Letter Sequence RAI |
|---|
|
Initiation
- Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: L-07-113, License Renewal Application. Appendix E: Applicants Environmental Report, L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System, L-08-189, Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass), L-08-261, Schedule for Submittal of Annual Update for License Renewal Application, L-08-262, License Renewal Application Amendment No. 23 and Revised License Renewal Boundary Drawings, L-08-263, Submittal of Revision to License Renewal Application Amendment No. 24, L-08-292, License Renewal Application Amendment No. 29 (Annual Update) and Revised License Renewal Application Boundary Drawing, L-08-316, License Renewal Application Amendment No. 26 (TAC Nos. MD6593 and MD6594), Revisions, L-08-393, License Renewal Application, Amendment No. 33, L-09-058, Comments on Safety Evaluation Report with Open Item Related to the License Renewal, L-09-138, License Renewal Application, Amendment No. 36, L-09-151, License Renewal Application Amendment No. 37, ML081000322, ML081000323, ML081000324, ML081000326, ML081000327, ML081000328, ML081000329, ML081000330, ML081000331, ML081000332, ML081640592, ML081640593, ML081640594, ML081640596, ML081640597, ML081640598, ML081640599, ML081640600, ML081640601, ML081640602, ML081640603, ML081640604, ML082550686, ML082550687, ML082550688, ML082550689, ML083010249, ML083040266, ML092740576, ML092920050, ML092920056, NRC-2009-0496, Beaver Valley Federal Register Notice - Record of Decision to Renew License
|
MONTHYEARL-07-113, License Renewal Application. Appendix E: Applicants Environmental Report2007-08-27027 August 2007 License Renewal Application. Appendix E: Applicants Environmental Report Project stage: Other L-07-130, Submittal of Pressure and Temperature Limits Report, Revision 42007-09-19019 September 2007 Submittal of Pressure and Temperature Limits Report, Revision 4 Project stage: Request ML0805902622008-03-0303 March 2008 Request for Additional Information, License Renewal Application Project stage: RAI ML0806402162008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 and 2, LRA Project stage: RAI ML0806010202008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807202882008-03-21021 March 2008 Request for Additional Information, Section B.2.35 Project stage: RAI ML0807907442008-03-26026 March 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application, for Sections B.2.6, B.2.19, and B.2.23 Project stage: RAI L-08-122, Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings2008-03-31031 March 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings Project stage: Response to RAI ML0807903922008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807905382008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI L-08-124, Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 52008-04-0202 April 2008 Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 5 Project stage: Response to RAI ML0807907352008-04-0303 April 2008 RAI for the Reveiw of the Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI ML0810002962008-04-0303 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application, Amendment No. 4, and Revised License Renewal Boundary Drawings Project stage: Response to RAI ML0810003222008-04-0303 April 2008 Drawing Lr 1-07-2, Rev. 4, Chemical and Volume Control System Project stage: Other ML0810003232008-04-0303 April 2008 Drawing Lr 1-07-3, Rev. 6, Chemical and Volume Control System Project stage: Other ML0810003242008-04-0303 April 2008 Drawing Lr 1-08-1, Rev. 4, Boron Recovery Degasifiers Project stage: Other ML0810003262008-04-0303 April 2008 Drawing Lr 1-09-2, Rev. 4, Vent and Drain System Project stage: Other ML0810003272008-04-0303 April 2008 Drawing Lr 1-12-1, Rev. 5, Containment Vacuum and Leakage Monitoring System Project stage: Other ML0810003282008-04-0303 April 2008 Drawing Lr 1-14A-1, Rev. 7, Sample System Project stage: Other ML0810003292008-04-0303 April 2008 Drawing Lr 1-14A-2, Rev. 5, Sample System Project stage: Other ML0810003302008-04-0303 April 2008 Drawing Lr 1-19-1, Rev. 5, Gaseous Waste Disposal System Project stage: Other ML0810003322008-04-0303 April 2008 Drawing Lr 1-30-1, Rev. 5, River Water System Project stage: Other L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System2008-04-0303 April 2008 Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System Project stage: Other ML0810003312008-04-0303 April 2008 Drawing Lr 1-24-1, Rev. 6, Feedwater System Project stage: Other ML0809804832008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810503332008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI L-08-143, Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 62008-04-18018 April 2008 Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 6 Project stage: Response to RAI L-08-144, Reply to Request for Additional Information for the Review of License Renewal Application2008-04-25025 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application Project stage: Response to RAI ML0811303942008-04-28028 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810502702008-04-30030 April 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI L-08-146, Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 72008-04-30030 April 2008 Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 7 Project stage: Response to RAI L-08-174, Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-0202 May 2008 Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-149, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-0505 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0814104162008-05-0808 May 2008 Transmittal of Correction to Reply to RAI for the Review of License Renewal Application, License Renewal Application Amendment No. 8 & Revised License Renewal Boundary Drawings Project stage: Request ML0810505432008-05-0808 May 2008 Request for Additional Information, Sections 3.5.2.2, B.2.1, B.2.3 and 4.6 