turtle Removal Monthly Report ML23216A1412023-06-30030 June 2023 August 2023 RP Inspection Document Request ML23248A1292023-06-29029 June 2023 NRR E-mail Capture - St Lucie 50.69 - Additional Audit Questions ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23198A0662023-06-22022 June 2023 NRR E-mail Capture - (External_Sender) Green Turtle Nest on Canal Bank, June 2023 ML23198A0642023-06-12012 June 2023 NRR E-mail Capture - (External_Sender) Loggerhead Nest on Canal Bank, May 2023 ML23163A1732023-06-10010 June 2023 NRR E-mail Capture - (External_Sender) May 2023 FPL Marine Turtle Removal Monthly Report ML23163A1222023-05-30030 May 2023 NRR E-mail Capture - (External_Sender) Nest on Intake Canal Bank ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23137A0942023-05-17017 May 2023 NRR E-mail Capture - Audit Plan - St Lucie Plant, Units 1 and 2 - 10 CFR 50.69 LAR ML23135A0292023-05-12012 May 2023 NRR E-mail Capture - (External_Sender) April 2023 FPL Marine Turtle Removal Monthly Report ML23129A8312023-05-0808 May 2023 NRR E-mail Capture - Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23198A1592023-04-0707 April 2023 NRR E-mail Capture - (External_Sender) March 2023 FPL Marine Turtle Removal Monthly Report ML23074A2292023-03-15015 March 2023 NRR E-mail Capture - (External_Sender) February 2023 FPL Marine Turtle Removal Monthly Report ML23041A2262023-02-10010 February 2023 NRR E-mail Capture - (External_Sender) January 2023 FPL Marine Turtle Removal Monthly Report ML23065A1142023-02-0101 February 2023 NRR E-mail Capture - (External_Sender) FPL St. Lucie Plant Biological Opinion SERO-2019-03494 - Submittal ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML23019A0142023-01-18018 January 2023 NRR E-mail Capture - (External_Sender) Regarding St. Lucie Olive Ridley Capture 1/3/2023 ML23006A1822023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) Psl Smalltooth Sawfish Capture 1/5/23 ML23006A1882023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) December 2022 FPL Marine Turtle Removal Monthly Report ML23006A0242023-01-0505 January 2023 NRR E-mail Capture - (External_Sender) Psl Olive Ridley Capture 1323 2024-09-06 |
Text
NRR-PMDAPEm Resource From: Orf, Tracy Sent: Wednesday, May 02, 2012 12:04 PM To: Travers, Allison
Subject:
FW: St. Lucie Unit 1 and 2 EPU - Draft EA RAI Responses Attachments: L-2012-199 Draft EA Responses.pdf Hi Allison, For your review.
- Thanks, Trace Tracy J. Orf, Project Manager St. Lucie Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Phone: (301) 415-2788 From: Hoffman, Jack [1]
Sent: Wednesday, May 02, 2012 11:38 AM To: Orf, Tracy Cc: Abbott, Liz; Barnes, Philip; Brown, Dave; DUBRUL, Stan; Folden, Jeff; Green, Philip; Hale, Steve; Howard, Angeline; joseph.creamer@shawgrp.com; Mermelstein, Irv; Onorato, Howard; Taylor, Terri
Subject:
St. Lucie Unit 1 and 2 EPU - Draft EA RAI Responses
- Trace, Attached is a letter providing a FPL's responses to the Unit 1 and 2 Draft EA questions. The original letter is being shipped to the NRC Document Desk via UPS. Tracking information is provided below.
Tracking Number: 1Z050A2R0194008072 Jack Hoffman Project Engineer - St. Lucie Power Uprate Office: (772) 467-7493 Mobile: (772) 201-0540 1
Hearing Identifier: NRR_PMDA Email Number: 373 Mail Envelope Properties (6566BAEC3DB1314381965386524904ECDF47B173AE)
Subject:
FW: St. Lucie Unit 1 and 2 EPU - Draft EA RAI Responses Sent Date: 5/2/2012 12:03:52 PM Received Date: 5/2/2012 12:02:33 PM From: Orf, Tracy Created By: Tracy.Orf@nrc.gov Recipients:
"Travers, Allison" <Allison.Travers@nrc.gov>
Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1196 5/2/2012 12:02:33 PM L-2012-199 Draft EA Responses.pdf 1267310 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: