- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML1011601822010-04-16016 April 2010 St. Lucie Unit 1 License Amendment Request for Extended Power Uprate Project stage: Request L-2010-181, Withdrawal of Extended Power Uprate License Amendment Request2010-08-13013 August 2010 Withdrawal of Extended Power Uprate License Amendment Request Project stage: Withdrawal ML1035604192010-11-22022 November 2010 St. Lucie, Unit 1 - Transmittal of Affidavits from Westinghouse, Areva and Caldon Ultrasonica Technology Center Re License Amendment Request for Extended Power Uprate Project stage: Request ML1107302992011-02-25025 February 2011 St. Lucie, Unit 2 - License Amendment Request for Extended Power Uprate, Attachment 5; Licensing Report Project stage: Request ML1107302822011-02-25025 February 2011 St. Lucie, Unit 2 - License Amendment Request for Extended Power Uprate, Attachment 2; Supplemental Environmental Report Project stage: Supplement ML1107301162011-02-25025 February 2011 St. Lucie, Unit 2 - License Amendment Request for Extended Power Uprate Project stage: Request ML1113200042011-05-12012 May 2011 EPU - Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Project stage: Acceptance Review ML11153A0482011-05-27027 May 2011 St. Lucie Plant, Unit 1 - Information Regarding Areva LOCA and Non-LOCA Methodologies Provided in Support of the License Amendment Request for Extended Power Uprate Project stage: Request ML11173A1042011-06-23023 June 2011 Acceptance for Review of License Amendment Request for Extended Power Uprate Project stage: Acceptance Review L-2011-273, Information Regarding Anticipated Transients Without Scram (ATWS) Provided in Support of the Extended Power Uprate License Amendment Request2011-07-22022 July 2011 Information Regarding Anticipated Transients Without Scram (ATWS) Provided in Support of the Extended Power Uprate License Amendment Request Project stage: Request L-2011-314, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-08-12012 August 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request NRC-2011-0190, St. Lucie Nuclear Plant, Units 1 and 2 - Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI2011-08-26026 August 2011 St. Lucie Nuclear Plant, Units 1 and 2 - Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Info Project stage: Approval ML11208B6442011-08-26026 August 2011 Federal Register Notice - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Information Project stage: Other ML11208B6422011-09-0101 September 2011 Transmittal Letter - Notice of Consideration of Issuance of Amendment to Facility Operating License, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Information Project stage: Other ML1123602302011-09-0202 September 2011 Request for Concurrence on List of Species with Essential Fish Habitat in the Vicinity of the St. Lucie Plant, Units 1 and 2 Project stage: Other L-2011-360, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-0202 September 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-383, Response to NRC Containment and Ventilation Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-22022 September 2011 Response to NRC Containment and Ventilation Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-389, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-09-22022 September 2011 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-404, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-10-0505 October 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-422, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information and Supplemental Information Regarding Extended Power Uprate License Amendment Request2011-10-10010 October 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information and Supplemental Information Regarding Extended Power Uprate License Amendment Request Project stage: Supplement L-2011-448, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-10-31031 October 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-466, Revision to Extended Power Uprate License Amendment Request Proposed Technical Specification 5.6, Design Features - Fuel Storage - Criticality2011-11-0404 November 2011 Revision to Extended Power Uprate License Amendment Request Proposed Technical Specification 5.6, Design Features - Fuel Storage - Criticality Project stage: Request L-2011-467, Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-11-14014 November 2011 Response to NRC Accident Dose Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-493, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-11-23023 November 2011 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-524, Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-12-27027 December 2011 Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request ML11332A0212011-12-28028 December 2011 