Other: L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System., L-08-189, Drawing Lr 2-27A-2, Rev. 4, Auxiliary Steam and Condensate System (Ass)., L-08-261, Schedule for Submittal of Annual Update for License Renewal Application, L-08-262, Drawing, Lr Drawing 2-31-1, Rev. 5, Demineralized Water System (Wtd)., L-08-263, Submittal of Revision to License Renewal Application Amendment No. 24, L-08-292, Lr Drawing 1-21-1, Rev. 7, Main Steam System (Ms)., L-08-316, License Renewal Application Amendment No. 26 (TAC Nos. MD6593 and MD6594), Revisions, L-08-393, License Renewal Application, Amendment No. 33, L-09-058, Comments on Safety Evaluation Report with Open Item Related to the License Renewal, L-09-138, License Renewal Application, Amendment No. 36, L-09-151, License Renewal Application Amendment No. 37, ML081000322, ML081000323, ML081000324, ML081000326, ML081000327, ML081000328, ML081000329, ML081000330, ML081000331, ML081000332, ML081640592, ML081640593, ML081640594, ML081640596, ML081640597, ML081640598, ML081640599, ML081640600, ML081640601, ML081640602, ML081640603, ML081640604, ML082550686, ML082550687, ML082550688, ML083010249, ML092740576, ML092920050, NRC-2009-0496, Beaver Valley Federal Register Notice - Record of Decision to Renew License
|
MONTHYEARL-07-130, Submittal of Pressure and Temperature Limits Report, Revision 42007-09-19019 September 2007 Submittal of Pressure and Temperature Limits Report, Revision 4 Project stage: Request ML0805902622008-03-0303 March 2008 Request for Additional Information, License Renewal Application (TAC Nos. MD6593 and MD6594) Project stage: RAI ML0806402162008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 and 2, LRA Project stage: RAI ML0806010202008-03-0505 March 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807202882008-03-21021 March 2008 Request for Additional Information, Section B.2.35 Project stage: RAI ML0807907442008-03-26026 March 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application, for Sections B.2.6, B.2.19, and B.2.23 Project stage: RAI L-08-122, Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings2008-03-31031 March 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings Project stage: Response to RAI ML0807903922008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI ML0807905382008-04-0101 April 2008 RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRA Project stage: RAI L-08-124, Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 52008-04-0202 April 2008 Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 5 Project stage: Response to RAI ML0807907352008-04-0303 April 2008 RAI for the Reveiw of the Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI ML0810002962008-04-0303 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application, Amendment No. 4, and Revised License Renewal Boundary Drawings Project stage: Response to RAI ML0810003222008-04-0303 April 2008 Drawing Lr 1-07-2, Rev. 4, Chemical and Volume Control System. Project stage: Other ML0810003232008-04-0303 April 2008 Drawing Lr 1-07-3, Rev. 6, Chemical and Volume Control System. Project stage: Other ML0810003242008-04-0303 April 2008 Drawing Lr 1-08-1, Rev. 4, Boron Recovery Degasifiers. Project stage: Other ML0810003262008-04-0303 April 2008 Drawing Lr 1-09-2, Rev. 4, Vent and Drain System. Project stage: Other ML0810003272008-04-0303 April 2008 Drawing Lr 1-12-1, Rev. 5, Containment Vacuum and Leakage Monitoring System. Project stage: Other ML0810003282008-04-0303 April 2008 Drawing Lr 1-14A-1, Rev. 7, Sample System. Project stage: Other ML0810003292008-04-0303 April 2008 Drawing Lr 1-14A-2, Rev. 5, Sample System. Project stage: Other ML0810003302008-04-0303 April 2008 Drawing Lr 1-19-1, Rev. 5, Gaseous Waste Disposal System. Project stage: Other ML0810003322008-04-0303 April 2008 Drawing Lr 1-30-1, Rev. 5, River Water System. Project stage: Other L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System.2008-04-0303 April 2008 Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System. Project stage: Other ML0810003312008-04-0303 April 2008 Drawing Lr 1-24-1, Rev. 6, Feedwater System. Project stage: Other ML0809804832008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810503332008-04-17017 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI L-08-143, Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 62008-04-18018 April 2008 Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 6 Project stage: Response to RAI L-08-144, Reply to Request for Additional Information for the Review of License Renewal Application2008-04-25025 April 2008 Reply to Request for Additional Information for the Review of License Renewal Application Project stage: Response to RAI ML0811303942008-04-28028 April 2008 Request for Additional Information, Review of License Renewal Application Project stage: RAI ML0810502702008-04-30030 April 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI L-08-146, Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 72008-04-30030 April 2008 Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 7 Project stage: Response to RAI L-08-174, Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-0202 May 2008 Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-149, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-0505 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0814104162008-05-0808 May 2008 Transmittal of Correction to Reply to RAI for the Review of License Renewal Application, License Renewal Application Amendment No. 8 & Revised License Renewal Boundary Drawings Project stage: Request ML0810505432008-05-0808 May 2008 Request for Additional Information, Sections 3.5.2.2, B.2.1, B.2.3 and 4.6 of License Renewal Application Project