ML093170424

From kanterella
Jump to navigation Jump to search
IR 05000285-09-004 and 072000054-09-001; 07/01/2009 - 09/30/2009; Fort Calhoun Station, Integrated Resident and Regional Report, and Emergency Plan Biennial Exercise Evaluation
ML093170424
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/13/2009
From: Clark J
NRC/RGN-IV/DRP/RPB-E
To: Bannister D
Omaha Public Power District
References
IR-09-001, IR-09-004
Download: ML093170424 (52)


See also: IR 05000285/2009004

Text

UNITED STATES

NUC LE AR RE G UL AT O RY C O M M I S S I O N

R E GI ON I V

612 EAST LAMAR BLVD , SU I TE 400

AR LI N GTON , TEXAS 76011-4125

November 13, 2009

David J. Bannister, Vice President

and Chief Nuclear Officer

Omaha Public Power District

Fort Calhoun Station FC-2-4

P. O. Box 550

Fort Calhoun, NE 68023-0550

Subject: FORT CALHOUN STATION NRC INTEGRATED INSPECTION REPORT

05000285/2009004 and 072000054/2009001

Dear Mr. Bannister:

On September 30, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Fort Calhoun Station. The enclosed integrated inspection report documents

the inspection findings, which were discussed on October 7, 2009, with Jeff Reinhart, Site Vice

President, and other members of your staff.

The inspections examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

This report documents one NRC-identified finding, and two self-revealing findings of very low

safety significance (Green), and one NRC-identified Severity Level IV violation. Three of these

findings were determined to involve violations of NRC requirements. If you contest these

violations or the significance of the noncited violations, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001, with

copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E.

Lamar Blvd, Suite 400, Arlington, Texas, 76011-4125; the Director, Office of Enforcement, U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident

Inspector at the Fort Calhoun facility. In addition, if you disagree with the characterization of any

finding in this report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your disagreement, to the Regional Administrator, Region IV, and the

NRC Resident Inspector at Fort Calhoun. The information you provide will be considered in

accordance with Inspection Manual Chapter 0305.

Omaha Public Power District -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its

enclosure, will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Jeffrey A. Clark, P.E.

Chief, Project Branch E

Division of Reactor Projects

Docket: 50-285

License: DPR-40

Enclosure:

NRC Inspection Report 05000285/200904 and 072000054/2009001

w/Attachment: Supplemental Information

cc w/Enclosure:

Jeffrey A. Reinhart

Site Vice President

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm

P.O. Box 550

Fort Calhoun, NE 68023-0550

Mr. Thomas C. Matthews

Manager - Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

Winston & Strawn

Attn: David A. Repke, Esq.

1700 K Street, NW

Washington, DC 20006-3817

Chairman

Washington County Board of Supervisors

P.O. Box 466

Blair, NE 68008

Omaha Public Power District -3-

Ms. Julia Schmitt, Manager

Radiation Control Program

Nebraska Health & Human Services R & L

Public Health Assurance

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Ms. Melanie Rasmussen

Radiation Control Program Officer

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

Chief, Technological Hazards Branch

FEMA, Region VII

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

Omaha Public Power District -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (John.Kirkland@nrc.gov)

Resident Inspector (Jacob.Wingebach@nrc.gov

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

FCS Site Secretary (Berni.Madison@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Team Leader, TSS (Chuck.Paulk@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

W. A. Maier, RSLO (Bill.Maier@nrc.gov)

R. E. Kahler, NSIR (Robert.Kahler@nrc.gov)

DRS STA (Dale.Powers@nrc.gov)

OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)

ROPreports (ROPreorts.Resource@nrc.gov)

OEMail Resource (OEMAIL.Resource@nrc.gov)

File located: R:\_REACTORS\_FCS\2009\FC 2009-04 RP-JCK.doc ML 093170424

SUNSI Rev Compl. : Yes No ADAMS  : Yes No Reviewer Initials

Publicly Avail  : Yes No Sensitive Yes : No Sens. Type Initials

PE:DRP/E SRI:DRP/E SPE:DRP/E RIV:SRI:DNMS C:DRS/EB2

WSchaup JKirkland RAzua LMWilloughby NFOKeefe

/RA - E/ /RA/via Email /RA/ /RA - E/ /RA/

11/09/09 10/16/09 10/07/09 11/09/09 11/09/09

C:DRS/OB C:DRS/PSB1 C:DRS/PSB2 C:DRP/E

RELantz MPShannon GEWerner JAClark

/RA/ /RA/ /RA/ /RA/

11/10/09 11/12/09 11/09/09 11/13/09

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-285

License: DPR-40

Report: 05000285/2009004 and 072000054/2009001

Licensee: Omaha Public Power District

Facility: Fort Calhoun Station

Location: Fort Calhoun Station FC-2-4 Adm.

P.O. Box 399, Highway 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates: July 1 through September 30, 2009

Inspectors: J. Kirkland, Senior Resident Inspector

W. Schaup, Project Engineer

P. Elkman, Senior Emergency Preparedness Inspector

C. Osterholtz, Senior Operations Engineer

G. Guerra, CHP, Emergency Preparedness Inspector

L. Willoughby, Senior Resident Yucca Mountain Project

L. Brookhart, Project Engineer

Approved By: Jeff A. Clark, Chief, Project Branch E

Division of Reactor Projects

-1- Enclosure

SUMMARY OF FINDINGS

IR 05000285/2009004 and 072000054/2009001; 07/01/2009 - 09/30/2009; Fort Calhoun

Station, Integrated Resident and Regional Report, and Emergency Plan Biennial Exercise

Evaluation.

The report covered a three-month period of inspection by resident inspectors and an announced

baseline inspections by a regional based inspectors. The significance of most findings is

indicated by their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609,

Significance Determination Process. Findings for which the significance determination

process does not apply may be Green or be assigned a severity level after NRC management

review. The NRC's program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated

December 2006.

A. NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Mitigating Systems

maintenance work instruction. While performing maintenance on the motor, the

HPSI Header - Charging Header Crosstie Valve, HCV-308, the maintenance

work instruction failed to ensure that the HPSI Alternate Header Isolation Valve,

HCV-2987, was closed, resulting in unexpected pressurization of the Number 2

HPSI Header.

The failure to provide an adequate maintenance work instruction was a

performance deficiency. This finding was greater than minor because the finding

was associated with the Mitigating Systems Cornerstone objective (procedure

quality attribute) to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences. Using

Manual Chapter 0609, Appendix A, Determining the Significance of Reactor

Inspection Findings for At-Power Situations, Phase 1 screening worksheet, the

inspectors determined that the finding was of very low safety significance (Green)

because it was not: (1) a design or qualification deficiency; (2) a loss of system

safety function; (3) an actual loss of safety function for greater than its technical

specification allowed outage time; (4) a loss of safety function of a nontechnical

specification train; or (5) a seismic, flooding or severe weather related finding.

There is no crosscutting aspect associated with this finding since the root cause

of the performance deficiency was not indicative of current plant performance.

(Section 4OA2)

10 CFR Part 21.21(a), Notification of failure to comply or existence of a defect

and its evaluation for the licensees failure to adopt appropriate procedures to

evaluate deviations and failures to comply associated with substantial safety

hazards. Specifically, the procedure fails to adequately assess the extent of

deviations, which are discovered, and the potential impact on other components

-2- Enclosure

either installed in the plant or stored in the warehouse. Additionally, the procedure

failed to adequately evaluate defects in components, which have never been

installed or used in the nuclear plant.

The inspectors determined that the failure to adopt appropriate procedures to

evaluate deviations and failures to comply associated with substantial safety

hazards was a performance deficiency. This finding was more than minor

because if the procedure were left uncorrected it could become a more serious

safety concern. Specifically, failure to notify the vendor upon discovery of a

deviation does not allow for adequate evaluation of other components that could

be subject to the deviation. Additionally, components with deviations could be

located in the licensees warehouse and subsequently installed in the plant

without the licensees knowledge, potentially creating a substantial safety hazard.

Because this issue affected a potential reporting requirement and NRCs ability

to perform its regulatory function, it was evaluated with the traditional

enforcement process. Consistent with the guidance in Section IV.A.3 and

Supplement VII paragraph D.4 of the NRC Enforcement Policy, this violation was

categorized at Severity Level IV noncited violation. There is no crosscutting

aspect associated with this finding because it is not indicative of current

performance in that the procedure is many years old. (Section 4OA3)

Cornerstone: Barrier Integrity

  • Green. The inspectors identified a finding of having very low safety significance

(Green) for failure to perform checks at the beginning of each shift on the main

hoist limit switches of the refueling area crane (HE - 2) in the spent fuel pool

area as specified in ANSI B30.2 - 1976, Overhead and Gantry Cranes, section

2-2.1.2 Frequent Inspections a.2, prior to using the crane to perform dry fuel

storage activities on June 29, 2009.

The failure to perform checks on the main hoist limit switches at the beginning of

each work shift is a performance deficiency because the dry cask personnel

used the crane to perform dry cask storage operations to lift items over the spent

fuel pool without performing the required checks per shift change. The

inspectors determined that the performance deficiency was more than minor in

accordance with Inspection Manual Chapter 0612, Appendix B, Issue

Screening, minor question 2 because if left uncorrected the performance

deficiency could lead to a more significant safety issue. Specifically, the main

hoist limit switches are installed to limit the main hoist travel and to prevent a two

blocking event. Preventing two blocking events ensures safe load handling of

heavy loads over the spent fuel pool. Using the NRC Manual Chapter 0609,

Phase 1 screening worksheet under the Barrier Cornerstone for spent fuel pool

issues, the finding screened as having very low safety significance because it did

not result in loss of cooling to the spent fuel pool, did not cause damage to the

fuel cladding or result in dropped fuel assembly or result in a loss of spent fuel

pool volume of greater than 10 percent. The finding had a crosscutting aspect in

human performance because the licensee failed to provide a complete and

accurate procedure to assure nuclear safety [H.2 (c)]. (Section 1R15)

-3- Enclosure

  • Green. A self-revealing Green noncited violation (NCV) of 10 CFR 50,

Appendix B, Criterion V, was identified for the failure of personnel to follow an

auxiliary building crane operating procedure. This resulted in the crane

contacting the fuel handling bridge and moving it approximately eight feet.

The failure to follow the prerequisites of the auxiliary building crane operating

procedure is a performance deficiency. The finding is greater than minor

because it would become a more significant safety concern if left uncorrected in

that a collision with the fuel handling bridge could cause damage such that

pieces of the mast could fall into the spent fuel pool and damage the spent fuel.

