ML052030180

From kanterella
Jump to navigation Jump to search
U1R28 Today
ML052030180
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/28/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML052030180 (2)


Text

NMC Comminodto NucldtoEJee/:n, Point Beach Refueling Outage Edition 71, May 28, 2004

£ CONTACT INFORMATION Control Room Emergency - x2911 EMT Pager 6442 Work Control Center- x6703 OCC - x 7190 - Option I Lessons Learned - x7190 - Option 2 Plant Status - x7190 - Option 3 Accomplishments

  • Continued Containment Cleanup
  • Rod Latch Tool Removed From Containment
  • Installed Conoseals
  • Installed Pressurizer Manway
  • I&C Cavity Restoration

.9ji

  • Containment Fan Cooler Testing ersonnel Last 24 Hours Outage to Safety 24Hus Date Z:,)- Recordable - 0 Recordable - V Schedule Focus AreaslPriorities

, Disabling - 0 Disabling - 0

  • Containment Cleanup
  • RCS Fill & Vent
  • OSHA Recordable - Back strain.
  • Fill Pressurizer Solid V.03 Invrmation in urs record was deleted inaccordance wit t Freedom of Inormon IIIUR11EY TO Act exem ___ _ ___ VEKCELLEF1CE POIIT BERCH
  • U[1RB8

I May 28, 2004 OUTAGE GOALS NUCLEAR SAFETY GOAL ACTUAL HUMAN PERFORMANCE GOAL ACTUAL PERFORMANCE Unplanned orangelred paths None None Security Violations s 12 loggable events 3 Station human performance dock None 4 Reactor trips (either unit) None I resets _ _ _ _ _ _

Safeguards actuation (either unit) None Non Rework s 1% On Goal Loss of shutdown cooling None None SCHEDULE PERFORMANCE Outage Duration Loss of Rx vessel level control None None (excludes extensions due to s 30 days Off Goal extended head or BMI inspections)

INDUSTRIAL SAFETY Mod Implementation 100% of Rev 0 On Goal PERFORMANCE

> 85% schedule Lost time accidents None None Schedule Compliance compliance with Off Goal outaoe milestone Emergent work (during s 2% late additions On Goal Personnel injuries (OSHA recordable) None 1 implementation) s 5% Emergent RADIOLOGICAL PERFORMANCE Scope Complete 2 95% of On Goal Rev 0 scope Radiation exposure (Excludes additional 100% of Scheduled dose from any head or BMI repair s 92 R 81.868 R Operator Burdens Operator Burdens On Goal contingencies) complete Personnel contaminations >5K CPM 11 Post Outage availability t 150 days of Available at Radiological events (defined as unplanned continuous operation a later date uptake wlassigned dose >10 mrem or s1 event 1 BDEPERFORMANCE BUGToutage Within -2%budget to 0%of Seriously Chaflenge dose event based on ED alarms .

Radmaterial event (defined as any rad :i event 0 material outside RCA 2 100 CPM) _ event_0 Operating Experience OE1 3709 - Inadvertent Unit 2 Train B Safety Injection During Performance of a Surveillance Procedure On February 26, 2002, at 1438 hours0.0166 days <br />0.399 hours <br />0.00238 weeks <br />5.47159e-4 months <br /> an inadvertent actuation of Unit 2 Train B Safety Injection (SI) occurred. Unit 2 was in Mode 4, heating up per the Unit 2 startup procedure. Reactor Coolant System (RCS) average temperature was approximately 336 degrees F and pressure was approximately 330 psig with 21 and 22 Si pumps in normal standby per procedure. The inadvertent actuation occurred during performance of a surveillance procedure (SP) to test reactor trip and bypass breakers auxiliary contacts. Plant electricians were installing voltmeter test probes on terminals TB6N-8 and TB6N-9 in Train B Safeguards Rack 2BSG2 in accordance with the procedure to obtain voltage readings during subsequent steps of the SP. After installing atest probe on terminal TB6N-9, the electrician proceeded to install the second test probe on TB6N-8 per the procedure. While installing the test probe, the electrician inadvertently made contact with the adjacent terminal TB6N-

7. This inadvertent contact shorted the two terminals (7and 8)causing Train B SI to actuate by energizing SIB relay. The actuation started Train B safeguards equipment.

Lessons Learned: The root cause was determined to be Interface Desicn - inadequate lavout and accessibility.

Human Performance Safety Snippet Job observations are the best - put your worker practices Before heat up, make sure someone has done to the test. Itwill make us better then the rest. Job the clean-up observations are performed to help reinforce and coach OE57698 April 2004, Palo Verde - Two mechanics workers on observed behaviors. This leads to enhanced received second degree burns to the face as the result of performance. Inthis industry we must strive for a flash fire that occurred as they began pre-heating for continuous improvement. Job observations are a welding. Isopropyl alcohol was used to clean and liquid necessary fact of our jobs. had accumulated in the casing of the equipment. The oncoming crew was not aware of this buildup as they began work.