ML092920050
| ML092920050 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 11/05/2009 |
| From: | Leeds E Office of Nuclear Reactor Regulation |
| To: | |
| Howard K, NRR/DLR, 415-2989 | |
| Shared Package | |
| ML092920015 | List: |
| References | |
| TAC MD6593 | |
| Download: ML092920050 (10) | |
Text
Renewed Operating License NPF-73 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 FIRSTENERGY NUCLEAR OPERATING COMPANY FIRSTENERGY NUCLEAR GENERATION CORP.
OHIO EDISON COMPANY THE TOLEDO EDISON COMPANY DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT 2 RENEWED FACILITY OPERATING LICENSE License No. NPF-73
- 1.
The Nuclear Regulatory Commission (the Commission or the NRC) has found that:
A.
The application to renew Facility Operating License No. NPF-73 filed by FirstEnergy Nuclear Operating Company (FENOC)* acting on its own behalf and as agent for FirstEnergy Nuclear Generation Corp., Ohio Edison Company, and The Toledo Edison Company (the licensees), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I, and all required notifications to other agencies or bodies have been duly made; B.
Construction of the Beaver Valley Power Station, Unit 2 (the facility), has been substantially completed in conformity with Construction Permit No. CPPR-105 and the application, as amended, the provisions of the Act, and the regulations of the Commission; C.
The facility will operate in conformity with the application, the provisions of the Act, and the regulations of the Commission (except as exempted from compliance in Section 2.D. below);
D.
There is reasonable assurance: (i) that the activities authorized by this renewed operating license can be conducted without endangering the health and safety of the public and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below);
- FENOC is authorized to act as agent for FirstEnergy Nuclear Generation Corp., Ohio Edison Company, and The Toledo Edison Company and has exclusive responsibility and control over the physical construction, operation, and maintenance of the facility.
Renewed Operating License NPF-73 E.
FENOC is technically qualified to engage in the activities authorized by this renewed operating license in accordance with the Commission's regulations set forth in 10 CFR Chapter I; F.
The licensees have satisfied the applicable provisions of 10 CFR Part 140, "Financial Protection Requirements and Indemnity Agreements," of the Commission's regulations; G.
The issuance of this renewed operating license will not be inimical to the common defense and security or to the health and safety of the public; H.
After weighing the environmental, economic, technical, and other benefits of the facility against environmental and other costs and considering available alternatives, the issuance of this Renewed Operating License No. NPF-73 is subject to the conditions for protection of the environment set forth in the Environmental Protection Plan attached as Appendix B, is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied; I.
The receipt, possession and use of source, byproduct and special nuclear material as authorized by this license will be in accordance with the Commission's regulations in 10 CFR Parts 30, 40, and 70.
J.
Actions have been identified and have been or will be taken with respect to: (1) managing the effects of aging on the functionality of structures and components that have been identified to require review under 10 CFR 54.21(a)(1) during the period of extended operation, and (2) time-limited aging analyses that have been identified to require review under 10 CFR 54.21(c), such that there is reasonable assurance that the activities authorized by this renewed operating license will continue to be conducted in accordance with the current licensing basis, as defined in 10 CFR 54.3 for the facility, and that any changes made to the facilitys current licensing basis in order to comply with 10 CFR 54.29(a) are in accordance with the Act and the Commissions regulations;
- 2.
Renewed Facility Operating License NPF-73 is hereby issued to FENOC, FirstEnergy Nuclear Generation Corp., Ohio Edison Company, and The Toledo Edison Company (the licensees) to read as follows:
A.
This renewed license applies to the Beaver Valley Power Station, Unit 2, a pressurized water reactor and associated equipment (the facility), owned by FirstEnergy Nuclear Generation Corp. (owner), leased to Ohio Edison Company (lessee), and The Toledo Edison Company (lessee) and operated by FENOC (collectively the licensees). The facility is located on the licensees' site on the southern shore of the Ohio River in Beaver County, Pennsylvania, approximately 22 miles northwest of Pittsburgh and 5 miles east of East Liverpool, Ohio, and is described in FENOC's Updated Final Safety Analysis Report, as supplemented and amended, and in its Environmental Report, as supplemented and amended; B.
