U1R28 Outage Risk Plan Ppg Outage Management
ML051890396
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 07/01/2005
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML051890396 (19)


Text

R128 Outage Schedule Safety Review results i-ct U1R28 Outage Risk Plan PPGOutage Management Introduction The philosophy of the Outage Planning Group with respect to risk assessment is to plan and schedule the shortest possible outage with the least total exposure to risk and provide reliable documentation from the schedule database of meeting this intent. The outage plan, (and outage schedule), will therefore:

  • Never provide direction to enter a "Red" condition, (See NP 10.3.6),
  • Limit to the greatest possible extent the quantity and duration of "Orange" condition(s),
  • Implement comprehensive contingency plans for any "Orange" condition and protect all operating and backup equipment when more than one KSF is at "Orange" condition at any one time, and
  • Actively seek to reduce duration of "Yellow" conditions when such reductions will not both significantly and adversely affect the overall cost or duration of an outage.

The risk profile of the unit 1, 286 refueling outage contains no periods of "Red" risk condition and 2 periods of "Orange" risk condition. This is due to primary S/G and other work on equipment that is un-isolable from the reactor. This work necessitates the lowering of RCS level to reduced inventory. Specific risk reduction contingency plans are required for the 2 periods of "Orange" risk condition. Those contingency plans will be drafted and issued separately from this document.

The containment equipment hatch will not be removed during UIR28, eliminating a significant contributor to the risk profile.

Significant scope exists for CVCS and RH, causing an increase in risk for inventory, core cooling, and reactivity Key Safety Functions (KSFs) to "Yellow" condition. This work will occur during the fuel and inisert shuffle in the refueling pool. This condition has not occurred in over 7 years at PBNP and will result in plant operating conditions that are not familiar to many workers. With effective planning, training and preparation, the cumulative risk profile ofUlR28 is acceptable. It should be noted thatNP 10.36 and Technical Specifications occasionally utilize similar terminology to describe differing conditions. This is of particular note when discussing the "cavity filled" condition. Further detail will be provided below.

The U1R28 Risk Plan This risk plan describes the risk conditions and the actions and tasks necessary to achieve adequate defense in depth during those conditions that will exist during the U1R28 outage. This plan acts as a primer for risk related information contained within the outage schedule. This plan does not replace the outage schedule, which is time based and updated regularly throughout the execution of the outage.

The plan will be presented in a structured format A general knowledge of Technical Specifications, Shutdown RiskPrincipals, Administrative Procedures, plant layout and function is assumed. The methods used to retain adequate "defense in depth" will be described in detail for each plant condition. The risk plan is divided into several sections. Each section will relate to an NMC outage phase.

Individual activities will be marked in the work group bar chart and detailed schedule documents to identify when human performance risk analysis has shown a high level ofpotential for error, (see NP 1.1.7).

Work that is acceptable for performance during reduced inventory periods and during ESF loss of AC power testing, O-RT-003A & B, will be marked in the work group bar chart and detailed schedule documents.

This will document pre-review and authorization activities so that execution may proceed wiih assurance. This is of particular value in the WCC at the interfaces with shift management and 'across the counter' with maintenance and engineering.

InfolastJiO in this record was deleted in accordance withe Freedom of .SiI?~o Act, exem p 6s1 n 1nf 19

R128 Outage Schedule Safety Review results 1 Offline to Enter Mode5 During the pre-outage period and through Modes 2, (Startup), & 3, (Hot Standby) risk is evaluated using the On Line Safety Monitor. NP 10.3.6 is not in effect until the plant achieves Mode 4.

Upon entry into Mode 4, all KSFs remain "GREEN"' and all safety equipment remains available or operable for raxinmum defense-in-depth. Fire Protection remains Condition I until entry into Mode 5

2) Enter Mode5 to Enter Mode6 Start Non-ESF related work and Prepare for ORT-3AJB Integrated "'ESF with Loss of AC Power" Testing Pre-Approved Concurrent Work:

Only work that has beenpre-approved for execution during ORT-003 may be performed. The following is a list of general work that has been pre-approved to occur during performance of ORT-003. It should be noted that further evaluation might result in additional pre-approvals. Any such pre-approvals will be so noted in the outage schedule.

  • CWAI 1- P-030A and related components.
  • CWB II - P-030B and related components.

