ML11340A082

From kanterella
Jump to navigation Jump to search
Submittal of After Action Report/Improvement Plan, Radiological Emergency Preparedness Program
ML11340A082
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/06/2011
From: Velasquez A
US Dept of Homeland Security, Federal Emergency Management Agency
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML11340A082 (108)


Text

U.S. Department of Homeland Security Region V 536 South Clark Street, Floor 6 Chicago, IL 60605 0FEMA NRC Headquarters Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 To Whom It May Concern:

Enclosed is one copy of the After Action Report (AAR)/Improvement Plan (IP) for the August 23, 2011, Radiological Emergency Preparedness (REP) Partial Participation Plume Exposure Pathway Exercise for the MNGP. The State of Minnesota, Sherburne and Wright Counties, and the utility owner/operator, Xcel Energy, participated in this exercise. The AAR/IP was prepared by the U.S. Department of Homeland Security/Federal Emergency Management Agency (DHS/FEMA) Region V, Radiological Emergency Preparedness Program.

No Deficiencies were identified for any jurisdiction during this exercise.

There was one Area Requiring Corrective Action (ARCA) identified for the State of Minnesota. The ARCA was identified under Criterion 6.d. 1-Support Operations/Facilities, whereby the Radiation Safety Officer did not properly complete the source check and scaling process for survey meters. The ARCA was successfully re-demonstrated during the exercise.

No ARCAs were identified for Sherburne County.

There was one ARCA for Wright County (39-09-1 c -A-0 1) identified under Criterion 1 .c. 1 which was issued in 2009 - Key personnel with functional roles for the Offsite Response Organizations provide direction and control to the part of the overall response effort for which they are responsible, whereby the Operations Chief (Nuclear Director) and other key EOC staff were not informed by staff that a decision to evacuate the County Jail population had been made. This ARCA was successfully re-demonstrated on November 8, 2011.

A detailed discussion and corrective actions taken for these ARCAs can be found in Part IV of this AAR /IP.

www.fema.gov

NRC HQ Document Control Desk Page 2 Based on the results of the August 23, 2011, exercise, the offsite radiological emergency response plans and preparedness for the State of Minnesota and affected local jurisdictions site-specific to the MNGP, can be implemented and are adequate to provide reasonable assurance that appropriate measures can be taken offsite to protect the health and safety of the public in the event of a radiological emergency at the site.

Therefore, the Title 44 CFR, Part 350, approval of the offsite radiological emergency response plans and preparedness for the State of Minnesota site-specific to the MNGP, granted on January 7, 1981, remains in effect.

Copies of this Report were transmitted to the DHS/FEMA Headquarters, the Nuclear Regulatory Commission Region III Office and the State of Minnesota.

If you have any questions, please contact Edward Golinski, Technological Hazards Specialist at (312) 408-5353 or William E. King, Chairman, Regional Assistance Committee, DHS/FEMA, Region V, at (312) 408-5575.

Sincerely, Andrew Velasquez III Regional Administrator Enclosures (1)

Monticello Nuclear Generating Plant After Action Report/

Improvement Plan Exercise Date - August 23, 2011 Radiological Emergency Preparedness (REP) Program FEMA .

Published November 29, 2011

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant This page is intentionally blank.

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant After Action Report/Improvement Plan Published November 29, 2011 Contents Executive Summary 5 Section 1: Exercise Overview 10 1.1 Exercise Details 10 1.2 Exercise Planning Team Leadership 10 1.3 Participating Organizations 13 Section 2: Exercise Design Summary 15 2.1 Exercise Purpose and Design 15 2.2 Exercise Objectives, Capabilities and Activities 15 2.3 Scenario Summary 15 Section 3: Analysis of Capabilities 17 3.1 Exercise Evaluation and Results 17 3.2 Summary Results of Exercise Evaluation 18 3.3 Criteria Evaluation Summaries 25 3.3.1 Minnesota Jurisdictions 25 3.3.1.1 State of Minnesota - Bureau of Criminal 25 Apprehension - Inital Warning Point 3.3.1.2 State of Minnesota - Emergency Operations Center 25 3.3.1.3 State of Minnesota - Emergency Operations Center - 26 Planning and Assessment Center 3.3.1.4 State of Minnesota - Emergency Operations Center - 27 Joint Information Center 3.3.1.5 State of Minnesota - Sherburne County Emergency 27 Operations Center - Regional Program Coordinator 3.3.1.6 State of Minnesota - Wright County Emergency 28 Operations Center - Regional Program Coordinator 3.3.1.7 State of Minnesota - Sherburne County Emergency 28 Operations Center - State Helicopter - Warning County Recreationalists 1

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 3.3.1.8 State of Minnesota - Sherburne County Emergency 29 Operations Center - Minnesota State Police - Traffic and Access Control Point 3.3.1.9 State of Minnesota - Sherburne County Emergency 29 Operations Center - Minnesota State Police - Traffic and Access Control - DCO Briefing 3.3.1.10 State of Minnesota - Princeton High School - 30 Evacuee Registration 3.3.1.11 State of Minnesota - Princeton High School - 30 Evacuee/Emergency Worker Monitoring and Decontamination 3.3.1.12 State of Minnesota - Princeton High School - 31 Evacuee/Emergency Worker Monitoring and Decontamination of Vehicles and Equipment 3.3.1.13 State of Minnesota - Fairview Northland Hospital - 32 Medical Services - Transportation 3.3.1.14 State of Minnesota - Fairview Northland Hospital - 32 Medical Services - Facility 3.3.2 Risk Jurisdictions 34 3.3.2.1 Sherburne County - Initial Warning Point 34 3.3.2.2 Sherburne County - Emergency Operations Center 34 3.3.2.3 Sherburne County - Emergency Operations Center - 35 Traffic and Access Control Point 3.3.2.4 Sherburne County - Emergency Operations Center - 36 Traffic and Access Control - DCO Briefing 3.3.2.5 Sherburne County - State Emergency Operations 36 Center/Joint Information Center - Public Information Officer 3.3.2.6 Sherburne County - Becker School District - 37 Evacuation School 3.3.2.7 Wright County - Initial Warning Point 37 3.3.2.8 Wright County - Emergency Operations Center 38 3.3.2.9 Wright County - Emergency Operations Center - 40 Traffic and Access Control - DCO Briefing 3.3.2.10 Wright County - Emergency Operations Center - 41 Traffic and Access Control Point 3.3.2.11 Wright County - State Emergency Operations 41 Center/Joint Information Center - Public Information Officer 2

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 3.3.2.12 Wright County - Rockford Fire Department - 42 Emergency Worker Registration 3.3.2.13 Wright County - RFD - Emergency Worker 42 Monitoring and Decontamination of Equipment and Vehicles 3.3.2.14 Wright County - Rockford Fire Department - 43 Emergency Worker Monitoring and Decontamination 3.3.2.15 Wright County - Maple Lake School District - 43 Evacuation School 3.3.2.16 Wright County - Monticello School District - 44 Evacuation School Section 4: Conclusion 45 Appendix A: Exercise Timeline 46 Appendix B: Exercise Evaluators and Team Leaders 49 Appendix C: Acronyms and Abbreviations 52 Appendix D: Exercise Plan 54 Appendix E: Scenario Details 91 3

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant II This page is intentionally blank.

4

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant EXECUTIVE

SUMMARY

On August 23, 2011, a Radiological Emergency Preparedness (REP) Partial Participation Plume Exposure Pathway Exercise evaluation was conducted by the U.S. Department of Homeland Security (DHS)/Federal Emergency Management Agency (FEMA) for the 10-mile Emergency Planning Zone (EPZ) around the Monticello Nuclear Generating Plant (MNGP). The purpose of the exercise was to assess the level of State and local preparedness in responding to a radiological emergency. This exercise was held in accordance with DHS/FEMA's policies and guidance concerning the exercise of State and local Radiological Emergency Response Plans (RERPs) and procedures.

The most recent exercise at this site was conducted on August 18, 2009. The qualifying emergency preparedness exercise was conducted on January 7, 1981.

DHS/FEMA wishes to acknowledge the efforts of the many individuals who participated in this exercise. In the State of Minnesota, the Counties of Sherburne and Wright participated along with State Government.

Protecting the public health and safety is the full-time job of some of the exercise participants and an additional assigned responsibility for others. Still others have willingly sought this responsibility by volunteering to provide vital emergency services to their communities.

Cooperation and teamwork on the part of all the participants were evident during this exercise.

This Final Report contains the evaluation of the biennial exercise and the evaluation of the following out-of-sequence interviews and activities:

- Evacuee Monitoring, Decontamination, Registration, and Vehicle Monitoring and Decontamination were demonstrated at Princeton High School and the Princeton Fire Department

  • Medical Services Transportation and Hospital evaluation at Princeton Fairview Northland Medical Center
  • Protective Actions for Schools (EV-2) for the Becker/Zimmerman, Maple Lake/Dassel Cokato, and the Monticello/Maple Grove School Districts
  • Emergency Worker Monitoring, Decontamination, Registration, and Vehicle Monitoring and Decontamination were demonstrated at the Rockford Fire Department 5

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

Except where noted in this report, the State and local organizations demonstrated knowledge of and adequately implemented their emergency response plans and procedures.

INTRODUCTION - EXERCISE BASIS On December 7, 1979, the President directed FEMA to assume the lead responsibility for all offsite nuclear planning and response. DHS/FEMA's activities are conducted pursuant to 44 Code of Federal Regulations (CFR) Parts 350 "Review and Approval of State and Local Radiological, Emergency Plans and Preparedness", 351 "Radiological Emergency Planning and Preparedness" and 352 "Commercial Nuclear Power Plants: Emergency Preparedness Planning."

These regulations are a key element in the Radiological Emergency Preparedness (REP) Program that was established following the Three Mile Island Nuclear Station accident in March 1979.

The FEMA Rule 44 CFR 350 establishes the policies and procedures for DHS/FEMA's initial and continued approval of State and local governments' radiological emergency planning and preparedness for commercial nuclear power plants. This approval is contingent, in part, on State and local governments' participation in joint exercises with licensees.

DHS/FEMA's responsibilities in radiological emergency planning for fixed nuclear facilities 3 include' the following:

  • Taking the lead in offsite emergency planning and in the review and evaluation of RERPs and procedures developed by State and local governments;
  • Determining whether such plans and procedures can be implemented on the basis of observation I and evaluation of exercises of the plans and procedures conducted by State and local governments;
  • Responding to requests by the U.S. Nuclear Regulatory Commission (NRC) pursuant to the Memorandum of Understanding between the NRC and FEMA dated June 17, 1993 (Federal 3 Register, Vol. 58, No. 176, September 14, 1993); and
  • Coordinating the activities of Federal agencies with responsibilities in the radiological emergency planning process: I

- U.S. Department of Agriculture;

- U.S. Department of Commerce;

- U.S. Department of Energy; 6 1 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

- U.S. Department of Health and Human Services;

- U.S. Department of the Interior;

- U.S. Department of Transportation;

- U.S. Environmental Protection Agency;

- U.S. Food and Drug Administration; and

- U.S. Nuclear Regulatory Commission.

Representatives of these agencies serve on the DHS/FEMA Region V Regional Assistance Committee (RAC), which is chaired by DHS/FEMA.

Formal submission of the RERPs for the MNGP to FEMA Region V by the State of Minnesota and involved local jurisdictions occurred on February 1, 1983. Formal approval of these RERPs was granted by FEMA on May 10, 1985, under 44 CFR 350.

A REP Partial Participation Plume Exposure Pathway Exercise was conducted on August 23, 2011, and evaluated by DHS/FEMA to assess the capabilities of State and local offsite emergency preparedness organizations in implementing their RERPs and procedures to protect the public health and safety during a radiological emergency involving the MNGP. The purpose of this exercise report is to present the exercise results and findings on the performance of the Offsite Response Organizations (OROs) during a simulated radiological emergency.

The findings presented in this report are based on the evaluations of the Federal evaluation team, with final determinations made by the DHS/FEMA Region V RAC Chairperson, and approved by the DHS/FEMA Headquarters.

The criteria utilized in the FEMA evaluation process are contained in:

  • NUREG-0654/FEMA-REP- 1, Rev. 1, "Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants," November 1980;
  • FEMA-REP-14, "Radiological Emergency Preparedness Exercise Manual," September 1991; and FEMA "Radiological Emergency Preparedness: Exercise Evaluation Methodology; Notice" as 7

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/improvement Plan Monticello Nuclear Generating Plant published in the Federal Register Notice, Vol. 67, No. 80, dated April 25, 2002.

Section 1 of this report, entitled "Exercise Overview", presents information pertaining to the team that planned and coordinated the exercise. This section also provides listing of all participating jurisdictions and functional entities that were evaluated.

U Section 2 of this report, entitled "Exercise Design Summary", contains the purpose and design of the exercise, a description of the plume pathway EPZ and presents basic information and data relevant to the exercise scenario.

Section 3 of this report, entitled "Analysis of Capabilities," presents detailed information on the I demonstration of applicable exercise criteria at each jurisdiction or functional entity evaluated in a jurisdiction-based, issues-only format. This section also contains: (1) descriptions of all Deficiencies and ARCAs (if any) assessed during this exercise, recommended corrective actions, and the State and local governments' schedule of corrective actions, if applicable, for each identified exercise issue; and (2) descriptions of unresolved ARCAs assessed during previous exercises and the status of the OROs' efforts to resolve them.

Section 4 of this report,. entitled "Conclusion" presents the DHS/FEMA summary of overall exercise conduct and results as evaluated against the requirements of 44 CFR 350. 3 EMERGENCY PLANNING ZONE (EPZ) DESCRIPTION The MNGP is located within the city limits of Monticello, Minnesota. The plant consists of approximately 1500 acres of land. The northwest and southwest sectors are mainly agricultural.

The northeast and southeast sectors are urban and manufacturing. Part of this property is on the north bank of the Mississippi River in Sherburne County and part is on the south bank of Wright County. The northwestern suburbs of Minneapolis are about 30 miles southeast of the MNGP.

The 10-mile EPZ for the MNGP consists of a circle with the utility at the center point. The EPZ m extends 10-miles outward in all directions from the plant for the plume exposure pathway planning zone and 50 miles outward for the Ingestion Pathway Zone (IPZ). In the event of a i serious accident, the plume exposure-planning zone will be in the area in which intensive efforts will be made to notify and protect residents and transient populations from exposure to radiation. i The population in the MNGP 10-mile EPZ is 87,871. This figure represents the permanent 81

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant population in the municipalities and unincorporated areas located in the 10-mile EPZ.

There are numerous lakes in the 10-mile EPZ, which are used for recreational purposes. Parts of Lake Saint Marie Park, Sandune State Park, and Game Refuge are within the 10-mile EPZ. The Mississippi River flows from the northwest to southeast through the 10-mile EPZ. The three major highways passing through the area are Interstate 94, U.S. 10, and State Highways 25 and

55. Railroad access is available from Burlington Northern and NorthStar Railway. Major waterways are the Mississippi Scenic River and Crow River and the Elk River and Saint Francis River watersheds; however these waterways are not navigable. There are no major airports in the 10-mile EPZ.

The following Sub-Areas are included within the 10-mile EPZ: Sub-Areas 2, 5N, 5E, 5S, 5W, 1ON, 10E, lOSE, lOS, 1OSW, lOW and 1ONW.

The 50-mile IPZ for. the MNGP has an estimated population of approximately 3,591,108 as of the year 2008. Approximately 90% reside in the Minneapolis-St. Paul metropolitan area. There are 22 counties in the 50-mile EPZ. They are: Anoka, Benton, Carver, Chisago, Dakota, Hennepin, Isanti, Kanabec, Kandiyohi, McLeod, Meeker, Mille Lacs, Morrison, Pine, Ramsey, Renville, Scott, Sherburne, Sibley, Steams, Washington, and Wright.

No Deficiencies were identified for any jurisdiction during this exercise.

There was one Area Requiring Corrective Action (ARCA) identified for the State of Minnesota.

The ARCA was identified under Criterion 6.d. 1-Support Operations/Facilities, whereby the Radiation Safety Officer did not properly complete the source check and scaling process for survey meters. The ARCA was successfully re-demonstrated during the exercise.

No ARCAs were identified for Sherburne County.

There was one ARCA for Wright County (39-09-1 c l-A-01) identified under Criterion 1.c. 1 which was issued in 2009 - Key personnel with functional roles for the Offsite Response Organizations provide direction and control to the part of the overall response effort for which they are responsible, whereby the Operations Chief (Nuclear Director) and other key EOC staff were not informed by staff that a decision to evacuate the County Jail population had been made.

This ARCA was successfully re-demonstrated on November 8, 2011.

