07/01/2008 Summary of Telephone Conference with Firstenergy Concerning Requests for Additional Information Pertaining to the Beaver Valley, Units 1 & 2 License Renewal Application
ML082120586
Person / Time
Site: Beaver Valley
Issue date: 08/07/2008
From: Kent Howard
NRC/NRR/ADRO/DLR
To:
Howard K, NRR/DLR/RPB2, 415-2989
References
TAC MD6593, TAC MD6594
Download: ML082120586 (6)


Text

August 7, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company held a telephone conference call on July 1, 2008, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Beaver Valley Power Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the participants and Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items.

The applicant had an opportunity to comment on this summary.

\RA\

Kent L. Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

As stated cc w/encls: See next page

ML082120586 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR NAME IKing KHoward RFranovich DATE 8/1/08 8/4/08 8/7/08

TELEPHONE CONFERENCE CALL BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 1, 2008 PARTICIPANTS AFFILIATIONS Kent Howard U.S. Nuclear Regulatory Commission (NRC)

George Wilson NRC Kenn Miller NRC Clifford I. Custer FirstEnergy Nuclear Operating Company John Thomas FENOC Steve Dort FENOC ENCLOSURE 1

REQUESTS FOR ADDITIONAL INFORMATION BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION JULY 1, 2008 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company held a telephone conference call on July 1, 2008, to discuss and clarify the following requests for additional information (RAIs) concerning the Beaver Valley Power Station (Beaver Valley), Units 1 and 2, license renewal application (LRA).

RAI 2.5-1 Clarify the description of the electrical scoping boundary in the Beaver Valley license renewal application, Section 2.5 to include the first breaker as described in ISG 2008-01.

Discussion The applicant indicated that the question is clear.

The discussion centered on scoping in Section 2.5 with respect to the station blackout scoping boundary. Specifically, the scope of license renewal shall include the switchyard breakers on the switchyard end of the two GDC 17 required circuits between the switchyard and the plant Class 1E busses. Figures 2.5-1 and 2.5-2 of the Beaver Valley LRA include the switchyard breaker, but the LRA text excludes them from boundary scope. This issue is specifically addressed in proposed License Renewal Interim Staff Guidance, LR-ISG-2008-01. The applicant indicated that this was an omission and the breakers are in scope and the text will be corrected.

ENCLOSURE 2

Memo to FirstEnergy Nuclear Operating Company from K. Howard, dated August, 7, 2008 DISTRIBUTION:

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter


KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan Director, Fleet Regulatory Affairs President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Mail Stop A-GO-19 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Manager, Site Regulatory Compliance James H. Lash FirstEnergy Nuclear Operating Company Senior Vice President of Operations Beaver Valley Power Station and Chief Operating Officer Mail Stop A-BV-A FirstEnergy Nuclear Operating Company P.O. Box 4, Route 168 Mail Stop A-GO-14 Shippingport, PA 15077 76 South Main Street Akron, OH 44308 Regional Administrator, Region I U.S. Nuclear Regulatory Commission Danny L. Pace 475 Allendale Road Senior Vice President, Fleet Engineering King of Prussia, PA 19406 FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 Resident Inspector 76 South Main Street U.S. Nuclear Regulatory Commission Akron, OH 44308 P.O. Box 298 Shippingport, PA 15077 Jeannie M. Rinckel Vice President, Fleet Oversight Cliff Custer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 Beaver Valley Power Station 76 South Main Street P.O. Box 4, Route 168 Akron, OH 44308 Shippingport, PA 15077 Paul A. Harden Steve Dort Vice President, Nuclear Support FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-14 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Mike Banko David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation Beaver Valley Power Station Mail Stop A-GO-15 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308