Other: L-07-113, License Renewal Application. Appendix E: Applicants Environmental Report, L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System, L-08-189, Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass), L-08-261, Schedule for Submittal of Annual Update for License Renewal Application, L-08-262, License Renewal Application Amendment No. 23 and Revised License Renewal Boundary Drawings, L-08-263, Submittal of Revision to License Renewal Application Amendment No. 24, L-08-292, License Renewal Application Amendment No. 29 (Annual Update) and Revised License Renewal Application Boundary Drawing, L-08-316, License Renewal Application Amendment No. 26 (TAC Nos. MD6593 and MD6594), Revisions, L-08-393, License Renewal Application, Amendment No. 33, L-09-058, Comments on Safety Evaluation Report with Open Item Related to the License Renewal, L-09-138, License Renewal Application, Amendment No. 36, L-09-151, License Renewal Application Amendment No. 37, ML081000322, ML081000323, ML081000324, ML081000326, ML081000327, ML081000328, ML081000329, ML081000330, ML081000331, ML081000332, ML081640592, ML081640593, ML081640594, ML081640596, ML081640597, ML081640598, ML081640599, ML081640600, ML081640601, ML081640602, ML081640603, ML081640604, ML082550686, ML082550687, ML082550688, ML082550689, ML083010249, ML083040266, ML092740576, ML092920050, ML092920056, NRC-2009-0496, Beaver Valley Federal Register Notice - Record of Decision to Renew License
|
MONTHYEARL-07-113, License Renewal Application. Appendix E: Applicants Environmental Report2007-08-27027 August 2007 License Renewal Application. Appendix E: Applicants Environmental Report Project stage: Other L-07-130, Submittal of Pressure and Temperature Limits Report, Revision 42007-09-19019 September 2007 Submittal of Pressure and Temperature Limits Report, Revision 4 Project stage: Request ML0805902622008-03-0303 March 2008 Request for Additional Information, License Renewal Application Project stage: RAI ML0806402162008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 and 2, LRA Project stage: RAI ML0806010202008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807202882008-03-21021 March 2008 Request for Additional Information, Section B.2.35 Project stage: RAI ML0807907442008-03-26026 March 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application, for Sections B.2.6, B.2.19, and B.2.23 Project stage: RAI L-08-122, Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings2008-03-31031 March 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings Project stage: Response to RAI ML0807903922008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807905382008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI L-08-124, Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 52008-04-0202 April 2008 Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 5 Project stage: Response to RAI ML0807907352008-04-0303 April 2008 RAI for the Reveiw of the Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI ML0810002962008-04-0303 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application, Amendment No. 4, and Revised License Renewal Boundary Drawings Project stage: Response to RAI ML0810003222008-04-0303 April 2008 Drawing Lr 1-07-2, Rev. 4, Chemical and Volume Control System Project stage: Other ML0810003232008-04-0303 April 2008 Drawing Lr 1-07-3, Rev. 6, Chemical and Volume Control System Project stage: Other ML0810003242008-04-0303 April 2008 Drawing Lr 1-08-1, Rev. 4, Boron Recovery Degasifiers Project stage: Other ML0810003262008-04-0303 April 2008 Drawing Lr 1-09-2, Rev. 4, Vent and Drain System Project stage: Other ML0810003272008-04-0303 April 2008 Drawing Lr 1-12-1, Rev. 5, Containment Vacuum and Leakage Monitoring System Project stage: Other ML0810003282008-04-0303 April 2008 Drawing Lr 1-14A-1, Rev. 7, Sample System Project stage: Other ML0810003292008-04-0303 April 2008 Drawing Lr 1-14A-2, Rev. 5, Sample System Project stage: Other ML0810003302008-04-0303 April 2008 Drawing Lr 1-19-1, Rev. 5, Gaseous Waste Disposal System Project stage: Other ML0810003322008-04-0303 April 2008 Drawing Lr 1-30-1, Rev. 5, River Water System Project stage: Other L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System2008-04-0303 April 2008 Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System Project stage: Other ML0810003312008-04-0303 April 2008 Drawing Lr 1-24-1, Rev. 6, Feedwater System Project stage: Other ML0809804832008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810503332008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI L-08-143, Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 62008-04-18018 April 2008 Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 6 Project stage: Response to RAI L-08-144, Reply to Request for Additional Information for the Review of License Renewal Application2008-04-25025 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application Project stage: Response to RAI ML0811303942008-04-28028 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810502702008-04-30030 April 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI L-08-146, Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 72008-04-30030 April 2008 Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 7 Project stage: Response to RAI L-08-174, Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-0202 May 2008 Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-149, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-0505 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0814104162008-05-0808 May 2008 Transmittal of Correction to Reply to RAI for the Review of License Renewal Application, License Renewal Application Amendment No. 8 & Revised