Using the NRC Manual Chapter 0609, Phase 1 screening worksheet under the

Barrier Integrity Cornerstone for spent fuel pool issues, the finding screened as

having very low safety significance because it did not result in loss of cooling to

the spent fuel pool, did not cause damage to the fuel cladding or result in

dropped fuel assembly or result in a loss of spent fuel pool volume of greater

than 10 percent. This finding has a crosscutting aspect in the area of human

performance associated with work practices because personnel failed to use

human error prevention techniques commensurate with the risk of the assigned

task, such that work activities were performed safely [H.4.(a)]. (Section 4OA2)

B. Licensee-Identified Violations

None

-4- Enclosure

REPORT DETAILS

Summary of Plant Status

The unit began this inspection period in Mode 1 at full rated thermal power and operated at

approximately 100 percent until July 24, 2009, when reactor power was reduced to 98 percent

for Moderator Temperature Coefficient Testing. Reactor power was returned to 100 percent

power on July 27, 2009, where it remained for the remainder of the inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

1R01 Adverse Weather Protection (71111.01)

.1 Summer Readiness for Offsite and Alternate AC Power

a. Inspection Scope

The inspectors performed a review of the licensees preparations for summer weather for

selected systems, including conditions that could lead to loss-of-offsite power and

conditions that could result from high temperatures. The inspectors reviewed the

licensees procedures affecting these areas and the communications protocols between

the transmission system operator and the plant to verify that the appropriate information

was being exchanged when issues arose that could affect the offsite power system.

Examples of aspects that were considered in the inspectors review included:

  • The coordination between the transmission system operator and the plant

during off-normal or emergency events

  • The explanations for the events
  • The estimates of when the offsite power system would be returned to a

normal state

  • The notifications from the transmission system operator to the plant when

the offsite power system was returned to normal

During the inspection, the inspectors focused on plant-specific design features and the

licensees procedures used to mitigate or respond to adverse weather conditions.

Additionally, the inspectors reviewed the Updated Safety Analysis Report and

performance requirements for systems selected for inspection, and verified that operator

actions were appropriate as specified by plant-specific procedures. Specific documents

reviewed during this inspection are listed in the attachment. The inspectors also

reviewed corrective action program items to verify that the licensee was identifying

adverse weather issues at an appropriate threshold and entering them into their

-5- Enclosure

corrective action program in accordance with station corrective action procedures. The

inspectors reviews focused specifically on the following plant systems:

  • Raw Water System

These activities constitute completion of one readiness for summer weather affect on offsite

and alternate ac power sample as defined in Inspection Procedure 71111.01-05.

b. Findings

No findings of significance were identified.

1R04 Equipment Alignments (71111.04)

.1 Partial Walkdown

a. Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant

systems:

Driven Auxiliary Feedwater Pump, FW-10

  • September 21, 2009, Compressed Air and Instrument Air Systems

The inspectors selected these systems based on their risk significance relative to the

reactor safety cornerstones at the time they were inspected. The inspectors attempted

to identify any discrepancies that could affect the function of the system, and, therefore,

potentially increase risk. The inspectors reviewed applicable operating procedures,

system diagrams, Updated Final Safety Analysis Report, technical specification

requirements, administrative technical specifications, outstanding work orders, condition

reports, and the impact of ongoing work activities on redundant trains of equipment in

order to identify conditions that could have rendered the systems incapable of

performing their intended functions. The inspectors also walked down accessible

portions of the systems to verify system components and support equipment were

aligned correctly and operable. The inspectors examined the material condition of the

components and observed operating parameters of equipment to verify that there were

no obvious deficiencies. The inspectors also verified that the licensee had properly

identified and resolved equipment alignment problems that could cause initiating events

or impact the capability of mitigating systems or barriers and entered them into the

corrective action program with the appropriate significance characterization. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of three partial system walkdown samples as

defined in Inspection Procedure 71111.04-05.

-6- Enclosure

b. Findings

No findings of significance were identified.

.2 Complete Walkdown

a. Inspection Scope

On September 11, 2009, the inspectors performed a complete system alignment

inspection of diesel generator 1 to verify the functional capability of the system. The

inspectors selected this system because it was considered both safety-significant and

risk-significant in the licensees probabilistic risk assessment. The inspectors walked

down the system to review mechanical and electrical equipment line ups, electrical

power availability, system pressure and temperature indications, as appropriate,

component labeling, component lubrication, component and equipment cooling, hangers

and supports, operability of support systems, and to ensure that ancillary equipment or

debris did not interfere with equipment operation. The inspectors reviewed a sample of

past and outstanding work orders to determine whether any deficiencies significantly

affected the system function. In addition, the inspectors reviewed the corrective action

program database to ensure that system equipment-alignment problems were being

identified and appropriately resolved. Specific documents reviewed during this

inspection are listed in the attachment.

These activities constitute completion of one complete system walkdown sample as

defined in Inspection Procedure 71111.04-05.

b. Findings

No findings of significance were identified.

1R05 Fire Protection (71111.05)

.1 Quarterly Fire Inspection Tours

a. Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability,

accessibility, and the condition of firefighting equipment in the following risk-significant

plant areas:

  • July 17, 2009, Fire Area 34A (Electrical Penetration Area Basement,

Room 20)

Area I, Room 21)

Area II, Room 22)

-7- Enclosure

  • July 20, 2009, Fire Area 13 (Mechanical Penetration Area, Room 13)

The inspectors reviewed areas to assess if licensee personnel had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and had implemented

adequate compensatory measures for out of service, degraded or inoperable fire

protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk

as documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to affect equipment that could initiate or mitigate a plant

transient, or their impact on the plants ability to respond to a security event. Using the

documents listed in the attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

fire detectors and sprinklers were unobstructed, that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four quarterly fire-protection inspection samples

as defined in Inspection Procedure 71111.05-05.

b. Findings

No findings of significance were identified.

1R11 Licensed Operator Requalification Program (71111.11)

a. Inspection Scope

On September 8, 2009, the inspectors observed a crew of licensed operators in the

plants simulator to verify that operator performance was adequate, evaluators were

identifying and documenting crew performance problems and training was being

conducted in accordance with licensee procedures. The inspectors evaluated the

following areas:

  • Licensed operator performance
  • Crews clarity and formality of communications
  • Crews ability to take timely actions in the conservative direction
  • Crews prioritization, interpretation, and verification of annunciator alarms
  • Crews correct use and implementation of abnormal and emergency

procedures

  • Control board manipulations

-8- Enclosure

  • Supervisors oversight and direction
  • Crews ability to identify and implement appropriate technical specification

actions and emergency plan actions and notifications

The inspectors compared the crews performance in these areas to pre-established

operator action expectations and successful critical task completion requirements.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one quarterly licensed-operator requalification

program sample as defined in Inspection Procedure 71111.11.

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness (71111.12)

a. Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk

significant systems:

  • July 13, 2009, Maintenance Rule function of the security diesel generator

and the Technical Support Center

  • September 28, 2009, a(1) status of the containment sump outlet strainer

SI-12A

The inspectors reviewed events such as where ineffective equipment maintenance has

resulted in valid or invalid automatic actuations of engineered safeguards systems and

independently verified the licensee's actions to address system performance or condition

problems in terms of the following:

  • Implementing appropriate work practices
  • Identifying and addressing common cause failures
  • Characterizing system reliability issues for performance
  • Charging unavailability for performance
  • Trending key parameters for condition monitoring

(a)(2)

-9- Enclosure

  • Verifying appropriate performance criteria for structures, systems, and

components classified as having an adequate demonstration of

performance through preventive maintenance, as described in 10 CFR

50.65(a)(2), or as requiring the establishment of appropriate and adequate

goals and corrective actions for systems classified as not having adequate

performance, as described in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the corrective action program with the appropriate

significance characterization. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of two quarterly maintenance effectiveness

samples as defined in Inspection Procedure 71111.12-05.

b. Findings

No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a. Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk

for the maintenance and emergent work activities affecting risk-significant and safety-

related equipment listed below to verify that the appropriate risk assessments were

performed prior to removing equipment for work:

  • July 22, 2009, Yellow risk condition while replacing Condenser FW-1A

Hotwell Level Controller LC-1190 while Containment Spray Pump SI-3B

and Air Compressor CA-1C were both out of service for maintenance

  • August 10, 2009, Emergent inspection activities in the switchyard by

substation personnel

heat exchanger AC-4A being out of service for maintenance

  • September 8, 2009, Orange risk activity associated with the Diesel

Generator DG-2 mini-overhaul

The inspectors selected these activities based on potential risk significance relative to

the reactor safety cornerstones. As applicable for each activity, the inspectors verified

that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)

and that the assessments were accurate and complete. When licensee personnel

performed emergent work, the inspectors verified that the licensee personnel promptly

assessed and managed plant risk. The inspectors reviewed the scope of maintenance

- 10 - Enclosure

work, discussed the results of the assessment with the licensee's probabilistic risk

analyst or shift technical advisor, and verified plant conditions were consistent with the

risk assessment. The inspectors also reviewed the technical specification requirements

and inspected portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four maintenance risk assessments and

emergent work control inspection samples as defined in Inspection

Procedure 71111.13-05.

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations (71111.15)

a. Inspection Scope

The inspectors reviewed the following issues:

  • July 24, 2009, Operability of the Auxiliary Building Crane HE-2 following the

failure of the upper electrical limit switch and the overweight trip

Pump FW-10 after steam passing by ST-16, requiring ST-16 to be taken

offline and ST-15 placed online

  • August 15, 2009, Operability on Diesel Generator DG-2 after fuel rack failed

to reset

  • August 20, 2009, Operability on HCV-506A and B after discovery of non-

CQE diaphragms

  • September 3, 2009, Operability of HCV-400A following air regulator setpoint

being out of specification low

The inspectors selected these potential operability issues based on the risk-significance

of the associated components and systems. The inspectors evaluated the technical

adequacy of the evaluations to ensure that technical specification operability was

properly justified and the subject component or system remained available such that no

unrecognized increase in risk occurred. The inspectors compared the operability and

design criteria in the appropriate sections of the technical specifications and Updated

Safety Analysis Report to the licensees evaluations, to determine whether the

components or systems were operable. Where compensatory measures were required

to maintain operability, the inspectors determined whether the measures in place would

function as intended and properly controlled. The inspectors determined, where

appropriate, compliance with bounding limitations associated with the evaluations.

Additionally, the inspectors also reviewed a sampling of corrective action documents to

- 11 - Enclosure

verify that the licensee was identifying and correcting any deficiencies associated with

operability evaluations. Specific documents reviewed during this inspection are listed in

the attachment.

These activities constitute completion of five operability evaluations inspection samples

as defined in Inspection Procedure 71111.15-04

b. Findings

Introduction. The inspectors identified a finding of having very low safety significance

(Green) for failure to perform checks at the beginning of each shift on the main hoist limit

switches of the refueling area crane (HE - 2) in the spent fuel pool area as specified in

ANSI B30.2 - 1976, Overhead and Gantry Cranes, section 2-2.1.2 Frequent

Inspections a.2, prior to using the crane to perform dry fuel storage activities on

June 29, 2009.

Description. On June 29, 2009, during dry fuel storage activities, dry fuel storage

personnel attempted to lift the transfer cask from the staging location in room 68 and

place it into the spent fuel pool. During the lift, the transfer cask could not be raised

enough to clear interferences between the bottom of the transfer cask and the spent fuel

pool floor. An investigation determined the hoist was actuating the upper rotary limit

switch, which prevents the hoist from rising any higher. It was determined that the upper

rotary limit switch had been set too low during a recent replacement of the switch.

