MONTHYEARML0933702752009-11-24024 November 2009 Final Safety Analysis Report, Amendment 95, Cover Letter Project stage: Request ML12192A3682009-12-0909 December 2009 Tennessee Department of Health Public Health Assessment 2009 Project stage: Request ML1001916862010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 8 - Electric Power Through 8E-12 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1002204742010-02-0505 February 2010 IP 37002, Construction Refurbishment Process - Watts Bar Unit 2 Project stage: Request ML1005500072010-03-11011 March 2010 Request for Additional Information Related to Licensees Final Safety Analysis Report Amendment 95 Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: RAI ML1007100112010-03-12012 March 2010 OL - List of Documents for Docketing Referenced on Page 5 of the Site Audit Trip Report Project stage: Request ML1010502032010-04-0808 April 2010 Additional Information Regarding Final Safety Analysis Report, Chapter 7, Instrumentation and Controls Review - Requested Common Q Proprietary Documents Project stage: Other ML1010405732010-04-0909 April 2010 Response to NRC Request for Additional Information Regarding Licensees Final Safety Analysis Report (FSAR) Amendment Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: Response to RAI ML1011701022010-04-27027 April 2010 Notice of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Submittals Project stage: Request ML1011303512010-05-0505 May 2010 Request for Withholding Information from Public Disclosure (Tac No. ME2731) Project stage: Withholding Request Acceptance ML1016102902010-05-27027 May 2010 Transmittal of Amendment 99 to Final Safety Analysis Report (FSAR) Project stage: Request ML1016203602010-06-17017 June 2010 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) to Discuss the Complete Status of TVA Hydrology Issues Including the Flooding Effects on the TVA Operating Nuclear Plants Project stage: Request ML1014500842010-06-23023 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Reactor Systems, Nuclear Performance and Code Review, Ansd Plant Systems Project stage: RAI ML1015402502010-06-24024 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Nuclear Performance and Code Review, Plant Systems, and Testing (Tac Nos. ME2731 and ME3091) Project stage: RAI ML1017903992010-06-28028 June 2010 Request for Additional Information (RAI) Regarding Licensees Final Safety Analysis Report Amendment Related to Section 4.2.2, Reactor Vessel Internal Components Project stage: Request ML1016200062010-06-29029 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Nuclear Performance and Code Review (Tac No. ME2731) Project stage: RAI ML1015304742010-07-0202 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Mechanical and Civil Engineering Systems Project stage: RAI ML1016000262010-07-0808 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report, Amendment Related to Quality and Vendor Branch Review Project stage: RAI ML1015303542010-07-12012 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Electrical Engineering Systems Project stage: RAI ML1018001562010-07-15015 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Chapter 8, Electric Power Project stage: RAI ML1020202812010-07-30030 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Chapter 3.11 Project stage: RAI ML1022904672010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-4 (Dwg No. 1-47W845-4, R32) Project stage: Other ML1022903662010-08-0505 August 2010 Final Safety Analysis Report Figure 8.3-8 (Dwg No. 1-45W760-211-10, R12) Project stage: Other ML1023003262010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-7 (Dwg No. 1-47W611-67-3, R2) Project stage: Other ML1023003272010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-4A (Dwg No. 1-47W845-5, R38) Project stage: Other ML1023003282010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-4B (Dwg No. 1-47W845-7, R14) Project stage: Other ML1023003292010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-5 (Dwg No. 1-47W611-67-1, R8) Project stage: Other ML1023003302010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-6 (Dwg No. 1-47W611-67-2, R5) Project stage: Other ML1023003312010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-8 (Dwg No. 1-47W611-67-4, R5) Project stage: Other ML1023003322010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-9 (Dwg No. 1-47W611-67-5, R10) Project stage: Other ML1023003332010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-10 (Dwg No. 1-47W610-67-1, R27) Project stage: Other ML1023003342010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-10 Sh a (Dwg No. 1-47W610-67-1A, R16) Project stage: Other ML1023003352010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-11 (Dwg No. 1-47W610-67-2, R15) Project stage: Other ML1023003432010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-12 Sh a (Dwg No. 1-47W610-67-3A, R7) Project stage: Other ML1023003442010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-13 (Dwg No. 1-47W610-67-4, R17) Project stage: Other ML1023003452010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-11 Sh a (Dwg No. 1-47W610-67-2A, R8) Project stage: Other ML1023003462010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-12 (Dwg No. 1-47W610-67-3, R12) Project stage: Other ML1023003472010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-14 (Dwg No. 1-47W610-67-5, R14) Project stage: Other ML1023003482010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-14 (Dwg No. 1-47W610-67-5A, R2) Project stage: Other ML1023003492010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-16 (Dwg No. 1-47W859-4, R23) Project stage: Other ML1023003502010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-17 (Dwg No. 1-47W859-3, R18) Project stage: Other ML1023003512010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-18 (Dwg No. 1-47W859-2, R36) Project stage: Other ML1023003522010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-19 (Dwg No. 1-47W859-1, R47) Project stage: Other ML1023003602010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-23 (Dwg No. 1-47W611-70-1, R9) Project stage: Other ML1023003612010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-20 (Dwg No. 1-47W610-70-1, R23) Project stage: Other ML1023003622010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-21 (Dwg No. 1-47W610-70-2, R29) Project stage: Other ML1023003632010-08-0505 August 2010 Final Safety Analysis Report Figure 9.2-21A (Dwg No. 1-47W610-70-2A, R15) Project stage: Other ML1023003822010-08-0505 August 2010 Final Safety Analysis Report Figure 9.5-20 Sh B (Dwg No. 1-47W840-1B, R11) Project stage: Other ML1023003952010-08-0505 August 2010 Final Safety Analysis Report Figure 9.4-24 (Dwg No. 1-47W839-1, R17) Project stage: Other 2010-05-05
[Table View] |
Text
Tennessee Valley Authority, Post Office Box 2000. Spring City, Tenn,essee 37381-2000 October 13, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 10 CFR 50.4(b)(6) 10 CFR 50.34(b) 10 CFR 2.390(d)(1)
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Response to Request for Additional Information Regarding the Preservice Inspection Program Plan (TAC Nos.
