Letter Sequence RAI |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement
|
MONTHYEARML0729006392007-10-29029 October 2007 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for Beaver Valley Power Station Units 1 and 2 Project stage: Other ML0729006502007-10-29029 October 2007 United States Nuclear Regulatory Commission Firstenergy Nuclear Operating Company Beaver Valley Power Station Unit Nos. 1 and 2 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process Project stage: Request ML0735202822007-11-27027 November 2007 Slides, Beaver Valley Power Station License Renewal Process and Environmental Scoping Meeting. Project stage: Meeting ML0734008432007-11-27027 November 2007 Transcript of the Beaver Valley Power Station License Renewal Public Meeting - Evening Session, November 27, 2007, Pages 1-49 Project stage: Meeting ML0733900322007-11-27027 November 2007 Transcript of Proceedings for Beaver Valley Power Station Public Meeting (Afternoon Session), November 27, 2007, Pages 1-39 Project stage: Request ML0735305392008-01-0909 January 2008 Summary of Public Environmental Scoping Meetings Related to the Renewal of the Beaver Valley Power Station, License Renewal Application (TAC Nos. MD6595 and MD6596) Project stage: Meeting ML0802203432008-01-14014 January 2008 Letter from George Dudash III, Comment Regarding the Beaver Valley Power Station Unit 1 and 2 License Renewal Project stage: Other ML0802307282008-01-28028 January 2008 Request for Additional Information Regarding Severe Accident Mitigation Alternatives for Beaver Valley Power Station, Units 1 and 2, License Renewal (TAC Nos. MD6595 and MD6596) Project stage: RAI ML0802404112008-01-30030 January 2008 Beaver, Units 1 and 2, Environmental Impact Statement Scoping Process Summary Report Project stage: Other ML0805606272008-02-27027 February 2008 Advisory Committee on Reactor Safeguards Review of the Vermont Yankee Nuclear Power Station License Renewal Application - Safety Evaluation Report Project stage: Approval ML0805605882008-03-13013 March 2008 RAI Refurbishment Impacts for Beaver Valley Units 1 & 2 License Renewal (TAC Nos. MD6595 and MD6596) Project stage: RAI ML0802902572008-03-17017 March 2008 Summary of Site Audit Related to the Review of the LRA for Beaver Valley, Units 1 and 2 Project stage: Approval ML0807301162008-03-21021 March 2008 Summary of Conference Call Between Us Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning the Impact of Table 8.0-1 Error on the Beaver Valley Severe Accident Mitigation Alternatives Request for Additional In Project stage: Request ML0807403922008-03-26026 March 2008 Summary of Telephone Conference Between NRC and Firstenergy Nuclear Operating Company, Concerning Clarification of Severe Accident Mitigation Alternatives Request for Additional Information Pertaining to Beaver Valley Units 1 & 2 Project stage: RAI ML0807401232008-04-0707 April 2008 Summary of Telephone Conference Call Held on March 05, 2008, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning the Request for Additional Information Pertaining to the Refurbishment Activit Project stage: RAI L-08-125, Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts, for License Renewal2008-04-25025 April 2008 Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts, for License Renewal Project stage: Response to RAI L-08-148, Reply to Follow-Up Questions Pertaining to Request for Additional Information Regarding Severe Accident Mitigation Alternatives for License Renewal2008-05-0202 May 2008 Reply to Follow-Up Questions Pertaining to Request for Additional Information Regarding Severe Accident Mitigation Alternatives for License Renewal Project stage: Request ML0813605572008-05-22022 May 2008 Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application Project stage: Approval L-08-179, Supplement to Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts for License Renewal2008-05-30030 May 2008 Supplement to Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts for License Renewal Project stage: Response to RAI L-08-200, Supplemental License Renewal Environmental Information Requested by Nuclear Regulatory Commission2008-06-0202 June 2008 Supplemental License Renewal Environmental Information Requested by Nuclear Regulatory Commission