Condition Report 2009-2997 was written to document the occurrence. The shift

manager stopped all dry fuel storage activities in order to correct the problem and dry

fuel storage personnel stopped work.

On June 30, 2009, licensee personnel determined that the upper limit rotary switch could

be bypassed using an installed bypass switch and that the mechanical limit switch would

provide sufficient protection from a two blocking event. During a subsequent crew

briefing of dry fuel storage personnel to recommence work, bypassing the upper limit

rotary switch was discussed and the licensee emphasized to not inadvertently test the

mechanical limit switch.

After the upper rotary limit switch was bypassed, the yoke assembly used to lift the

transfer cask was on the hoist and the crane was being positioned to rig to the transfer

cask when another problem with the crane occurred and dry fuel storage activities were

again stopped. The upper limit rotary switch was subsequently adjusted to the required

setting to provide sufficient hook height for dry fuel activities over the spent fuel pool.

During review of the events on the evening of June 29, 2009, the inspectors determined

that the once-per-shift checks on the main hoist limit switches had not been performed

by either shift, nor was the mechanical limit stop checked with no load on the hook prior

to use after the upper rotary limit switch was bypassed in accordance with ANSI B30.2 -

1976.

Analysis. The failure to perform checks on the main hoist limit switches at the beginning

of each work shift is a performance deficiency because the dry cask personnel used the

crane to perform dry cask storage operations to lift items over the spent fuel pool without

- 12 - Enclosure

performing the required checks per shift change. The inspectors determined that the

performance deficiency was more than minor in accordance with Inspection Manual

Chapter 0612, Appendix B, Issue Screening, minor question 2 because if left

uncorrected the performance deficiency could lead to a more significant safety issue.

Specifically, the main hoist limit switches are installed to limit the main hoist travel and to

prevent a two blocking event. Preventing two blocking events ensures safe load

handling of heavy loads over the spent fuel pool. Using the NRC Manual Chapter 0609,

Phase 1 screening worksheet under the Barrier Cornerstone for spent fuel pool issues,

the finding screened as having very low safety significance because it did not result in

loss of cooling to the spent fuel pool, did not cause damage to the fuel cladding or result

in dropped fuel assembly or result in a loss of spent fuel pool volume of greater than

10 percent. The finding had a crosscutting aspect in problem identification and

resolution because the licensee failed to take appropriate corrective actions to address

safety issues [P.1 (d)].

Enforcement. In Section 2-2.1.2 in ANSI B30.2 - 1976, Frequent Inspections, a.2,

states, in part, that all limit switches should be checked, without a load on the hook, at

the beginning of each shift. Contrary to the above, on June 29 2009, dry cask

personnel did not perform the once-per-shift checks of the limit switches on either shift,

nor was a check performed on the mechanical limit switch after the upper rotary limit

switch was bypassed.

Enforcement action does not apply because the performance deficiency did not involve

a violation of a regulatory requirement. The finding is of very low safety significance and

the issue was addressed in the corrective action program as Condition Report

CR 2009-3063. This finding will be identified as FIN 05000285/2009004-03, Failure to

perform checks at the beginning of each work shift on the main hoist limit switches.

1R18 Plant Modifications (71111.18)

a. Inspection Scope

The inspectors reviewed the following temporary modifications to verify that the safety

functions of important safety systems were not degraded:

  • August 26, 2009, Patch on 18-inch grid backwash piping (Circulating Water

System)

The inspectors reviewed the temporary modification and the associated safety

evaluation screening against the system design bases documentation, including the

Updated Final Safety Analysis Report and the technical specifications, and verified that

the modification did not adversely affect the system availability. The inspectors also

verified that the installation and restoration were consistent with the modification

documents and that configuration control was adequate. Additionally, the inspectors

verified that the temporary modification was identified on control room drawings,

appropriate tags were placed on the affected equipment, and licensee personnel

evaluated the combined effects on mitigating systems and the integrity of radiological

barriers.

- 13 - Enclosure

These activities constitute completion of one sample for temporary plant modifications as

defined in Inspection Procedure 71111.18-05

b. Findings

No findings of significance were identified.

1R19 Postmaintenance Testing (71111.19)

a. Inspection Scope

The inspectors reviewed the following postmaintenance activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

  • July 16, 2009, Postmaintenance testing of Heat Exchanger Component

Cooling Water inlet valve HCV-481 following work on Shutdown Cooling

Heat Exchanger AC-4B

  • July 28, 2009, Postmaintenance testing of Cooling Coil VA-8B Component

Cooling Water inlet valve HCV-403A following flowscan maintenance

  • July 31, 2009, Postmaintenance testing of Charging Pump CH-1C following

maintenance

  • August 6, 2009, Postmaintenance testing of Refueling Area Crane HE-2

following resetting of pressure switch PS-2

following pump replacement

The inspectors selected these activities based upon the structure, system, or

component's ability to affect risk. The inspectors evaluated these activities for the

following (as applicable):

  • The effect of testing on the plant had been adequately addressed; testing

was adequate for the maintenance performed

  • Acceptance criteria were clear and demonstrated operational readiness;

test instrumentation was appropriate

The inspectors evaluated the activities against the technical specifications, the Updated

Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various

NRC generic communications to ensure that the test results adequately ensured that the

equipment met the licensing basis and design requirements. In addition, the inspectors

reviewed corrective action documents associated with postmaintenance tests to

determine whether the licensee was identifying problems and entering them in the

corrective action program and that the problems were being corrected commensurate

with their importance to safety. Specific documents reviewed during this inspection are

listed in the attachment.

- 14 - Enclosure

These activities constitute completion of five postmaintenance testing inspection samples as

defined in Inspection Procedure 71111.19-05.

b. Findings

No findings of significance were identified.

1R22 Surveillance Testing (71111.22)

a. Inspection Scope

The inspectors reviewed the Updated Final Safety Analysis Report, procedure

requirements, and technical specifications to ensure that the surveillance activities listed

below demonstrated that the systems, structures, and components tested were capable

of performing their intended safety functions. The inspectors either witnessed or

reviewed test data to verify that the significant surveillance test attributes were adequate

to address the following:

  • Preconditioning
  • Evaluation of testing impact on the plant
  • Acceptance criteria
  • Test equipment
  • Procedures
  • Test data
  • Testing frequency and method demonstrated technical specification

operability

  • Test equipment removal
  • Restoration of plant systems
  • Engineering evaluations, root causes, and bases for returning tested

systems, structures, and components not meeting the test acceptance

criteria were correct

  • Reference setting data

The inspectors also verified that licensee personnel identified and implemented any

needed corrective actions associated with the surveillance testing.

- 15 - Enclosure

  • August 11, 2009, Diesel Generator DG-2 starting air compressors

discharge check valve exercise test

  • August 17, 2009, Component Cooling Category B Valve Exercise Test

(OP-ST-CCW-3001A)

  • August 28, 2009, AC-3C Component Cooling Water Pump Inservice Test
  • September 1, 2009, Component Cooling Category A and B Valve Exercise

Test (OP-ST-CCW-3005B)

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four surveillance testing inspection sample(s) as

defined in Inspection Procedure 71111.22-05.

b. Findings

No findings of significance were identified.

Cornerstone: Emergency Preparedness

1EP1 Exercise Evaluation (71114.01)

a. Inspection Scope

The inspectors reviewed the objectives and scenario for the 2009 Biennial Emergency

Plan Exercise to determine if the exercise would acceptably test major elements of the

emergency plan. The scenario simulated a tornado touchdown within the site protected

area, an unanticipated closing of main steam isolation valves, failures of automatic and

manual systems to shut down the reactor, a small reactor coolant leak in containment, a

steam generator tube leak, fission product barrier failures, core damage, a radiological

release to the environment via a stuck-open main steam line relief valve, and changes in

wind direction vectors, to demonstrate licensee personnels capability to implement their

emergency plan.

The inspectors evaluated exercise performance by focusing on the risk-significant

activities of event classification, offsite notification, recognition of offsite dose

consequences, development of protective action recommendations in the control room

simulator, and the following dedicated emergency response facilities:

  • Operations Support Center
  • Emergency Operations Facility

The inspectors also assessed recognition of, and response to, abnormal and emergency

plant conditions, the transfer of decision-making authority and emergency function

- 16 - Enclosure

responsibility between emergency response facilities, onsite and offsite communications,

protection of emergency workers, emergency repair evaluation and capability, and the

overall implementation of the emergency plan to protect public health and safety and the

environment. The inspectors reviewed the current revision of the facility emergency

plan, emergency plan implementing procedures associated with operation of the

licensees emergency response facilities, procedures for the performance of associated

emergency functions, and other documents as listed in the attachment to this report.

The inspectors compared the observed exercise performance with the requirements in

the facility emergency plan, 10 CFR 50.47(b), 10 CFR Part 50, Appendix E, and with the

guidance in the emergency plan implementing procedures and other federal guidance.

The inspectors attended the post-exercise critiques in each emergency response facility

to evaluate the initial licensee self-assessment of exercise performance, and attended a

subsequent formal presentation of critique items to plant management. The specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one sample as defined in Inspection

Procedure 71114.01-05.

b. Findings

No findings of significance were identified.

1EP4 Emergency Action Level and Emergency Plan Changes (71114.04)

a. Inspection Scope

The inspectors performed an in-office and on-site reviews of:

Classification, Revision 46, issued May 14, 2009

  • TBD-EPIP-OSC-1A, Technical Basis Document, Revision 0, issued

May 14, 2009

  • Radiological Emergency Response Plan, Section B, Organizational Control

of Emergencies, Revision 29, issued May 14, 2009

  • Radiological Emergency Response Plan, Section D, Emergency

Classification System, Revision 14, issued May 14, 2009

  • Radiological Emergency Response Plan, Section E, Notification Methods

and Procedures, Revision 25, issued May 14, 2009

  • Radiological Emergency Response Plan, Section H, Emergency Facilities

and Equipment, Revision 37, issued May 14, 2009

- 17 - Enclosure

  • Radiological Emergency Response Plan,Section I, Accident Assessment,

Revision 14, issued June 23, 2009

These revisions implemented an emergency action level scheme based on Nuclear

Energy Institute (NEI) Report 99-01, Emergency Action Level Methodology, Revision 5,

transferred some oversight responsibilities during medical emergencies from the Shift

manager to the medical coordinator, updated emergency response organization titles,

and made minor editorial corrections. The licensees revised emergency action level

scheme was approved by the NRC in a safety analysis report dated

September 22, 2008, (Agency Document and Management System Accession Numbers

ML0826605731 and ML082320484).