ME4074 and ME3113)
Reference:
1.
Letter from NRC to TVA, 'Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information from the Component Performance and Testing Branch Regarding Preservice Inspection Program Plan (TAC No. ME3113)," dated September 28, 2010 [ADAMS Accession No. ML102630535]
By letter dated June 17,2010 (ADAMS Accession No. ML101680561), TVA submitted the Preservice Inspection Program Plan as part of the Final Safety Analysis Report for WBN, Unit 2.
The NRC staff reviewed the information provided by TVA.
In a letter to TVA dated September 28,2010 (Reference 1), the NRC provided a Request for Additional Information (RAI) needed to complete the NRC staff review. This letter provides the response to that RAI. contains the new Regulatory Commitment contained in this submittal. If you have any questions, please contact Bill Crouch at (423) 365-2004.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 13!b. day of October, 2010.
Sincerely, Masoud B W ani Watts Bar Unit 2 Vice President
U.S. Nuclear Regulatory Commission Page 2 October 13, 2010
Enclosure:
- 1.
Response to RAI Regarding the Preservice Inspection Program Plan
- 2.
List of New Regulatory Commitments cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
ENCLOSURE 1 Response to RAI Regarding the Preservice Inspection Program Plan Tennessee Valley Authority - Watts Bar Nuclear Plant - Unit 2, Docket No. 50-391 E1-1 The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the information submitted by Tennessee Valley Authority (the licensee) in its letter dated June 17, 2010 (Agencywide Documents Access and Management System Accession No. ML101680561), in which the licensee proposed its Preservice Inspection (PSI) Program Plan in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.55a for Watts Bar Nuclear Plant (WBN),
Unit 2. The licensee requested NRC to review its proposed PSI Program Plan for WBN, Unit 2 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),
Section XI inspection requirements. The applicable ASME Code,Section XI code of record for the WBN, Unit 2 PSI Program Plan is the 2001 Edition through the 2003 Addenda.
In Section 3.4.1.4, the licensee stated that "[t]he IWF-5000 requirements for preservice examination and testing of snubbers will be performed using Subsection ISTD of the ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda, as permitted by 10 CFR 50.55a(b)(3)(v). Examination shall be performed using the VT-3 visual examination method described in IWA-2213." A similar statement is made in Section 3.18.3.
Please explain what WBN procedures or part of the ASME OM Code Subsection ISTD will be used for snubbers inservice visual examination and testing, because the submittal only includes various WBN procedures for visual examination and nondestructive examination related to ASME Section XI.
Response
TVA will issue a Temporary Change to Nondestructive Examination (NDE)
Procedure N-VT-1 to perform VT-3 examination of snubbers in accordance with the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda. The temporary change will implement the preservice examination requirements of ISTD-4100, Preservice Examination. TVA has utilized this process in the past at another nuclear site for performance of VT-3 examination of snubbers.
Testing of mechanical snubbers will be performed by a vendor (to be selected) utilizing their snubber testing program and procedures to meet the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda.
The snubber testing requirements will implement ISTD-5100, Preservice Operational Readiness Testing.
ENCLOSURE 2 List of New Regulatory Commitments Tennessee Valley Authority - Watts Bar Nuclear Plant - Unit 2, Docket No. 50-391 E2-1
- 1.
By November 19, issue a Temporary Change to Nondestructive Examination (NDE)
Procedure N-VT-1 to perform VT-3 examination of snubbers in accordance with the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda. The temporary change will implement the preservice examination requirements of ISTD-4100, Preservice Examination.