9

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant SECTION 1: EXERCISE OVERVIEW I 1.1 Exercise Details Exercise Name Monticello Nuclear Generating Plant Type of Exercise PlumeI Exercise Date August 23, 2011 Program I Department of Homeland Security/FEMA Radiological Emergency Preparedness Program Scenario Type Radiological Emergency 1.2 Exercise Planning Team Leadership I William King Radiological Assistance Committee, Chairman DHS/FEMA Chief, Technological Hazards Branch 536 South Clark Chicago, Illinois; 60605 312-408-5575 William.King5@fema.dhs.gov Dwaine Warren I Exercise Director DHS/FEMA Supervisory REP Team Leader 536 South Clark I 10

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Chicago, Illinois, 60605 312-408-5342 Dwaine.Warren@fema.dhs.gov Gary Naskrent Alternate Exercise Director DHS/FEMA Supervisory REP Team Leader 536 South Clark Street Chicago, Illinois, 60605 312-408-5214 Gary.Naskrent@fema.dhs.gov Edward Golinski Minnesota Site Specialist/Exercise Coordination DHS/FEMA Technical Hazards Program Specialist 536 South Clark Chicago, Illinois, 60605 312-408-5353 Edward.Golinski@fema.dhs.gov Kevin Leuer Director, Preparedness Branch Division of Homeland Security & Emergency Management Director 444 Cedar Street - Suite 223 St. Paul, Minnesota, 55101 651-201-7406 Kevin.Leuer@state.mn.us Patrick McLaughlin REP Exercise Coordinator 11

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Division of Homeland Security & Emergency Management REP Administrator 444 Cedar Street - Suite 223 St. Paul, Minnesota, 55101 651-201-7434 Patrick.McLaughlin@state.mn.us Robert Hines REP Exercise Coordinator Homeland Security Emergency Management REP Exercise Coordinator 444 Cedar Street - Suite 223 St. Paul, Minnesota, 55101 651-201-7415 Robert.Hines@state.mn.us Gerald Holthaus Scenario Developer Xcel Energy - Monticello Nuclear Generating Plant Emergency Planning Coordinator 2807 W. CR 75 Monticello, Minnesota, 55362 763-295-1633 Gerald.Holthaus@xenuclear.com Charlie Dixon Offsite Coordination/Controller Monticello Nuclear Generating Plant - Xcel Energy Corporate Emergency Planning Coordinator 414 Nicollet Mall (MP4)

Minneapolis, Minnesota, 55401 612-330-6438 Charles.Dixon@xenuclear.com 12

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 1.3 Participating Organizations Agencies and organizations of the following jurisdictions participated in the Monticello Nuclear Generating Plant exercise:

State Jurisdictions State of Minnesota Governor's Office Department of Public Safety, Division of Homeland Security and Emergency Management Minnesota Department of Agriculture Minnesota Department of Education Minnesota Department of Health Minnesota Department of Health, Public Health Laboratory Minnesota Emergency Medical Services Regulatory Board Minnesota Department of Human Services Minnesota Department of Military Affairs Minnesota Department of Natural Resources Minnesota Department of Transportation Minnesota State Patrol State of Minnesota National Guard Department of Public Safety, Office of Communication Minnesota Geospatial Information Office Minnesota Voluntary Organizations Active in Disasters School Safety Center (State of Minnesota)

Bureau of Criminal Apprehension Xcel Energy Risk Jurisdictions Becker School District Elk River Area Independent School District Maple Lake School District Monticello School District Sherburne County Sheriffs Office Wright County Sherriffs Office Support Jurisdictions Amateur Radio Emergency Services 13

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant American Red Cross Boy Scouts of America Salvation Army I

I I

I I

U I

14

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant SECTION 2: EXERCISE DESIGN

SUMMARY

2.1 Exercise Purpose and Design The DHS/FEMA Region V Office evaluated the MNGP REP Partial Participation Plume Exposure Pathway Exercise conducted on August 23, 2011, to assess the capabilities of local emergency preparedness organizations in implementing their RERP and procedures to protect the public health and safety during a radiological emergency involving the MNGP. The purpose of this report is to present the results and findings on the performance of the OROs during a simulated radiological emergency.

2.2 Exercise Objectives, Capabilities and Activities Exercise objectives and identified Capabilities/REP Criteria selected to be demonstrated are discussed in Appendix E "Exercise Plan." The Exercise Planning Team (EPT) selected objectives that focus on evaluating emergency response procedures, identifying areas for improvement, and fostering collaboration between the various OROs and stakeholders. This exercise focused on the following objectives:

" ORO demonstration of effective Emergency Operations Management

  • ORO demonstration of effective Protective Action Decision Making

" ORO demonstration of effective Protective Action Implementation

  • ORO demonstration of effective Emergency Notification and Public Information
  • ORO demonstration of effective Support Operations and Facilities 2.3 Scenario Summary Appendix F "Scenario Details," contains a summary of the Exercise Scenario, a simulated sequence of events that was used as the basis for invoking emergency response actions by OROs in the MNGP REP Partial Participation Plume Exposure Pathway exercise on August 23, 2011.

This exercise scenario was submitted by the State of Minnesota and Xcel Energy and accepted by DHS/FEMA Region V on July 14, 2011.

During the exercise, in addition to information and data provided through the MNGP onsite scenario, controllers from the State of Minnesota provided "inject messages" containing scenario 15

I Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant events and/or relevant data to those persons or locations who would normally receive notification of such events. These inject messages were the method used for invoking additional specific response actions by OROs.

The details of the scenario are included in Appendix F "Scenario Details."

I I

U I

I I

I I

I I

I I

I 16 1 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant SECTION 3: ANALYSIS OF CAPABILITIES 3.1 Exercise Evaluation and Results Contained in this section are the results and findings of the -evaluation of all jurisdictions and functional entities that participated in the August 23, 2011, REP Partial Participation Plume.

Exposure Pathway Exercise conducted to test the offsite emergency response capabilities of State and local governments in the EPZ surrounding the MNGP.

Each jurisdiction and functional entity was evaluated based on its demonstration of exercise criteria delineated-in Federal Register Notice: Vol. 67, No. 80, dated April 25, 2002. Detailed information on the exercise criteria and the extent-of-play agreements used in this exercise are found in Appendix E "Exercise Plan" of this report.

Presented below are definitions of the terms used in this report relative to the criteria demonstration status:

- M - Met: The status of a REP exercise Evaluation Area Criterion indicating that the participating ORO demonstrated all demonstration criteria for the Evaluation Area Criterion to the level required in the extent-of-play agreement with no Deficiencies or ARCAs assessed in the current exercise and no unresolved prior ARCAs.

  • D - Deficiency: An observed or identified inadequacy of organizational performance in an exercise that could cause a finding that offsite emergency preparedness is not adequate to provide reasonable assurance that appropriate protective measures can be taken in the event of a radiological emergency to protect the health and safety of the public living in the vicinity of a nuclear power plant.
  • A - Area Requiring Corrective Action (ARCA) - An observed or identified inadequacy of organizational performance in an exercise that is not considered, by itself, to adversely impact public health and safety. Listing of the demonstrated exercise criteria under which one or more ARCAs was/were assessed during the current exercise or ARCAs assessed during prior exercises remain unresolved. Included is a description of any ARCAs assessed during this exercise and the recommended corrective action to be demonstrated before or during the next biennial exercise.

- P - Planning Issue - An observed or identified inadequacy in the ORO's emergency plan or implementing procedures, rather than in the ORO's performance.

  • N - Not Demonstrated - Exercise criteria that were not demonstrated as scheduled during this 17

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant exercise and the reason(s) they were not demonstrated.

- Prior ARCAs - Resolved - Descriptions of ARCAs assessed during previous exercises that were resolved and the corrective actions demonstrated in this exercise.

- Prior ARCAs - Unresolved - Descriptions of ARCAs assessed during prior exercises that were not resolved in this exercise. Included is the reason the ARCA remains unresolved and recommended corrective actions to be demonstrated before or during the next exercise.

3.2 Summary Results of Exercise Evaluation The matrix presented in Table 3.1, on the following pages, presents the status of all exercise criteria from Federal Register Notice: Vol. 67, No. 80, dated April 25, 2002, which were scheduled for demonstration during this exercise by all participating jurisdictions and functional entities. The criterion status box is blank if it was not scheduled for demonstration.

This subsection provides information on the evaluation of each participating jurisdiction and 3 functional entity in a jurisdiction-based, issues-only format.

The DHS has developed a standardized system for numbering exercise issues. This system is I used to achieve consistency in numbering exercise issues among DHS Regions and site-specific exercise reports within each Region. It also is used to expedite tracking of exercise issues on a 3 nationwide basis.

The identifying number of Deficiencies, ARCAs, and Planning Issues includes the following U elements, with each element separated by a hyphen (-).

  • Plant Site Identifier - A two-digit number, corresponding to the Utility Billable Plant Site Code (39 for MNGP). 3 "Exercise Year - The last two digits of the year the exercise was conducted.

" Criterion Number - An alpha and two-digit number corresponding to the criteria numbers in the six Exercise Evaluation Areas described in Federal Register Notice, Vol. 67, No. 80, dated April 25, 2002, which amends FEMA-REP 14, Radiological Emergency Preparedness Exercise Manual. I

  • Issue Classification Identifier - (D = Deficiency, A = ARCA, P = Planning Issue).

" Exercise Identification Number - A separate two or three-digit indexing number assigned to I each issue identified in the exercise.

18 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Table 3.1 - Summary of Exercise Evaluation (3 pages) 0

5) U 0 0

0.

0 p., Cs U

(5 U U 5)

U I-, 5)

DATE: 2011-08-23 p.,

SITE: Monticello Nuclear Generating Plant, MN (A 5) 5)

U 0 U p C) 0 U U Cs M: Met, A: ARCA, D: Deficiency, P: Plan Issue, N: Not 0 C)

Cs 0 Demonstrated 0 U U U U (A 5)

U 5)

.0 0

0 0 0 (A 5) 5l)

'-C-,

U 5) 0? C-)

0 0

0 .0 (A p.,

C01 (A

Emergency Operations Management Mobilization lal M M M M M M Facilities IbI Direction and Control Ic M M M Communications Equipment Idl M MM M M M M M Equip & Supplies to support operations lel M M M M M M M Protective Action Decision Making Emergency Worker Exposure Control 2al M M M M Radiological Assessment and PARs 2bl M M Decisions for the Plume Phase - PADs 2b2 M M M M PADs for protection of special populations 2cl M M M Rad Assessment and Decision making for Ingestion Pathway 2dl Rad Assess/Decision making concerning Relocation, Reentry, and Return 2e 1 Protective Action Implementation Implementation of emergency worker exposure control 3al M M M M Implementation of KI decision 3bl M M M1 Implementation of protective actions for special populations - EOCs 30 Implementation of protective actions for Schools 3c2 M Implementation of traffic and access control 3dt M M Impediments to evacuation are identified and resolved 3d2 M Implementation of ingestion pathway decisions - availability/use of info 3e 1 Materials for Ingestion Pathway PADs are available 3e2 Implementation of relocation, re-entry, and return decisions 3fl Field Measurement and Analysis Adequate Equipment for Plume Phase Field Measurements 4al Field Teams obtain sufficient information 4a2 Field Teams Manage Sample Collection Appropriately 4a3 Post plume phase field measurements and sampling 4bl Laboratory operations 4c0 Emergency Notification and Public Info Activation of the prompt alert and notification system 5al M M M M1 Activation of the prompt alert and notification system - Fast Breaker 5a2 Activation of the prompt alert and notification system - Exception areas 5a3 Emergency information and instructions for the public and the media 5bI __ M M M M M Support Operations/Facilities 19

Unclassified I

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

Mon/Decon of evacuees and EWs and registration of evacuees 6al M Mon/Decon of EW worker equipment Temporary care of evacuees Transportation and treatment of contaminated injured individuals 6bl 6cl I

6dl I

I I

I I

I I

I I

I I

I I

I 20 I I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Table 3.1 - Summary of Exercise Evaluation (Continued. page 2/3) 0 a) a) a) 0* Ca 0

1 rj~ 0 U 0 DATE: 2011-08-23 0, C,

U DO 0

SITE: Monticello Nuclear Generating Plant, MN a) 0 U U a) '0 H Ca C U a)

M: Met, A: ARCA, D: Deficiency, P: Plan Issue, N: Not Ca a,)

0 U Demonstrated r:j~ 0 U C

z z a) 0 0 a) a)

a) a) U U U C a.)

Ca a) 4.1 -C -Cl Fm.-roenrv Oner~itine Nklncsoement Mobilization lal M M Facilities 1bl Direction and Control ic 1 M Communications Equipment idl M MIM M M MIMM M M Equip & Supplies to support operations lel M M M M M M M M Protective Action Decision Making Emergency Worker Exposure Control 2al M Radiological Assessment and PARs 2b1 Decisions for the Plume Phase - PADs 2b2 M PADs for protection of special populations 2c I M Rad Assessment and Decision making for Ingestion Pathway 2dl Rad Assess/Decision making concerning Relocation, Reentry, and Return 2el Protective Action Implementation Implementation of emergency worker exposure control 3al M M M M M M M Implementation of KI decision 3bl_ M M M Implementation of protective actions for special populations - EOCs 33c M Implementation of protective actions for Schools 3c2 M M Implementation of traffic and access control 3dl M M Impediments to evacuation are identified and resolved 3d2 M Implementation of ingestion pathway decisions - availability/use of info 3el Materials for Ingestion Pathway PADs are available 3e2 Implementation of relocation, re-entry, and return decisions 3fl Field Measurement and Analysis Adequate Equipment for Plume Phase Field Measurements 4al Field Teams obtain sufficient information 4a2 Field Teams Manage Sample Collection Appropriately 4a3 Post plume phase field measurements and sampling 4b 1 Laboratory operations 4c1 Emergency Notification and Public Info Activation of the prompt alert and notification system 5al M Activation of the prompt alert and notification system - Fast Breaker 5a2 Activation of the prompt alert and notification system - Exception areas 5a3 Emergency information and instructions for the public and the media 5bl M _ MI_

Support Operations/Facilities 21

Unclassified I

I Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Mon/Decon of evacuees and EWs and registration of evacuees 6a1 IMI M Mon/Decon of EW worker equipment Temporary care of evacuees ITransnortation and treatment of contaminated injured individuals 6b 1 6c 1 I

16dl I Iiiim iI I I I Transnortation and treatment of contaminated iniured individuals I

I I

I I

I I

I I

I I

I I

I 22 I I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Table 3.1 - Summary of Exercise Evaluation (Continued. page 3/3) 0 0

0 0 DATE: 2011-08-23 SITE: Monticello Nuclear Generating Plant, MN 0 U

w. P.) 0. 0 C) 0 0 M: Met, A: ARCA, D: Deficiency, P: Plan Issue, N: Not 0 0 0 .i0

.0 U. 0 15)

Demonstrated ZJ-0 UI UJ 0

0 U- U. C. C.)

.1i Emereencv Onerations Management Mobilization tat M M Facilities 1b1 Direction and Control lcl M Communications Equipment ldl M M M M M M M M M Equip & Supplies to support operations lel M M M M M M M M Protective Action Decision Making Emergency Worker Exposure Control 2al M Radiological Assessment and PARs 2b1 Decisions for the Plume Phase - PADs 2b2 M PADs for protection of special populations 2cl M Rad Assessment and Decision making for Ingestion Pathway 2dl Rad Assess/Decision making concerning Relocation, Reentry, and Return 2el Protective Action Implementation Implementation of emergency worker exposure control 3al M M M M M M Implementation of KI decision 3bl M M M M Implementation of protective actions for special populations - EOCs 3c 1 M Implementation of protective actions for Schools 3c2 M M M Implementation of traffic and access control 3d1 M M _

Impediments to evacuation are identified and resolved 3d2 M _

Implementation of ingestion pathway decisions - availability/use of info 3e1 Materials for Ingestion Pathway PADs are available 3e2 Implementation of relocation, re-entry, and return decisions 3fl Field Measurement and Analysis Adequate Equipment for Plume Phase Field Measurements 4al Field Teams obtain sufficient information 4a2 Field Teams Manage Sample Collection Appropriately 4a3 Post plume phase field measurements and sampling 4bl Laboratory operations 4c 1 Emergency Notification and Public Info Activation of the prompt alert and notification system 5al M Activation of the prompt alert and notification system - Fast Breaker 5a2 Activation of the prompt alert and notification system - Exception areas 5a3 Emergency information and instructions for the public and the media 5bl M M Support Operations/Facilities 23

I After Action Report/Improvement Plan Unclassified Radiological Emergency Preparedness Program (REP)

Monticello Nuclear Generating Plant I

Mon/Decon of evacuees and EWs and registration of evacuees Mon/Decon of EW worker equipment 16a1 6b1 MI IM I I ,I Temporary care of evacuees 6c1 Transnortation and treatment of contaminated iniured individuals 1 6d1 I I I m I I I I I

I I

I I

I I

I I

I I

I I

I I

24 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 3.3 Criteria Evaluation Summaries 3.3.1 Minnesota Jurisdictions 3.3.1.1 State of Minnesota - Bureau of Criminal Apprehension - Inital Warning Point The State of Minnesota's Bureau of Criminal Apprehension Initial Warning Point (IWP) demonstrated the Target Capability of an IWP including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The IWP used effective procedures to alert, notify, and mobilize emergency personnel and activate facilities in a timely manner. Dispatchers were familiar with their nuclear incident notification procedures. There are redundant communication systems available at the IWP, and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 1.d.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.2 State of Minnesota - Emergency Operations Center The State of Minnesota's Emergency Operations Center (EOC) demonstrated the Target Capability of Emergency Operations Center Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The State of Minnesota provided sufficient multi-agency coordination for an incident at the Monticello Nuclear Generating Station by promptly activating and operating for the duration of the incident. The EOC was managed efficiently and effectively completed an activation, notification and staffed to an operational level. The EOC manager provided solid management, direction and control using briefings. This allowed the staff of the EOC to maintain a common operating picture and overall response to the event. The EOC manager coordinated with other jurisdictions including the State to make decisions and ensure that appropriate actions were taken to protect the health and safety of the public.

25

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant In summary, the status of DHS/FEMA criteria for this location is as follows: I

a. MET: 1.a.1, 1.c.1, 1.d.1, 1.e.1, 2.a.1, 2.b.1, 2.b.2, 2.c.1, 3.c.2, 3.d.1, 3.d.2, 5.a.1, 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None I
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None 3
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.3 State of Minnesota - Emergency Operations Center - Planning and Assessment I Center I

The State of Minnesota's Planning and Assessment Center (PAC) demonstrated the Target Capability of PAC Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The PAC Manager used a decision-making process that involved considerations of appropriate factors, including utility recommendations, plant status, release rate, dose projections, field measurements, weather I conditions and knowledge of the area. He also provided necessary coordination to make appropriate and timely Protective Action Recommendations (PAR) to the State Emergency 3 Operations Center Manager while providing consistent PARs for the protection of the public.