Subject to the conditions and requirements incorporated herein, the Commission hereby licenses:
(1)
Pursuant to Section 103 of the Act and 10 CFR Part 50, FENOC to possess, use, and operate the facility at the designated location in Beaver County, Pennsylvania, in accordance with the procedures and limitations set forth in this license;
Renewed Operating License NPF-73 (2)
Pursuant to the Act and 10 CFR Part 50, FirstEnergy Nuclear Generation Corp., Ohio Edison Company, and The Toledo Edison Company to possess the facility at the designated location in Beaver County, Pennsylvania, in accordance with the procedures and limitations set forth in the license; (3)
Pursuant to the Act and 10 CFR Part 70, FENOC, to receive, possess, and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Updated Final Safety Analysis Report, as supplemented and amended; (4)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, FENOC to receive, possess, and use at any time any byproduct, source, and special nuclear material such as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, FENOC to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or other activity associated with radioactive apparatus or components; (6)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, FENOC to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility authorized herein.
(7)
(a)
Ohio Edison Company and The Toledo Edison Company are authorized to transfer any portion of their respective leased interests in BVPS Unit 2 and a proportionate share of their leased interests in the BVPS common facilities to certain potential investors identified in their submittals of July 14, 16, 22 and 31, and September 14, 17 and 18, 1987, and at the same time to lease back from such purchasers such interest transferred in the BVPS Unit 2 facility. The term of the lease is for approximately 29-1/2 years subject to a right of renewal. Such sale and leaseback transactions are subject to the representations and conditions set forth in the aforementioned submittals. Specifically, a lessor and anyone else who may acquire an interest under these transactions are prohibited from exercising directly or indirectly any control over the license of BVPS Unit 2. For purposes of this condition the limitations in 10 CFR 50.81, as now in effect and as may be subsequently amended, are fully applicable to the lessor and any successor in interest to that lessor as long as the license for BVPS Unit 2 remains in effect; these financial transactions shall have no effect on the license for the BVPS Unit 2 facility throughout the term of the license.
Renewed Operating License NPF-73 (b)
Further, the licensees are also required to notify the NRC in writing prior to any change in: (i) the term or conditions of any lease agreements executed as part of these transactions; (ii) the BVPS Operating Agreement, (iii) the existing property insurance coverage for BVPS Unit 2, and (iv) any action by a lessor or others that may have adverse effect on the safe operation of the facility.
C.
This renewed operating license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations set forth in 10 CFR Chapter 1 and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level FENOC is authorized to operate the facility at a steady state reactor core power level of 2900 megawatts thermal.
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 170, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto are hereby incorporated in the license. FENOC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
Renewed Operating License NPF-73 (3)
Initial Startup Test Program (Section 14 of the SER, and Supplements 3 and 5)
Deleted (4)
Fresh Fuel Storage The following criteria apply to the storage and handling of new fuel assemblies in the fuel handling building:
(a)
No more than two fuel assemblies shall be out of approved shipping containers or fuel assembly storage racks at any one time.
(b)
The minimum edge-to-edge distance between the above two new assemblies, the shipping container array, and the storage rack arrays shall be at least 12 inches.
(c)
New fuel assemblies shall be stored in such a manner that water would drain freely from the assemblies in the event of flooding and subsequent draining of the fuel storage area.
(5)
Inservice Inspection (Section 6.6 of SER Supplement 5)
Deleted (6)
Formal Federal Emergency Management Agency Finding In the event that the NRC finds that the lack of progress in completion of the procedures in the Federal Emergency Management Agency's final rule, 44 CFR Part 350, is an indication that a major substantive problem exists in achieving or maintaining an adequate state of emergency preparedness, the provisions of 10 CFR Section 50.54(s)(2) will apply.