2.nfl9

R128 Outage Schedule Safety Review results

  • CSXO1 - non-pump-related Condensate.
  • CVXOI - High Pressure Letdown, (after RHR letdown in service).
  • RCAI I - Reactor Coolant Pump motor determination and preparation for lift to the 66' stand.
  • CONTXO1 - Setup in the reactor head lay-down area, equipment load-in to containment and temporary power service for under-head inspection.

o During Preparation and recovery phases of each train of the ORT3 test, I&C will continue to perform a normal distribution of work, all of which will be stopped during the actual performance of the ORT3 test.

o During the actual performance of the ORT3 test, I&C will be performing secondary temperature calibrations, containment H2 calibrations, a very small amount of secondary valve diagnostics, and EH fluid system components. None of which will impact operations in the control room.

o Line 121 will be OOS and Appleton work on Line 121 will continue throughout ORT3 testing. Line 121 will not be returned to service until after ORT3 is complete.

Start "B" train only ESF related work:

A small amount of primary work may start immediately after the 'B" train integrated engineered safeguards test is complete. The following is a listing of functional equipment groups that can be cleared for work immediately after ORT-003B recovery is complete:

  • VNCCB51 - Containment Fan Cooler C The KSF status for ORT-003A is listed below:

(If 1'9

0 f0.

9.7C 1:77V/n..luACh A- .r1 -r Reactor over-head disassembly Start remaining ESF related work.l A significant amount ofboth primary and secondary work may not start until the integrated engineered safeguards test is complete. The following is a listing of functional equipment groups that can be cleared for work immediately after ORT-003 recovery is complete:

  • CSA1 1 - P-025A and related components
  • CSB1 1 - P-025B and related components
  • CSA12 - P-028A and related components
  • CSB12 - P-028B and related components
  • CVX05 - Excess Letdown and Seal Return
  • SIAOI-HHSIA Loop
  • VNCCA5 1- Containment Fan Cooler A
  • VNCCA52 - Containment Fan Cooler B RCS Draln-Down Sequence (part 1)

Following O-RT-003, The RCS is drained 60% to 70% Reactor vessel level and the SIG tubes are burped, (reactor coolant is displaced with Nitrogen gas), per OP-4). The RCS will then be vented to allow removal of a majority of the S/G primry manway bolts. Actual breach of the RCS boundary is still not allowed 4 Ii

~4nfl9

RI1u uurage .scneaule Sarety Hevtew results Reduced Inventory and Mid-Loop RCS Drain-Down Sequence (part 2)

Following SIG tube burp and initial RCS vent, the RCS will be drained to Mid-loop.

During this period NO work will be allowed that could distract watch standers in any way.

When the RCS is at mid-loop and stable work will be allowed to resume as expressly authorized by the approved Orange Condition Contingency Plan.

Work That May Start While The RCS Is AT Reduced Inventory (after Draining complete and stable conditions are established)

Additional FEGs and components may be removed from service for maintenance during the reduced inventory period. The following is a list of FEGs and components that may be removed from service.

  • RCX00 - RCS Boundary - During this time the pressurizer mnanway will be removed to establish a large hot leg vent. This is required to be complete prior to installing any hot leg nozzle dam.
  • RCX02 - Mid-loop Work - Remove S/G primary manways, survey channel-heads, and install nozzle dams. Also the work on SI-00845A will be performed during this timeframe. This work must proceed expeditiously to allow rapid exit of ORANGE risk condition.

5 onfl _

R128 OutafAe schedunlpSafety Review results

3) Enter Mode 6 to Start of Fuel Movement Disassemble Reactor and Prepare to Move Fuel Work That May Start When The RCS Is No Longer at Reduced Inventory Additional FEGs and components may be removed from service for maintenance immediately following the reduced inventory period. The following is a list of FEGs and components that may be removed from service.
  • MSA21- Steam GeneratorA Feed Check Testing
  • SIBO - Safety Injection B-train.

VNCC52B - Containment Fan Cooler D.

6 nfl1

R128 Outage Schedule Safety Review results When the Refueling Cavity is filled to Rod Unlatch Height, the Inventory KSF changes state as follows:

When the Upper Internals are removed, the Core Cooling KSF changes state, (this change of state may have occurred earlier based upon TTB but is not credited until this point for purposes of the plan). Additionally, the Containment KSF changes reliance on DHE capability from fan coolers to the refueling cavity with internals removed AND Inventory margin is increased by removal of the flow restriction caused by the upper internals. Changes occur as follows:

  • l.