In summary, the status of DHS/FEMA criteria for this location is as follows: I

a. MET: 1.a.1, 1.c.1, 1.d.1, 1.e.1, 2.a.1, 2.b.1, 2.b.2, 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None I
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None I

I 26I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 3.3.1.4 State of Minnesota - Emergency Operations Center - Joint Information Center The State of Minnesota's Joint Information Center (JIC) demonstrated the Target Capability of a JIC including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. Key personnel with leadership roles provided appropriate direction and control. Emergency information and instructions were presented to the public and the news media in a timely manner.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 1.c.1, 1.d.1, 1.e.1, 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.5 State of Minnesota - Sherburne County Emergency Operations Center - Regional Program Coordinator The State of Minnesota's Regional Program Coordinator (RPC) located at Sherburne County demonstrated the Target Capability of Emergency Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The State RPC assigned to Sherburne County Emergency Operations Center demonstrated the capabilities of having sufficient equipment, maps, displays and other supplies to support operations.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 2.a.1, 2.b.2, 2.c.1, 5.a.1, 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 27

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan 4 Monticello Nuclear Generating Plant 3.3.1.6 State of Minnesota - Wright County Emergency Operations Center - Regional Program Coordinator The State of Minnesota's Regional Program Coordinator (RPC) located at Wright County I demonstrated the Target Capability of Emergency Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The State RPC assigned to Wright County Emergency Operations Center demonstrated the capabilities of having sufficient equipment, maps, displays and other supplies to support operations.

In summary, the status of DHS/FEMA criteria for this location is as follows: I

a. MET: 1.a. 1, 2.a. 1, 2.b.2, 2.c. 1,5.a. 1, 5.b. 1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None I 3.3.1.7 State of Minnesota - Sherburne County Emergency Operations Center - State Helicopter - Warning County Recreationalists The State of Minnesota's Helicopter demonstrated the Target Capability of Emergency I Operations Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The State Helicopter used effective procedures to alert, notify, and mobilize emergency personnel and activate in a timely manner. Pilots were familiar with their nuclear incident notification procedures, dosimetry and the ability to manage emergency. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise. This included the provision of worker radiological exposure including the decision to implement potassium iodide.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.a.1, 3.b.1, 5.a.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None 28 U

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.8 State of Minnesota - Sherburne County Emergency Operations Center - Minnesota State Police - Traffic and Access Control Point The State of Minnesota demonstrated the Target Capability of Emergency Public Safety and Security Response at Sherburne County through an interview which included the distribution of dosimetry, emergency worker radiological exposure management, and the capability to implement Traffic and Access Control Points (TACPs) within the 10-mile Emergency Planning Zone. During the interview, the Trooper demonstrated knowledge of the provisions of the Emergency Operations Plan related to the establishment of TACPs in addition to the use of the appropriate dosimetry procedures, documentation and communication equipment including portable radios, cell phones and mobile data terminals. This included the provision of dosimetry and the ability to manage emergency worker radiological exposure including the decision to implement potassium iodide.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.a.1, 3.b.1, 3.d.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.9 State of Minnesota - Sherburne County Emergency Operations Center - Minnesota State Police - Traffic and Access Control - DCO Briefing The State of Minnesota demonstrated the Target Capability of Emergency Public Safety and Security Response at Sherburne County through an interview which included the distribution of dosimetry and emergency worker radiological exposure management within the 10-mile Emergency Planning Zone. Appropriate dosimetry, record-keeping documents, and information on how to manage each emergency workers dose was discussed by the Radiological Officer.

29

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Equipment requiring calibration and testing was within proper dates. The DCO provided instructions on potassium iodide and instructions on when to ingest.

In summary, the status of DHS/FEMA criteria for this location is as follows: I

a. MET: 1.d.1, L.e.1, 3.a.1, 3.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None 3
c. DEFICIENCY: None
d. PLAN ISSUES: None 3
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.10 State of Minnesota.- Princeton High School - Evacuee Registration 3 The State of Minnesota's Princeton High School Evacuee Registration demonstrated the Target Capability of Mass Care including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. Princeton High School had adequate resources, and trained personnel to provide Evacuee Registration. This included the provision of worker radiological exposure. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d. 1, 1.e. 1, 3.a. 1, 6.a. 1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None I
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None 3
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3 3.3.1.11 State of Minnesota - Princeton High School - Evacuee/Emergency Worker Monitoring and Decontamination 3 The State of Minnesota's Princeton High School Evacuee/Emergency Worker Monitoring and 3 Decontamination demonstrated the Target Capability of Monitoring and Decontaminating Emergency Workers including the use of effective procedures to alert, notify and mobilize 30 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant emergency personnel and activate facilities in a timely manner. Princeton High School had adequate resources, and trained personnel to provide Evacuee/Emergency Worker Monitoring and Decontamination. This included the provision of worker radiological exposure. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1,3.a.1,6.a.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None f.. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.12 State of Minnesota - Princeton High School - Evacuee/Emergency Worker Monitoring and Decontamination of Vehicles and Equipment The State of Minnesota Princeton Emergency High School Evacuee/Emergency Worker Equipment and Vehicles Monitoring and Decontamination demonstrated the Target Capability of Monitoring and Decontaminating Emergency Workers Equipment and Vehicles including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. Princeton High School had adequate resources, and trained personnel to provide Evacuee/Emergency Worker Equipment and Vehicles Monitoring and Decontamination. This included the provision of worker radiological exposure. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1,3.a.1,6.a.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None 31

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/improvement Plan Monticello Nuclear Generating Plant

g. PRIOR ISSUES - UNRESOLVED: None 3.3.1.13 State of Minnesota.- Fairview Northland Hospital - Medical Services -

TransportationI The State of Minnesota's Fairview Northland Hospital Ambulance Service demonstrated the Target Capability of Triage and Pre-Hospital Treatment of Contaminated Patients including the use of effective procedures to alert, notify andmobilize emergency personnel and activate in a timely manner. Fairview Northland Hospital Ambulance had adequate resources, and trained personnel to provide pre-hospital medical services to contaminated injured individuals. This included the provision of worker radiological exposure. There were redundant communication i systems available and both primary and back-up systems were used effectively during this exercise. 3 In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.a.1, 6.d.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None i
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None 1
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3 3.3.1.14 State of Minnesota - Fairview Northland Hospital - Medical Services - Facility The State of Minnesota's Fairview Northland Hospital demonstrated the Target Capability of Triage and Treatment of Contaminated Patients including the use of effective procedures to alert, i notify and mobilize emergency personnel and activate facilities in a timely manner. Fairview Northland Hospital had proper space, resources, and trained personnel to monitor, decontaminate and provide medical services to contaminated injured individuals. This included the provision of worker radiological exposure. There were redundant communication systems available and both I

primary and back-up systems were used effectively during this exercise. 3 In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1,3.a.1, 6.d.1.

32

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

b. AREAS REQUIRING CORRECTIVE ACTION: 6.d. 1.

ISSUE NO.: 39-11-6dl-A-01 CRITERION: Facility/ORO has the appropriate space, adequate resources, and trained personnel to provide transport, monitoring, decontamination, and medical services to contaminated injured individuals. (NUREG-0654, F.2., H.10., K.5.a.b.,

L.1., 4)

CONDITION: The Ludlum 3 survey meter instrument check was not conducted properly which could have resulted mis-identification of radiation contamination on the contaminated injured individual and emergency worker.

POSSIBLE CAUSE: The written instrument check procedure was clear but the Radiation Safety Officer was not proficient with the instrument to effectively complete check.

REFERENCE:

NUREG-0654, F.2., H.10., K.5.a.b., L.1., 4 Subement-6.d - Transportation and treatment of contaminated injured individuals Fairview Northland Health Medical Center, Radiological Preparedness Plan, Radiation Officer Control Job Action Sheet, Page 3, Preoperational check of Survey Meter EFFECT: Mis-identification of radiological contamination due to improperly calibrated survey meter on a contaminated injured individual or emergency worker could have resulted undetected contamination and unnecessary dose.

CORRECTIVE ACTION DEMONSTRATED: After a brief discussion of the situation, the controller and evaluator agreed that source check and scaling process training of the RSO was necessary. The evaluator stepped out of the room while the training was conducted by the controller. After training the RSO successfully described and performed the source check process.

33

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

c. DEFICIENCY: None 3
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None i
g. PRIOR ISSUES -UNRESOLVED: None I

3.3.2 Risk Jurisdictions 3.3.2.1 Sherburne County - Initial Warning Point I The Sherburne County Initial Warning Point (IWP) demonstrated the Target Capability of an 3 IWP including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The IWP used effective procedures to alert, notify, and 3 mobilize emergency personnel-and activate facilities in a timely manner. Dispatchers were familiar with their nuclear incident notification procedures. There are redundant communication systems available at the IWP, and both primary and back-up systems were used effectively i during this exercise.

I In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 1.d.1. 3
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None I
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None i
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.2 Sherburne County - Emergency Operations Center i The Sherburne County Emergency Operations Center (EOC) demonstrated the Target Capability 1 of Emergency Operations Center Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. Sherburne 3 County provided sufficient multi-agency coordination for an incident at the Monticello Nuclear .

Generating Station by promptly activating and operating for the duration of the incident. The EOC was managed efficiently and effectively completed an activation, notification and staffed to an operational level. The EOC manager provided solid management, direction and control using 34

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant briefings. This allowed the staff of the EOC to maintain a common operating picture and overall response to the event. The EOC manager coordinated with other jurisdictions including the State to make decisions and ensure that appropriate actions were taken to protect the health and safety of the public.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 1.c.1, 1.d.1, 1'.e.1, 2.a.1, 2.b.2, 2.c.1, 3.a.1, 3.b.1, 3.c.1, 3.c.2, 3.d.1, 3.d.2, 5.a.1, 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.3 Sherburne County - Emergency Operations Center - Traffic and Access Control Point Sherburne County demonstrated the Target Capability of Emergency Public Safety and Security Response through interview which included the distribution of dosimetry, emergency worker radiological exposure management, and the capability to implement Traffic and Access Control Points (TACPs) within the 10-mile Emergency Planning Zone. During the interview, the Deputy demonstrated thorough knowledge of the provisions of the Emergency Operations Plan related to the establishment of TACPs in addition to the use of appropriate dosimetry procedures, documentation and communications equipment including portable radios, cell phones and mobile data terminals.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, L.e.1, 3.a.1, 3.b.1, 3.d.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None 35

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.4 Sherburne County - Emergency Operations Center - Traffic and Access Control -

DCO Briefing Sherburne County demonstrated the Target Capability of Emergency Public Safety and Security Response at Sherburne County through an interviewwhich included the distribution of dosimetry and emergency worker radiological exposure management within the 10-mile i Emergency Planning Zone. Appropriate dosimetry, record-keeping documents, and information U on how to manage each emergency workers dose was discussed by the Radiological Officer (RADEF). Equipment requiring calibration and testing was within proper dates. The RADEF I provided instructions on potassium iodide and instructions on when to ingest.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d. 1, 1.e. 1, 3.a. 1, 3.b. 1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.5 Sherburne County - State Emergency Operations Center/Joint Information Center - I Public Information Officer I

The Sherburne County Public Information Officer in the State Joint Information Center (JIC) demonstrated the Target Capability of a JIC including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. Key personnel with leadership roles provided appropriate direction and control. Emergency information and instructions were presented to the public and the news media in a timely I manner.

i In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 5.b.1. 3
b. AREAS REQUIRING CORRECTIVE ACTION: None 36 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.6 Sherburne County - Becker School District - Evacuation School Sherburne County demonstrated the Target Capability of Citizen Evacuation and Shelter-in-Place for school children through interview. The Becker School District representative described plans and procedures to safely evacuate students from the Monticello Generating Station Emergency Planning Zone and reunite them with their families. The school district demonstrated sufficient personnel, current contact information and communications capabilities to notify families and guardians regarding how to reunite with evacuated students.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.c.2.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.7 Wright County - Initial Warning Point The Wright County Initial Warning Point (IWP) demonstrated the Target Capability of an IWP including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The IWP used effective procedures to alert, notify, and mobilize emergency personnel and activate facilities in a timely manner. Dispatchers were familiar with their nuclear incident notification procedures. There are redundant communication systems available at the IWP, and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

37

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

a. MET: 1.a.1, 1.d.1. 3
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.8 Wright County - Emergency Operations Center I The Wright County Emergency Operations Center (EOC) demonstrated the Target Capability of I Emergency Operations Center Management including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The Wright 5 County EOC provided sufficient multi-agency coordination for an incident at the Monticello Nuclear Generating Station by promptly activating and operating for the duration of the incident.

The EOC was managed efficiently and effectively completed an activation, notification and I

staffed to an operational level. The EOC manager provided solid management, direction and control using briefings. This allowed the staff of the EOC to maintain a common operating picture and overall response to the event. The EOC manager coordinated with other jurisdictions including the State to make decisions and ensure that appropriate actions were taken to protect 3 the health and safety of the public.

The Area Requiring Protective Action (ARCA) (39-09-1c 1-A) from the 2009 MNGP Exercise I was to be re-demonstrated by the Wright County EOC via a Controller Inject during the 2011 MNGP Exercise. It was to address the lack of coordination in determining whether to shelter-in- 1 place or evacuate the Wright County Dispatch Center and Jail, located in Sub-Area 1OS. In 2009, the Sheriff made the decision to evacuate without any coordination with the EOC and the WCSD 3 Representative did not inform the WCND of the evacuation; thus the ARCA was not successfully re-demonstrated. 3 On November, 8, 2011, via controller inject and interview, the Wright County EOC successfully re-demonstrated the ARCA. The ARCA is now closed. . 3 In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.a.1, 1.c.1, 1.d.1, 1.e.1, 2.a.1, 2.b.2, 2.c.1, 3.a.1, 3.b.1, 3.c.1, 3.c.2, 3.d.1, 3.d.2, 5.a.1, 5.b.1.3 38

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: 1.c.1.

ISSUE NO.: 39-09-1cl-A-01 ISSUE: The decision by the Jail Captain at 1246 hours0.0144 days <br />0.346 hours <br />0.00206 weeks <br />4.74103e-4 months <br /> to evacuate the jail population was not coordinated with the EOC, and the Nuclear Director/Operations Chief did not become aware of the action until about 1300 hours0.015 days <br />0.361 hours <br />0.00215 weeks <br />4.9465e-4 months <br /> near the end of the exercise.

Options for sheltering-in-place or evacuating were not considered, and the RADEF staff and Operations Chief were not consulted regarding appropriate actions.

CORRECTIVE ACTION DEMONSTRATED: ARCA (39-09-1cl-A-01) was to be redemonstrated by interview via an Inject (Message 8 - Demonstrate the decision making processes and procedures to evacuate or shelter-in-place the jail population).

At 1140 hours0.0132 days <br />0.317 hours <br />0.00188 weeks <br />4.3377e-4 months <br />, the Controller provided the Inject to the Wright County Sheriff s Department (WCSD). The Evaluator discussed the process with the WCSD. The WCSD indicated that the information would be relayed to the Sheriff at the Wright County Dispatch Center and Jail and the Sheriff would make the evacuation decision.

The Evaluator asked if there would be any coordination with the Wright County Nuclear Director or Wright County Radiological Defense Officer prior to any decision. The WCSD indicated that he was only a Liaison and as such could not answer the question. the WCSD indicated again that the Sheriff makes the decision.

This does not concurr with Wright County Sheriff's Department Jail Policy and Procedure Manual dated August 6, 2009:

Evacuation:

1. Through regular contact with the EOC, if necessary the Jail will be advised to evacuate.
2. If directed to evacuate, the Wright county Jail will follow the Evacuation Plan policy 9.04 39

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant The above Policy Manual and Extent-of-Play both mention that the Sheriff will be 3 advised to evacuate or shelter-in-place. This action was clearly not demonstrated.

The procedures need to be more clearly defined and training conducted to illustrate i the correct procedure for all to follow.

I On November 8, 2011, Wright County successfully re-demonstrated that key personnel with leadership roles provided direction and control for an overall response for which they are responsible.

The Area Requiring Corrective Action (39-09-lcl-A-01) has been successfully re- i demonstrated and is closed.