These revisions were compared to their previous revisions, to the criteria of

NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency

Response Plans and Preparedness in Support of Nuclear Power Plants, Revision 1, to

Nuclear Energy Institute Report 99-01, Emergency Action Level Methodology,

Revision 5, and to the standards in 10 CFR 50.47(b) to determine if the revision

adequately implemented the requirements of 10 CFR 50.54(q). These reviews were not

documented in safety evaluation reports and did not constitute approvals of licensee

generated changes; therefore, these revisions are subject to future inspection. The

specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four samples as defined in Inspection

Procedure 71114.04-05.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator Verification (71151)

.1 Data Submission Issue

a. Inspection Scope

The inspectors performed a review of the performance indicator data submitted by the

licensee for the third quarter 2008, fourth quarter 2008, first quarter 2009, and second

quarter 2009 for any obvious inconsistencies prior to its public release in accordance

with Inspection Manual chapter 0608, Performance Indicator Program.

This review was performed as part of the inspectors normal plant status activities and,

as such, did not constitute a separate inspection sample.

b. Findings

No findings of significance were identified.

- 18 - Enclosure

.2 Safety System Functional Failures (MS05)

a. Inspection Scope

The inspectors sampled licensee submittals for the Safety System Functional Failures

performance indicator for the period from the third quarter 2008 through the fourth

quarter 2009. To determine the accuracy of the performance indicator data reported

during those periods, performance indicator definitions and guidance contained in

NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline,

Revision 5, and NUREG-1022, Event Reporting Guidelines 10 CFR 50.72 and 50.73"

definitions and guidance were used. The inspectors reviewed the licensees operator

narrative logs, operability assessments, maintenance rule records, maintenance work

orders, issue reports, event reports and NRC integrated inspection reports for the period

of July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors also reviewed the licensees issue report database to determine if any

problems had been identified with the performance indicator data collected or

transmitted for this indicator and none were identified. Specific documents reviewed are

described in the attachment to this report.

These activities constitute completion of one safety system functional failures sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.3 Mitigating Systems Performance Index - Emergency ac Power System (MS06)

a. Inspection Scope

The inspectors sampled licensee submittals for the Mitigating Systems Performance

Index - Emergency ac Power System performance indicator for the period from the third

quarter 2008 through the fourth quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, mitigating systems performance index derivation

reports, issue reports, event reports and NRC integrated inspection reports for the period

of July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable

NEI guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index

emergency ac power system sample as defined in Inspection Procedure 71151-05.

- 19 - Enclosure

b. Findings

No findings of significance were identified.

.4 Mitigating Systems Performance Index - High Pressure Injection Systems (MS07)

a. Inspection Scope

The inspectors sampled licensee submittals for the Mitigating Systems Performance

Index - High Pressure Injection Systems performance indicator for the period from the

third quarter 2008 through the fourth quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, issue reports, mitigating systems performance index

derivation reports, event reports and NRC integrated inspection reports for the period of

July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable

NEI guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index

high-pressure injection system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.5 Mitigating Systems Performance Index - Heat Removal System (MS08)

a. Inspection Scope

The inspectors sampled licensee submittals for the Mitigating Systems Performance

Index - Heat Removal System performance indicator for the period from the third quarter

2008 through the fourth quarter 2009. To determine the accuracy of the performance

indicator data reported during those periods, performance indicator definitions and

guidance contained in NEI Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees

operator narrative logs, issue reports, event reports, mitigating systems performance

index derivation reports, and NRC integrated inspection reports for the period of

July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors reviewed the MSPI component risk coefficient to determine if it had changed

by more than 25 percent in value since the previous inspection, and if so, that the

change was in accordance with applicable NEI guidance. The inspectors also reviewed

- 20 - Enclosure

the licensees issue report database to determine if any problems had been identified

with the performance indicator data collected or transmitted for this indicator and none

were identified. Specific documents reviewed are described in the attachment to this

report.

These activities constitute completion of one mitigating systems performance index heat

removal system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.6 Mitigating Systems Performance Index - Residual Heat Removal System (MS09)

a. Inspection Scope

The inspectors sampled licensee submittals for the Mitigating Systems Performance

Index - Residual Heat Removal System performance indicator for the period from the

third quarter 2008 through the fourth quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, issue reports, mitigating systems performance index

derivation reports, event reports and NRC integrated inspection reports for the period of

July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable

NEI guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index

residual heat removal system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.7 Mitigating Systems Performance Index - Cooling Water Systems (MS10)

a. Inspection Scope

The inspectors sampled licensee submittals for the Mitigating Systems Performance

Index - Cooling Water Systems performance indicator for the period from the third

quarter 2008 through the fourth quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

- 21 - Enclosure

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, issue reports, mitigating systems performance index

derivation reports, event reports and NRC integrated inspection reports for the period of

July 1, 2008 through June 30, 2009 to validate the accuracy of the submittals. The

inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable

NEI guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index

cooling water system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.8 Drill and Exercise Performance (EP01)

a. Inspection Scope

The inspectors sampled licensee submittals for the Drill and Exercise Performance,

performance indicator for the period from the third quarter 2008 through the fourth

quarter 2009. To determine the accuracy of the performance indicator data reported

during those periods, performance indicator definitions and guidance contained in

Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees

records associated with the performance indicator to verify that the licensee accurately

reported the indicator in accordance with relevant procedures and the Nuclear Energy

Institute guidance. Specifically, the inspectors reviewed licensee records and processes

including procedural guidance on assessing opportunities for the performance indicator;

assessments of performance indicator opportunities during predestinated control room

simulator training sessions, and other licensee drills. The specific documents reviewed

are described in the attachment to this report.

These activities constitute completion of the drill/exercise performance sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.9 Emergency Response Organization Drill Participation (EP02)

a. Inspection Scope

- 22 - Enclosure

The inspectors sampled licensee submittals for the Emergency Response Organization

Drill Participation performance indicator for the period the third quarter 2008 through the

fourth quarter 2009. To determine the accuracy of the performance indicator data

reported during those periods, performance indicator definitions and guidance contained

in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees

records associated with the performance indicator to verify that the licensee accurately

reported the indicator in accordance with relevant procedures and the Nuclear Energy

Institute guidance. Specifically, the inspectors reviewed licensee records and processes

including procedural guidance on assessing opportunities for the performance indicator,

rosters of personnel assigned to key emergency response organization positions, and

exercise participation records. The specific documents reviewed are described in the

attachment to this report.

These activities constitute completion of the emergency response organization drill

participation sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.10 Alert and Notification System (EP03)

a. Inspection Scope

The inspectors sampled licensee submittals for the Alert and Notification System

performance indicator for the period July 2008 through June 2009. To determine the

accuracy of the performance indicator data reported during those periods, performance

indicator definitions and guidance contained in Nuclear Energy Institute

Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5,

was used. The inspectors reviewed the licensees records associated with the

performance indicator to verify that the licensee accurately reported the indicator in

accordance with relevant procedures and the Nuclear Energy Institute guidance.

Specifically, the inspectors reviewed licensee records and processes including

procedural guidance on assessing opportunities for the performance indicator and the

results of periodic alert notification system operability tests. The specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of the alert and notification system sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

- 23 - Enclosure

4OA2 Identification and Resolution of Problems (71152)

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Physical Protection

.1 Routine Review of Identification and Resolution of Problems

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees

corrective action program at an appropriate threshold, that adequate attention was being

given to timely corrective actions, and that adverse trends were identified and

addressed. The inspectors reviewed attributes that included (1) the complete and

accurate identification of the problem; (2) the timely correction, commensurate with the

safety significance; (3) the evaluation and disposition of performance issues, generic

implications, common causes, contributing factors, root causes, extent of condition

reviews, and previous occurrences reviews; and (4) the classification, prioritization,

focus, and timeliness of corrective actions. Minor issues entered into the licensees

corrective action program because of the inspectors observations are included in the

attached list of documents reviewed.

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure, they were considered an

integral part of the inspections performed during the quarter and documented in

Section 1 of this report.

b. Findings

No findings of significance were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific

human performance issues for follow-up, the inspectors performed a daily screening of

items entered into the licensees corrective action program. The inspectors

accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status

monitoring activities and, as such, did not constitute any separate inspection samples.

b. Findings

No findings of significance were identified.

- 24 - Enclosure

.3 Semi-Annual Trend Review

a. Inspection Scope

The inspectors performed a review of the licensees corrective action program and

associated documents to identify trends that could indicate the existence of a more

significant safety issue. The inspectors focused their review on repetitive equipment

issues, but also considered the results of daily corrective action item screening

discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human

performance results. The inspectors nominally considered the period of

January 1, 2009, through August 31, 2009, although some examples expanded beyond

those dates where the scope of the trend warranted.

The inspectors also included issues documented outside the normal corrective action

program in major equipment problem lists, repetitive and rework maintenance lists,

departmental challenges lists, system health reports, quality assurance audit reports,

self-assessment reports, and Maintenance Rule assessments. The inspectors

compared and contrasted their results with the results contained in the licensees

corrective action program trending reports. Corrective actions associated with a sample

of the issues identified in the licensees trending reports were reviewed for adequacy.

These activities constitute completion of one single semi-annual trend inspection sample

as defined in Inspection Procedure 71152-05.

b. Findings

No findings of significance were identified.

.4 Selected Issue Follow-up Inspection

a. Inspection Scope

During a review of items entered in the licensees corrective action program, the

inspectors recognized a corrective action item documenting repetitive problems

associated with the auxiliary building crane during the spent fuel pool campaign. The

inspectors reviewed the individual incidents to ascertain any commonalities to the

incidents.

The inspectors reviewed items entered in the licensees corrective action program; the

inspectors recognized a corrective action item documenting an inadequate maintenance

work order. The inspectors reviewed the events leading to the discovery of the

inadequate work order, a review of their apparent cause analysis, and the proposed

corrective actions.

These activities constitute completion of two in-depth problem identification and

resolution samples as defined in Inspection Procedure 71152-05.

- 25 - Enclosure

b. Findings

i. Introduction. A self-revealing Green noncited violation (NCV) of 10 CFR Part 50,

Appendix B, Criterion V, was identified for the failure of personnel to follow an

auxiliary building crane operating procedure. This resulted in the crane contacting

the fuel handling bridge and moving it approximately eight feet.

Description. On June 30, 2009, activities were taking place in the fuel building

associated with dry fuel storage campaign. Personnel were preparing to move the

dry fuel transfer cask from its storage location in Room 68 into the spent fuel pool.

This activity required rigging the transfer cask yoke with the Refueling Area Crane

(HE-2), attaching the yoke to the transfer cask, then lifting the transfer cask from its

storage location and placing it in the spent fuel pool.

The crane is normally operated from the cab control with the crane operator

physically inside the cab; but can also be operated by radio control where the crane

operator manipulates the crane using a portable radio transmitter. On June 30,

2009, the crane operator was using the radio transmitter to operate the crane. The

crane operator lifted the transfer cask yoke, and was in the process of moving the

yoke to the storage area of the transfer cask. Since the crane operator was

operating the crane with the radio transmitter, he did not have a direct line of sight to

the cranes cab. While moving the yoke laterally with the crane, the cab struck the

mast of the fuel handling bridge (FH-12), moving the bridge approximately eight

feet.

