Letter Sequence RAI |
|---|
TAC:ME4074, Clarify Application of Setpoint Methodology for LSSS Functions (Withdrawn, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
- Supplement, Supplement, Supplement
Results
Other: CNL-14-077, Responses to Degraded Voltage Issue Requests for Additional Information, ML101050203, ML102240630, ML102290358, ML102290360, ML102290361, ML102290362, ML102290363, ML102290364, ML102290365, ML102290366, ML102290367, ML102290368, ML102290383, ML102290384, ML102290385, ML102290386, ML102290387, ML102290388, ML102290389, ML102290390, ML102290391, ML102290392, ML102290403, ML102290404, ML102290405, ML102290406, ML102290407, ML102290408, ML102290409, ML102290410, ML102290411, ML102290414, ML102290439, ML102290440, ML102290441, ML102290442, ML102290443, ML102290444, ML102290445, ML102290446, ML102290447, ML102290448, ML102290458, ML102290459, ML102290460, ML102290461, ML102290462, ML102290463, ML102290464... further results
|
MONTHYEARML0933702752009-11-24024 November 2009 Final Safety Analysis Report, Amendment 95, Cover Letter Project stage: Request ML12192A3682009-12-0909 December 2009 Tennessee Department of Health Public Health Assessment 2009 Project stage: Request ML1001916862010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 8 - Electric Power Through 8E-12 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1002204742010-02-0505 February 2010 IP 37002, Construction Refurbishment Process - Watts Bar Unit 2 Project stage: Request ML1005500072010-03-11011 March 2010 Request for Additional Information Related to Licensees Final Safety Analysis Report Amendment 95 Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: RAI ML1007100112010-03-12012 March 2010 OL - List of Documents for Docketing Referenced on Page 5 of the Site Audit Trip Report Project stage: Request ML1010502032010-04-0808 April 2010 Additional Information Regarding Final Safety Analysis Report, Chapter 7, Instrumentation and Controls Review - Requested Common Q Proprietary Documents Project stage: Other ML1010405732010-04-0909 April 2010 Response to NRC Request for Additional Information Regarding Licensees Final Safety Analysis Report (FSAR) Amendment Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: Response to RAI ML1011701022010-04-27027 April 2010 Notice of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Submittals Project stage: Request ML1011303512010-05-0505 May 2010 Request for Withholding Information from Public Disclosure (Tac No. ME2731) Project stage: Withholding Request Acceptance ML1016102902010-05-27027 May 2010 Transmittal of Amendment 99 to Final Safety Analysis Report (FSAR) Project stage: Request ML1016203602010-06-17017 June 2010 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) to Discuss the Complete Status of TVA Hydrology Issues Including the Flooding Effects on the TVA Operating Nuclear Plants Project stage: Request ML1014500842010-06-23023 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Reactor Systems, Nuclear Performance and Code Review, Ansd Plant Systems Project stage: RAI ML1015402502010-06-24024 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Nuclear Performance and Code Review, Plant Systems, and Testing (Tac Nos. ME2731 and ME3091) Project stage: RAI ML1017903992010-06-28028 June 2010 Request for Additional Information (RAI) Regarding Licensees Final Safety Analysis Report Amendment Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: Request ML1016200062010-06-29029 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Nuclear Performance and Code Review (Tac No. ME2731) Project stage: RAI ML1015304742010-07-0202 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Mechanical and Civil Engineering Systems Project stage: RAI ML1016000262010-07-0808 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report, Amendment Related to Quality and Vendor Branch Review Project stage: RAI ML1015303542010-07-12012 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Electrical Engineering Systems Project stage: RAI ML1018001562010-07-15015 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Chapter 8, Electric Power Project stage: RAI ML1020202812010-07-30030 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Chapter 3.11 Project stage: RAI ML1023003322010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-9 (Dwg No. 1-47W611-67-5, R10) Project stage: Other ML1022904662010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-3 (Dwg No. 1-47W845-3, R23) Project stage: Other ML1023003332010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-10 (Dwg No. 1-47W610-67-1, R27) Project stage: Other ML1023003342010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-10 Sh a (Dwg No. 1-47W610-67-1A, R16) Project stage: Other