Project stage: Supplement ML0812304992008-06-0303 June 2008 Teleconf Held 4/30/08 Between NRC and Firstenergy Concerning the RAI Pertaining to the Refurbishment Activities at Beaver, Units 1 and 2, LRA Project stage: Request L-08-210, Supplement to Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts, License Renewal2008-06-26026 June 2008 Supplement to Reply to Request for Additional Information Regarding Postulated Refurbishment Impacts, License Renewal Project stage: Response to RAI ML0825403992008-09-17017 September 2008 Notice of Availability of the Draft Plant-Specific Supplement 36 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants the Beaver Valley Power Station, Units 1 and 2 (TAC Nos. MD6595 and MD6596) Project stage: Draft Other ML0826001472008-09-30030 September 2008 NUREG-1437 Supp 36, Dfc, Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Beaver Valley Power Station, Units 1 & 2 (Draft for Comment) Project stage: Draft Other ML0831005872008-10-21021 October 2008 Comment (1) of Vincent Biancucci, on Behalf of Self, Beaver Valley Power Station, Renewal and Extension of Licensing for Units 1 and 2 Project stage: Request ML0832505192008-10-30030 October 2008 Official Transcript of Proceedings for the Beaver Valley Draft Environmental Impact Statement Public Meeting Afternoon Session, Thursday, October 30, 2008, Pages 1-45 Project stage: Request ML0832505202008-10-30030 October 2008 Transcript of Beaver Valley Power Station, Units 1 & 2, Public Meeting Evening Session: Evening Session, 10/30/2008, Pages 1-33 Project stage: Request ML0831507282008-10-30030 October 2008 Letter from PA Historical and Museum Commission Bureau for Historic Preservation Regarding the Beaver Valley Power Station License Renewal Project stage: Other ML0832902542008-11-10010 November 2008 Comment (2) of Diane M. Kemp on Behalf of Borough of Midland Re License Renewal of Beaver Valley, Units 1 and 2 Project stage: Other ML0832400512008-11-17017 November 2008 Preliminary Results of Environmental Review Project stage: Request ML0835204932008-11-19019 November 2008 Us Dept. of Interior, Office of the Secretary Comment on Draft Generic Environmental Impact Statement for License Renewal of Beaver Valley, Units 1 & 2, NUREG-1437, Supplement 36 L-08-365, FENOC Comments to NUREG-1437 Supplement 36, Bearer Valley Power Station Draft Environmental Impact Statement2008-11-24024 November 2008 FENOC Comments to NUREG-1437 Supplement 36, Bearer Valley Power Station Draft Environmental Impact Statement ML0833301862008-11-24024 November 2008 NUREG-1437 Supplement 36, Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Beaver Valley Power Station, Units 1 & 2 (Draft for Comment). ML0835700412008-12-10010 December 2008 Comment (4) of William Arguto on Behalf of the U. S. Environmental Protection Agency, Region III on Draft Generic Supplemental Environmental Impact Statement (Dgseis) for the Beaver Valley Power, Units 1 and 2 (Report Number NUREG-1437, Sup Project stage: Request ML0835700422008-12-12012 December 2008 Comment (3) of Diane Johnson on Behalf of United Way of Southern Columbiana County in Support of the Firstenergy Nuclear Operating Company Beaver Valley Power Station Project stage: Request ML0836600292009-01-0909 January 2009 10/30/08 Summary of Public Meeting on the Draft Supplemental Environmental Impact Statement Regarding the Beaver Valley Power Station, License Renewal Review ML0912600242009-05-12012 May 2009 Final Supplement 36 to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (BVPS) Project stage: Acceptance Review ML0912504132009-05-12012 May 2009 Final Supplement 36 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS) Regarding Beaver Valley Power Station, Units 1 and 2 (TAC Nos. MD6595 and MD6596) Project stage: Other ML0912503632009-05-14014 May 2009 Notice of Availability of the Final Plant-Specific Supplement 36 to the GEIS for License Renewal of Nuclear Plants Regarding Beaver Valley Power Station Project stage: Other ML0912600112009-05-31031 May 2009 NUREG-1437 Supplement 36 Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Beaver Valley Power Station Units 1 and 2 Final Report Project stage: Acceptance Review ML0926105222009-09-28028 September 2009 Revision of Schedule for the Conduct of Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application (TAC MD6593, MD6594, MD6595, MD6596) Project stage: Approval 2008-03-17