The crane was being operated in accordance with operating instruction

GM-OI-HE-2, Auxiliary Building Crane Normal Operation. Both the crane cab and

the fuel handling bridge are equipped with proximity detectors. The operating

instruction prerequisites require energizing the proximity detectors on the crane cab

and on the fuel handling bridge. There is an additional prerequisite to move and

park the fuel handling bridge with its mast at the west end of the bridge.

Section 6.31 of the precautions and limitations section of the operating instruction

states: During radio controlled operation of HE-2, the Crane Operator may be

located in such a way that the FH-12 proximity detector indications are not visible.

To avoid the risk of a collision, FH-12 shall be parked with the mast at the west end

of the bridge. When the crane struck the fuel handling bridge, the mast was parked

on the east end of the bridge, and the proximity detectors were energized neither on

the crane nor on the fuel handling bridge.

Analysis. The failure to follow the prerequisites of the auxiliary building crane

operating procedure is a performance deficiency. The finding is greater than minor

because it would become a more significant safety concern if left uncorrected in that

a collision with the fuel handling bridge could cause damage such that pieces of the

mast could fall into the spent fuel pool and damage the spent fuel. Using the

NRC Manual Chapter 0609, Phase 1 screening worksheet under the Barrier

Integrity Cornerstone for spent fuel pool issues, the finding screened as having very

low safety significance because it did not result in loss of cooling to the spent fuel

pool, did not cause damage to the fuel cladding or result in dropped fuel assembly

or result in a loss of spent fuel pool volume of greater than 10 percent. This finding

- 26 - Enclosure

has a crosscutting aspect in the area of human performance associated with work

practices because personnel failed to use human error prevention techniques

commensurate with the risk of the assigned task, such that work activities were

performed safely [H.4.(a)].

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, require that activities affecting Quality shall be

prescribed by documented procedures of a type appropriate to the circumstances

and shall be accomplished in accordance with these procedures. Operating

Instruction GM-OI-HE-2, Auxiliary Building Crane Normal Operation Revision 18,

contained the requirements for positioning of the fuel handling bridge mast and

energizing the proximity detectors on the cranes cab and the fuel handling bridge.

Contrary to the above, on June 30, 2009, personnel failed to park the mast of the

fuel handling bridge at the west end of the bridge and failed to energize the

proximity detectors in accordance with Operating Instructions GM-OI-HE-2. This

failure resulted in the crane colliding with the fuel handling bridge mast. Because

the finding is of very low safety significance and has been entered into the

licensees corrective action program as Condition Report CR-2009-3002, this

violation is being treated as an NCV consistent with Section VI.A of the Enforcement

Policy: NCV 05000285/2009004-04, Failure to Follow Auxiliary Building Crane

Operating Instructions.

ii. Introduction. A self-revealing, Green noncited violation of Technical Specification 5.8.1.a (Procedures) was identified for failure to provide an adequate maintenance

work instruction. While performing maintenance on the motor, the HPSI Header -

Charging Header Crosstie Valve, HCV-308, the maintenance work instruction failed

to ensure that the HPSI Alternate Header Isolation Valve, HCV-2987, was closed,

resulting in unexpected pressurization of the Number 2 HPSI Header.

Description. On July 17, 2009, the licensee was performing Motor Control Center

and Fast Fourier Transform testing on the, HPSI Header - Charging Header

Crosstie Valve motor of HCV-308. The work instructions consisted of seven

sections contained on one page. Section 3.0 Impact Statement noted HCV-308

will be out of service for this work task, and Valve will be cycled throughout

testing. Section 6.0 Work Instructions stated Perform MC2 Diagnostic Testing

on HCV-308 per the procedure EM-RR-VX-0406, (MC2 Diagnostic Test Procedure

for Motor Operated Valves).

The Motor Control Center diagnostic equipment and data acquisition system were

installed on HCV-308. Step 7.3.2 of the diagnostic test procedure then directed

stroke the valve in the desired direction. Though not specifically referenced in the

maintenance work instruction, the operator referenced Surveillance Test

Procedure OP-ST-SI-3001, Safety Injection System Category A and B Valve

Exercise Test to open HCV-308. Details on opening this specific valve are

included in Attachment 8, Section 5 of the Surveillance Test Procedure.

After opening HCV-308, control room personnel noted a steady increase in the

Reactor Coolant Drain Tank level. While investigating the source of water into the

tank, the control room noted that the differential pressure across the Number 2

- 27 - Enclosure

HSPI header injection valves exceeded 1300 psig below the valve seat. Nominally,

the differential pressure across these valves is 250 psi above the valve seat.

Further investigation determined that the HPSI Alternate Header Isolation Valve,

HCV-2987, was open, and provided charging pump discharge pressure to the

header injection valves once HCV-308 was opened.

Though the maintenance work instruction did not provide adequate guidance to

open HCV-308, the Surveillance Test Procedure should provide the needed

guidance. There is a note in Attachment 8 of the surveillance test that states HCV-

2987 should remain closed during stroke testing of HCV-308 However, this note

is contained in the section of the procedure to stroke HCV-2987, and could go

unnoticed when using the procedure only to stroke HCV-308.

Analysis. The failure to provide an adequate maintenance work instruction was a

performance deficiency. This finding was greater than minor because the finding

was associated with the Mitigating Systems Cornerstone objective (procedure

quality attribute) to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. Using Manual

Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection

Findings for At-Power Situations, Phase 1 screening worksheet, the inspectors

determined that the finding was of very low safety significance (Green) because it

was not: (1) a design or qualification deficiency; (2) a loss of system safety

function; (3) an actual loss of safety function for greater than its technical

specification allowed outage time; (4) a loss of safety function of a nontechnical

specification train; or (5) a seismic, flooding or severe weather related finding.

There is no crosscutting aspect associated with this finding since the inadequacy of

the surveillance test procedure was a significant contributor to the result, not the

performance deficiency.

Enforcement. Fort Calhoun Technical Specification 5.8.1.a states, in part, Written

procedures... shall be established, implemented and maintained covering the

following activities... The applicable procedures recommended in Regulatory

Guide 1.33, Revision 2, Appendix A, 1978. Regulatory Guide 1.33, Revision 2,

Appendix A, 1978, Section 9(a), recommends, in part, maintenance that can affect

the performance of safety-related equipment should be properly preplanned and

performed in accordance with written procedures, documented instructions, or

drawings appropriate to the circumstances. The licensee performed maintenance

on the motor of HCV-308 in accordance with Work Order 00333467-01. Contrary to

the above, as of July 17, 2009, the maintenance work instruction for performing

motor testing on HCV-308 was not adequate to satisfy this requirement because the

instruction failed to provide adequate steps to ensure that HCV-2987 was closed

prior to opening HCV-308. Since this finding was of very low safety significance

and was documented in the licensees corrective action program as Condition

Report CR2009-3256, this violation is being treated as a noncited violation (NCV),

consistent with Section VI.A of the NRC Enforcement Policy (NCV 05000285/2009004-01), Inadequate Valve Motor Maintenance Work Instructions.

- 28 - Enclosure

.5 In-Depth Review of Operator Workarounds

a. Inspection Scope

The inspectors selected this issue for review to verify that licensee personnel were

identifying operator workaround problems at an appropriate threshold and entering them

in the corrective action program, and has proposed or implemented appropriate

corrective actions. The inspectors considered the following, as applicable, during the

review of the licensee's actions: (1) complete and accurate identification of the problem

in a timely manner; (2) evaluation and disposition of operability/reportability issues;

(3) consideration of extent of condition, generic implications, common cause, and

previous occurrences; (4) classification and prioritization of the resolution of the problem;

(5) identification of root and contributing causes of the problem; (6) identification of

corrective actions; and (7) completion of corrective actions in a timely manner.

b. Findings

No findings of significance were identified.

4OA3 Event Follow-up (71153)

.1 (Opened) LER 05000285/2009003-00, Void in Safety Injection Piping During

Operation Due to Inadequate Procedural Guidance

On April 30, 2009, a void was discovered on the cooled suction line to High

Pressure Safety Injection Pump SI-2B. Based on the period from the end of the

2008 Refueling Outage to the time of the discovery of the void, this made SI-2B

inoperable for greater than the Technical Specification allowed 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Actions

were taken to successfully vent the void. Follow-up ultrasonic testing was done to

confirm the location was water filled.

.2 (Opened and Closed) LER 05000285/2009002-00, Technical Specification Violation

due to Installation of an Unqualified Part in a Radiation Monitor

On November 21, 2008, a non-qualified relay was mistakenly installed in the pump

control circuit of a process radiation monitor, rendering it inoperable. The licensee

discovered the condition on April 13, 2009. In the intervening 143 days, a stack

radiation monitor was inoperable at the same time in Violation of Technical

Specification 2.15. The LER was reviewed by the inspectors, no findings of

significance were identified, and no violation of NRC requirements occurred. The

licensee documented the failed equipment in Condition Report CR 2009-2537.

This LER is closed.

.3 (Closed) URI 05000285/2009007-04, Failure to Report a Potential Defect of

Breaker Trip Bars per 10 CFR Part 21

a. Inspection Scope.

On July 14, 2009, Inspection Report 05000285/2009007 documented an unresolved

- 29 - Enclosure

item concerning the extent of a deviation originally discovered in a failed safety-related

breaker. An inadequate evaluation of the deviation was performed that could result in an

event or condition not being properly reported under 10 CFR Part 21, 10 CFR Part

50.72, 10 CFR Part 50.73 or 10 CFR Part 73.71.

b. Finding

. Failure To Adopt Appropriate Procedures To Evaluate Deviations And Failures To Comply

With 10 CFR Part 21

Introduction. The NRC identified a Severity Level IV noncited violation of

10 CFR Part 21.21(a), Notification of failure to comply or existence of a defect and its

evaluation for the licensees failure to adopt appropriate procedures to evaluate

deviations and failures to comply associated with substantial safety hazards.

Specifically, the procedure fails to adequately assess the extent of deviations, which are

discovered, and the potential impact on other components either installed in the plant or

stored in the warehouse. Additionally, the procedure failed to adequately evaluate

defects in components, which have never been installed or used in the nuclear plant.

Description. On August 24, 2007, a safety related breaker (MCC-4B1-B01, Pressurizer

Backup Heaters Bank 3 Group 8) failed its instantaneous trip setting on one phase. A

failure analysis was performed by a third party vendor who determined the failure to be

curvature of the trip bar was likely due to a material defect. This failure is a deviation as

defined by 10 CFR Part 21 (a departure from the technical requirements included in a

procurement document) and the licensees governing procedure SO-R-1, Reportability

Determinations. The licensee arbitrarily determined the extent of the deviation to be

limited to breakers with the same date code as the failed breaker. This determination

was made with no engineering basis. In instances where deviations are attributed to the

vendor, only the vendor can fully determine the extent of the deviation and its potential

effect on similar components. Since procedure SO-R-1 did not direct vendor notification

unless the initial deviation is potentially associated with a substantial safety hazard, it is

not possible to fully determine whether the deviation occurred in other components.

