ML24177A251

From kanterella
Jump to navigation Jump to search

Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years
ML24177A251
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 02/12/2024
From: Natreon Jordan
Plant Licensing Branch II
To: Mack K
Florida Power & Light Co
Jordan N
Shared Package
ML24177A254 List:
References
EPID L-2024-LLR-0004
Download: ML24177A251 (1)


Text

From:

Natreon Jordan To:

Mack, Kenneth Cc:

Mack, Jarrett; Falkiewicz, Timothy

Subject:

Acceptance Review for RR#7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years Date:

Monday, February 12, 2024 6:09:00 PM Mr. Mack,

By submittal dated January 18, 2024, (Agencywide Documents and Access Management System (ADAMS) Accession No. ML24018A064), pursuant to Title 10, Code of Federal Regulations, Part 50, (10 CFR 50.55a(z)(1)), Florida Power & Light (the licensee) requested relief from the examination requirements of the American Society of Mechanical Engineers (ASME),Section XI, Subsection IWB-2411, "Inspection Program", for St. Lucie Nuclear Plant (St. Lucie) Unit 1. The proposed alternative would extend the inspection of welds and nozzle inner radius under Examination Categories B-A and B-D of the ASME Code,Section XI from once each 10-year inservice inspection interval to once every twenty years.

The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed the proposed relief request and concluded that the submittal provides technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment.

Instances may arise in which issues that impact the NRC staffs ability to complete the detailed technical review are identified. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review.

If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal the NRC staff has estimated that this licensing request will take approximately 215 hours0.00249 days <br />0.0597 hours <br />3.554894e-4 weeks <br />8.18075e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is February 12, 2025. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application, and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC

advisory committees or hearing-related activities.

If you have any questions, please contact me.

Natreon (Nate) Jordan Nuclear Engineer (Project Manager)