1

g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.9 Wright County - Emergency Operations Center - Traffic and Access Control - DCO i Briefing 1 Wright County demonstrated the Target Capability of Emergency Public Safety and Security Response at Wright County through an interview which included the distribution of dosimetry 3 and emergency worker radiological exposure management within the 10-mile Emergency Planning Zone. Appropriate dosimetry, record-keeping documents, and information on how to manage each emergency workers dose was discussed by the Radiological Defense Officer(RADEF). Equipment requiring calibration and testing was within proper dates. The RADEF provided instructions on potassium iodide and instructions on when to ingest. 3 In summary, the status of DHS/FEMA criteria for this location is as follows:
a. MET: 1.d.1, 1.e.1, 3.a.1, 3.b. 1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None 1
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None i 40

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 3.3.2.10 Wright County - Emergency Operations Center - Traffic and Access Control Point Wright County demonstrated the Target Capability of Emergency Public Safety and Security Response through interview which included the distribution of dosimetry, emergency worker radiological exposure management, and the capability to implement Traffic and Access Control Points (TACPs) within the 10-mile Emergency Planning Zone. During the interview, the Deputy demonstrated thorough knowledge of the provisions of the Emergency Operations Plan related to the establishment of TACPs in addition to the use of appropriate dosimetry procedures, documentation and communications equipment including portable radios, cell phones and mobile data terminals.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.a.1, 3.b.l, 3.d.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.11 Wright County - State Emergency Operations Center/Joint Information Center -

Public Information Officer Wright County demonstrated the Target Capability of Providing Emergency Public Information through the County Public Information Officers (PIOs) at the Joint Information Center (JIC). Wright County PIOs coordinated with their counterparts in the JIC and County EOC to provide timely, accurate and useful information to the public. The JIC facility is well designed and serves as an efficient facility. The Telephone Response Center had access to pre-scripted FAQs, media advisories and special news broadcasts, enhancing their ability to deliver accurate information and maintain good situational awareness. The State of Minnesota HSEM staff provided leadership to the state and local components of the JIC.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 5.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None 41

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant

c. DEFICIENCY: None I
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.12 Wright County - Rockford Fire Department - Emergency Worker Registration Wright County and the Rockford Fire Department demonstrated the Target Capability of m Registering Emergency Workers including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The Rockford Fire I Department had adequate resources, and trained personnel to register Emergency Workers. This included the provision of worker radiological exposure. There were redundant communication 3 systems available and both primary and back-up systems were used effectively during this exercise. 3 In summary, the status of DHS/FEMA criteria for this location is as follows:
a. MET: 1.d.1, 1.e.1, 3.a.1, 3.b.1, 6.a.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.13 Wright County - RFD - Emergency Worker Monitoring and Decontamination of Equipment and Vehicles Wright County and the Rockford Fire Department demonstrated the Target Capability of Monitoring and Decontaminating Emergency Workers Equipment and Vehicles including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The Rockford Fire Department had adequate resources and trained 3 personnel to provide Emergency Worker Equipment and Vehicles Monitoring and Decontamination. This included the provision of worker radiological exposure. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise. i 42 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.a.1, 6.b.1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.14 Wright County - Rockford Fire Department - Emergency Worker Monitoring and Decontamination Wright County and the Rockford Fire Department demonstrated the Target Capability of Monitoring and Decontaminating Emergency Workers including the use of effective procedures to alert, notify and mobilize emergency personnel and activate facilities in a timely manner. The Rockford Fire Department had adequate resources, and trained personnel to provide Emergency Workers Monitoring and Decontamination. This included the provision of worker radiological exposure. There were redundant communication systems available and both primary and back-up systems were used effectively during this exercise.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d. 1, 1.e. 1, 3.a. 1, 6.a. 1.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.15 Wright County - Maple Lake School District - Evacuation School Wright County demonstrated the Target Capability of Citizen Evacuation and Shelter-in-Place for school children through interview. The Maple Lake County School District representative described plans and procedures to safely evacuate students from the Monticello Generating Station Emergency Planning Zone and reunite them with their families. The school district 43

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant demonstrated sufficient personnel, current contact information and communications capabilities 3 to notify families and guardians regarding how to reunite with evacuated students.

In summary, the status of DHS/FEMA criteria for this location is as follows:

a. MET: 1.d.1, 1.e.1, 3.c.2.
b. AREAS REQUIRING CORRECTIVE ACTION: None 3
c. DEFICIENCY: None
d. PLAN ISSUES: None 3
e. NOT DEMONSTRATED: None
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None 3.3.2.16 Wright County - Monticello School District - Evacuation School 3 Wright County demonstrated the Target Capability of Citizen Evacuation and Shelter-in-Place for school children through interview. The Monticello School District representative described plans and procedures to safely evacuate students from the Monticello Generating Station Emergecny Planning Zone and reunite them with their families. The school district demonstrated sufficient personnel, current contact information and communications capabilities to notify families and guardians regarding how to reunite with evacuated students. 3 In summary, the status of DHS/FEMA criteria for this location is as follows:
a. MET: 1.d.1, 1.e.1, 3.c.2.
b. AREAS REQUIRING CORRECTIVE ACTION: None
c. DEFICIENCY: None 3
d. PLAN ISSUES: None
e. NOT DEMONSTRATED: None 3
f. PRIOR ISSUES - RESOLVED: None
g. PRIOR ISSUES - UNRESOLVED: None I 44

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Reportflmprovement Plan Monticello Nuclear Generating Plant SECTION 4: CONCLUSION No Deficiencies were identified for any jurisdiction during this exercise.

There was one Area Requiring Corrective Action (ARCA) identified for the State of Minnesota.

The ARCA was identified under Criterion 6.d. 1-Support Operations/Facilities, whereby the Radiation Safety Officer did not properly complete the source check and scaling process for survey meters. The ARCA was successfully re-demonstrated during the exercise.

No ARCAs were identified for Sherburne County.

There was one ARCA for Wright County (39-09-1 c l-A-01) identified under Criterion 1.c. 1 which was issued in 2009 - Key personnel with functional roles for the Offsite Response Organizations provide direction and control to the part of the overall response effort for which they are responsible, whereby the Operations Chief (Nuclear Director) and other key EOC staff were not informed by staff that a decision to evacuate the County Jail population had been made.

This ARCA was successfully re-demonstrated on November 8, 2011.

Based on the results of the August 23, 2011, exercise, the offsite radiological emergency response plans and preparedness for the State of Minnesota and affected local jurisdictions, site-specific to the MNGP, can be implemented and are adequate to provide reasonable assurance that appropriate measures can be taken offsite to protect the health and safety of the public in the event of a radiological emergency at the site.

Therefore, the Title 44 CFR, Part 350, approval of the offsite radiological emergency response plans and preparedness for the State of Minnesota site-specific to the MNGP, granted on January 4, 1981, remain in effect.

45

I Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant APPENDIX A: EXERCISE TIMELINE I Table 1, on the following page, presents the times at which key events and activities occurred 5 during the MNGP REP Partial Participation Plume Exposure Pathway exercise conducted on August 23, 2011. Also included are times notifications were made to the participating jurisdictions/functional entities.

I I

U I

I I

I I

I I

U I

46 1 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Table 1 - Exercise Timeline DATE: 2011-08-23, SITE: Monticello Nuclear Generating Plant, MN U U U0 U 0 Emergency Classification Level or 0 Event - o 5)0 co5) En05) 0 (A

0)5 0

C4 -5 F Unusual Event N/A N/A N/A N/A N/A N/A N/A Alert 0825 0847 0852 N/A N/A 0847 0852 Site Area Emergency 0959 N/A 1015 1020 1015 N/A 1022 General Emergency 1055 N/A 1 115 1116 1115 N/A 1115 Simulated Rad. Release Started 0953 N/A N/A 0953 N/A N/A N/A Simulated Rad. Release N/A N/A N/A N/A N/A N/A N/A Terminated Facility Declared Operational N/A 0919 0919 0919 N/A 0900 Declaration of State of Emergency N/A 1023 N/A N/A N/A 1026 Exercise Terminated N/A 1315 N/A N/A N/A 1323 Early Precautionary Actions: DNR ordered to N/A 1023 N/A N/A N/A N/A evacuate State parks and hunting areas Early Precautionary Actions: State issued rail N/A 1030 N/A N/A N/A N/A restriction Early Precautionary Actions: State issued N/A 1036 N/A N/A N/A N/A livestock advisory Early Precautionary Actions: State issued N/A 1037 N/A N/A N/A. N/A Northstar railway restriction Early Precautionary Actions: State issued air N/A 1039 N/A N/A N/A N/A restriction Early Precautionary Actions: State issued water N/A 1054 N/A N/A N/A N/A restriction Early Precautionary Actions: Ordered to N/A N/A N/A N/A N/A 1022 evacuate schools and special populations General Information Message: Public advised of N/A N/A N/A 0947 N/A N/A incident at utility 1st Protective Action Recommendation: (2, 5S, N/A 1117 N/A N/A N/A 1117 5W) 1st Protective Action Decision: (2, 5S, 5W) N/A 1122 N/A N/A N/A 1122 1st Siren Activation N/A N/A N/A N/A N/A 1132 1st EAS or EBS Message N/A 1134 N/A N/A N/A N/A 2nd Protective Action Recommendation: (2, 5S, N/A 1230 N/A N/A N/A 1230 5W, 5N) 2nd Protective Action Decision: (2, 5S, 5W, 5N) N/A 1234 N/A N/A N/A 1237 2nd Siren Activation N/A N/A N/A N/A N/A 1244 2nd EAS or EBS Message N/A 1246 N/A N/A N/A N/A KI Administration Decision for General N/A 1122 N/A N/A N/A N/A Population: (2, 5S, 5W)

KI Administration Decision for General N/A 1237 N/A N/A N/A N/A Population: (2, 5S, 5W, 5N)

KI Administration Decision for Emergency N/A 1032 N/A N/A N/A 1034 Workers 47

Unclassified I

I Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Table 1 - Exercise Timeline DATE: 2011-08-23, SITE: Monticello Nuclear Generating Plant, MN I

Emergency Classification Level or U

0 I

I Event 0 0 Unusual Event Alert .

Site Area Emergency N/A 0825 0959 N/A 0847 N/A N/A 0852

.1016 I

U General Emergency 1055 N/A 1113 Simulated Rad. Release Started 0953 N/A N/A Simulated Rad. Release Terminated N/A N/A N/A Facility Declared Operational N/A 0913 Declaration of State of Emergency Exercise Terminated N/A N/A 1023 1314 U

Early Precautionary Actions: DNR ordered to N/A N/A evacuate State parks and hunting areas Early Precautionary Actions: State issued rail restriction N/A N/A I Early Precautionary Actions: State issued livestock N/A N/A advisory Early Precautionary Actions: State issued Northstar railway restriction N/A N/A I Early Precautionary Actions: State issued air N/A N/A restriction Early Precautionary Actions: State issued water restriction N/A N/A I U

Early Precautionary Actions: Ordered to evacuate N/A 1016 schools and special populations General Information Message: Public advised of N/A N/A incident at utility I st Protective Action Recommendation: (2, 5S, 5W) 1st Protective Action Decision: (2, 5S, 5W) 1st Siren Activation N/A N/A N/A 1117 1122 1132 I

1st EAS or EBS Message N/A N/A 2nd Protective Action Recommendation: (2, 5S, 5W, 5N) 2nd Protective Action Decision: (2, 5S, 5W, 5N)

N/A N/A 1230 1237 I

2nd Siren Activation 2nd EAS or EBS Message KI Administration Decision for General Population:

N/A N/A N/A 1244 N/A N/A U

(2, 5S, 5W)

KI Administration Decision for General Population:

(2; 5S, 5W, 5N)

KI Administration Decision for Emergency N/A N/A N/A 1034 I

I Workers 48 I I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant APPENDIX B: EXERCISE EVALUATORS AND TEAM LEADERS The following is a list of the personnel that evaluated the MNGP REP Partial Participation Plume Exposure Pathway Exercise on August 23, 2011. The list includes the evaluation team leadership and all evaluators. The organization each evaluator represents is indicated by the following abbreviations:

DHS/FEMA - Department of Homeland Security/Federal Emergency Management Agency ICF - Consulting Title Name Organization Radiological Assistance Committee, Chairman William E. King DHS/FEMA Exercise Director Dwaine Warren DHS/FEMA Alternate Exercise Director Gary Naskrent DHS/FEMA Site Specialist Edward Golinski DHS/FEMA Team Leader - Minnesota Darren Bates DHS/FEMA Team Leader - Sherburne County Carl Bebrich DHS/FEMA Team Leader - Wright County Edward Diaz DHS/FEMA 49

Unclassified I

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

DATE: 2011-08-23, SITE: Monticello Nuclear Generating Plant, MN LOCATION State of Minnesota - Bureau of Criminal Apprehension - Inital EVALUATOR Richard Grundstrom AGENCY ICFI I

Warning Point State of Minnesota - Emergency Operations Center John Arszulowicz Johanna Berkey FEMA HQ FEMA RX I

John Simpson FEMA RV State of Minnesota - Emergency Operations Center - Planning and Assessment Center State of Minnesota - Emergency Operations Center - Joint Information Thomas Essig John Simpson ICFI FEMA RV I

Center State of Minnesota - Sherburne County Emergency Operations Center

- Regional Program Coordinator

State of Minnesota - Wright County Emergency Operations Center - *Edward Diaz FEMA RV Regional Program Coordinator State of Minnesota - Sherburne County Emergency Operations Center

- State Helicopter - Warning County Recreationalists Karl Rabenhorst FEMA RV I I

State of Minnesota - Sherburne County Emergency Operations Center Richard Echavarria FEMA RIX

- Minnesota State Police - Traffic and Access Control Point State of Minnesota - Sherburne County Emergency Operations Center Paul Nied ICFI

- Minnesota State Police - Traffic and Access Control - DCO Briefing State of Minnesota - Princeton High School - Evacuee Registration State of Minnesota - Princeton High School - Evacuee/Emergency Worker Monitoring and Decontamination Cheryl Weaver Christopher Bellone ICF FEMA RV I State of Minnesota - Princeton High School - Evacuee/Emergency Worker Monitoring and Decontamination of Vehicles and Equipment State of Minnesota - Fairview Northland Hospital - Medical Services -

Paul Nied Deborah Fulk ICFI FEMA RV I

Transportation State of Minnesota - Fairview Northland Hospital - Medical Services -

Facility Sherburne County - Initial Warning Point Christopher Bellone Lashawn Halsey FEMA RV FEMA HQ I

Sherburne County - Emergency Operations Center Rebecca Fontenot Deborah Fulk Edward Golinski Lashawn Halsey FEMA HQ FEMA RV FEMA RV FEMA HQ I

Sherburne County - Emergency Operations Center - Traffic and Access Control Point James King Lashawn Halsey FEMA RV FEMA HQ I Sherburne County - Emergency Operations Center - Traffic and Delwyn Kinsley FEMA RV Access Control - DCO Briefing Sherburne County - State Emergency Operations Center/Joint Information Center - Public Information Officer Richard Grundstrom ICFI I Sherburne County - Becker School District - Evacuation School Wright County - Initial Warning Point Wright County - Emergency Operations Center Richard Echavarria Steve Marshall Bridget Ahlgrim FEMA RIX FEMA HQ FEMA HQ I

I David Ortman FEMA RV Dennis Wilford ICFI Wright County - Emergency Operations Center - Traffic and Access Dennis Wilford ICFI Control - DCO Briefing Wright County - Emergency Operations Center - Traffic and Access Control Point Steve Marshall Wright County - State Emergency Operations Center/Joint Information Richard Grundstrom FEMA HQ ICFI I

Center - Public Information Officer 50 I I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Wright County - Rockford Fire Department - Emergency Worker Rebecca Fontenot FEMA HQ Registration Wright County - RFD - Emergency Worker Monitoring and Delwyn Kinsley FEMA RV Decontamination of Equipment and Vehicles Wright County - Rockford Fire Department - Emergency Worker James King FEMA RV Monitoring and Decontamination Wright County - Maple Lake School District - Evacuation School Cheryl Weaver ICF Wright County - Monticello School District - Evacuation School Karl Rabenhorst FEMA RV

  • Team Leader 51

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvemcnt Plan Monticello Nuclear Generating Plant APPENDIX C: ACRONYMS AND I

ABBREVIATIONS I ANI American Nuclear Insurers I

ARC American Red Cross ARCA ARES Area Requiring Corrective Action Amateur Radio Emergency Services I

CAP CR Civil Air Patrol County Road I DCO Dosimetry Control Officer DHS DRD Department of Homeland Security Direct Reading Dosimeter I

EAL Emergency Action Level EAS ECL Emergency Alert System Emergency Classification Level I

EMSRB EMT Emergency Medical Services Regulatory Board Emergency Medical Technician I EOC Emergency Operations Center EOF EPA Emergency Operations Facility Environmental Protection Agency I

EPZ Emergency Planning Zone ERDS ERP Emergency Response Data System Emergency Response Plan I

ESD EW Emergency Services Director Emergency Worker I FDA Federal Drug Administration FEMA GAR Federal Emergency Management Agency Governor's Authorized Representative I

GE GIS General Emergency Geographic Information Systems I HSEM Homeland Security Emergency Management.

IWP JIC Initial Warning Point Joint Information Center I

JIS Joint Information System LPIO Lead Public Information Officer MDO Minnesota Duty Officer MGHS Maple Grove High School 52

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant MNGP Monticello Nuclear Generating Plant MSD Monticello School District MSP Minnesota State Police NARAC National Atmospheric Release Advisory Center NRC Nuclear Regulatory Commission OC Operations Chief ORO Offsite Response Organization OSL Optically Stimulated Luminescence OSLD Optically Stimulated Luminescent Dosimeter PAC Planning Assessment Center PAD Protective Action Decision PAG Protective Action Guidelines PAR Protective Action Recommendation PFD Princeton Fire Department P1O Public Information Officer RAC Regional Assistance Committee RAP Radiological Assistance Program REA Radiation Emergency Area REP Radiological Emergency Preparedness RFD Rockford Fire Department RO Radiological Officer RPS Radiological Protection Specialist RSO Radiation Safety Officer SAE Site Area Emergency SCEOC Sherbume County Emergency Operation Center SEOC State Emergency Operations Center SIM State Incident Manager SOG Standard Operating Guideline SOP Standard Operating Procedure TACP Traffic Access Control Point TEDE Total Effective Dose Equivalent TLD Thermo Luminescence Dosimeters TSC Technical Support Center VFR Visual Flight Rule WCDC Wright County Dispatch Center WCHD Wright County Highway Department WCHS Wright County Human Services WCND Wright County Nuclear Director WCSD Wright County Sheriffs Department 53

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Reportlimprovement Plan Monticello Nuclear Generating Plant APPENDIX D: EXERCISE PLAN This appendix lists the exercise criteria, which were scheduled for demonstration in the MNGP Radiological Emergency Preparedness Partial Participation Plume Exposure Pathway Exercise on August 23, 2011, and the offsite extent-of-play agreement accepted by DHS/FEMA Region V on July 14, 2011. The exercise criteria, contained in the FEMA "Radiological Emergency Preparedness Exercise Evaluation Methodology; Notice," as published in the Federal Register Notice/Vol. 67, dated April 25, 2002, represent a functional translation of the planning standards and evaluation criteria of NUREG-0654/FEMA-REP-1, Rev 1, "Criteria for the Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants," November 1980. Since the exercise criteria are intended for use at all nuclear power plant sites, and due-to variations among offsite plans and procedures, an extent-of-play agreement is prepared by the State and accepted by DHS/FEMA, to provide evaluators with guidance on expected actual demonstration of the criteria.