The licensee determined there were no other breakers with the same date code located

anywhere on site, thus the only breaker assumed to have the deviation was the initial

breaker that failed. Due to the safety-related function of the particular breaker, there was

no substantial safety hazard, and the event was not reportable under 10 CFR 50.72 or

10 CFR 50.73. Thus, the licensee determined that any reporting requirements under

10 CFR Part 21 were satisfied, as described in 10 CFR 21.2(c). The inspectors noted

Step 1.3 in Procedure SO-R-1 which states, in part, for in-service components, if the

event or condition is appropriately evaluated under 10 CFR 50.72, 50.73 or 73.71 (e.g.,

via the use of Reportability Evaluation Checklist Part 1 and/or Part 6, as appropriate) no

additional evaluation is needed with respect to 10 CFR Part 21. In addition, no specific

guidance is included in the procedure to address affected components, which may be

located in the warehouse.

On July 31, 1991, the NRC published Statements of Consideration in the Federal

Register (56 FR 36081) Criteria and Procedures for the Reporting of Defects and

Conditions of Construction Permits. This publication noted, One category of defects,

- 30 - Enclosure

which will still be reported by power plant operating license holders under Part 21 rather

than Sections 50.72 and 50.73, are those defects discovered by licensees in equipment

that has never been installed or used in the nuclear plant. This category of defects is

normally associated with components stored in the licensee's warehouse. Following

Step 1.3 in Procedure SO-R-1, conditions could exist where a deviation is evaluated

under 10 CFR 50.72 or 10 CFR 50.73 and determined to be not reportable, then no

further evaluation would be required, even though the defect may occur in a component

or components in the warehouse.

Analysis. The inspectors determined that the failure to adopt appropriate procedures to

evaluate deviations and failures to comply associated with substantial safety hazards

was a performance deficiency. This finding was more than minor because if the

procedure were left uncorrected it could become a more serious safety concern.

Specifically, failure to notify the vendor upon discovery of a deviation does not allow for

adequate evaluation of other components that could be subject to the deviation.

Additionally, components with deviations could be located in the licensees warehouse

and subsequently installed in the plant without the licensees knowledge, potentially

creating a substantial safety hazard. Because this issue affected a potential reporting

requirement and NRCs ability to perform its regulatory function, it was evaluated with

the traditional enforcement process. Consistent with the guidance in Section IV.A.3 and

Supplement VII paragraph D.4 of the NRC Enforcement Policy, this violation was

categorized at Severity Level IV noncited violation. There is no crosscutting aspect

associated with this finding because it is not indicative of current performance in that the

procedure is many years old.

Enforcement. Title 10 CFR Part 21.21(a), Notification of failure to comply or existence

of a defect and its evaluation, states, in part, that each individual corporation subject to

the regulations in this part shall adopt appropriate procedures to evaluate deviation and

failures to comply associated with substantial safety hazards. Contrary to the above, as

of May 15, 2009, the licensee failed to adequately address the evaluation of defects

discovered in equipment that has never been installed or used in the nuclear plant.

Additionally, there is no guidance to evaluate the extent of the deviation to determine if

defective components are located in the warehouse. This is a Severity Level IV violation

consistent with Section IV.A.3 and Supplement VII, paragraph D.4, of the NRC

Enforcement Policy.

Because this finding was of very low safety significance and has been entered into the

corrective action program as Condition Report CR 2009-2276, this violation is being

treated as a noncited violation, consistent with section VI.A of the NRC Enforcement

Policy: NCV 05000285/2009004-02, "Failure to Adopt Appropriate Procedures to

Evaluate Deviations and Failures to Comply with 10 CFR Part 21 Evaluations."

- 31 - Enclosure

4OA5 Other Activities

.1 Quarterly Resident Inspector Observations of Security Personnel and Activities

a. Inspection Scope

During the inspection period, the inspectors performed observations of security force

personnel and activities to ensure that the activities were consistent with Fort Calhouns

security procedures and regulatory requirements relating to nuclear plant security.

These observations took place during both normal and off-normal plant working hours.

These quarterly resident inspector observations of security force personnel and activities

did not constitute any additional inspection samples. Rather, they were considered an

integral part of the inspectors normal plant status review and inspection activities.

b. Findings

No findings of significance were identified.

.2 Operation of an Independent Spent Fuel Storage Installation at Operating

Plants (60855.1); Review of 10 CFR 72.212(b) Evaluations at Operating

Plants (60856.1)

a. Inspection Scope

Inspectors reviewed aspects of the stations 10 CFR 72 specific license. At the time of

this inspection, Fort Calhoun Stations independent spent fuel storage installation

contained five loaded Transnuclear Standardized NUHOMS Horizontal Modular Storage

units. The licensee was loading casks in compliance with the requirements contained in

Transnuclear Standardized NUHOMS Horizontal Modular Storage System Certificate of

Compliance 1004, License Amendment 9, and the Standardized NUHOMS Horizontal

Modular Storage System Final Safety Analysis Report, Revision 7, for use during the

current cask loading campaign.

Portions of the operations associated with loading of canister 7 were observed. (Note:

Canister numbers do not reflect actual loading sequence.) Activities in process included

the use of the forced helium to remove the moisture from the dry shielded canister,

helium backfill operation, dry shielded canister closure welding, nondestructive testing of

weld joints, and the loading of the canister into the Standardized NUHOMS Horizontal

Module.

The characteristics of the spent fuel assemblies selected for loading into dry shielded

canister 7 were reviewed and found to be in compliance with Certificate of

Compliance 1004 technical specification requirements. The fuel assemblies had been

selected for loading in accordance with the requirements contained in licensee

Procedure RE-AD-0005, Fuel Selection and DSC Planning for Dry Cask Storage,

Revision 2.

- 32 - Enclosure

A tour of the independent spent fuel storage installation was performed by the

inspectors. The condition of the Standardized NUHOMS Horizontal Modular Storage

units and the associated vents were determined to be adequate. Material being stored

on the independent spent fuel storage installation pad, and used for supporting

independent spent fuel storage operations, met the fire hazard analysis requirements.

The Transnuclear Standardized NUHOMS Horizontal Modular Storage System

Technical Specification 1.3 provides the licensee two methods, Technical Specification 1.3.1 or 1.3.2, for monitoring the thermal performance of the horizontal storage modules

on a daily basis. The licensee chose Technical Specification 1.3.2 as their thermal

performance monitoring method that monitors the inlet and outlet air temperature of

each horizontal storage module. The licensee has incorporated the requirements to

obtain these daily readings in the plant operations logs.

b. Findings

No findings of significance were identified.

4OA6 Meetings

Exit Meeting Summary

On July 24, 2009, the inspectors presented the results of the inspection of the onsite emergency

preparedness exercise and the onsite review of licensee changes to the Radiological

Emergency Response Plan and emergency plan implementing procedures, to

Mr. T. Nellenbach, Division Manager, Nuclear Operations/Plant Manager, and other members of

the licensees staff. The licensee acknowledged the issues presented. The inspector asked the

licensee whether any materials examined during the inspection should be considered

proprietary. No proprietary information was identified.

On August 7, 2009, the inspectors presented the inspection results of the Dry Fuel Storage

Campaign inspection activities to Mr. J. Reinhart, Site Vice President, and other members of the

licensee staff. The licensee acknowledged the issues presented. The inspectors asked the

licensee whether any materials examined during the inspection should be considered

proprietary. No proprietary information was identified.

On October 7, 2009, the inspectors presented the inspection results to Mr. J. Reinhart,

Site Vice President, and other members of the licensee staff. The licensee acknowledged the

issues presented. The inspector asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

- 33 - Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

R. Acker, Station Licensing Engineering

R. Clemens, Division Manager, Nuclear Engineering

P. Cronin, Manager, Operations

K. Erdman, Supervisor Materials Engineering

H. Faulhaber, Division Manager, Nuclear Asset Management

M. Frans, Manager, System Engineering

J. Gasper, Manager, Design Engineering

S. Gebers, Manager, Emergency Preparedness and Health Physics

D. Guinn, Supervisor Regulatory Compliance

J. Herman, Manager, Engineering Programs

R. Hodgson, Manager, Radiation Protection

T. Hutchinson, Reliability Engineer

T. Matthews, Manager, Nuclear Licensing

E. Matzke, Senior Nuclear Licensing Engineer

T. Nellenbach, Division Manager, Nuclear Operations/Plant Manager

T. Pilmaier, Manager, Performance Improvement

J. Reinhart, Site Vice President

G. Roets, Manager Major Projects

R. Short, Manager, Major Projects

C. Simmons, Supervisor, Emergency Preparedness

M. Tesar, Division Manager, Nuclear Support

T. Uehling, Manager, Chemistry

B. VanSant, Manager, Nuclear Projects

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2009003-00 LER Void in Safety Injection Piping During Operation Due to

Inadequate Procedural Guidance (4OA3)05000282/2009004-01 NCV Inadequate Valve Motor Maintenance Work Instructions (4OA2)05000285/2009004-02 NCV Failure to Adopt Appropriate Procedures to Evaluate Deviations

and Failures to Comply with 10 CFR Part 21 Evaluations (4OA3)05000285/2009004-03 FIN Failure to perform checks at the beginning of each work shift on

the main hoist limit switches (1R15)05000285/2009004-04 NCV Failure to Follow Auxiliary Building Crane Operating Instructions

(40A2)

Opened and Closed

05000282/2009002-00 LER Technical Specification Violation Due to Installation of an

Unqualified Part in a Radiation Monitor (4OA3)

A-1 Attachment

Closed

05000285/2009007-04 URI Void in Safety Injection Piping During Operation Due to

Inadequate Procedural Guidance (4OA3)