(7)
Plant Safety Monitoring System (PSMS)
Deleted
Renewed Operating License NPF-73 (8)
Detailed Control Room Design Review (DCRDR)
Deleted (9)
Safety Parameter Display System (SPDS)
Deleted (10)
Fire Protection Modifications (Section 9.5.1 of SER Supplement 6)
Deleted (11)
Additional Conditions The Additional Conditions contained in Appendix D, as revised through Amendment No. 163, are hereby incorporated into this license. FENOC shall operate the facility in accordance with the Additional Conditions.
(12)
Steam Generator Surveillance Interval Extension Deleted (13)
Mitigation Strategy License Condition The licensee shall develop and maintain strategies for addressing large fires and explosions and that include the following key areas:
(a)
Fire fighting response strategy with the following elements:
- 1.
Pre-defined coordinated fire response strategy and guidance
- 2.
Assessment of mutual aid fire fighting assets
- 3.
Designated staging areas for equipment and materials
- 4.
Command and control
- 5.
Training of response personnel (b)
Operations to mitigate fuel damage considering the following:
- 1.
Protection and use of personnel assets
- 2.
Communications
- 3.
Minimizing fire spread
- 4.
Procedures for implementing integrated fire response strategy
- 5.
Identification of readily-available pre-staged equipment
- 6.
Training on integrated fire response strategy
- 7.
Spent fuel pool mitigation measures (c)
Actions to minimize release to include consideration of:
- 1.
Water spray scrubbing
- 2.
Dose to onsite responders
Renewed Operating License NPF-73 D.
Exemptions The following exemptions are authorized by law and will not endanger life or property or the common defense and security, and certain special circumstances are present. With the granting of these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.
(1)
The facility requires an exemption from the requirements of General Design Criterion (GDC) 4, Appendix A to 10 CFR 50. The staff has described in detail in Supplement 4 and Supplement 5 to the Safety Evaluation Report the technical basis and "special circumstances" associated with this exemption. The staff's environmental assessment was published on March 27, 1987 (52 FR 9979). Therefore, pursuant to 10 CFR 50.12(a)(1), 10 CFR 50.12(a)(2)(ii) and (iv), Beaver Valley Power Station, Unit 2 is exempt from the requirements of GDC 4, Appendix A to 10 CFR 50 with respect to the dynamic loading effects associated with the postulated pipe breaks described in detail in Section 3.6.3 of Supplement 4 to the Safety Evaluation Report. These dynamic loading effects include pipe whip, jet impingement, and break-associated dynamic transients.
Specifically, this eliminates the need to install jet impingement barriers and pipe whip restraints associated with postulated pipe breaks in the pressurizer surge line, reactor coolant bypass system, safety injection system, and residual heat removal system. This exemption will expire when the current GDC 4 rulemaking changes have been completed.
Renewed Operating License NPF-73 (2)
The facility requires an exemption from the requirements of 10 CFR 50, Appendix J, Section III.D.2(b)(ii). The justification of this exemption is contained in Section 6.2.6 of Supplement 5 to the Safety Evaluation Report and modified by a letter dated July 26, 1995. The staff's environmental assessment was published on May 12, 1987 (52 FR 17651) and on June 9, 1995 (60 FR 30611). Therefore, pursuant to 10 CFR 50.12(a)(1) and 10 CFR 50.12(a)(2)(ii) and (iii), Beaver Valley Power Station, Unit 2 is exempt from the quoted requirements and instead, is required to perform the overall air lock leak test at pressure Pa before establishing containment integrity if air lock maintenance has been performed that could affect the air lock sealing capability. Local leak rate testing at a pressure of not less than Pa may be substituted for an overall air lock test where the design permits.