Exercise Criteria Listed on the following pages are the specific radiological emergency preparedness criteria that were scheduled for demonstration during this exercise.

54

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Monticello Nuclear Generating Plant Plume Phase Exercise Extent of Play Agreement The Monticello Nuclear Generating Plant Exercise will take place the week of August 22 2011. The exercise week will involve in-sequence and out-of-sequence demonstrations including MS-l, EV-2 and Emergency Worker Monitoring & Decontamination on Monday August 22, the partial Plume Phase demonstration, Reception Center and Evacuee vehicle monitoring and decontamination demonstrations on August 23. The State of Minnesota, Sherburne County, and Wright County are the off-site response organizations (ORO's).

Criteria that can be re-demonstrated immediately for credit, at the discretion of the evaluator, include the following: 3.a.1, 3.d.1, 3.d.2, 4.a.3, 4.b.1, 6.a.1, 6.b.1, 6.c.1 and 6.d.1. Criteria that may be re-demonstrated, as approved on a case-by-case basis by the Chairperson of the Regional Assistance Committee, include the following: 2.a.1, 2.b.1, 2.b.2, 5.a.1 and 5.b.1. Minnesota prefers to re-demonstrate whenever possible.

Overview of Exercise Schedule and Sites Moda Auus 22 n MS-1 Evaluations Princeton North Ambulance 6:30 am 911 Northland Dr.

Princeton, MN 55371 Princeton Fairview Northland 7:00 am 911 Northland Dr.

Medical Center Princeton, MN 55371 Pre-Exercise Briefing Entrance Meeting 2:00 pm Holiday Inn 9200 Quaday Ave. NE Otsego, MN 55330 EV-2 Evaluations Maple Lake - Dassel Cokato 10:00 am Maple Lake School District 200 State Hwy 55 East Maple Lake 55358 Becker - Zimmerman 10:00 am Becker School District Office 12000 Hancock St.

Becker MN 55308 Monticello - Maple Grove 1:00 pm Monticello Public Schools District Office 302 Washington St.

Monticello 55362 55

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 I

Emergency Worker Monitoring &

Decontamination - Rockford 7:00 pm Rockford Fire Station 6700 Main Street I

Rockford MN 55373 I

Full scale Plume Phase Exercise Evaluator Briefing 7:00 am State Emergency Operations Center 1

444 Cedar Street. Suite 223 State Duty Officer St. Paul MN 55101 Bureau of Criminal Apprehension I

1430 Maryland Ave E St Paul, MN 55106 I

State EOC & PAC Town Square 444 Cedar St Suite 223 St. Paul MN 55101 I JIC Town Square 444 Cedar St Suite 223 St. Paul MN 55101 I Media Briefing Room Town Square 444 Cedar St Suite 100 St. Paul MN 55101 I

Wright County EOC Wright County Gov't Center 10 2nd St NW Buffalo, MN 55313 I

Sherburne County EOC Sherburne County Gov't Center 13880 Highway 10 Elk River, MN 55330 I

Wright County Dispatch Center and Jail

- Wright County Dispatch and Jail 3800 Braddock Av NE I

Buffalo MN 55313 Minnesota State Patrol Helicopter Notification Demonstration 8:00 am Sherburne County Gov't Center 13880 Highway 10 I

(Out of Sequence weather Elk River, MN 55330 permitting) I Reception Center Princeton Reception Center 7:00 pm Princeton Highth School 807 South 8 ' Avenue Princeton MN, 55371 56

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Evacuee Vehicle Monitoring 7:00 pm Princeton High School 807 South 8t? Avenue Princeton MN, 55371 Evacuee Vehicle Decontamination 7:00 pm Princeton Fire Department 203 4th Ave South Princeton MN, 55371 57

Unclassified I

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 I

FEMA players debriefing 9:00 am Wright County Gov't Center I

10 2nd St NW FEMA media out briefing 10:00 am Buffalo, MN 55313 Wright County Gov't Center I

10 2nd St NW NOTE: The State of MN will provide the notification to the media for the FEMA out brief Buffalo, MN 55313 I

Additional Exercise Notes

" Minnesota is NOT a Homerule State - decision-making for radiological events I rests with the State not the Counties.

  • The call to Target to stop KI distribution at the Alert ECL will be simulated.
  • The initial notification to FRMAC at the Alert ECL and subsequent updates will be I simulated.
  • The call to the Northstar Rail at the Site Area Emergency ECL will be simulated.
  • The Governor's Office is not directly participating in the exercise and phone calls, I faxing and e-mailing of emergency executive orders to the Governor and the Secretary of State will be simulated.
  • The information hotline and field teams will be simulated. I PREVIOUS EXERCISE FINDINGS AND PLANNING ISSUES State of Minnesota I North Memorial Medical Center in Robbinsdale received 2 Areas Requiring Corrective Action from the August 2009 Monticello Exercise. The first one (39-09-1 el-A) involved the Landauer TLD cards which did not have an exchange I date specified and there was no reference available to determine when the TLDs needed to be exchanged. The other ARCA (39-09-6d 1-A), Model 3 survey meters were response checked to ensure they responded to a radioactive check I source, but were not checked using a specified range of reading for a particular source. These ARCAs will be redemonstrated in 2013 the next time North Memorial Medical Center in Robbinsdale participates in a nuclear power plant I exercise.

Wright County Wright County received an Area Requiring Corrective Action (39-09-1cl-A)

I during the August 2009 Monticello Exercise where the decision by the Jail Captain to evacuate the jail population was not coordinated with the Wright County EOC. This ARCA will be redemonstrated during this exercise.

I Sherburne County There are no unresolved ARCAs for Sherburne County.

I 58

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 EVALUATION AREA 1 - EMERGENCY OPERATIONS MANAGEMENT SUB-ELEMENT l.a - Mobilization Criterion 1.a.1: OROs use effective procedures to alert, notify, and mobilize emergency personnel and activate facilities in a timely manner.

State of Minnesota Minnesota State Emergency Operations Center (SEOC)

The Plume Phase Exercise will take place on August 2 3 rd. The SEOC will be activated at the ALERT Emergency Classification Level (ECL). The Minnesota Duty Officer (MDO) at the BCA Communications Center will take the initial call and make notifications by telephone and pagers. Verification of the call is via a fax from the nuclear generating plant which is received before proceeding with the call down. If the FAX is not received; the Minnesota Duty Officer would use the phone numbers on the power plant process sheet to call the power plant in order to verify the call.

The BCA Communications Center (Duty Officer) at the Bureau of Criminal Apprehension 1430 Maryland Avenue East St. Paul, MN 55106 will take the initial call on August 23, 2011 from the Monticello Nuclear Generating Plant. The BCA Communications Center will then demonstrate the call-out of staff and transfer of communications from the call center to the SEOC in a timely manner.

The SEOC is located at 444 Cedar Street, Suite 223, St. Paul, MN. The State Regional Program Coordinators (RPCs) will act as liaisons to the counties and will be pre-positioned in the area of Wright and Sherburne County EOCs due to long travel time. The RPCs will wait an appropriate amount of time before interacting with other county responders.

Radiological Accident Deployment (RAD) Field Teams The Minnesota Radiological Accident Deployment Field Teams are not selected to play for this exercise so notification of the field teams will be simulated.

Joint Information Center (JIC)

The JIC will be activated at the Alert Emergency Classification Level (ECL).

Once activated, it will be maintained until the termination of the exercise. The work area for the JIC is located in the SEOC. Both Sherburne and Wright County PlOs will be pre-positioned near the SEOC. They will not engage before they are notified and will wait the appropriate length of time before beginning play.

Sufficient 24-hour

  • staffing capability of key nd personnel will be presented at the exercise entrance meeting on August 2 2n.

59

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Sherburne County I The initial call will be received in the Sheriff's dispatch office of the Sherburne County Law Enforcement Center. The Sherburne County Government Center and the County EOC are located at 13880 Highway 10, Elk River, MN.

Initial calls to activate EOC staff will begin in the dispatch office. Sherburne County will fully activate their EOC and a PIO will be pre-positioned near the SEOC and wait until notified to respond to the SEOC during the plume phase exercise.

Sufficient 24-hour staffing capability of key personnel will be presented at the exercise entrance meeting on August 22. 3 Wright County The initial call will be received in the Sheriff's dispatch office of the Wright County Dispatch Center located at 3800 Braddock Av NE, Buffalo MN 55313.

Initial calls to activate EOC staff will then begin in the dispatch center. Wright County will fully activate their EOC. A Wright County PIO will be pre-positioned near the SEOC and wait until notified to respond to the SEOC during the plume phase exercise. 3 Sufficient 24-hour staffing capability of key personnel will be presented at the exercise entrance meeting on August 22.

SUB-ELEMENT 1.b - Facilities Criterion 1.b.1: Facilities are sufficient to support the emergency response. I State of Minnesota, Sherburne County, Wright County This criterion has been previously evaluated and is therefore not selected for evaluation in this exercise.

I SUB-ELEMENT 1.c - Direction and Control I Criterion 1.c.1: Key personnel with leadership roles for the ORO provide direction and control to that part of the overall response effort for which they are responsible.

I State of Minnesota The SEOC State Incident Manager (SIM), the Sherburne County Emergency 3

Preparedness Coordinator and the Wright County Nuclear Director (county operations chiefs) will coordinate decisions and emergency activities.

60 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 61

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

REV 3.1 I

Sherburne County The Sherburne County Emergency Preparedness Coordinator (county operations chief) will provide direction and control including coordinating emergency i

activities within the county. Activities will be coordinated with the State, Wright County EOC, and field staff as necessary. I Wright County The Wright County Nuclear Director (county operations chief) will coordinate decisions and emergency activities within the county. Activities will be I

coordinated with the State, Sherburne County EOC, and field staff as necessary.

SUB-ELEMENT 1.d - Communications Equipment I Criterion 1.d.1: At least two communication systems are available, at least one operates properly, and communication links are established and maintained with I appropriate locations. Communications capabilities are managed in support of emergency operations.

I State of Minnesota The state will demonstrate the primary means of communication between the counties, the field monitoring teams and Monticello Nuclear Generating Plant. I The state will also demonstrate one additional (either secondary, tertiary or alternative) means of communication between the Planning and Assessment Center (PAC) and the controller for the Field Monitoring Teams. I Line of Communication Primary Secondary Tertiary Alternative I

SEOC to County EOC Sherbume Dedicated Private Branch Exchange number (PBX)

Commercial telephone/FAX Public Safety Radio VHF/800 MHz Satellite telephone I machine ARMER system Wright Dedicated Private Branch Exchange number (PBX)

Commercial telephone/FAX machine Public Safety Radio VHF/800 MHz ARMER system Satellite telephone I SEOC to Monticello and Prairie Island Nuclear Generating Auto-Ring (dedicated)

Hotline: SEOC to Technical Support Center Commercial telephone/FAX 800 MHz NSPM I

Plants (TSC) and EOF machine SEOC to Federal

Response

Organizations Commercial Satellite telephone National Warning Amateur Radio I

(FEMA, NRC, DOE, telephone/FAX machine System (NAWAS) and Corps of Engineers)

SEOC to Field Commercial telephone/ 800 MHz ARMER Satellite telephone Amateur Radio Monitoring Teams Cell phone 62

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Line of Primary Secondary Tertiary ' Alternative Communication SEOC to Fixed Commercial Satellite Phone VHF/800 MHzRadio Public Safety AmtuRai Amateur Radio Medical Support telephone/FAX Machine ARMER system Facility (primary and backup hospitals)

Public Safety Radio SEOC to Mobile Commercial telephone to VHF/800 MHz Amateur Radio Medical Support primary/backup hospital ARMER system On August 23, 2011 the State of Minnesota will demonstrate the primary means of communication with the risk counties of Sherburne and Wright and with the Monticello Nuclear Generating Plant.

Line of PiayScn Communication Primary Secondary Tertiary Alternative MDO to Risk County Public Safety Radio EOC/Dispatcheo telephone/FAX VHF/800 MHz Satellite Phone hMachine ARMER system MDO to Monticello Commercial Nuclear Generating telephone/FAX 800 MHz NSPM Cell Phones Plants Machine Commercial Public Safety Radio National Warning MDO to SEOC telephone/FAX VHF/800 MHz Satellite Phone Machine ARMER system System (NAWAS)

Sherburne County The Sherburne County EOC's primary communication link is a Commercial phone line to the Monticello Nuclear Generating Plant verification is through fax or callback to the plant. A Dedicated Private Branch Exchange circuit is the primary communications link between the County EOC and the State Emergency Operations Center (SEOC).

The secondary communications method is a privately owned utility frequency radio to the Monticello Nuclear Generating Plant and a Commercial telephone/FAX line to the SEOC.

The tertiary communication method with the Monticello Nuclear Generating Plant is a public dispatch number on commercial telephone/FAX machine and a Public Safety Radio VHF/800 MHz ARMER system with the SEOC. Sherburne County EOC staff will demonstrate functionality of the primary and one of their back up methods of communication.

63

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

REV 3.1 I

Line of Communication Primary Secondary Tertiary Alternative I I

MNGP to Sherburne Commercial phone line 800 MHz Utility Public dispatch number County EOC/Dispatcher specific to MNGP with Frequency radio on Commercial verification call back to telephone/FAX plant or verification by fax machine-verification call back to plant I

Wright County The Wright County EOC's primary communication link is a Commercial phone line to the Monticello Nuclear Generating Plant verification is through fax or I callback to the plant. A Dedicated Private Branch Exchange circuit is the primary communications link between the County EOC and the State Emergency Operations Center (SEOC). I The secondary communications method is a privately owned utility frequency radio to the Monticello Nuclear Generating Plant and a Commercial telephone/FAX line to the SEOC.

The tertiary communication method with the Monticello Nuclear Generating Plant I is a public dispatch number on commercial telephone/FAX machine and a Public Safety Radio VHF/800 MHz ARMER system with the SEOC. Wright County EOC staff will demonstrate functionality of the primary and one of their back up I methods of communication.

Line of Communication Primary Secondary Tertiary Alternative MNGP to Wright County Commercial phone line 800 MHz Utility Public dispatch number EOC/Dispatcher specific to MNGP with Frequency radio on Commercial verification call back to telephone/FAX plant or verification by fax machine-verification call back to plant SUB-ELEMENT i.e - Equipment and Supplies to Support Operations Criterion 1.e.1: Equipment, maps, displays, dosimetry, potassium iodide (KI), and other supplies are sufficient to support emergency operations.

State of Minnesota Equipment, Maps and Displays:

The state will demonstrate the use of equipment, maps, and displays at the SEOC, JIC, and Command Van as necessary to support emergency operations.

64

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 65

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Dosimetry:

Emergency workers will use pocket dosimeters and TLDs and control exposure as follows:

Emergency Worker Dosimeter Range Pick-up I Location State Patrol Helicopter crew (Alert and notification) 0-20 R TLD Sherburne County EOC, weather I

permitting Ambulance crew (Do not 0-200mR TLD Reception Center take KI)

Reception Center Staff (Do 0-200 mR TLD Reception Center not take KI) I Potassium Iodide (KI):

Packets of KI are a part of the state field team response kits. The helicopter crew (weather permitting) and State Highway Patrol (at traffic control points) will I

simulate taking KI when directed. The shelf life of Minnesota's current supply of KI is approved until July 2015. I Per the State of Minnesota Emergency Operations Plan, emergency workers located at the reception center do not take KI. I Equipment Maintenance:

All routine equipment checks and maintenance is reported in the Annual Letter of Certification. Calibration of radiological detection equipment will be reviewed on I

August 22 by FEMA. All radiation monitoring equipment will be operationally checked prior to use. I Traffic Control Points Traffic control equipment is permanently located at the designated Trunk Highway Traffic Control Points (TCP) in the area surrounding the Monticello I

Nuclear Generating Plant. The equipment is to be used to close access into the 10 mile Emergency Planning Zone (EPZ) in conjunction with State Patrol staffing.

The equipment is deployed at the request of the SEOC and coordinated with the 1

county. The Minnesota Department of Transportation personnel will set up the barricades and has additional daily use equipment deployed throughout the districts to supplement as needed.

I 66

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 The barricades are deployed as follows:

Truck Station Location # of Barricades Maintenance Area 3B HQ/St. 3725 12 th Street North 12 Cloud Sub-Area St. Cloud, MN 56303 Buffalo Truck Station/Lake 1137 Highway 25 SE 4 Sub-Area Buffalo MN 55313 Monticello Truck Station/Lake 112 Chelsea Road 8 Sub-Area Monticello, MN 55362 Elk River Truck Station/Elk 18938 Dodge Ave NW 19 River Sub-Area Elk River, MN 55330 Sherburne County Ecuipment. Maps and Displays:

Sherburne County will demonstrate the use of equipment, maps, and displays at the Sherburne County EOC as necessary to support emergency operations.