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections ML23026A3552023-01-31031 January 2023 Summary of Public Meeting with Energy Harbor Nuclear Corp. Regarding Beaver Valley Power Station License Amendment Request to Consolidate Fuel Decay Time TS Into New Limiting Condition for Operation ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML22105A3932022-04-20020 April 2022 Summ. of March 17, 2022, Public Meeting with Ehnc Regarding Planned License Amendment Request to Consolidate Fuel Decay Time Requirements in a New Limiting Condition for Operation for Beaver Valley Power Station, Units 1 and 2 ML22053A2982022-02-25025 February 2022 Summary of the February 15, 2022, Meeting with Energy Harbor Nuclear Corp. Regarding the License Amendment Request Related to Revising TS 5.6.3 Core Operating Limits Report (COLR) ML21308A0712021-11-0909 November 2021 Summary of Teleconference with Energy Harbor Nuclear Corp. Regarding Fall 2021 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20197A2722020-07-15015 July 2020 2020 Beaver Valley, Calvert Cliffs, Limerick Peach Bottom, Susquehanna Annual Assessment Webinar Summary ML20148M3852020-06-0101 June 2020 Summary of May 26, 2020, Public Meeting with Energy Harbor Nuclear Corp. Potential License Amendment Request Related to Steam Generator Tube Sleeve Inspections and Maintenance ML20122A0032020-05-19019 May 2020 Summary of April 22, 2020, Teleconference with Energy Harbor Nuclear Corp. Regarding Spring 2020 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20111A0142020-04-27027 April 2020 Summary of March 31, 2020, Public Meeting with Energy Harbor Nuclear Corp. to Discuss COVID-19 Potential Submittals of Regulatory Actions ML16125A5072019-10-22022 October 2019 Ti 191 Issue Matrix ML19280A0382019-10-22022 October 2019 Ti 2515-191 Summary of Findings ML19191A1882019-07-0909 July 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - Meeting Summary ML18325A0232018-11-28028 November 2018 Summary of Teleconference with Firstenergy Nuclear Operating Company Regarding Fall 2018 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML18099A0812018-04-0606 April 2018 Bv Annual Assessment Meeting Summary and Attendance List 2018 ML17347A8082017-12-20020 December 2017 December 5, 2017, Summary of Public Meeting with Firstenergy Nuclear Operating Company to Discuss a Proposed License Amendment Request Extending Sleeve Life on the Steam Generator at Beaver Valley Power Station, Unit 2 ML17158B1662017-06-0909 June 2017 Summary of Meeting with Firstenergy Nuclear Operating Company Regarding the Spring 2017 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML17082A1842017-03-28028 March 2017 March 20, 2017, Summary of Annual Assessment Meeting with Beaver Valley, Units 1 and 2 ML16250A5012016-10-0303 October 2016 Summary of August 30, 2016, Meeting with Firstenergy Nuclear Operating Company Regarding Planned Submittal of Emergency Action Level Scheme Change ML16105A0082016-04-25025 April 2016 March 30, 2016, Summary of Meeting with Firstenergy Nuclear Operating Company on Its Draft Probabilistic Risk Assessment RAI Related to Its License Amendment Request to Adopt NFPA Standard 805 ML16091A0702016-03-31031 March 2016 2016 Beaver Valley Annual Assessment Meeting Summary 2016 ML15320A3912015-11-24024 November 2015 Summary of Conference Call Regarding the Fall 2015 Steam Generator Inspections ML15225A4812015-08-14014 August 2015 July 23, 2015, Summary of Meeting with Representatives of the U.S. Army Corps, U.S. Nuclear Regulatory Commission and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station ML15135A2982015-05-21021 May 2015 Summary of April 28, 2015, Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station, ML15104A6652015-04-14014 April 2015 April 9, 2015 Summary of Annual Assessment Meeting with Beaver Valley Power Station, Units 1 and 2 ML14325A7782014-12-16016 December 2014 October 6, 2014, Summary of Pre-Application Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Combination of Site Emergency Plans ML14184B1962014-08-14014 August 2014 Summary of June 18, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and