stage: RAI ML0811604672008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0812009202008-05-0808 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application (TAC MD6593 and MD6594) Project stage: RAI ML0811205392008-05-15015 May 2008 Request for Additional Information, License Renewal Application (TAC Nos. MD6593 and MD6594) Project stage: RAI ML0814405432008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Amendment No. 9. and Revised License Renewal Boundary Drawings Project stage: Response to RAI L-08-169, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application2008-05-19019 May 2008 Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML0811304122008-05-22022 May 2008 Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0813605572008-05-22022 May 2008 Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0811505772008-05-28028 May 2008 Request for Additional Information for Sections B.2.27, 4.3 and 4.7.4 of the BVPS LRA Project stage: RAI L-08-180, Reply to Request for Additional Information for the Review of the License Renewal Application2008-05-28028 May 2008 Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-08-147, Reply to Request for Additional Information for Renewal License Application2008-06-0202 June 2008 Reply to Request for Additional Information for Renewal License Application Project stage: Response to RAI ML0814306872008-06-0404 June 2008 Request for Additional Information the Review of Beaver Valley, Units 1 and 2, License Renewal Application Project stage: RAI L-08-181, Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 102008-06-0606 June 2008 Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application, Amendment No. 10 Project stage: Response to RAI ML0816405052008-06-0909 June 2008 Reply to Request for Additional Information for the Review of the License Renewal Application License Renewal Application Amendment No. 11, and Revised License Renewal Boundary Drawings Project stage: Response to RAI ML0816405922008-06-0909 June 2008 Drawing Lr 1-14A-1, Rev. 8, Sample System (Ss). Project stage: Other ML0816405932008-06-0909 June 2008 Drawing Lr 1-21-1, Rev. 6, Main Steam System (Ms). Project stage: Other ML0816405942008-06-0909 June 2008 Drawing Lr 1-22-1, Rev. 4, Condensate System (Cn). Project stage: Other 2008-04-03
[Table View] |
|
---|
Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
Text
April 28, 2008 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND MD6594)
Dear Mr. Sena:
By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted an application pursuant to 10 CFR Part 54, to renew the operating licenses for Beaver Valley Power Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with Mr. Cliff Custer of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-2989 or via e-mail at kent.howard@nrc.gov.
Sincerely,
/RA/
Kent L. Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosure:
As stated cc w/encl: See next page
ML081130394 OFFICE LA:DLR SRXB:DSS PM:RPB2:DLR BC:RPB2:DLR NAME SFigueroa LLois KHoward RFranovich DATE 4/23/08 4/28/08 4/25/08 4/28/08
BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION, SECTION 4.2.4 Section 4.2.4 RAI 4.2.4-1 In the BVPS LRA, it is not readily apparent if the Low-Temperature Overpressure Protection System (OPPS) was affected by recent plant changes (extended power uprates). The applicant states that, "As part of any update, the OPPS setpoints (OPPS enable temperature and power-operated relief valve setpoints) for both units are reviewed and updated as required based on the updated P-T limit curves." Please provide additional details or documentation to show if the OPPS itself was/was not affected by the extended power uprate.
Letter to P. Sena from K. Howard, dated April 28, 2008 DISTRIBUTION:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6593 AND MD6594)
HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter
KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan Director, Fleet Regulatory Affairs President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Mail Stop A-GO-19 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Manager, Site Regulatory Compliance James H. Lash FirstEnergy Nuclear Operating Company Senior Vice President of Operations Beaver Valley Power Station and Chief Operating Officer Mail Stop A-BV-A FirstEnergy Nuclear Operating Company P.O. Box 4, Route 168 Mail Stop A-GO-14 Shippingport, PA 15077 76 South Main Street Akron, OH 44308 Commissioner James R. Lewis West Virginia Division of Labor Danny L. Pace 749-B, Building No. 6 Senior Vice President, Fleet Engineering Capitol Complex FirstEnergy Nuclear Operating Company Charleston, WV 25305 Mail Stop A-GO-14 76 South Main Street Director, Utilities Department Akron, OH 44308 Public Utilities Commission 180 East Broad Street Jeannie M. Rinckel Columbus, OH 43266-0573 Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Director, Pennsylvania Emergency Mail Stop A-GO-14 Management Agency 76 South Main Street 2605 Interstate Drive Akron, OH 44308 Harrisburg, PA 17110-9364 David W. Jenkins, Attorney Dr. Judith Johnsrud FirstEnergy Nuclear Operating Company Environmental Coalition on Nuclear Power Mail Stop A-GO-15 Sierra Club 76 South Main Street 433 Orlando Avenue Akron, OH 44308 State College, PA 16803 Manager, Fleet Licensing Director FirstEnergy Nuclear Operating Company Bureau of Radiation Protection Mail Stop A-GO-2 Pennsylvania Department of 76 South Main Street Environmental Protection Akron, OH 44308 Rachel Carson State Office Building P.O. Box 8469 Ohio EPA-DERR Harrisburg, PA 17105-8469 ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149
Beaver Valley Power Station, Units 1 and 2 cc:
Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 2