Dosimetry:

All county emergency workers will wear direct reading dosimeters and TLDs to monitor and control exposure as follows:

Emergency. Worker Dosimeter Range Pick-up Location Emergency Workers Sherburne Co.

(Traffic Control Points, 0-20 R TLD EOC etc.)

Potassium Iodide (KI):

KI for emergency workers is stored at the Sherburne County EOC in the Emergency Preparedness Coordinators office/EOC. The shelf life of Minnesota's current supply of KI has been approved until July 2015..

Equipment maintenance:

All routine equipment checks and maintenance, have been reported in the Annual Letter of Certification. Calibration of radiological detection equipment will be reviewed on August 22 by FEMA. All radiation monitoring equipment will undergo a response check prior to use to verify that the equipment responds to a radioactive check source.

Wright County Equipment, Maps and Displays:

67

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Wright County will demonstrate the use of equipment, maps, and displays at the Wright County EOC as necessary to support emergency operations. All County decontamination equipment is stored at the Rockford Fire Department, except the survey meters and dosimetry that are stored in the Wright County EOC.

Dosimetry:

Wright County Emergency Workers will use direct reading dosimeters and TLDs and control exposure as follows:

Emergency Worker Emergency Workers (Route Alerting, Traffic Control Dosimeter Range Pick-up Location U

0-20 R TLD Wright Co. EOC Points, etc.)

Responders at the 0-200 I Emergency Worker mR TLD Rockford Fire Station Decontamination Facility U

Potassium Iodide (KI):

KI for emergency workers is stored at the County EOC. The shelf life of Minnesota's current supply of KI has been approved until July 2015.

I Equipment Maintenance:

All routine equipment checks and maintenance is reported in the Annual Letter of I

Certification. Calibration of radiological detection equipment will be reviewed on August 22 by FEMA. All radiation monitoring equipment will undergo a response check prior to use to verify that the equipment responds to a radioactive check I

source.

EVALUATION AREA 2 - PROTECTIVE ACTION DECISION-MAKING I SUB-ELEMENT 2.a - Emergency Worker Exposure Control I

Criterion 2.a.1: OROs use a decision-making process, considering relevant factors and appropriate coordination, to ensure that an exposure control system, including the use of KI, is in place for emergency workers including provisions to I authorize radiation exposure in excess of administrative limits or protective action guides.

I State of Minnesota All emergency workers inside the 10-mile EPZ have a radiation exposure limit of 3 R with a turn back limit of 1 R as read on a DRD. The withdraw limit for State RAD Teams is 100 mR/hr. The Planning Chief may authorize radiation exposure I

to emergency workers in excess of the administrative limit in accordance with 68 I I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 standard operating guidelines. If not demonstrated as part of the scenario, this can be demonstrated via interview.

When the decision to administer KI to emergency workers in the Emergency Planning Zone (EPZ) is made (or controller data is injected), the Planning Chief will recommend to the State Incident Manager (SIM) and the Operation Chief that field operations staff take KI (simulated). State Patrol personnel receive their kits at county EOCs per procedure. State emergency workers that will simulate KI administration are:

0 State Patrol Helicopter crew, weather permitting (helicopter crew-alerting the public, if in the air)

  • State Highway Patrol (traffic control points)

Note: at a GeneralEmergency, all emergency workers are advised to take potassium iodide (KI).

Sherburne County, Wright County The Sherburne and Wright County Radiological Officers will instruct county emergency workers to take KI after the recommendation is made by the SEOC Planning and Assessment Center (PAC).

All emergency workers inside the 10-mile EPZ have a radiation exposure limit of 3 R and a turnback limit of I R. The County Radiological Officer, after authorization from the Planning Chief in the SEOC, can allow radiation exposures of county emergency workers in excess of the administrative limit. If a dose extension is not demonstrated through the scenario, the County Radiological Officer can discuss with the evaluator their knowledge of the dose extension procedures/guidelines.

SUB-ELEMENT 2.b - Radiological Assessment and Protective Action Recommendations and Decisions for the Plume Phase of the Emergency Criterion 2.b.1: Appropriate protective action recommendations are based on available information on plant conditions, field monitoring data, and licensee and ORO dose projections, as well as knowledge of onsite and offsite environmental conditions.

State of Minnesota The Planning Chief will evaluate the Monticello Nuclear Generating Plant information and complete independent dose projections based on the information and field-monitoring data provided by a controller acting as the Command Van.

The Planning Chief will make an evaluation of the data and recommend a PAR.

Once there is concurrence between the Operations Chief at the SEOC and the county Operations Chiefs, the SIM will approve the PAR and give it to the Governor or Governor's Authorized Representative for signing and approval.

69

I Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 1 Sherburne County, Wright County The counties will not demonstrate this criterion.

Criterion 2.b.2: A decision-making process involving consideration of appropriate factors and necessary coordination is used to make protective action decisions (PADs) for the general public (including the recommendation for the use of KI, if ORO policy). 3 I

I I

I I

I I

I I

I I

70 1 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 State of Minnesota The Governor or Governor's Authorized Representative (GAR) will demonstrate the ability to make appropriate protective action decisions based on a recommendation from the State Incident Manager and the Planning Chief.

Decision-making for incidents at the Monticello Nuclear Generating Plant is the responsibility of the Governor or GAR as outlined in state statute.

KI is pre-distributed on a voluntary basis to members of the general public living in the Monticello Nuclear Generating Plant 10-mile EPZ. A standing order from the Minnesota Department of Health authorizes the secondary protective action of taking KI when directed to evacuate or shelter-in-place in the affected areas at the General Emergency ECL. KI is not distributed post incident and is not available at reception centers. The call to Target at the ALERT ECL to stop KI distribution will be simulated.

Sherburne County, Wright County Sherburne and Wright counties participate in the protective action decision process in accordance with the state's PAR process. This includes concurrence and coordination between the SEOC and Sherburne and Wright counties.

Note: Minnesota is not a home-rule state.

SUB-ELEMENT 2.c - Protective Action Decision Consideration for the Protection of Special Populations Criterion 2.c.1: Protective action decisions are made, as appropriate, for special population groups.

State of Minnesota It is the responsibility of the counties to make protective actions for special populations; the state of Minnesota is responsible for establishing facilities and providing resources to be made available for the special population groups.

Resources that are available can be discussed with the evaluator.

Sherburne County, Wright County Staff at the Sherburne County and Wright County EOCs will demonstrate this criterion according to their guidelines. Counties are responsible for initiating the notification for evacuation, and identifying needed transportation for special population groups. Resources that are available will be discussed with the evaluator.

71

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 SUB-ELEMENT 2.d - Radiological Assessment and Decision-Making for the Ingestion Exposure Pathway Criterion 2.d.1: Radiological consequences for the ingestion pathway are assessed and appropriate protective action decisions are made based on the ORO planning criteria.

State of Minnesota This criterion is not selected for evaluation.

Sherburne County This criterion is not selected for evaluation.

Wright County This criterion is not selected for evaluation.

Ingestion Counties This criterion is not selected for evaluation.

SUB-ELEMENT 2.e - Radiological Assessment and Decision-Making Concerning Relocation, Re-entry, and Return Criterion 2.e.1: Timely relocation, re-entry, and return decisions are made and coordinated as appropriate, based on assessments of radiological conditions and criteria in the ORO's plan and/or procedures.

State of Minnesota This criterion is not selected for evaluation.

Sherburne County This criterion is not selected for evaluation.

Wright County This criterion is not selected for evaluation.

Ingestion Counties This criterion is not selected for evaluation.

EVALUATION AREA 3 - PROTECTIVE ACTION IMPLEMENTATION SUB-ELEMENT 3.a - Implementation of Emergency Worker Exposure Control Criterion 3.a.1: The OROs issues appropriate dosimetry and procedures, and manages radiological exposure to emergency workers in accordance with the 72

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 plan and procedures. Emergency workers periodically and at the end of each mission read their dosimeters and record the readings on the appropriate exposure record or chart.

State of Minnesota All emergency workers that are issued dosimetry will demonstrate appropriate use of that dosimetry and record keeping in accordance with their established procedures/guidelines. The Emergency workers will demonstrate their knowledge of the turn-back exposure rate and administrative limits as dictated by the scenario or by interview.

Note: HSEM staff will be providing the initialbriefing and dosimetry to the ambulance personnelin the parking lot just before the demonstration.

Sherburne County All emergency workers that are issued dosimetry will demonstrate appropriate use of that dosimetry and record keeping in accordance with their established procedures/guidelines.

As driven by the scenario, field personnel (i.e. Sheriff's deputies), will be called into the EOC (all will be simulated except 1 deputy) to pick up dosimetry, receive a briefing and their emergency assignment.

Wright County All emergency workers that are issued dosimetry will demonstrate appropriate use of that dosimetry and record keeping in accordance with their established procedures/guidelines.

As driven by the scenario, field personnel (i.e. Sheriff's deputies), will be called into the EOC (all will be simulated except 1 deputy) to pick up dosimetry, receive a briefing and their emergency assignment.

Workers at the Wright County Dispatch Center will be notified by the Wright County RADEF officer and issued dosimetry at the General Emergency ECL if and only if the 1OS subarea is affected during a General Emergency ECL.

SUB-ELEMENT 3.b - Implementation of KI Decision Criterion 3.b.1: KI and appropriate instructions are made available should a decision to recommend use of KI be made. Appropriate record keeping of the administration of KI for emergency workers and institutionalized individuals (not the general public) is maintained.

State of Minnesota 73

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 All emergency workers that are directed to take KI will demonstrate the availability of KI, appropriate instructions, and record keeping in accordance with their procedures/guidelines. The actual taking of KI will be simulated.

' 1 Sherburne and Wright County All emergency workers that are directed to take KI will demonstrate the availability of KI, appropriate instructions, and record keeping in accordance with their procedures/guidelines. KI administration instructions to county emergency workers disseminate from the Sherburne County and Wright County EOCs. The I

evaluators will discuss KI administration with the deputy sheriffs of Wright and Sherburne County while demonstrating traffic control.

Workers at the Wright County Dispatch Center will be notified by the Wright County RADEF officer and issued KI at the General Emergency ECL if and only if I the 10S subarea is affected during a General Emergency ECL. The actual taking of KI will be simulated. I SUB-ELEMENT 3.c - Implementation of Protective Actions for Special Populations Criterion 3.c.1: Protective action decisions'are implemented for special m populations other than schools within areas subject to protective actions.

State of Minnesota I This is a county responsibility and will not be demonstrated by the state.

Sherburne County m Sherburne County Will demonstrate this criterion by an interview process with EOC staff. It is the intent of Sherburne County to evacuate all special populations at the General Emergency ECL. All special population calls will beI simulated and contacts logged. Sherburne County's one transportation provider (Elk River Fire) will be contacted.

Wright County Wright County will demonstrate this criterion by an interview process with EOC staff. It is the intent of Wright County to shelter-in-place inmates and personnel at the Wright County Jail and evacuate all other special populations at the General Emergency ECL. All special population calls will be simulated and contacts logged. One of each type of transportation provider will be contacted.

The threeand types of transportation providers are (ambulance, handi-cap lift van I

provider contracted bus service).

The Wright County Dispatch Center located at 3800 Braddock Av NE, Buffalo MN 55313 intends to shelter-in-place at a General Emergency and will evacuate if advised by the county EOC. 74 74 Ii

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 The Wright County Jail located at 3800 Braddock Av NE, Buffalo MN 55313 intends to shelter-in-place at a General Emergency and will evacuate if advised by the county EOC.

75

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Criterion 3.c.2: OROs/School officials decide upon and implement protective actions for schools.

State of Minnesota Evacuation Evacuation of schools is a pre-determined protective action for all schools in the EPZ and is initiated at a Site Area Emergency ECL. This action is a county and school district responsibility and will not be demonstrated by the state during the exercise. Information about reporting back the status of school evacuation may be observed at the SEOC. It is also the responsibility of the State to notify schools outside the EPZ that have children which live within the EPZ to not send students home. This notification will be simulated at the SEOC during the Site Area Emergency ECL.

Sherburne County Evacuation Evacuation will be simulated. Notifications to the schools by the county EOC will begin at the Alert ECL. I EV-2 Becker/Zimmerman EV-2 is scheduled for Monday August 22nd from 10:00 to 12:00 located at the Becker School District Office 12000 Hancock St. Becker MN 55308. Becker's agreement is with the Zimmerman School District. Evaluation I

will be through interview of the necessary school and transportation officials that should include but not limited to: the superintendent, one principal, one nurse, I one transportation provider and a host school representative.

Preschools and daycares are notified by county human services agencies at the Alert ECL and are treated as the general population at the General Emergency ECL.

Wright County Evacuation Evacuation will be simulated. Notifications to the schools by the county EOC will begin at the Alert ECL.

3 Maple LakelDassel Cokato EV-2 is scheduled for Monday August 2 2 nd from 10:00 to 12:00 at the Maple Lake School District 200 State Hwy 55 East in Maple 3

Lake 55358. Maple Lake's agreement is with the Dassel Cokato school District.

The evaluation will be through an interview of the necessary school and transportation officials which should include but is not limited to: the I

superintendent, one principal, one nurse, one transportation provider and a host school representative.

76

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Monticello/Maple Grove EV-2 is scheduled for Monday August 2 2 nd from 1:00 to 3:00 at the Monticello Public Schools District Office 302 Washington St. in Monticello 55362. Monticello's plan agreement is with the Maple Grove School District. Evaluation will be through an interview of the necessary school and transportation officials which should include but is not limited to: the superintendent, one principal, one nurse, one transportation provider and a host school representative.

Preschools and daycares are notified by county human services agencies at the Alert ECL and are treated as the general population at the General Emergency ECL.

SUB-ELEMENT 3.d - Implementation of Traffic and Access Control Criterion 3.d.1: Appropriate traffic and access control is established. Accurate instructions are provided to traffic and access control personnel.

State of Minnesota According to procedures the SEOC will notify air, rail (including Northstar rail),

and waterway transportation at the Site Area Emergency ECL. This will be demonstrated through simulated calls at the SEOC during the exercise.

MNDOT and the Minnesota State Patrol from the state EOC will assist with identification of traffic and access control points necessary to implement recommended protective actions.

The State Highway Patrol will demonstrate traffic control as coordinated through the Sherburne County EOC. State Patrol and MnDOT personnel other than those in the SEOC will receive their briefing and pick up dosimetry from the Sherburne County EOC. MnDOT personnel will participate by simulating the movement of barriers and by interview. The evaluator will meet the responding State Patrol Officer and MnDOT personnel at the EOC then proceed to the parking lot for the interview. No barricades will actually be placed on the roadside.

Sherburne County The Sherburne County EOC staff will select, establish, and coordinate staffing of traffic and access control points consistent with the protective action decisions for evacuation areas. This criterion will be demonstrated by simulation and staff interview.

A deputy and/or public works employee will simulate proceeding to a conveniently located, pre-determined roadblock location. No barricade will 77

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 actually be placed on the roadside. An evaluator will conduct a procedural n interview outside of the EOC in the parking lot.

Wright County The Wright County EOC staff will select, establish, and coordinate staffing of traffic and access control points consistent with the protective action decisions for evacuation areas. This criterion will be demonstrated by simulation and staff interview.

A deputy and/or public works employee will simulate proceeding to a conveniently located, pre-determined roadblock location. No barricade will actually be placed on the roadside. An evaluator will conduct a procedural interview outside of the EOC in the parking lot. I Criterion 3.d.2: Impediments to evacuation are identified and resolved.

State of Minnesota I The State is responsible for state highways and waterways within the EPZ used for route evacuations and for manning traffic control points on these state highways and waterways. The state will demonstrate the necessary actions to reroute traffic on state highways or waterways as dictated by the scenario. A I

controller inject will be used to simulate a traffic impediment on one of the evacuation routes. Actual deployment of assets will be simulated, but all actual or simulated contacts made should be logged.

Sherburne County, Wright County n A controller message(s) will be used to create a simulated evacuation impediment. Each county will demonstrate appropriate corrective actions.

Actual deployment of assets will be simulated, but all actual or simulated contacts made should be logged.

I SUB-ELEMENT 3.e - Implementation of Ingestion Pathway Decisions I Criterion 3.e.1: The ORO demonstrates the availability and appropriate use of adequate information regarding water, food supplies, milk and agricultural production within the ingestion exposure pathway emergency planning zone for implementation of protective actions.

State of Minnesota This criterion was not selected for this exercise. 3 Sherburne County This criterion was not selected for this exercise.

78 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Wright County This criterion was not selected for this exercise.

Ingestion Counties This criterion was not selected for this exercise.

Criterion 3.e.2: Appropriate measures, strategies, and pre-printed instructional material are developed for implementing protective action decisions for contaminated water, food products, milk, and agricultural production.

State of Minnesota This criterion was not selected for this exercise.

Sherburne County This criterion was not selected for this exercise.

Wright County This criterion was not selected for this exercise.

Ingestion Counties This criterion was not selected for this exercise.

SUB-ELEMENT 3.f - Implementation of Relocation, Re-entry, and Return Decisions Criterion 3.f.1: Decisions regarding controlled re-entry of emergency workers and relocation and return of the public are coordinated with appropriate organizations and implemented.

State of Minnesota This criterion was not selected for this exercise.

Sherburne County This criterion was not selected for this exercise.

Wright County This criterion was not selected for this exercise.

Ingestion Counties This criterion was not selected for this exercise.

EVALUATION AREA 4 - FIELD MEASUREMENT AND ANALYSIS SUB-ELEMENT 4.a - Plume Phase Field Measurement and Analyses 79

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Criterion 4.a.1: The field teams are equipped to perform field measurements of direct radiation exposure (cloud and ground shine) and to sample airborne radioiodine and particulates.