Firstenergy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Stat ML14160B1032014-07-10010 July 2014 June 6, 2014 Summary of Meeting with FENOC Flooding Hazard Reevaluation Extension Request for Beaver Valley Power Station, Units 1 and 2 and Flooding Hazard Reevaluation Report for Davis-Besse Nuclear Power Station, Unit 1 ML14142A0872014-06-0909 June 2014 Summary of Conference Call Regarding the Spring 2014 Steam Generator Inspections ML14099A1732014-04-0909 April 2014 Annual Assessment Meeting Summary, ROP14 ML13295A2182013-10-22022 October 2013 Summary of Public Meeting with Beaver Valley, ML13114A2072013-04-22022 April 2013 Summary of Annual Assessment Meeting at Beaver Valley ML13057A6782013-03-11011 March 2013 2/20/2013 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Request for Additional Information Response Regarding Beaver Valley Power Station End-of-Life Moderator Temperature Coefficient Testing ML12321A3012012-11-29029 November 2012 Summary of November 15, 2012, Meeting with Firstenergy Nuclear Operating Company to Discuss Upcoming License Amendment Request Relating to the Implementation of the Alternate Pressurized Thermal Shock Rule ML12310A0662012-11-13013 November 2012 Summary of Conference Call with Firstenergy Nuclear Operating Company to Discuss 2012 Steam Generator Tube Inspections ML12293A0402012-11-0101 November 2012 October 18, 2012 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Request for Additional Information Regarding Fenoc'S Extension Request for Upcoming Beaver Valley Power Station National Fire Protection Association ML12277A4082012-10-0303 October 2012 September 26, 2012, Summary of Public Meeting to Discuss FENOC Fleet Performance ML12223A4672012-08-22022 August 2012 August 1, 2012 - Summary of Meeting with FENOC to Discuss Upcoming National Fire Protection Association Standard 805 License Amendment Request Status ML12195A1132012-07-16016 July 2012 Summary of Public Meeting with FENOC Regarding Licensing Practices and Processes ML12104A1052012-04-13013 April 2012 Meeting Summary of Annual Assessment Meeting on March 22, 2012 ML1115805152011-06-15015 June 2011 (BVPS-2) - Summary of Conference Call Regarding the Spring 2011 Steam Generator Tube Inspection Results ML1112504622011-05-0505 May 2011 Summary of Annual Assessment Open House Public Meeting, Beaver Valley ML1035606612010-12-29029 December 2010 Summary of Beaver Valley Power Station, Unit 2 Public Conference Call Regarding Spent Fuel Pool Rerack LAR Draft RAI Responses Discussion ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 ML1014105172010-05-21021 May 2010 Summary of the May 2010 Annual Assessment Open-House Public Meeting ML1013206652010-05-18018 May 2010 Summary of Category 1 Teleconference with Firstenergy Nuclear Operating Company to Discuss NRC Request for Additional Information Regarding Generic Letter 2004-02 ML1009502432010-04-0505 April 2010 Meeting Summary of 3-31-10 Public Meeting with FENOC ML0931407282009-11-18018 November 2009 Steam Generator Tube Inspections 2024-06-03
[Table view] |
Text
April 7, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 05, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6595 and MD6596)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on March 05, 2008, to discuss the Refurbishment Activities Request for Additional Information (RAI) concerning the Beaver Valley Power Station Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants. Enclosure 2 is a summary of the discussion between FENOC and NRC staff.
If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard, at 301-415-2989 or KLH1@nrc.gov.
Sincerely
/RA/
Kent Howard, License Renewal Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
As stated
April 7, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 05, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6595 and MD6596)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on March 05, 2008, to discuss the Refurbishment Activities Request for Additional Information (RAI) concerning the Beaver Valley Power Station Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants. Enclosure 2 is a summary of the discussion between FENOC and NRC staff.
If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard, at 301-415-2989 or KLH1@nrc.gov.