Federal Register Notice - Draft Environmental Assessment and Draft Finding of No Significant Impact Related to the Proposed Extended Power Uprate Project stage: Request ML11332A0202011-12-28028 December 2011 Transmittal Letter - Draft Environmental Assessment and Draft Finding of No Significant Impact Related to the Proposed Extended Power Uprate Project stage: Draft Other L-2011-533, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-12-29029 December 2011 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-566, Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-532, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-565, Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-14014 January 2012 Response to NRC Instrumentation & Controls Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-534, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-18018 January 2012 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2011-441, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-18018 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-012, Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-21021 January 2012 Response to NRC Reactor Systems Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-009, Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-01-21021 January 2012 Response to NRC Reactor System Branch and Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-043, Comment (1) of Richard L. Anderson, on Behalf of Florida Power & Light, Regarding Draft Environmental Assessment and Draft Finding of No Significant Impact Related the Proposed Extended Power Uprate2012-01-30030 January 2012 Comment (1) of Richard L. Anderson, on Behalf of Florida Power & Light, Regarding Draft Environmental Assessment and Draft Finding of No Significant Impact Related the Proposed Extended Power Uprate Project stage: Draft Other ML12044A1272012-02-13013 February 2012 Comment (2) from Edward W. Johnson Opposing Ncr Permit Approval for St. Lucie 1 & 2 Project stage: Request L-2012-059, Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-02-29029 February 2012 Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-075, Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0606 March 2012 Response to NRC Mechanical and Civil Engineering Branch (Emcb) Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-100, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0606 March 2012 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-094, Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-0808 March 2012 Response to NRC Steam Generator Tube Integrity and Chemistry Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-106, Response to Nuclear Performance and Code Review Branch Request for Additional Information Identified During an Audit of Analyses Supporting the Extended Power Uprate License Amendment Request2012-03-15015 March 2012 Response to Nuclear Performance and Code Review Branch Request for Additional Information Identified During an Audit of Analyses Supporting the Extended Power Uprate License Amendment Request Project stage: Request L-2012-114, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-16016 March 2012 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-113, Response to Request for Additional Information Identified During Audit of the Loss of Coolant Accident Safety Analyses Calculations for the Extended Power Uprate License Amendment Request2012-03-17017 March 2012 Response to Request for Additional Information Identified During Audit of the Loss of Coolant Accident Safety Analyses Calculations for the Extended Power Uprate License Amendment Request Project stage: Response to RAI L-2012-116, Response to Request for Additional Information Identified During Audit of the Reactor Systems Branch (Srxb) Fluid System Analyses for the Extended Power Uprate License Amendment2012-03-25025 March 2012 Response to Request for Additional Information Identified During Audit of the Reactor Systems Branch (Srxb) Fluid System Analyses for the Extended Power Uprate License Amendment Project stage: Response to RAI L-2012-141, Response to NRC Steam Generator Tube Integrity and Chemical Engineering Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-03-31031 March 2012 Response to NRC Steam Generator Tube Integrity and Chemical Engineering Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-131, Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-04-0505 April 2012 Response to NRC Reactor Systems Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-122, Response to NRC Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2012-04-0505 April 2012 Response to NRC Nuclear Performance Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request L-2012-150, Response to Request for Additional Information Identified During Audit of the Non-Loss of