State of Minnesota I State RAD Teams are not selected for this exercise. All field team data will be simulated and injected via phone by a controller. 3 Equipment maintenance:

All routine equipment checks and maintenance will be documented in a current PR-I report, which will be provided at the entrance meeting.

Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

Criterion 4.a.2: Field teams are managed to obtain sufficient information to help characterize the release and to control radiation exposure.

State of Minnesota This activity is not selected for this exercise.

Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

Criterion 4.a.3: Ambient radiation measurements are made and recorded at appropriate locations, and radioiodine and particulate samples are collected.

Teams will move to an appropriate low background location to determine whether any significant (as specified in the plan and/or procedures) amount of radioactivity has been collected on the sampling media.

State of Minnesota This activity is not selected for this exercise.

Field team data will be communicated to the Planning and Assessment Center (PAC) by a controller acting as the command van. The controller will communicate with the PAC via phone.

Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

SUB-ELEMENT 4.b - Post Plume Phase Field Measurements and Sampling 80

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Criterion 4.b.1: The field teams demonstrate the capability to make appropriate measurements and to collect appropriate samples (e.g., food crops, milk, water, vegetation, and soil) to support adequate assessments and protective action decision-making.

State of Minnesota This criterion was not selected for this exercise.

Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

SUB-ELEMENT 4.c - Laboratory Operations Criterion 4.c.1: The laboratory is capable of performing required radiological analyses to support protective action decisions.

State of Minnesota This criterion was not selected for this exercise.

Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

EVALUATION AREA 5 - EMERGENCY NOTIFICATION AND PUBLIC INFORMATION SUB-ELEMENT AREA 5.a - Activation of the Prompt Alert and Notification System Criterion 5.a.1: Activities associated with primary alerting and notification of the public are completed in a timely manner following the initial decision by authorized offsite emergency officials to notify the public of an emergency situation. The initial instructional message to the public must include as a minimum the elements required by current FEMA REP guidance.

State of Minnesota The development and dissemination of an Emergency Alert System (EAS) message will be demonstrated in the SEOC. The EAS is activated only when there is a protective action (i.e., evacuation or sheltering) for people. The State EAS Plan states that the code for a nuclear generating plant incident is monitored by all relay stations and is set to automatically transmit the message from the State EOC.

The following is a summary of the PAD and EAS process:

1. The Planning and Assessment Center (PAC) receives a recommendation from the utility.

81

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1

2. The PAC makes an independent assessment of the data and develops its recommendation.
3. The EAS Message and corresponding Special News Bulletins are selected by the Planning Chief and communicated to the Operations Chief.
4. The Operations Chief gets concurrence on the Protective Action Recommendation (PAR) from the risk counties.
5. The PAR is communicated to the Minnesota State Incident Manager (SIM)
6. The PAR is communicated to the Governor's Authorized Representative (GAR) where once approved, it becomes a Protective Action Decision (PAD).
7. The time that the sirens are sounded and the time the EAS is activated is determined by the SIM after the PAD has been approved by the GAR.
8. A copy of the approved PAD goes to the Operations Chief to coordinate these times with Wright and Sherburne counties via a conference call -

the EAS message is the State's responsibility.

9. The sirens are sounded (simulated).
10. The EAS message is transmitted (simulated).
11. Special News Bulletins are sent out.
12. Media Briefings occur.

NOTE: The first PAR is pre-approved and does not require the Governor's approval, only the State Incident Manager's (SIM's) approval. All subsequent PARs require the Governor's or GAR's approval.

An EAS Writer (located in the SEOC) will directly broadcast by radio transmission an EAS message using an encoder/decoder, which is automatically monitored by encoders/decoders by major relay stations. In addition, the EAS Writer has the capability to send a message directly over NOAA weather alert radios utilizing a link to the National Weather Service headquarters in Chanhassen, Minnesota.

EAS messages will contain basic information regarding the event. Additional information will be disseminated through the JIC using special news broadcasts and media releases.

Weather permitting, a State Patrol helicopter, equipped with a public address system, will warn recreational area individuals and/or groups. The State Patrol helicopter will do this as an out of sequence event at approximately 8:00 AM on the morning of Tuesday August 23rd and will operate from the Sherburne County Law Enforcement Center located at 13880 Highway 10, Elk River, MN. The helicopter decontamination process will be demonstrated by interview with the helicopter crew.

Activation of sirens, EAS, weather radios and the broadcast of media messages will be simulated. 8 82

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 The State of Minnesota will be using various social media services (Twitter, Facebook, etc.) to notify the public, but these will not be evaluated.

Sherburne County All EAS messages are developed and disseminated by the SEOC. After PAR concurrence via a conference call with the other county and the state, sirens are sounded once following each evacuation or sheltering PAR. Wright County has the lead for siren activation coordination with Sherburne County. The coordination of alert and notification implementation will be demonstrated in the Sherburne County EOC (siren activation will be simulated). Special populations are notified using Alertcast.

83

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Wright County I All EAS messages are developed and disseminated by the SEOC. After PAR concurrence via a conference call with the other county and the state, sirens are sounded once following each evacuation or sheltering PAR. Wright County has the lead for siren activation coordination with Sherburne County. The I

coordination of alert and notification implementation will be demonstrated in the Wright County Dispatch Center (siren activation will be simulated). Special populations are notified using Tone Alert Radios. Citywatch may also be used, I

but it will not be evaluated. 3 5.a.2: [RESERVED]

Criterion 5.a.3: Activities associated with FEMA approved exception areas (where I applicable) are completed within 45 minutes following the initial decision by authorized offsite emergency officials to notify the public of an emergency situation. Backup alert and notification of the public is completed within 45 minutes following the detection by the ORO of a failure of the primary alert and notification system. I State of Minnesota This criterion is the responsibility of the counties and will not be demonstrated by the state.

Sherburne County Sherburne County has 100% siren coverage and is not demonstrating route alerting, unless a siren is inoperable due to a controller inject.

During the General Emergency, the MNGP monitors informer units in the TSC to pick up when the counties activate their sirens. When the county activates the 5

sirens, the MNGP will poll them and call the county (either the RADEF Officer when the EOC is activated or the County Dispatch when the EOC is not activated) and inform them of the status of siren activation. If the EOC is I

activated, the RADEF Officer will notify the law enforcement in the EOC of the inoperable sirens. The law enforcement staff in the EOC will dispatch deputies to run routes for inoperable sirens.

I If the EOC is not activated, the dispatch will dispatch deputies to run backup route(s) for the inoperable siren(s) to notify the public in that area where the siren was inoperable.

Note: During the exercise there will not be any actual siren activation.

84 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Wright County Wright County has 100% siren coverage and is not demonstrating route alerting, unless a siren is inoperable due to a controller inject.

During the General Emergency, the MNGP monitors informer units in the TSC to pick up when the counties activate their sirens. When the county activates the sirens, the MNGP will poll them and call the county (either the RADEF Officer when the EOC is activated or the County Dispatch when the EOC is not activated) and inform them of the status of siren activation. If the EOC is activated, the RADEF Officer will notify the law enforcement in the EOC of the inoperable sirens. The law enforcement staff in the EOC will dispatch deputies to run routes for inoperable sirens.

If the EOC is not activated, the dispatch will send deputies to run backup route(s) for the inoperable siren(s) to notify the public in that area where the siren was inoperable.

Note: During the exercise there will not be any actual siren activation.

Backup alert and notification:

This criterion will not be demonstrated.

SUB-ELEMENT 5.b - Emergency Information and Instructions for the Public and the Media Criterion 5.b.1: OROs provide accurate emergency information and instructions to the public and the news media in a timely manner.

State of Minnesota After the SIM has approval of the PAD from the GAR, pre-scripted EAS messages communicating emergency information and instructions is released to the public. The State of Minnesota uses pre-scripted EAS messages. Initiating release of pre-scripted EAS messages is the responsibility of the SEOC Planning Chief. Special news bulletins will be pre-scripted and modified as needed and coordinated with all applicable agencies. The public will be told to remain tuned to their radio and television stations for further information. Special news broadcasts will be announced in the JIC media briefing room.

The Lead PIO and other organizational PlOs will work together in the JIC work area (located in the SEOC). They will determine what information is released to the general public. Media briefings will be demonstrated in the media briefing room.

85

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 PlOs will simulate the distribution of news releases and advisories via e-mail and will log the distribution, recording what they would have actually sent out. A list of the media organizations will be provided to the evaluator. The Lead PIO will coordinate all information released to the media. 3 An Information Hotline (public inquiry) will be simulated during this exercise and not staffed and operational. Simulated rumor trends coming into the hotline will be communicated to the JIC using controller injects.

Sherburne County Emergency information released to the public and the news media are the responsibility of the SEOC and the JIC. The Sherburne County Public Information Liaison will demonstrate the coordination of county public information through the JIC. The Sherburne County PIO state liaison will be pre-positioned I near the SEOC and will wait an appropriate amount of time before beginning play. i Sherburne County will not be demonstrating any local briefings.

Wright County i Emergency information released to the public and the news media are the responsibility of the SEOC and the JIC. The Wright County Public Information Liaison will demonstrate the coordination of county public information through the JIC. The Wright County PIO state liaison will be pre-positioned near the SEOC I

and will wait an appropriate amount of time before beginning play.

Wright County will not be demonstrating any local briefings EVALUATION AREA 6 - SUPPORT OPERATION/FACILITIES SUB-ELEMENT 6.a - Monitoring and Decontamination of Evacuees and Emergency Workers and Registration of Evacuees Criterion 6.a.1: The reception center/emergency worker facility has appropriate space, adequate resources, and trained personnel to provide monitoring, I decontamination, and registration of evacuees and/or emergency workers.

State of Minnesota Evacuee monitoring will be demonstrated on August 2 3 rd, 2011 at 7:00 pm at the Princeton Reception Center located at Princeton High School, 807 South 8 th U

Avenue.

The facility Director of Operations is a Safety Officer from the Minnesota Department of Human Services (DHS). The evacuee monitoring stations use 86

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 both vehicle and personnel portal monitors and will monitor at least 4 evacuees to demonstrate the 20% EPZ population monitoring capability in a 12-hour period. Hand held survey instruments (Ludlum Model 3s) are used by monitoring staff in the decontamination areas. A check source is used to ensure that the instruments respond. Hand held instruments are calibrated annually. Reception Center volunteer staff will conduct monitoring and serve as recorders. Volunteer mock evacuees will go through the reception center monitoring, decontamination and registration process. At least one "evacuee" will require decontamination.

The decontamination process will be demonstrated by interview with reception center staff. Contamination levels, monitoring and decontamination results will be provided by controllers.

All evacuees who pass through the Reception Center will be processed through the registration station.

Ambulance personnel will be set up onsite to respond to potentially contaminated and injured evacuees, but this portion will not be evaluated. Evaluation of the ambulance response (MS-I) will occur on Monday August 2 2 nd at 6:30 AM at Fairview Northland Medical Center located at 911 Northland Dr. Princeton MN 55371.

Household pet decontamination and monitoring may be set up, but will not be evaluated as a part of this exercise.

Vehicle Monitoring and Decontamination Two evacuee vehicles will be monitored with at least one requiring decontamination. The vehicle decontamination process will be demonstrated at 7:00 PM Wednesday August 2 3 rd at Princeton High School, 807 South 8 th Avenue. The vehicles are decontaminated and returned to the clean vehicle lot as time and resources permit. Unmonitored vehicles are directed to an unmonitored holding lot at the Reception Center.

Wright County Emergency Worker Monitoring and Decontamination will be demonstrated at 7:00 PM Monday August 2 2 nd at the Rockford Fire Station located at 6700 Main Street in Rockford.

At least one emergency worker will go through the Emergency Worker monitoring, decontamination and registration process. Only one emergency worker will be wearing Tyvek. The decontamination process will be demonstrated by interview with Emergency Worker Decontamination Center staff.

Controllers will provide contamination levels and monitoring and decontamination 87

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 results.

Sherburne County Sherburne County will not be demonstrating this criterion.

SUB-ELEMENT6.b - Monitoring and Decontamination of Emergency Worker Equipment Criterion 6.b.1: The facility/ORO has adequate procedures and resources for the accomplishment of monitoring and decontamination of emergency worker equipment, including vehicles.

State of Minnesota This is a county responsibility and will not be demonstrated by the state.

Wright County Monitoring and decontamination of emergency worker equipment and vehicles will be demonstrated at the Rockford Fire Station located at 6700 Main Street at 7:00 PM August 2 2 nd. At least one emergency worker vehicle will be monitored and will require decontamination. The vehicle decontamination process will be demonstrated by an interview with the Rockford Decontamination Center staff.

Hand held survey instruments (Ludlum Model 3s) will be used to monitor emergency workers. A check source is used to ensure that the instruments respond. Hand held instruments are calibrated annually.

Controllers will provide contamination and monitoring levels along with decontamination results.

Sherburne County Sherburne County is not scheduled to demonstrate this capability.

SUB-ELEMENT 6.c - Temporary Care of Evacuees Criterion 6.c.1: Managers of congregate care facilities demonstrate that the centers have resources to provide services and accommodations consistent with American Red Cross planning guidelines. (Found in MASS CARE - Preparedness Operations, ARC 3031) Managers demonstrate the procedures to assure that evacuees have been monitored for contamination and have been decontaminated I as appropriate prior to entering congregate care facilities.

State of Minnesota This criterion is not selected for this exercise because the site is managed by the American Red Cross.

88

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

SUB-ELEMENT 6.d - Transportation and Treatment of Contaminated Injured Individuals Criterion 6.d.1: The facility/ORO has the appropriate space, adequate resources, and trained personnel to provide transport, monitoring decontamination, and medical services to contaminated injured individuals.

89

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant REV 3.1 State of Minnesota I MS-1 Transportation (Ambulance)

Princeton North Ambulance will demonstrate this criterion on Monday August 22nd at 6:30 AM in the parking lot outside the Princeton Fairview Northland Medical Center 911 Northland Dr. Princeton, MN 55371. A controller will provide the ambulance crew with a simulated contaminated injured evacuee. The ambulance crew will assess the person's medical condition and wrap the patient up but will not monitor them. They will then prepare the patient for transport to Fairview Northland Medical Center. Communications between the Ambulance and the hospital will be demonstrated at this time.. Ambulance contamination monitoring will be demonstrated by the hospital staff through an interview process.

MS- 1 (Facilities)

Princeton Fairview Northland Medical Center located at 911 Northland Dr.

Princeton, MN 55371 will demonstrate this criterion at 7:00 AM on Monday August 2 2 nd. The transportation aspect of this demonstration will be performed at I

the same location. A contaminated injured evacuee will arrive at the emergency room by ambulance. Upon notification by the ambulance, hospital personnel will I prepare the emergency room area for arrival of a contaminated patient, including appropriate contamination control measures. Hospital radiation specialists will conduct radiological monitoring. Appropriate equipment and supplies will be available. The setting of priorities between medical treatment and contamination I

controls will be demonstrated. Samples will be collected and decontamination procedures will be demonstrated. The screening of the ambulance for I contamination will be demonstrated at this time by interview.

I Sherburne County, Wright County This is a state function and will not be demonstrated by the counties.

90

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant APPENDIX E: SCENARIO DETAILS This appendix contains a summary of the Exercise Scenario, a simulated sequence of events that was used as the basis for invoking emergency response actions by OROs during the MNGP REP Partial Participation Plume Exposure Pathway exercise on August 23, 2011.

Results of a technical review of the scenario, submitted by the State of Minnesota and Xcel Energy on July 14, 2011, indicated that the scenario was adequate to support demonstration of Department of Homeland Security's requirements, as well as criteria selected by the OROs provided in the State's July 20, 2011, extent-of-play submission.

This exercise scenario was accepted by DHS/FEMA Region V on July 21, 2011.

During the exercise, in addition to information and data provided through the MNGP onsite scenario, controllers from the State of Minnesota gave "inject messages" containing scenario events and/or relevant data to those persons or locations who would normally receive notification of such events.

The inject messages were the method used for invoking additional specific response actions by OROs.

DHS/FEMA concurred with the offsite scenario and extent-of-play submission for the State of Minnesota, Sherburne and Wright Counties for the August 23, 2011 Biennial Radiological Emergency Preparedness Exercise for the MNGP.

91

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant Offsite Timeline - Rev. 1 August 23, 2011 TIME E EVENT

SUMMARY

0700 INITIAL CONDITIONS The reactor has been at continuous operation for 98 days.

A few hours after a minor rod pattern adjustment was performed on the nightshift,

  • operations personnel noticed that a minor fuel defect had occurred. Currently, the cause of the failure is unknown. i Winds are from the East at 4- 5 mph. Temperature is in the mid 80's with noon time temperatures expected in the mid 90's.

-0810 While lifting the hatch cover for weather seal replacement, the operator loses control of the load and the Grove tips and crashes into the intake structure. The concrete hatch cover is dropped through the ventilation plenum and the overload alarm is received in the Control Room. (Note: Receipt of alarms is the start of the 15 minute classification clock for the Alert.)

0810-0825 Once the visible damage is verified, the Shift Manager should declare an ALERT i based on HAI.3, "Vehicle crash within the plant PROTECTED AREA boundary and causing VISIBLE DAMAGE to any plant structures or equipment therein or Control Room indication of degraded performance of those systems" =

a:2-04 Offie Noiiain Ste( an Contes fo th Alr shul be completed .

1. Call list notifications take place. S(OTR E MESAG 1]

I

2. Emergency Operating Center (EOC) activation (State of Minnesota, Wright and Sherburne Counties) occurs.

I

- EOC security system initiated

- Maps, displays set up, messages forms, logs, etc. distributed

- Communication links established and maintained throughout I

the exercise

- Assembled EOC personnel briefed, with additional briefings held periodically throughout the exercise I Note: The BCA Duty Officer participation is complete when notifications are completed and they are informed by the Planning and Assessment Center that they have taken I

over communication with the plant.