LIST OF DOCUMENTS REVIEWED

Section 1RO1: Adverse Weather Protection

DOCUMENT TYPE

NUMBER TITLE REVISION

AOP-31 161 kV Grid Malfunctions 9

NOD-QP-36 Grid Operations and Control of Switchyard at FCS 18

OI-EG-3 EMS Post-FCS-Trip 161 KV Voltage Prediction and Switchyard 7

Status

Section 1RO4: Equipment Alignment

DRAWINGS

NUMBER TITLE REVISION

11405-M-10, Sheet 1 Auxiliary Cooling Component Cooling System Flow 66

Diagram P&ID

11405-M-10, Sheet 2 Auxiliary Cooling Component Cooling System Flow 17

Diagram P&ID

11405-M-10, Sheet 3 Auxiliary Cooling Component Cooling System Flow 24

Diagram P&ID

11405-M-10, Sheet 4 Auxiliary Cooling Component Cooling System Flow 11

Diagram P&ID

11405-M-10, Sheet COV Composite Flow Diagram Auxiliary Cooling Component 29

Cooling System P&ID

11405-M-253, Sheet 1 Condensate Flow Diagram Steam Generator Feedwater 92

and Blowdown P&ID

11405-M-253, Sheet 2 Condensate Flow Diagram Steam Generator Feedwater 24

and Blowdown P&ID

11405-M-253, Sheet 3 Condensate Flow Diagram Steam Generator Feedwater 16

and Blowdown P&ID

11405-M-253, Sheet 4 Condensate Flow Diagram Steam Generator Feedwater 39

and Blowdown P&ID

A-2 Attachment

Section 1RO4: Equipment Alignment

DRAWINGS

NUMBER TITLE REVISION

11405-M-253, Sheet COV Condensate Flow Diagram Steam Generator Feedwater 46

and Blowdown P&ID

11405-M-263, Sheet 1 Flow Diagram Compressed Air P&ID 69

11405-M-263, Sheet 2 Flow Diagram Compressed Air P&ID 26

11405-M-263, Sheet COV Composite Flow Diagram Compressed Air P&ID 41

11405-M-264, Sheet 1 Flow Diagram Instrument Air Diagram Aux Building & 61

Containment P&ID

11405-M-264, Sheet COV Composite Flow Diagram Instrument Air Diagram Aux 30

Building & Containment P&ID

B120F04002, Sheet 1 Jacket Water Schematic for DG-1 P&ID 25

B120F07001, Sheet 1 Starting Air System Schematic for DG-1 (Rm 63) P&ID 34

D-4665 DG-1 Diesel Generator One Line Diagram P&ID 6

E-23866-210-130, Sheet 1 Safety Injection and Containment Spray System Flow 100

Diagram P&ID

E-23866-210-130, Sheet 2 Safety Injection and Containment Spray System Flow 64

Diagram P&ID

E-23866-210-130, Sheet 2A Safety Injection and Containment Spray System Flow 20

Diagram P&ID

E-23866-210-130, Sheet 2B Safety Injection and Containment Spray System Flow 12

Diagram P&ID

E-23866-210-130, Sheet 3 Safety Injection and Containment Spray System Flow 18

Diagram P&ID

E-23866-210-130, Sheet Composite Flow Diagram Safety Injection and 53

COV Containment Spray System P&ID

A-3 Attachment

PROCEDURES

NUMBER TITLE REVISION

OI-AFW-1 Auxiliary Feedwater Actuation System Normal Operation 72

OI-CA-1 Compressed Air Normal Operation 62

OI-CC-1 Operating Instruction, Component Cooling System Normal Operation 65

OI-DG-1 Diesel Generator No. 1 47

OI-SC-1 Operating Instruction, Shutdown Cooling Initiation 48

OI-SI-1 Operating Procedure, Safety Injection - Normal Operation 115

OP-1 Operating Procedure, Master Checklist For Plant Startup 97

Section 1RO5: Fire Protection

PROCEDURES

NUMBER TITLE REVISION

AOP-6 Fire Emergency 21

EA-FC-97-001 Fire Hazards Analysis Manual 14

SO-G-28 Standing Order, Station Fire Plan 76

SO-G-58 Standing Order, Control of Fire Protection System Impairments 36

SO-G-91 Standing Order, Control and Transportation of Combustible 25

Materials

SO-G-102 Standing Order, Fire Protection Program Plan 8

SO-G-103 Standing Order, Fire Protection Operability Criteria And 23

Surveillance Requirements

FC05814 UFHA Combustible Loading 8

AOP-6-01 Fire Emergency, Auxiliary Building Radiation Controlled Areas 1

and Containment

AOP-6-02 Fire Emergency, Uncontrolled Areas of Auxiliary Building 0

AOP-6-03 Fire Emergency, Miscellaneous Areas 0

USAR 9.11 Updated Safety Analysis Report Fire Protection Systems 19

DRAWINGS

NUMBER TITLE REVISION

D-4147, Sheet 1 Containment & Auxiliary Building Elevation 1036 Portable Fire 8

Extinguisher Locations

A-4 Attachment

DRAWINGS

NUMBER TITLE REVISION

D-4147, Sheet 1 Containment & Auxiliary Building Roof Elevations Portable Fire 0

Extinguisher Locations

D-4147, Sheet 2 Auxiliary Building & Containment Elevation 1025-0 Portable Fire 6

Extinguisher Locations

Section 1R11: Licensed Operator Requalification Program

MISCELLANEOUS DOCUMENTS

TITLE DATE

Class Attendance Records for Simulator Evaluations September 8, 2008

Current operator license list from Fort Calhoun Station

Current Simulator Differences List

Open Simulator Discrepancy Reports (All)

Section 1R12: Maintenance Effectiveness

CONDITION REPORTS

200604163

PROCEDURES

NUMBER TITLE REVISION

PBD-16 Program Basis Document, Maintenance Rule 8

PED-SEI-34 Maintenance Rule Program 6

MISCELLANEOUS DOCUMENTS

Maintenance Rule Scoping Data Sheet CNTSMP

Maintenance Rule Scoping Data Sheet TSCBLG

Maintenance Rule Scoping Data Sheet TSCVAC

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

Work Orders

00326453 00335922 00331001

A-5 Attachment

PROCEDURES

NUMBER TITLE REVISION

DATE

ANSI N18.7 Administrative Controls for Nuclear Power Plants 1972

NOD-QP-36 Grid Operations and Control of Switchyard at Fort Calhoun Station 18

SO-M-100 Standing Order, Conduct of Maintenance 52

SO-M-101 Standing Order, Maintenance Work Control 83

MISCELLANEOUS DOCUMENTS

TITLE DATE

Summary of scheduled activities affecting plant risk week of July 20, 2009

Summary of scheduled activities affecting plant risk week of August 17, 2009

Summary of scheduled activities affecting plant risk week of Sept 6, 2009

Section 1R15: Operability Evaluations

Condition Reports

200303491 200303522 2009-2997 2009-3113 2009-3661

2009-3702 2009-3792

PROCEDURES

NUMBER TITLE REVISION

AOP-12 Loss of Containment Integrity 6

NOD-QP-31 Operability Determination Process (ODP) 40

OP-ST-DG-0001 Diesel Generator 1 Check 65

TDB VIII Technical Data Book, Equipment Operability Guidance 40

DRAWINGS

NUMBER TITLE REVISION

11405-M-252, Sheet COV Composite Flow Diagram Main Steam P&ID 42

11405-M-252, Sheet 1 Flow Diagram Steam P&ID 100

11405-M-252, Sheet 2 Flow Diagram Steam P&ID 14

11405-M-252, Sheet 3 Flow Diagram Steam P&ID 23

A-6 Attachment

MISCELLANEOUS DOCUMENTS

TITLE REVISION

ANSI B302.2.0-1976, Overhead and Gantry Cranes (Top Running Bridge, Multiple

Girder)

Updated Safety Analysis Report Section 9.4, Auxiliary Feedwater System 17

Various Control Room Operating Logs

Section 1R18: Plant Modifications

MISCELLANEOUS DOCUMENTS DATE

Temporary Modification Number EC47000, Soft Patch on 18 E Trash Grid August 24, 2009

Backwash Piping (CW System),

Section 1R19: Post Maintenance Testing

WORK ORDERS

00240532 00247270 00286329 00312810 00339628

003348570

PROCEDURES

NUMBER TITLE REVISION

IC-RR-VX-0409 Diagnostic Testing of Air Operated Valves 0

IC-ST-CCW-3001 Instrument Air Accumulator Check Valve Operability Test 7

IC-ST-IA-3010B Accumulator, Check Valve and Trip Valve Testing for Train 0

B 400 Series Containment Fan Cooler Inlet and Outlet

Valves

MD-AD-0013 Post Maintenance Testing Selection Instructions 3

MM-RR-CH-001 Inspection and Repair of Charging Pump Hydraulic Section 7

OP-ST-CCW-3001A Component Cooling Category B Valve Exercise Test 13

OP-ST-CCW-3005A Component Cooling Category A and B Valve Exercise Test 10

(for the A and B valves)

OP-ST-CH-3003 Chemical & Volume Control System Pump/Check Valve 51

Inservice Test

OP-ST-VX-3005A Component Cooling Water System Remote Position 4

Indicator Verification Surveillance Test

OP-ST-VX-3007A Component Cooling Water System Remote Position 3

Indicator Verification Surveillance Test

A-7 Attachment

PROCEDURES

NUMBER TITLE REVISION

PE-RR-VX-0424 Inspection and repair of Dresser industries Hancock Type 4

7150/7250 Globe valves

SO-M-100 Standing Order, Conduct of Maintenance 52

SO-M-101 Standing Order, Maintenance Work Control 84

DRAWINGS

NUMBER TITLE REVISION

11405-M-10, Sheet 1 Auxiliary Cooling Component Cooling System 66

Flow Diagram P&ID

11405-M-10, Sheet 2 Auxiliary Cooling Component Cooling System 17

Flow Diagram P&ID

11405-M-10, Sheet 3 Auxiliary Cooling Component Cooling System 24

Flow Diagram P&ID

11405-M-10, Sheet 4 Auxiliary Cooling Component Cooling System 11

Flow Diagram P&ID

11405-M-10, Sheet COV Composite Flow Diagram Auxiliary Cooling 29

Component Cooling System P&ID

11405-M-40, Sheet 1 Auxiliary Cooling Component Cooling System 36

P&ID

11405-M-40, Sheet 2 Auxiliary Cooling Component Cooling System 34

P&ID

11405-M-40, Sheet 3 Auxiliary Cooling Component Cooling System 23

P&ID

11405-M-40, Sheet COV Composite Flow Diagram Auxiliary Cooling 9

Component Cooling System P&ID

E-23866- 2A210-120, Sheet 2B Chemical & Volume Control System P&ID 18

E-23866-210-120, Sheet 1 Chemical & Volume Control System P&ID 70

E-23866-210-120, Sheet 1A Chemical & Volume Control System P&ID 22

E-23866-210-120, Sheet 2A Chemical & Volume Control System P&ID 13

A-8 Attachment

DRAWINGS

NUMBER TITLE REVISION

E-23866-210-120, Sheet COV Composite Flow Diagram Chemical & Volume 42

Control System P&ID

E-23866-210-121, Sheet 1 Chemical & Volume Control System P&ID 50

E-23866-210-121, Sheet 2 Chemical & Volume Control System P&ID 13

E-23866-210-121, Sheet COV Composite Flow Diagram Chemical & Volume 13

Control System P&ID

Section 1R22: Surveillance Testing

CONDITION REPORTS

2009-3677 2009-0285 2009-0487 2009-0507 2009-1023

2009-1035 2009-1111 2009-2477 2009-3766

PROCEDURES

NUMBER TITLE REVISION

IC-ST-SA-3001B Starting Air Compressors Discharge Check Valve Exercise 0

Test

OI-CC-1 Component Cooling System Normal Operation 65

OP-ST-CCW-3001A Component Cooling Category B Valve Exercise Test 13

OP-ST-CCW-3005B Component Cooling Category A And B Valve Exercise Test 15

(for the C and D valves)