Coolant Accident Safety Analyses Calculations for the Extended Power Uprate License Amendment Request2012-04-0606 April 2012 Response to Request for Additional Information Identified During Audit of the Non-Loss of Coolant Accident Safety Analyses Calculations for the Extended Power Uprate License Amendment Request Project stage: Response to RAI L-2012-157, Response to Request for Additional Information Identified During Audit of the Reactor Systems Branch (Srxb) Fluid System Analyses for the Extended Power Uprate License Amendment Request2012-04-10010 April 2012 Response to Request for Additional Information Identified During Audit of the Reactor Systems Branch (Srxb) Fluid System Analyses for the Extended Power Uprate License Amendment Request Project stage: Response to RAI 2011-08-26
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23019A2052022-12-24024 December 2022 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors - Acceptance Review ML21266A0412021-09-17017 September 2021 SLR Application Accepted-email to FPL ML21039A1932021-01-19019 January 2021 NRC Acceptance Review: St Lucie, Units 1 and 2 - License Amendment to Allow Risk Informed Completion Times (RICT) for the 120-Volt AC ML21035A0172020-12-11011 December 2020 NRC Acceptance Review: St Lucie, Unit 2- RR 15 - Extension of St. Lucie, Unit 2 RPV Welds from 10 to 20 Years ML21036A2422020-03-12012 March 2020 NRC Acceptance Review: St Lucie 2 LAR for RCS Pressure/Temperature Limits and LTOP Applicable for 55 EFPY ML19324C5772019-11-19019 November 2019 NRC Acceptance Review: St Lucie 2 Flywheel LAR ML16029A1722016-02-0101 February 2016 Acceptance of Requested Licensing Action Regarding the Use of Gothic Computer Code Vacuum Analyses ML15281A2292015-11-0505 November 2015 Acceptance Review of Relief Request 10, Revision 0, Concerning Control Element Drive Mechanism Welds - Fourth 10-Year Interval ML15223B2042015-08-24024 August 2015 Acceptance of Requested Licensing Action Regarding Removal the 10-Year Sediment Cleaning of the Fuel Oil Storage Tank from Technical Specifications and Relocated to License-Controlled Documents (TAC Nos. MF6488-89) ML14210A3972014-07-28028 July 2014 NRR E-mail Capture - Acceptability Review of the Relief Request No 16 (MF4340) ML14210A4252014-07-23023 July 2014 NRR E-mail Capture - Acceptability Review of the Relief Request No. 6 (MF336) ML14118A2442014-03-19019 March 2014 E-mail Re. Acceptance Review: PSL2 Amendment, 10-year ISI Snubber Surveillance ML13169A2962013-06-18018 June 2013 Acceptance Review Concerning License Amendment Request to Adopt NFPA-805, Performance-Based at Standard for Fire Protection for Light Water Reactor Electric Generating Plants, ML1130800452011-11-0303 November 2011 Acceptance Review - One-Time Exemption Request 10 CFR 26.205(d)(3) - Work Hour Controls ML1123109812011-08-19019 August 2011 Acceptance Review ISI Third Ten-Year Interval Relief Request No. 12 ML11173A1042011-06-23023 June 2011 Acceptance for Review of License Amendment Request for Extended Power Uprate ML1114306512011-05-23023 May 2011 Acceptance Review of Exemption P-T Limit Curves ML1002008292010-01-14014 January 2010 Plants Units 1 and 2 - Request for Exemption from Certain Requirements of the Fitness for Duty Rule for Managing Fatigue 2023-04-19
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 23, 2011 Mr. Mano Nazar Executive Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420
SUBJECT:
ST. LUCIE PLANT, UNIT 2 - ACCEPTANCE FOR REVIEW OF LICENSE AMENDMENT REQUEST FOR EXTENDED POWER UPRATE (TAC NO. ME5843)
Dear Mr. Nazar:
By letter dated February 25, 2011, Florida Power & Light Company submitted a license amendment for S1. Lucie, Unit No.2. The proposed amendment would increase the licensed core power level of St. Lucie, Unit No.2, from 2700 megawatts thermal (MWt) to 3020 MWt.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there was sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
M. Nazar - 2 If you have any questions regarding this matter, 'may be reached at 301-415-2788 or by email at tracy.orf@nrc.gov.
Sincerely, Tracy J. Orf, Project Manager Plant licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-389 cc: Distribution via Listserv
M. Nazar -2 If you have any questions regarding this matter, I may be reached at 301-415-2788 or by email at tracy.ort@nrc.gov.
Sincerely, IRA!
Tracy J. Ort, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-389 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 rtf RidsAcrsAcnw_MailCTR RidsN rrDorl RidsNrrDorlDpr RidsNrrDorlLpl2-2 RidsNrrLABClayton RidsNrrPMStLucie RidsOgcRp RidsRgn2MailCenter ADAMS Accession No. ML11173A104 Ii
. OFFICE LPL2-2/PM LPL2-2/LA LPL2-2/BC LPL2-2/PM
- NAME TOrt BClayton DBroaddus TOrt DATE 06/22/11 06/22/11 06/23/11 06/23/11 OFFICIAL RECORD COpy