(3)
The facility was previously granted an exemption from the criticality alarm requirements of 10 CFR 70.24 (see License No. SNM-1954) dated April 9, 1986, which granted this exemption). Beaver Valley Power Station, Unit 2 is hereby exempted from the criticality alarm system provisions of 10 CFR 70.24 so far as this section applies to the storage of fuel assemblies held under this license.
E.
Physical Security FENOC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21 is entitled: "Beaver Valley Power Station (BVPS)
Physical Security Plan" submitted by letter September 9, 2004, and supplemented September 30, 2004, October 14, 2004, and May 12, 2006.
F.
Fire Protection Program (Section 9.5.1 of SER Supplement 3)
FENOC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report through Amendment No. 17, and submittals dated May 18, May 20, May 21, June 24 and July 6, 1987, and as described in the Safety Evaluation Report dated October 1985, and Supplements 1 through 6, subject to the following provision:
Renewed Operating License NPF-73 FENOC may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
G.
Reporting to the Commission DELETED H.
Financial Protection The licensee shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I.
License Renewal Commitments - The UFSAR supplement, as revised, submitted pursuant to 10 CFR 54.21(d), describes certain future activities to be completed prior to and/or during the period of extended operation. FENOC shall complete these activities in accordance with Appendix A of NUREG-1929, Safety Evaluation Report Related to the Beaver Valley Power Station, Units 1 and 2, dated October 2009, and Supplement 1 of NUREG-1929, dated October 2009, and shall notify the NRC in writing when activities to be completed prior to the period of extended operation are complete and can be verified by NRC inspection.
J.
UFSAR Supplement Changes - The information in the UFSAR supplement, as revised, submitted pursuant to 10 CFR 54.21(d), shall be incorporated into the UFSAR as required by 10 CFR 50.71(e) following the issuance of this renewed operating license. Until that update is complete, FENOC may not make changes to the information in the supplement. Following incorporation into the UFSAR, the need for prior Commission approval of any changes will be governed by 10 CFR 50.59.
K.
Capsule Withdrawal Schedule - For the renewed operating license term, all capsules in the reactor vessel that are removed and tested must meet the test procedures and reporting requirements of American Society for Testing and Materials (ASTM) E 185-82 to the extent practicable for the configuration of the specimens in the capsule. Any changes to the capsule withdrawal schedule, including spare capsules, must be approved by the NRC prior to implementation.
L.
Containment Liner Volumetric Inspection -
a) If degradation (greater than 10 percent of the nominal thickness not attributable to fabrication/erection practices) is identified in the non-random areas examined using ultrasonic testing (UT) as described in Supplement 1 of NUREG-1929, UT examinations shall be performed at additional non-random areas, to be selected based on this operating experience. Should additional degradation be identified, additional non-random areas shall be UT examined until no further degradation (greater than 10 percent of the nominal thickness) is identified. All areas with degradation shall be reexamined over at least the next three successive inspection periods to ensure that progression of the degradation is not occurring.
b) If degradation (greater than 10 percent of the nominal thickness not attributable to fabrication/erection practices) is identified in the random samples examined using ultrasonic testing (UT) as described in Supplement 1 of NUREG-1929, UT examinations shall be performed on additional random
Renewed Operating License NPF-73 samples, to ensure a 95 percent confidence that 95 percent of the unexamined accessible containment liner is not degraded. If additional degradation is identified, the sample size for UT examinations shall be further expanded until the statistical sampling has achieved the 95 percent confidence goal described previously. All areas with degradation shall be reexamined over at least the next three successive inspection periods to ensure that progression of the degradation is not occurring.
- 3.
Expiration This renewed operating license is effective as of the date of issuance and shall expire at midnight on May 27, 2047.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Eric J. Leeds, Director Office of Nuclear Reactor Regulation Attachments:
- 1.
Appendix A - Technical Specifications
- 2.
Appendix B - Environmental Protection Plan
- 3.
Appendix D - Additional Conditions Date of Issuance: November 05, 2009