Letter Sequence Response to RAI |
---|
|
|
MONTHYEARML1016004772010-06-0303 June 2010 Final Safety Analysis Report (FSAR) - Response to Preliminary Requests for Additional Information Project stage: Other ML1034807082010-12-10010 December 2010 Final Safety Analysis Report - Response to Requests for Additional Information Project stage: Response to RAI ML11104A0592011-04-13013 April 2011 Response to Request for Additional Information (Rais) Related to FSAR Sections 9.2.1 and 9.2.2 Project stage: Response to RAI ML1110306242011-04-27027 April 2011 Accident Analyses Audit Report Westinghouse Documents Relating to Final Safety Analysis Report Accident Analyses Project stage: Other ML11215A1322011-07-29029 July 2011 Response to Request for Additional Information Regarding June 28, 2011 NRC Audit- Steam Line Break (Slb) and Other Miscellaneous RAIs Project stage: Response to RAI 2011-04-13
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) 2024-09-05
[Table view] |
Text
Withhold from Public Disclosure Under 10 CFR 2.390 Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 December 10, 2010 10 CFR 50.4(b)(6) 10 CFR 50.34(b) 10 CFR 2.390(d)(1)
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information This letter responds to a number of requests for additional information (RAIs) regarding the Unit 2 FSAR. provides the responses to RAIs involving multiple FSAR chapters. This includes a revised version of the response to RAI SBPB 9.1 - 2 originally provided by TVA letter dated July 31, 2010 (Reference 1.). provides the layout drawings and calculation for RAI 12 - 6. provides summary heat load and flow tables for RAI 9.2 - CCS - 4. provides the response to RAI 15.0.0 - 1.b. Enclosure 4 contains information proprietary to Westinghouse. The nonproprietary version of Enclosure 4 and the applications for withholding will be provided two weeks after receipt from Westinghouse. TVA requests that the Westinghouse proprietary information be withheld from public disclosure in accordance with 10 CFR § 2.390. provides summary heat load and flow tables for RAI 9.2.1 - ERCW - 3. provides the new commitments contained in this letter.
If you have any questions, please contact Bill Crouch at (423) 365-2004.
6
U.S. Nuclear Regulatory Commission Page 2 December 10, 2010 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 10 day of December, 2010.
Sincerely, Masoud B stani" Watts B //nit,2 Vice President
Enclosures:
- 1. Responses to RAIs Regarding Unit 2 FSAR
- 2. Response to RAI 12 - 6.
- 3. Summary Heat Load and Flow Tables for RAI 9.2 - CSS - 4.
- 4. Response to RAI 15.0.0 - 1.b.
- 5. Summary Heat Load and Flow Tables for RAI 9.2.1 - ERCW - 3.
- 6. List of New Regulatory Commitments Attachments:
- 1. Draft Change Pages Referenced in the Response to RAIs 9.2 - CCS -1, 9.2 - CCS -1, and 9.2 - CCS -1
- 2. Drawings Referenced in the Response to RAI 10.4.9 - BOP - AFW - 3
- 3. Figures Referenced in the Response to RAI 15.5 - 2
U.S. Nuclear Regulatory Commission Page 3 December 10, 2010
References:
- 1. TVA to NRC letter dated July 31, 2010, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Final Safety Analysis Report (FSAR) - Response to Preliminary Requests for Additional Information and Requests For Additional Information" (ADAMS Accession No. ML1102290258)
- 2. NRC to TVA letter dated August 27, 2010, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information Regarding Licensee's Final Safety Analysis Report Amendment
.Related to Chapters 11, 'Radioactive Waste Management' and 12, 'Radiation Protection' (TAC No. ME2731)" (ADAMS Accession No. ML1102360201)
- 3. TVA to NRC letter dated June 3, 2010, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Final Safety Analysis Report (FSAR) - Response to Preliminary Requests for Additional Information" (ADAMS Accession No. ML101600477)
- 4. NRC to TVA letter dated September 17, 2010, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information Regarding Final Safety Analysis Report Amendment Related to Section 9.2 (TAC No. ME4074)" (ADAMS ML102510313)
- 5. NRC to TVA letter dated September 20, 2010, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information Regarding Final Safety Analysis Report.Related to Section 15 (TAC No. ME4074)" (ADAMS Accession No. ML102590244)
- 6. NRC to TVA letter dated October 20, 2010, 'Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information Regarding Final Safety Analysis Report Amendment Related to Section 9.2.1 (TAC No, ME4074)" (ADAMS ML102880442)
- 7. NRC to TVA letter dated November 9, 2010, 'Watts Bar Nuclear Plant, Unit 2 - Request For Additional Information Regarding Final Safety Analysis Report Amendment Related to Section 10.4.9 (TAC No. ME4074)" (ADAMS ML103060411) cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
U.S. Nuclear Regulatory Commission Page 4 December 10, 2010 bcc (Enclosures):
Stephen Campbell U.S. Nuclear Regulatory Commission MS 08H4A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Loren R. Plisco, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
U.S. Nuclear Regulatory Commission Page 5 December 10, 2010 bcc (Enclosures):
WDC:TLE:CLH:DLB.
G. P. Arent, LP 5A-C M. Bajestani, EQB 1B-WBN R. R. Baron, EQB 1B-WBN A. S. Bhatnagar, LP 6A-C M. K. Brandon, ADM 1L-WBN W. D. Crouch, EQB 1B-WBN D. E. Grissette, ADM 1V-WBN J. R. Hopson, ADM 1V-WBN R. M. Krich, LP 3R-C A. L. Sterdis, LP 5A-C-E. J. Vigluicci, WT 6A-K K. W. Whittenburg, SP 2B-C EDMS, WT 3B-K (Re: T02 100731 001; A02 100907 002; T02 100604 002; A02 100927 001; A02 100927 002; A02 101028 002; A02 101115 003)