Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application (TAC MD6593, MD6594, MD6595, MD6596)
ML092610522
Person / Time
Site: Beaver Valley
Issue date: 09/28/2009
From: Kent Howard
License Renewal Projects Branch 2
To: Sena P
FirstEnergy Nuclear Operating Co
Howard K, NRR/DLR/RPB2, 415-2989
References
TAC MD6593, TAC MD6594, TAC MD6595, TAC MD6596
Download: ML092610522 (6)


Text

September 28, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593, MD6594, MD6595 AND MD6596)

Dear Mr. Sena:

Enclosed is a revised schedule for the review of the Beaver Valley Power Station, Units 1 and 2, license renewal application. This schedule has been revised to reflect schedule changes for the Beaver Valley Power Station license renewal application in order for the staff to evaluate the containment liner degredation operating experience. If you have any questions on the revised schedule, please contact me by telephone at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov.

Sincerely,

\RA\

Kent L. Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosure:

As stated cc w/encl: See next page

ML092610522 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR NAME SFigueroa KHoward DWrona *

(by phone)

DATE 09/21/09 09/22/09 09/28/09

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestones Schedule Actual Receive License Renewal (LR) Application 08/27/07 08/28/07 FRN Published- Receipt & Availability 09/24/07 09/24/07 FRN Published - Acceptability/Opportunity for Hearing and Intent/

10/26/07 10/26/07 Environmental Scoping Meeting FRN Published-Notice of Intent to Conduct Environmental Scoping 11/02/07 11/05/07 Audit - Environmental 11/13/07 11/13/07 Public Meeting - LR Overview & Environmental Scoping 11/27/07 11/27/07 Audit - Scoping & Screening Methodology 12/03/07 12/03/07 Deadline for Filing Hearing Requests and Petitions for Intervention 12/26/07 12/26/07 Environmental Scoping Period Ends 01/02/08 01/07/08 Environmental Requests for Additional Information (RAIs) Issued 02/04/08 02/04/08 Audit - Aging Management Programs (AMPs/AMR/TLAAs) 03/03/08 03/03/08 Environmental RAIs - Response Received 03/05/08 03/03/08 Audit - Aging Management Reviews (AMRs) Canceled Canceled Audit - 3rd Optional AMP/TLAA/AMR 06/23/08 Canceled Inspection - Regional 06/23/08 06/23/08 Safety RAIs - Issued 06/30/08 06/30/08 Safety RAI - Responses Received 07/30/08 07/30/08 Public Exit Meeting - Regional Inspections 11/12/08 11/12/08 Draft Supplemental Environmental Impact Statement (SEIS) - Issued 09/17/08 09/19/08 EPA FRN Published - Availability / Comment on draft SEIS 09/25/08 09/24/08 Public Meeting - draft SEIS 10/30/08 10/30/08 End of draft SEIS Comment Period 12/03/08 12/17/08 Safety Evaluation Report (SER) with Open Items - Issued 12/29/08 01/09/09 Inspection - Final Optional TBD N/A ACRS Subcommittee Meeting on SER with Open Items 02/04/09 02/04/09 SER with Open Items - Responses Received 03/24/09 03/24/09 Final SEIS - Issued 05/13/09 05/14/09 Enclosure

EPA FRN Published - Availability of Final SEIS 05/22/09 05/21/09 SER - Issued 05/29/09* 06/08/09 ACRS Full Committee Meeting #1 on SER 07/08/09 07/08/09 ACRS Full Committee Meeting #2 on SER 09/11/09 09/11/09 ACRS Letter - Issued 09/16/09* 09/16/09 Supplemental SER - Issued 09/29/09 Regional Administrator's letter - Issued 10/01/09*

Staff Recommendation to Director, NRR 10/30/09*

Decision Director NRR - Approval 11/05/09*

  • Revised Dates

Letter to P.Sena III from K. Howard, dated September 28, 2009 DISTRIBUTION:

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593, MD6594, MD6595 AND MD6596)

HARD COPY:

DLR RF E-MAIL:

PUBLIC [or NON-PUBLIC, if applicable RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource


KHoward NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan Manager, Fleet Licensing President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Mail Stop A-GO-19 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Director, Fleet Regulatory Affairs James H. Lash FirstEnergy Nuclear Operating Company Senior Vice President of Operations Mail Stop A-GO-2 and Chief Operating Officer 76 South Main Street FirstEnergy Nuclear Operating Company Akron, OH 44308 Mail Stop A-GO-14 76 South Main Street Manager, Site Regulatory Compliance Akron, OH 44308 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Danny L. Pace Mail Stop A-BV-A Senior Vice President, Fleet Engineering P.O. Box 4, Route 168 FirstEnergy Nuclear Operating Company Shippingport, PA 15077 Mail Stop A-GO-14 76 South Main Street Regional Administrator, Region I Akron, OH 44308 U.S. Nuclear Regulatory Commission 475 Allendale Road Jeannie M. Rinckel King of Prussia, PA 19406 Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Resident Inspector Mail Stop A-GO-14 U.S. Nuclear Regulatory Commission 76 South Main Street P.O. Box 298 Akron, OH 44308 Shippingport, PA 15077 Paul A. Harden Cliff Custer Vice President, Nuclear Support FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-14 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Steve Dort David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation Beaver Valley Power Station Mail Stop A-GO-15 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077