of License Renewal Application Project stage: RAI ML0811604672008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0812009202008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0811205392008-05-15015 May 2008 Request for Additional Information, License Renewal Application Project stage: RAI ML0814405432008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Amendment No. 9. and Revised License Renewal Boundary Drawings Project stage: Response to RAI L-08-169, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0811304122008-05-22022 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0813605572008-05-22022 May 2008 Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0811505772008-05-28028 May 2008 Request for Additional Information for Sections B.2.27, 4.3 and 4.7.4 of the BVPS LRA Project stage: RAI L-08-180, Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-28028 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-147, Reply to Request for Additional Information for Renewal License Application2008-06-0202 June 2008 Reply to Request for Additional Information for Renewal License Application Project stage: Response to RAI ML0814306872008-06-0404 June 2008 Request for Additional Information the Review of Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI L-08-181, Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 102008-06-0606 June 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 10 Project stage: Response to RAI ML0816405972008-06-0909 June 2008 Drawing Lr 1-25-1, Rev. 5, Steam Generator Blowdown System (Bd) Project stage: Other L-08-189, Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass)2008-06-0909 June 2008 Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass) Project stage: Other ML0816406012008-06-0909 June 2008 Drawing Lr 2-14A-1, Rev. 6, Reactor Plant Sample System, (Ssr) Project stage: Other 2008-04-28
[Table View] |
Text
April 30, 2008 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND MD6594)
Dear Mr. Sena:
By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted an application pursuant to 10 CFR Part 54, to renew the operating licenses for Beaver Valley Power Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with Mr. Cliff Custer of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-2989 or e-mail Kent.Howard@nrc.gov.
Sincerely,
/RA/
Kent L. Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosure:
As stated cc w/encl: See next page
ML081050270 OFFICE LA:DLR BC:RER2:DLR PM:RLRB:DLR BC:RPB2:DLR NAME IKing RAuluck w/correction KHoward RFranovich (JRowley for)
DATE 04/28/08 04/29/08 04/15/08 04/30/08 BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION SECTIONS B.2.13 AND B.2.39 Section B.2.39 RAI B.2.39-1 Beaver Valley Power Station (BVPS) license renewal application (LRA) does not discuss the issue of aging of coatings or has any aging management program (AMP) to manage the aging of coatings. The generic aging lessons learned (GALL) Report recommends such a program.
Please justify why an aging management program for coatings is not needed at BVPS. The failure of coatings could result in aging effects for the steel shell in containment. The failure of coatings could also result in the failure of safety systems to perform their intended functions (for instance, safety injection).
RAI B.2.39-2 In the BVPS LRA, AMP B.2.39, Structures Monitoring Program, is not clear as to how it satisfies the GALL Report program element Parameters Monitored/Inspected. BVPS enhancement for this program element does not include the frequency of periodic sampling of groundwater for pH, chloride, and sulfate concentrations. Please, provide the time frame of your periodic sampling, and the results for the last two samplings of groundwater.
RAI B.2.39.3 BVPS LRA, AMP B.2.39, Structures Monitoring Program, does not include the 2006 inspection results. Please provide:
- a.
2006 inspection results, and how these compare with the 1996 baseline inspection, and the 2001 inspection results.
- b.
The location, size, and depth of the reappear corroded steel found in 2001 inspection, which was painted as a result of the 1996 baseline inspection. What was the condition found in 2006 inspection? Was any other corrective action taken to ensure its capability to maintain its design function for the end of period of extended operation?
RAI B.2.39.4 In the BVPS LRA, AMP B.2.39, Structures Monitoring Program, is not clear in how it satisfies the GALL Report program element Parameters Monitored/Inspected. Specifically, the GALL Report program element suggested ACI 349.3R-96 and ANSI/ASCE 11-90 for an acceptable basis for selection of parameters to be monitored.
ENCLOSURE
On page B.2.109 of the LRA, under operating experience element, the applicant stated, The Structures Monitoring Program inspection of floors was found to be sufficient to identify and repair any cracks large enough to allow water seepage. Please, explain when does a crack become large enough and which industry codes, standards, and guidelines form the basis for this program element?
Section B.2.13 RAI B.2.13-1 In the BVPS LRA, AMP B.2.13, Electrical Wooden Poles/Structures Inspection Program
[Unit 2 Only], it is not clear as to how it satisfies the GALL Report program element parameter monitored/inspected. Please clarify the parameters of electrical wooden poles/structures that need inspection for aging effects and aging effects mechanisms affecting the ability of the wooden poles to perform their intended function. How will the buried part of the wooden pole be monitored/inspected?
Letter to P. Sena from K. Howard, dated April 30, 2008 DISTRIBUTION:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND MD6594)
HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI
Beaver Valley Power Station Units 1 and 2 cc:
Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Drive Harrisburg, PA 17110-9364
Beaver Valley Power Station Units 1 and 2 cc:
Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077