I 92

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant

.Offsite Timeline - Rev. 1 August 23, 2011 TIME EVENT

SUMMARY

3. Radiological Accident Deployment (RAD) teams and Team Captain respond to Maple Grove fire station (Simulated). From there they will be dispatched to affected areas.

[LU Rl4422 IS3 4. Department of Natural Resources and Department of Agriculture Department Operations Centers (DOCs) are activated (simulated).

5. Local and state first responders are put on standby.
6. Joint Information Center (JIC) is activated.

- Public Information Officers (PlOs) notified

- JIC displays and media information kits arranged.

- JIC Security and Moderator report to media briefing room Initial JIC Management Team meeting Initial news briefing conducted by HSEM Director Preparation and issue of Public Information Bulletins and news releases will continue until the termination of the exercise.

7. Planning Chief requests additional radiological assets from the 55thCST and DOE radiological assets are requested through FRMAC. (Simulated).
8. The Planning and Assessment Center initiates dose assessment

-0845 The. Electrical Pressure Regulator (EPR) fails, causing a Reactor Coolant System Pressure Spike.

0910-0925 Sixty minutes after the declaration of the ALERT, the Technical Support Center (TSC), Operational Support Center (OSC), Access Control and the Emergency Operations Facility (EOF) should be manned and operating.

-0940 A complete valve packing failure occurs in the steam chase. The packing failure results in steam chase tunnel temperatures increasing rapidly. As a result, the operating crew is expected to SCRAM the reactor to isolate the leak. Upon reactor SCRAM both steam lines (inboard and outboard) fail to close. (Note: this starts the 15 minute classification clock for the SAE.)

0940-0955 The ERO should classify and make declaration of the event as a SITE AREA EMERGENCY based on FSl.1 "Log'or Potential Loss of ANY Two Barriers EAL criterion applicable are:

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant Offsite Timeline - Rev. I August 23, 2011

[TIME EVENT

SUMMARY

1. Reactor Coolant System Barrier Loss
2. Primary Containment Barrier Loss

-1000 Shortly after the declaration of the SITE AREA EMERGENCY a plant/site evacuation should be initiated.

1. EOC and field staff are notified of the classification upgrade.
  • Sherburne and Wright County EOCs
  • RAD Teams Maple Grove & Plymouth (simulated)
  • Decontamination Centers (simulated/out of sequence activity)
  • Reception Centers are activated (simulated/out of sequence activity)
2. Congregate Care Center is activated (simulated)
3. Schools are evacuated to sister schools (simulated).
4. MDA and DNR field sampling teams put on standby (simulated).
5. Governor advised of incident status. "State of Emergency" recommended by State Incident Manager.
6. "State of Emergency" declared by Governor.
7. Livestock placed on covered water and stored feed.

-1025 Communications lost between the Field Team Command Van and the PAC 1 011 A,

-1030 ra COTR meamenSSAE56 L

-1030 Significant fuel failure begins. Vent and Stack release rates escalate rapidly. The Reactor Building Vent release readings increase from -300 to -70,000 pCi/Sec over the next 5-8 minutes. An increase in Area dose rates in steam and adjacent areas of the Reactor and Turbine Buildingqccurs.

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant Offsite Timeline - Rev. 1 August 23, 2011 TIME EVENT

SUMMARY

I The Containment High Radiation Monitor readings begin increasing.

-1054 The Containment High Range Radiation Monitor readings exceed 1800 R/Hr indicating the Loss of the Fuel Cladding Barrier. (Note: When the Containment High Range Radiation Monitor reaches 1800 R/Hr, this starts the 15 minute classification clock for the GE.)

The reactor continues blowing down to the steam chase. The packing failure is not sufficient to cause the blow out panels to release but provides sufficient volume/airborne activity for the off-site release. Major fuel failure continues. An off-site airborne radioactive release via #11 Standby Gas Treatment and the Off-gas Stack commences. The reactor will continue to experience fuel damage and the release will continue for approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

1054-1109 The ERO should classify and make declaration of the event as a GENERAL EMERGENCY based on FGI.1 "Loss of Any Two Barriers AND Loss or Potential Loss of Third Barrier (Table F-I)" The EAL criterion applicable are:

1. Reactor Coolant System Barrier Loss
2. Primary Containment Barrier Loss
3. Fuel Cladding Barrier Loss An initial Protective Action Recommendation should be processed for inclusion with the GENERAL EMERGENCY notifications. The initial PAR should be to Evacuate ALL sectors out to 2 miles and L, M, and N sectors out to 5 miles with the affected geopolitical subareas being 2, 5W, and 5S.

119.12 Th of-st ntfcios to th stat an conis of th GENEA EMREC an Inta PA shul be compete.

1. EOC and field staff are notified of the classification upgrade.

o State EOC, JIC o Wright and Sherburne County EOCs o RAD Teams (simulated) o Decontamination Centers 95

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant Offsite Timeline - Rev. I August 23, 2011 i TIME I EVENT

SUMMARY

2. Minnesota's default protective action recommendation (PAR) is to evacuate the 2-mile sub-area and the 5-mile sub-area(s) in the downwind sectors. Sub Areas 2, 5W, and 5S will be recommended by the Planning Chief to the State Incident Manager.
3. When PADs are approved, the Public Alert and Notification System (PANS) will be implemented. The EAS system will be activated and sirens sounded (simulated).
4. As PADs are recommended, necessary traffic control points are activated for evacuee traffic flow and to restrict incoming traffic (simulated).

=

5. RAD teams are in the field monitoring radiation levels and reporting to planning and assessment staff in State EOC (Simulated - done using a controller).
6. All emergency response organizations are fully activated. I
7. Radiological response support requested from FEMA 1140 Demonstrate the decision making processes and procedures for the evacuation or shelterin, of the Wriqht County jail population to clear the outstanding ARCA.

1208-1223 MIDAS 15 minute average met data indicates a windshift resulting in the off-site airborne plume affecting new geopolitical subareas. Winds are now from the East South-East at 3-6 mph. Once identified by MIDAS, the Radiation Protection Support Supervisor in the EOF should initiate and develop a PAR change to include the I

newly affected subarea. The follow-up PAR should include the initial areas evacuated (sectors L, M, & N) and P & Q sectors out to 5 miles with the additional affected geopolitical subarea being 5N. New PAR is evacuate all sectors I

I

1. EOC and field staff are notified.
2. Second PAR is recommended by Planning Chief to State Incident Manager.

I PAR approval process begins

3. When PAD is approved, the Public Alert and Notification Systems (PANS) will I

be implemented. The EAS sycem will be activated and sirens sounded (simulated).

I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant Monticello Nuclear Generating Plant Offsite Timeline - Rev. I August 23, 2011 TIME [EVENT

SUMMARY

4. Media briefing occurs

-1330 Plant is stable, the exercise is terminated.

97

Unclassified i

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant I

I I

I I

I MONTICELLO NUCLEAR GENERATING I PLANT I EMERGENCY PLAN EXERCISE  !

I SECTION 5 PART I NARRATIVE

SUMMARY

AND TIME LINE I I

AUGUST 23, 2011 I

I I

I 98 I

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant SCENARIO NARRATIVE

SUMMARY

& TIME LINE Time Event / Condition 0700 INITIAL CONDITIONS (MESSAGES #1, 2, 3, 4, & 5)

The reactor has been at continuous operation for 98 days.

A few hours after a minor rod pattern adjustment was performed on the nightshift, operations personnel noticed a rising trend on the stack WRGMs. Chemistry was notified and sampling was conducted which indicated that a minor fuel defect had occurred. Currently, the cause of the failure is unknown. Power suppression testing to isolate the defect is being planned.

The reactor water cleanup influent sample obtained on the midnight shift indicated a reactor coolant 1-131 dose equivalent of 1.OE-3 uCi/gram.

  1. 12 CRD Pump has been isolated and disassembled to replace a leaking shaft seal. It is scheduled to return to service 8/25/11.

The electrical distribution system is in condition Green.

Reactor Coolant Sampling is in-progress.

Winds are from the East at 4- 5 mph. Temperature is in the mid 80's with noon time temperatures expected in the mid 90's.

Core Damage Frequency (CDF) is 1.98E-5 per year (YELLOW).

RCIC was taken out of service 8-22-11 for replacement of the RCIC Pump outboard bearing due to elevated vibration levels. This is day 2 of a 14-day LCO. The bearing replacement work has commenced and the new bearing has been installed.

Remaining work activities include torquing the bolts and putting the upper bearing cap on. It's estimated that it will take -2 hours to complete the remaining maintenance work once work recommences on dayshift.

The 'A' train of SBGT is out of service due to fan (#11) maintenance. This is day one of a 7-day LCO. The train is expected to be out of service for 3 days. A work order has been initiated and the work has commenced. Currently the job is on hold awaiting the delivery of a replacement part which is expected to arrive on site in the mid to late afternoon.

The midnight operating crew placed "A" loop Torus cooling in service to support upcoming RCIC testing. #11 Residual Heat Removal (RHR) and #11 Residual Heat Removal Service Water (RHRSW) pumps are in service.

99

Unclassified I

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 5 I

  1. 11 Service Water Pump (SWP) is out-of-service for packing replacement. A WO has been initiated. #12 SWP and #13 SWP are in service.

1

  1. 11 Recirc Pump seal began degrading on 8-19-11. Current DW identified leakage (equipment drain sump) is elevated at 2.4 gpm. The upper seal pressure is stable 3

at 160 psig, and the seal cavity temperature is normal at -1 160 F. An ODMI is being prepared.

"B" outboard MSIV has a moderate packing leak which developed on 8-13-11 during MSIV Partial Stroke Exercise Test 0255-07-IA-8 (WO# 00421632). Steam chase temperatures are 0elevated. Trending of area temperatures indicate that they have leveled off at -132 F.

Mechanical Maintenance is setting up the Grove to lift the #11 EDG-ESW and #13 EFT - ESW concrete hatch cover on the Intake Structure to replace its weather 1

seal which has degraded and is leaking.

"B" Stack WRGM reading is elevated and erratic when compared to "A" Stack WRGM (AR 01274766/WR00065537/ WO 00424432)

-0810 While lifting the #11 EDG-ESW and #13 EFT - ESW hatch cover for weather seal I replacement, the operator loses control of the load and the Grove tips and crashes into the intake structure. The concrete hatch cover is dropped through the ventilation plenum over the #11 RHRSW pump. #11 RHRSW pump trips and the

  1. 11RHR SW overload alarm is received in the Control Room. The dropped concrete hatch cover is resting on top of the #11 RHRSW motor and has severely damaged it. (MESSAGE #6). (Note: Receipt of alarms is the start of the 15 minute classification clock for the Alert.)

I 0810-0825 Once the visible damage is verified, the Shift Manager should declare an ALERT based on HAl.3, "Vehicle crash with in the plant PROTECTED AREA boundary and causing VISIBLE DAMAGE to any plant structures or equipment therein (Table H-1) or Control Room indication of degraded performance of those systems" *

(MESSAGE # 7: Alert Contingency, MESSAGE #8: SEC ERO pager activation and met data for Alert Notification, MESSAGE #9: ENS/HPN Bridge line, MESSAGE

  1. 10: Instruction for logging onto Shemp, MESSAGE #11: Weather Forecast) 3 0825-0840 Offsite Notifications (State and Counties) for the Alert should be completed.

-0840 Low level Alarm for Torus (4B4 Suppression Pool), (MESSAGE #12: OSC Team Investigation).

-0845 The Electrical Pressure Regulator (EPR) fails, causing a Reactor Coolant System Pressure Spike.

Operators or OSC team sent out to perform system walk-downs of the intake.

Operators or OSC teams also sent1 0 ot to investigate EPR failure. (MESSAGE I

Unclassified Radiological Emergency Preparedness Program (REP)

After. Action Report/Improvement Plan Monticello Nuclear Generating Plant

  1. 13). Operators should reference C.4-B.05.09.B Main Steam Pressure Regulator Failure Causing Increasing Pressure and work through C4 procedures.

0910-0925 Sixty minutes after the declaration of the ALERT, the Technical Support Center (TSC), Operational Support Center (OSC), Access Control and the Emergency Operations Facility (EOF) should be manned and operating.

-0940 Walkdown of Intake Structure and Screen House is complete with affected equipment being secured.

A complete valve packing failure occurs on "B" outboard MSIV in the steam chase.

The packing failure results in steam chase tunnel temperatures increasing rapidly. As a result, the operating crew is expected to SCRAM the reactor to isolate the leak.

Upon reactor SCRAM both "B" steam line MSIVs (inboard and outboard) fail to close. The steam-chase blow-out panel remains intact. (Note: When MSIVs are given the close signal starts the 15 minute classification clock for the SAE.)

0940-0955 The ERO should classify and make declaration of the event as a SITE AREA EMERGENCY based on FSl.1 "Loss or Potential Loss of ANY Two Barriers (Table F-i)" The Table F-1 EAL criterion applicable are:

1. Reactor Coolant System Barrier Loss #3 - RCS Leak Rate
2. Primary Containment Barrier Loss # 3 - CNMT Isolation Failure or Bypass (MESSAGE #14: Site Area Emergency Contingency)

-1000 Shortly after the declaration of the SITE AREA EMERGENCY a plant/site evacuation should be initiated. (MESSAGE #15: Site Evacuation Siren Interject.)

Dosimetry issuance should commence in the OSC and TSC if not already performed.

0955-1010 The off-site notifications to the state and counties of the SITE AREA EMERGENCY should be completed.

-1015 LC-104 high temperature alarm is received in the Control Room. (MESSAGE # 16:

LC-104 Alarm Investigation)

-1030 Significant fuel failure begins. Vent and Stack release rates escalate rapidly. The Reactor Building Vent release readings increase from -300 to -70,000 pCi/Sec over the next 5-8 minutes. An increase in Area dose rates in steam and adjacent areas of the Reactor and Turbine Building occurs.

The Containment High Radiation Monitor readings begin increasing.

Operators should manually initiate SBGT at 9,000 pCi/SEC per ARP C-259-A-6.

-1054 The Containment High Range Radiation Monitor readings exceed 1800 R/Hr indicating the Loss of the Fuel Cladding Barrier. (Note: When the CHRRM reaches 1800 R/Hr starts the 15 minute classification clock for the GE.)

101

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/improvement Plan Monticello Nuclear Generating Plant The reactor continues blowing down to the steam chase. The packing failure is not I sufficient to cause the blow out panels to release but provides sufficient volume/airborne activity for the off-site release. Major fuel failure continues. An off-site airborne radioactive release via #11 Standby Gas Treatment and the Off-gas Stack commences. The reactor will continue to experience fuel damage and the I

release will continue for approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. (To reduce the chance of the operators implementing a blow-down to the torus the scenario in-plant radiation and I temperature levels will be maintained such that two max safe radiation or two max safe temperatures setpoints will not exceeded.) (MESSAGE #17: Rx Blowdown Contingency) 1054-1109 The ERO should classify and make declaration of the event as a GENERAL EMERGENCY based on FG1.1 "Loss of Any Two Barriers AND Loss or Potential Loss of Third Barrier (Table F-i)" The Table F-1 EAL criterion applicable are:

1. Reactor Coolant System Barrier Loss #3 - RCS Leak Rate
2. Primary Containment Barrier Loss # 3 - CNMT Isolation Failure or Bypass
3. Fuel Cladding Barrier Loss #3 - Drywell Radiation Monitoring An initial Protective Action Recommendation should be processed for inclusion with the GENERAL EMERGENCY notifications. The initial PAR should be to Evacuate ALL sectors out to 2 miles and L, M, and N sectors out to 5 miles with the affected geopolitical subareas being 2, 5W, and 5S. (MESSAGE #18: General Emergency I

Contingency) 1109-1124 The off-site notifications to the state and counties of the GENERAL EMERGENCY and Initial PAR should be completed.

-1137 The # 11 Recirc Pump seal leakage rate increases. The Drywell Equipment Drain I Sump and Floor Drain Sump pump rates increase with the increase seal leakage..

-1151 Two containment drywell cooling fans (#2 and #4) trip due to a relay failure and I won't restart. Operations enter the EOPs. Control Room operators attempt to restart the fans per the EOPS but are unsuccessful. (MESSAGE #19: DW Fan Breaker Indication) I

-1200 MNGP Field Team Environmental Sampling commences (MESSAGE #20:

Controller Interject).

Emergency Worker Exposure Authorization demonstration. (MESSAGE #21:

Controller Interject) 1208-1223 MIDAS 15 minute average met data indicates a windshift resulting in the off-site airborne plume affecting new geopolitical subareas. Winds are now from the East South-East at 3-6 mph. Once identified by MIDAS, the Radiation Protection Support Supervisor in the EOF should initiate and develop a PAR change to include the I

newly affected subarea. The followup PAR should include the initial areas evacuated (sectors L, M, & N) and P & Q sectors out to 5 miles with the additional affected geopolitical subarea beind 52l. New PAR is evacuate All sectors (MESSAGE #22: PAR Change Contingency)

Unclassified Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant 1223-1238 The PAR change developed and approved is communicated to the State

-1300 Terminate the drill and conduct post drill ERF critiques. Area critiques will be held immediately following the Drill (MESSAGE #23 Drill termination).

-1500 Preliminary post-drill critique for ALL controllers. Complete post-drill objection review critique to be conducted 8/24/11.

103

Unclassified.

Radiological Emergency Preparedness Program (REP)

After Action Report/Improvement Plan Monticello Nuclear Generating Plant This page is intentionally blank.

I I

I 104