Sincerely,
/RA/
Kent Howard, License Renewal Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
As stated cc w/encls: See next page DISTRIBUTION: See next page Adam Accession No: ML080740123 OFFICE: LA:DLR PM:DLR:RPB2 PM:DLR:RPB1 PM:DLR:RPB2 BC: DLR:RPB2 w/comments NAME: SFigueroa ESayoc DStuyvenberg M Sayoc for KHoward RFranovich w/ comments DATE: 3/20/08 3/24/08 3/28/08 3/24//08 4/7/08 OFFICIAL RECORD COPY
LIST OF PARTICIPANTS FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION March 05, 2008 PARTICIPANTS AFFILIATIONS Rani Franovich U.S. Nuclear Regulatory Commission (NRC)
Kent Howard NRC Emmanuel Sayoc NRC Bo Pham NRC Andrew Stuyvenberg NRC Cliff Custer FirstEnergy Nuclear Operating Company (FENOC)
Jeffery Jeffries FENOC Steve Dort FENOC Dave Kunsemiller FENOC Mike Banko FENOC Anne Lovell TetraTech (TtNUS)
Amy Stanford TtNUS ENCLOSURE 1
SUMMARY
FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION March 05, 2008 The staff requested the conference call to seek clarification on FENOCs environmental report (ER), which states that the aging management review has identified a possible need for Unit 2 steam generator repair or replacement during the license renewal term. The ER also states that the steam generator replacement activities will be done during scheduled outages and therefore are bounded by the environmental impacts analyzed in the Final Environmental Statement (FES).
The NRC explained that the frame of reference for license renewal environmental reviews is the Generic Environmental Impact Statement for License Renewal (GEIS), not the FES for initial licensing. More specifically, GEIS Section 2.6.2.6 provides some examples of major refurbishment and replacement activities (including replacement of steam generators).
Furthermore, the GEIS indicates that these activities can have environmental impacts requiring analysis that need to be considered in a site-specific supplement to the GEIS.
The staff further explained that, if a refurbishment activity is associated with license renewal, then the environmental impacts associated with the activity must be analyzed in accordance with 10 CFR 51.53(c)(2). The NRC staff indicated that a request for additional information would be issued to obtain clarification from FENOC regarding whether or not the steam generator replacement activity for Beaver Valley Unit 2 is associated with license renewal, and if it is associated with license renewal, to obtain FENOCs analysis of impacts from the activity.
ENCLOSURE 2
Letter to FirstEnergy from K. Howard, dated April 7, 2008 DISTRIBUTION:
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 05, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc PBuckberg NMorgan MModes, RI PCataldo, RI DWerkheiser, RI
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan Manager, Fleet Licensing President and Chief Nuclear Officer FirstEnergy Nuclear Operating FirstEnergy Nuclear Operating Company Company Mail Stop A-GO-2 Mail Stop A-GO-19 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Ohio EPA-DERR James H. Lash ATTN: Zack A. Clayton Senior Vice President of Operations P.O. Box 1049 and Chief Operating Officer Columbus, OH 43266-0149 FirstEnergy Nuclear Operating Company Director, Fleet Regulatory Affairs Mail Stop A-GO-14 FirstEnergy Nuclear Operating 76 South Main Street Company Akron, OH 44308 Mail Stop A-GO-2 76 South Main Street Danny L. Pace Akron, Ohio 44308 Senior Vice President, Fleet Engineering Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating FirstEnergy Nuclear Operating Company Company Mail Stop A-GO-14 Beaver Valley Power Station 76 South Main Street Mail Stop A-BV-A Akron, OH 44308 P.O. Box 4, Route 168 Shippingport, PA 15077 Jeannie M. Rinckel Vice President, Fleet Oversight Commissioner James R. Lewis FirstEnergy Nuclear Operating West Virginia Division of Labor Company 749-B, Building No. 6 Mail Stop A-GO-14 Capitol Complex 76 South Main Street Charleston, WV 25305 Akron, OH 44308 Director, Utilities Department David W. Jenkins, Attorney Public Utilities Commission FirstEnergy Nuclear Operating 180 East Broad Street Company Columbus, OH 43266-0573 Mail Stop A-GO-15 76 South Main Street Director, Pennsylvania Emergency Akron, OH 44308 Management Agency 2605 Interstate Dr.
Harrisburg, PA 17110-9364
Beaver Valley Power Station, Units 1 and 2 cc:
Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077