License Renewal Boundary Drawings Project stage: Request ML0810505432008-05-0808 May 2008 Request for Additional Information, Sections 3.5.2.2, B.2.1, B.2.3 and 4.6 of License Renewal Application Project stage: RAI ML0811604672008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0812009202008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0811205392008-05-15015 May 2008 Request for Additional Information, License Renewal Application Project stage: RAI ML0814405432008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Amendment No. 9. and Revised License Renewal Boundary Drawings Project stage: Response to RAI L-08-169, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0811304122008-05-22022 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0813605572008-05-22022 May 2008 Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0811505772008-05-28028 May 2008 Request for Additional Information for Sections B.2.27, 4.3 and 4.7.4 of the BVPS LRA Project stage: RAI L-08-180, Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-28028 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-147, Reply to Request for Additional Information for Renewal License Application2008-06-0202 June 2008 Reply to Request for Additional Information for Renewal License Application Project stage: Response to RAI ML0814306872008-06-0404 June 2008 Request for Additional Information the Review of Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI L-08-181, Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 102008-06-0606 June 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 10 Project stage: Response to RAI ML0816405972008-06-0909 June 2008 Drawing Lr 1-25-1, Rev. 5, Steam Generator Blowdown System (Bd) Project stage: Other L-08-189, Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass)2008-06-0909 June 2008 Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass) Project stage: Other ML0816406012008-06-0909 June 2008 Drawing Lr 2-14A-1, Rev. 6, Reactor Plant Sample System, (Ssr) Project stage: Other 2008-04-28
[Table View] |
Text
April 1, 2008 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND 6594)
Dear Mr. Sena:
By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted an application pursuant to 10 CFR Part 54, to renew the operating licenses for Beaver Valley Power Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with Mr. Cliff Custer of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-2989 or by e-mail at klh1@nrc.gov.
Sincerely,
/RA/
Kent L. Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosure:
As stated cc w/encl: See next page
ML080790392 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR w/comment NAME IKing KHoward RFranovich DATE 03/31/08 03/21/08 04/1/08 REQUEST FOR ADDITIONAL INFORMATION (RAI)
BEAVER VALLEY POWER STATION, UNIT 2 LICENSE RENEWAL APPLICATION MECHANICAL AND CIVIL ENGINEERING BRANCH SECTION 4.7.5 - SETTLEMENT OF STRUCTURES RAI 4.7.5-1 The applicant did not list the number and type of safety significant structures and piping which have experienced, or may experience, significant settlement, and are therefore included in the Settlement Monitoring Program. The applicant did not state which structures will be monitored to the end of the period of extended operation. This is relevant information for writing the safety evaluation.
For each structure included in the Settlement Monitoring Program, indicate if the structure is being monitored and if it will be monitored to the end of the period of extended operation.
RAI 4.7.5-2 This RAI addresses specifically which safety related piping systems will be monitored for differential settlement. For each system, the RAI requests that the applicant provide the projected differential settlements for the monitored piping systems, and the maximum projected stresses and allowable stresses, to verify that a margin will be available at the end of the period of extended operation.
Provide a list of the safety-related piping systems that are subject to differential structure settlement of the attached structures. For each piping system provide the following:
A.
The projected 40-year and 60-year differential settlement of the anchor points.
B.
The highest projected stresses for 40-years and 60-years of operation, and the corresponding allowable stress.
RAI 4.7.5-3 The applicant stated that settlement monitoring has been discontinued for a number of structures. This RAI requests which structures were discontinued, and the basis for discontinuing this monitoring. This information is needed to complete the staffs evaluation.
Provide a list of the structures that were initially in the Settlement Monitoring Program, and for which monitoring has been discontinued. Provide the basis for discontinuing the monitoring.
ENCLOSURE
RAI 4.7.5-4 The applicant did not mention that there is fatigue associated with the buried piping, and yet refers to Unit 2 piping fatigue Tables. This RAI requests that the applicant provide any missing information on this subject, or else justify the statement regarding piping time-limited aging analysis (TLAA).
The last sentence of Section 4.7.5 states that the Unit 2 piping fatigue TLAAs have been dispositioned in accordance with 10 CFR 54.21(c)(1)(iii). Identify the fatigue effects on the buried piping associated with piping settlement, and clarify how the piping fatigue TLAA for the buried piping was dispositioned.
Letter to P. Sena III from K. Howard, dated, April 1, 2008 DISTRIBUTION:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND 6594)
HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Drive Harrisburg, PA 17110-9364
Beaver Valley Power Station, Units 1 and 2 cc:
Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077