OP-ST-CCW-3022 AC-3C Component Cooling Water Pump Inservice Test 16

PBD-2 Program Basis Document, Inservice Inspection Program 11

PED-QP-33 Inservice Inspection and Inservice Test Program 7

SO-G-23 Standing Order, Surveillance Test Program 54

DRAWINGS

NUMBER TITLE REVISION

11405-M-10, Sheet 1 Auxiliary Cooling Component Cooling System Flow 66

Diagram P&ID

11405-M-10, Sheet 2 Auxiliary Cooling Component Cooling System Flow 17

Diagram P&ID

A-9 Attachment

11405-M-10, Sheet 3 Auxiliary Cooling Component Cooling System Flow 24

Diagram P&ID

11405-M-10, Sheet 4 Auxiliary Cooling Component Cooling System Flow 11

Diagram P&ID

11405-M-10, Sheet COV Composite Flow Diagram Auxiliary Cooling Component 29

Cooling System P&ID

B120F070001, Sheet 2 DG-2 Starting Air System 25

MISCELLANEOUS DOCUMENTS

TITLE Revision

Apparent Cause Analysis Report, Air Leak on Positioner for HCV-400C, CCW Outlet 1

Valve, Condition Report 2009-0487

Apparent Cause Analysis Report, VA-1A CCW Outlet Valve, HCV-400C, Failed to 0

Close During OP-ST-CCW-3005B, Condition Report 2009-1023

Updated Safety Analysis Report Section 4.5, Reactor Coolant System Test and 14

Inspections

Updated Safety Analysis Report Section 6.5, Engineered Safeguards Specific 15

References

Updated Safety Analysis Report Section 9.7, Component Cooling Water System 15

Section 1EP1: Exercise Evaluation

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION/DATE

Lesson Plan 1070-011: Exercise Controller and Evaluator 5

Training Student Handbook

Emergency Plan Implementation Refresher (Slide Show)

EP-08-022 Drill Evaluation Report: February 5, 2008

EP-08-066 Drill Evaluation Report: June 24, 2008

EP-08-129 Drill Evaluation Report: August 26, 2008

EP-08-185 Drill Evaluation Report: Hostile Action Drill November 6, 2008

EP-09-044 Drill Evaluation Report: First Quarter 2009 Training Drills January 20, 27,

and

February 10, 2009

A-10 Attachment

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION/DATE

EP-09-070 Drill Evaluation Report: May 19, 2009

EPIP-EOF-1 Activation of the Emergency Operations Facility 18

EPIP-EOF-21 Potassium Iodide Issuance 8

EPIP-EOF-6 Dose Assessment 38

EPIP-EOF-7 Protective Action Guides 19

EPIP-OSC-1 Emergency Classification 46

EPIP-OSC-15 Communicator Actions 23

EPIP-OSC-2 Command and Control Position Actions and Notifications 50

EPIP-OSC-21 Activation of the Operations Support Center 21

EPIP-OSC-9 Emergency Team Briefings 13

EPIP-RR-11 Technical Support Center Director Actions 17

EPIP-RR-21 Operations Support Center Director Actions 17

EPIP-TSC-1 Activation of the Technical Support Center 31

EPIP-TSC-8 Core Damage Assessment 19

FCSG-32 Work Week Management 18

CORRECTIVE ACTION DOCUMENTS

2009-1454 2009-2537 2009-3308 2009-3320 2009-3324

2009-3330 2009-3403

Section 4OA1: Performance Indicator Verification

PROCEDURE/DOCUMENTS

NUMBER TITLE REVISION/DATE

Condition Report 2009-0687 February 13, 2009

EPDM-14 Emergency Preparedness Performance Indicator Program 11

EPIP-EOF-7 Protective Action Guides 18,19

EPIP-OSC-1 Emergency Classification 44, 45, 46

EPIP-OSC-2 Command and Control Position Actions and Notifications 50

EPT-1 Alert Notification System Silent Test 15, 16

EPT-2 Alert Notification System Growl Test 19, 20

EPT-3 Alert Notification System Complete Cycle Test 14, 15

A-11 Attachment

MISCELLANEOUS DOCUMENTS

NUMBER TITLE REVISION

TDB-IV.7 Technical Data Book, Process Monitor Setpoints 215

CONDITION REPORTS

2008-4506 2008-4516 2008-4517 2008-4518 2008-4551

2008-4626 2008-4659 2008-4662 2008-4707 2008-4711

2008-4716 2008-4765 2008-4767 2008-4800 2008-4943

2008-4973 2008-5030 2008-5048 2008-5064 2008-5065

2008-5086 2008-5087 2008-5104 2008-5155 2008-5160

2008-5172 2008-5186 2008-5201 2008-5218 2008-5224

2008-5238 2008-5256 2008-5272 2008-5281 2008-5381

2008-5382 2008-5383 2008-5384 2008-5386 2008-5387

2008-5388 2008-5475 2008-5477 2008-5497 2008-5529

2008-5558 2008-5607 2008-5623 2008-5641 2008-5667

2008-5674 2008-5695 2008-5741 2008-5793 2008-5797

2008-5833 2008-5848 2008-5986 2008-6022 2008-6065

2008-6112 2008-6135 2008-6143 2008-6326 2008-6335

2008-6350 2008-6429 2008-6439 2008-6460 2008-6470

2008-6503 2008-6548 2008-6550 2008-6590 2008-6649

2008-6753 2008-6763 2008-6770 2008-6781 2008-6794

2008-6800 2008-6833 2008-6836 2008-6838 2008-6924

2008-6941 2008-6966 2008-6985 2008-7010 2008-7060

2008-7075 2008-7083 2008-7085 2008-7086 2008-7111

2008-7251 2008-7257 2009-0031 2009-0089 2009-0092

2009-0102 2009-0109 2009-0135 2009-0209 2009-0250

2009-0329 2009-0339 2009-0409 2009-0413 2009-0424

2009-0470 2009-0475 2009-0480 2009-0536 2009-0540

2009-0541 2009-0550 2009-0552 2009-0559 2009-0596

2009-0608 2009-0639 2009-0724 2009-0729 2009-0760

2009-0763 2009-0791 2009-0833 2009-0871 2009-0872

2009-0882 2009-0902 2009-0903 2009-0905 2009-0947

2009-0948 2009-0984 2009-1001 2009-1080 2009-1082

2009-1179 2009-1272 2009-1378 2009-1406 2009-1413

2009-1461 2009-1471 2009-1476 2009-1477 2009-1478

2009-1493 2009-1503 2009-1603 2009-1611 2009-1611

2009-1622 2009-1625 2009-1656 2009-1683 2009-1686

2009-1690 2009-1706 2009-1713 2009-1717 2009-1729

2009-1750 2009-1802 2009-1812 2009-1817 2009-1818

2009-1821 2009-1865 2009-1873 2009-1891 2009-1899

2009-1900 2009-1922 2009-1935 2009-2005 2009-2017

2009-2023 2009-2024 2009-2025 2009-2029 2009-2037

2009-2069 2009-2111 2009-2123 2009-2165 2009-2194

2009-2205 2009-2219 2009-2238 2009-2247 2009-2265

2009-2275 2009-2278 2009-2283 2009-2298 2009-2304

2009-2438 2009-2465 2009-2466 2009-2468 2009-2537

2009-2601 2009-2613 2009-2614 2009-2615 2009-2617

2009-2677 2009-2690 2009-2803 2009-2866 2009-2867

A-12 Attachment

CONDITION REPORTS

2009-2901 2009-2902 2009-2904 2009-2979 2009-2990

2009-3006 2009-3019

MISCELLANEOUS DOCUMENTS

TITLE REVISION/DATE

MSPIBD, Mitigating Systems Performance Index Basis 1

Document for Fort Calhoun Station

NEI 99-02, Regulatory Assessment Indicator Guideline 5

Procedure NOD-QP-37, Performance Indicators Program 16

Various Operator logs July 1, 2008 through June 30, 2009

Section 4OA2: Identification and Resolution of Problems

CONDITION REPORTS

2008-5514 2008-6481 2008-6511 2008-6485 2008-7425

2009-0181 2009-0019 2008-6824 2009-1446 2009-2070

2009-2096 2009-2118 2009-2607 2009-2614 2009-2892

2009-2732 2009-2997 2009-3002 2009-3063 2009-3089

2009-3108 2009-3113 2009-3148 2009-3186 2009-3243

2009-3177 2009-3915 2009-2466 2009-2468 2009-4236

2009-3294 2009-3300 2009-3305 2009-3394 2009-3476

2009-3501 2009-3507 2009-3547 2009-3570 2009-3576

2009-3583 2009-3622 2009-3802 2009-3843 2009-4031

2009-4257 2009-4258 2009-4308 2008-4922 2008-4936

2009-4521 2009-3873 200503564 200606023 2008-4865

2009-3964

WORK ORDERS

00263046 00345039

PROCEDURES

NUMBER TITLE REVISION

FCSG-45 Operator Challenge Program 2

GM-OI-HE-2 Auxiliary Building Crane Normal Operation 18

MISCELLANEOUS DOCUMENTS

TITLE REVISION/DATE

ANSI B302.2.0-1976, Overhead and Gantry Cranes (Top Running Bridge,

Multiple Girder)

A-13 Attachment

MISCELLANEOUS DOCUMENTS

TITLE REVISION/DATE

Dry Fuel Storage Recovery Action Plan July 2, 2009

EC41654, Site Acceptance Test, OPPD Fort Calhoun Aux Building 106 Ton X- 0

SAM Crane Upgrade

FC07539, NUHOMS 32PT-S100 Operational Lift Weight Calculation with 0

OS197-3 (OS197H) Cask

NUREG 0554, Single-Failure Proof Cranes for Nuclear Power Plants May, 1979

Operator Challenge List

Root Cause Analysis Report, HE-2, Auxiliary Building Crane Contacting FH- 0

12, Spent Fuel Handling Machine, Condition Report 2009-3302

Section 4OA5: Other Activities

CONDITION REPORTS

2007-1082 2007-1525 2008-4253 2008-6668 2009-0569

2009-1039 2009-2269 2009-2363 2009-2625 2009-2888

2009-2988 2009-3062

PROCEDURES

NUMBER TITLE REVISION

GM-OI-HE-2 Auxiliary Building Crane Normal Operation 20

OP-12 Fueling Operations 55

RE-AD-0005 Fuel Selection and DSC Planning for Dry Cask Storage 2

RE-RR-DFS-0001 DSC/TC Prep for Fuel Loading Operations 5

RE-RR-DFS-0002 Dry Shielded Canister Sealing Operations 8

RE-RR-DFS-0003 Loaded DSC/TC from Auxiliary building to ISFSI Operations 7

RE-RR-DFS-0004 DSC from TC to HSM Transfer Operations 6

MISCELLANEOUS DOCUMENTS

NUMBER TITLE REVISION

Fort Calhoun Station Independent Spent Fuel Storage 1

Installation 10 CFR 72.212 Evaluation Report, Docket 72-054

1004 Certificate of Compliance for Spent Fuel Storage Casks, 9

Docket 72-1004

1004 Attachment A Technical specifications - Transnuclear, Standardized 9

NUHOMS Horizontal Modular Storage System, Docket

72-1004

LR 721004-399 10 CFR 72.48 Applicability and 10 CFR 71 Review Form 1

A-14 Attachment

A-15 Attachment