ML1023003352010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-11 (Dwg No. 1-47W610-67-2, R15) Project stage: Other ML1023003432010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-12 Sh a (Dwg No. 1-47W610-67-3A, R7) Project stage: Other ML1023003442010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-13 (Dwg No. 1-47W610-67-4, R17) Project stage: Other ML1023003452010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-11 Sh a (Dwg No. 1-47W610-67-2A, R8) Project stage: Other ML1023003462010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-12 (Dwg No. 1-47W610-67-3, R12) Project stage: Other ML1023003472010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-14 (Dwg No. 1-47W610-67-5, R14) Project stage: Other ML1023003482010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-14 (Dwg No. 1-47W610-67-5A, R2) Project stage: Other ML1023003492010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-16 (Dwg No. 1-47W859-4, R23) Project stage: Other ML1023003502010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-17 (Dwg No. 1-47W859-3, R18) Project stage: Other ML1023003512010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-18 (Dwg No. 1-47W859-2, R36) Project stage: Other ML1023003522010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-19 (Dwg No. 1-47W859-1, R47) Project stage: Other ML1023003602010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-23 (Dwg No. 1-47W611-70-1, R9) Project stage: Other ML1023003612010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-20 (Dwg No. 1-47W610-70-1, R23) Project stage: Other ML1023003622010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-21 (Dwg No. 1-47W610-70-2, R29) Project stage: Other ML1023003632010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-21A (Dwg No. 1-47W610-70-2A, R15) Project stage: Other ML1023003642010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-22 (Dwg No. 1-47W610-70-3, R17) Project stage: Other ML1023003652010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-24 (Dwg No. 1-47W611-70-2, R11) Project stage: Other ML1023003672010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-25 (Dwg No. 1-47W611-70-3, R4) Project stage: Other ML1023003682010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-25A (Dwg No. 1-47W611-70-4, R4) Project stage: Other ML1023003692010-08-0505 August 2010 Final Safety Analysis Report Figure 9.3-1 (Dwg No. 1-47W610-32-1, R15) Project stage: Other ML1023003702010-08-0505 August 2010 Final Safety Analysis Report Figure 9.3-2 (Dwg No. 1-47W610-32-2, R19) Project stage: Other ML1023003732010-08-0505 August 2010 Final Safety Analysis Report Figure 9.3-6 (Dwg No. 1-47W848-1, R24) Project stage: Other ML1022903682010-08-0505 August 2010 Final Safety Analysis Report Figure 8.3-14B (Dwg No. 1-45W760-82-1, R17) Project stage: Other ML1022903652010-08-0505 August 2010 Final Safety Analysis Report Figure 8.3-7 (Dwg No. 1-45W760-211-9, R16) Project stage: Other 2010-05-05
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 20, 2011 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING FINAL SAFETY ANALYSIS REPORT RELATED TO SECTION 15 (TAC NO. ME4074)
Dear Mr. Bhatnagar:
By letters dated February 10 and May 24,2011, Tennessee Valley Authority in part provided its response to a request for additional information (RAI) by the U.S. Nuclear Regulatory Commission (NRC) staff regarding the analysis of a potential chemical and volume control system malfunction that increases reactor coolant inventory as described in Chapter 15 of the Final Safety Analysis Report for Watts Bar Nuclear Plant, Unit 2.
The NRC staff has reviewed the information provided and has determined that the following information is required to complete its review. The specific questions are discussed in the enclosed RAI.
A response is required within 30 days of receipt of this letter.
If you should have any questions, please contact me at 301-415-1457.
Sincerely, Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
RAI cc w/encl: Distribution via Listserv
Request for Additional Information Watts Bar Nuclear Plant, Unit 2 Final Safety Analysis Report Section 15 Tennessee Valley Authority Docket No. 50-391 By letters dated February 10 and May 24,2011, Tennessee Valley Authority (TVA) in part provided its response to a request for additional information (RAI) by the U.S. Nuclear Regulatory Commission (NRC) staff regarding the analysis of a potential chemical and volume control system (CVCS) malfunction that increases reactor coolant inventory as described in Chapter 15 of the Final Safety Analysis Report for Watts Bar Nuclear Plant (WBN), Unit 2. The NRC staff has reviewed the information provided and has determined that the following information is required to complete its review.
FSAR Section 15.2.4, "Chemical and Volume Control System Malfunction that Results in a Decrease in Boron Concentration in the Reactor Coolant" Section 15.4.6 of NRC Report NUREG-0800, "Standard Review Plan" [Reference 1] lists the following acceptance criteria for boron dilution event analyses:
If operator action is required to terminate the transient, the following minimum time intervals must be available between the time an alarm announces an unplanned moderator dilution and the time shutdown margin is lost:
A. During refueling: 30 minutes:
B. During startup, cold shutdown, hot shutdown, hot standby, and power operation: 15 minutes.
In response to the NRC staff's question RAI 15.0.0-1.b [Reference 2], TVA listed the following acceptance criteria for boron dilution event analyses:
If operator action is required to terminate the transient, the following minimum intervals must be available between the initiation of the uncontrolled boron dilution event and the time of complete loss of shutdown margin:
- a. Refueling (Mode 6): 30 minutes
- b. Startup and Power (Modes 2 and 1): 15 minutes Consequently, TVA's analysis of the CVCS malfunction that results in a decrease in boron concentration addresses only Modes 1, 2, and 6.
- 1.
Provide the analyses for this event in Modes 3, 4, and 5 (hot standby, hot shutdown, and cold shutdown, respectively). Initial conditions should consider the available shutdown Enclosure
- 2 margin, reactor coolant system (ReS) pressure and charging flow, control rod positions and operability, available instrumentation and protective functions, and active ReS water volume (e.g., mid-loop operation) that are appropriate to each of these Modes.
- 2.
List the trips, alarms, and other indications that are required to be operable in each Mode that could alert the operator to an abnormal situation involving eves.
- 3.
Identify the trip, alarm, or other indication that is assumed to alert the operator to the possibility that a boron dilution event is occurring.
- 4.
Provide a discussion that shows that the operator, working according to the applicable procedures, will locate the boron dilution source and flow path(s). and terminate the dilution flow within 15 minutes after receipt of the assumed trip. alarm, or other indication.
References:
[1]
Standard Review Plan, NUREG-0800 (formerly NUREG-75/087), Revision 1, March 2007.
[2]
Letter from M. Bajestani (TVA) to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 - Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information,"
December 1 0, 2010.
July 20, 2011 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING FINAL SAFETY ANALYSIS REPORT RELATED TO SECTION 15 (TAC NO. ME4074)
Dear Mr. Bhatnagar:
By letters dated February 10 and May 24, 2011, Tennessee Valley Authority in part provided its response to a request for additional information (RAI) by the U.S. Nuclear Regulatory Commission (NRC) staff regarding the analysis of a potential chemical and volume control system malfunction that increases reactor coolant inventory as described in Chapter 15 of the Final Safety Analysis Report for Watts Bar Nuclear Plant, Unit 2.
The NRC staff has reviewed the information provided and has determined that the following information is required to complete its review. The specific questions are discussed in the enclosed RAI.
A response is required within 30 days of receipt of this letter.
If you should have any questions, please contact me at 301-415-1457.
Sincerely, IRA!
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
RAI cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrPMWattsBar2 Resource RidsRgn2MailCenter Resource LPWB Reading File RidsNrrDssSrxb Resource RidsOgcRp Resource RidsNrrDorlLpwb Resource RidsNrrLABClayton Resource RidsNrrDorlDpr RidsAcrsAcnw _MaiICTR Resource ADAMS A ccesslon N o. ML111861537
'*'per memo NAME LPWB/PM I PMilano LPWB/LA BClavton SRXB/BC AUlses*
OGC NLO AJones LPWB/BC SCampbell DATE I 07/05/11 07/05/11 05/19/11 07/19/11 07/20/11 OFFICIAL AGENCY RECORD