Work That Must finish to support fuel motion The approaching MCC B42 outage and the significant quantity of RWST and CVCS work will require that the SI "A" boration flow path be restored to service to support fuel motion during the next phase. SI-00826A will be opened and de-energized to support this 7 ofl 9

R128 Outage Schedule Safety Review results

4) Start Fuel Movement to Reload Complete The Refueling Pool Is Filled Work That May Start When the Refueling Pool is Full Additional FEGs and components may be removed from service for maintenance after the refueling cavity is full. The following is a list of FEGs and components that may be removed from service.
  • CVX02 - Low Pressure Letdown
  • CVX03 - Normal Charging Header
  • CVX04 - Seal Injection
  • CVX06 - Auxiliary Charging Header
  • CVX07 - Blender and RWST injection flow paths
  • CVX08 -Emergency Borate flow path
  • SIX31-Refueling Water Storage Tank, in particular, the ivork on SI-00742.
  • RHBO 1 - Residual Heat Removal B train, in particular, the bus bar bracing work on MCC B-42 and the replacement of the P-01OB Rotating Assembly.
  • Y-04 breaker replacements.
  • AFBII -P-038B will be lostto Unit 2 fora period oftime to perform some of the MR 00-037, control room MOB replacement modification, work packages. This will result in a 3.7.5.C Auxiliary Feed "B" TSAC of 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> duration.

It is imperative that these 1WPs be worked as scheduled so as to limit the adverse impact to risk significant components on either unit or protected components on the refueling unit.

  • 4KVXOI - X04 Transformer work. THEN when X04 is RTS,
  • 13KVXOI - X03 Transformer work will be performed.

n

  • X

. Infl9

R128 Outage Schedule Safety Review results 6C Re-Fuel the Reactor 4t5

. 9nfl(

k1zd uucage bcneauie barecy tceview resuics (5) Reload Complete to Head Set Please note that although not required, tits expectedthatfuel motion will be complete priorto DHR trainswap.

Work That May Start When the Reactor is Re-Fueled Additional FEGs and components may be removed from service for maintenance after the Reactor is refueled. The following is a list ofFEGs and components that may be removed from service.

SIAOI - Safety Injection "" train.

It 91 Steam Generator Secondary Side Work Steam Generator secondary side internal work will be performed during this period of time as hoses may now be placed through the personnel hatch. This includes tasks that although not critical, are significant to the completion of outage and to the Containment KSF:

  • Tube-sheet Cleaning
  • Feed-water flow transmitter root valve replacements
  • Repack if CS-146, FRV outlet bypass valve.

During the work on the Feed water flow root valves and the repack of CS-I 46, the containment boundary will be maintained by CS476AA, the main feed check valve. This valve will have been tested leak tight earlier in the outage per IT-305.

Work That Must Finish to Swap DIR Loops In nfl1

+/-uze uurage bcneauie barecy Keview resuits Some FEGs and components must be returned to service for operations use before work may commence on the 2Ud train of RHRIDHR. The following is a list of FEGs and components that must be returned to service.

  • RHB0I - "B" train RER loop. Specificallyreplacement of the P-OIOB Rotating Assembly and completion of the bus bracing modification to MCC B42.

SIDC31 - Refueling Water Storage Tank, in particular, the work on SI-00742. Return of the RWST is required to refill RHR ¶B"-train.

  • AFB 1 - P-03 8B related work packages for MR 00-037, control room MOB replacement modification. This will exit the 3.7.5.C Auxiliary Feed "B" TSAC.

It is imperative that these IWPs be worked as scheduled so as to limit the adverse impact to risk significant components on either unit or protected components on the refueling unit.

Work That May Start After DHR Train Swap Additional FEGs and components may be removed from service for maintenance afier "B" train of DHR has been returned to service. The following is a list of FEGs afid components that may be removed from service.

  • RHAO1 -Residual Heat Removal "A" train.
  • AFAI 1 - P-038A will be lost to Unit 2 to perform some of the MR 00-037, control room MOB replacement modification, work packages. This will result in a 3.7.5.C Auxiliary Feed "A" TSAC of 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> duration.

It is imperative that these IWPs be worked as scheduled so as to limit the adverse impact to risk significant components on either unit or protected components on the refueling unit. v 11 nf IC)

R128 Outage Schedule Safety Review results Work That Must Finish before the ECCS LRPM Testing Some FEGs and components must be returned to service prior to proceeding with testing that requires fuel motion to be complete and the refueling pool to be fall. The following is a list of FEGs and components that must be returned to service to perform ECCS LRPM testing.

  • SIA01 -High Head SafetyInjection A-Train
  • SIB01 - High Head Safety Injection B-Train.

12 nf 19

R128 Outage Schedule Safety Review results Risk associated with A-Train ECCS LRPM testing Perfomnance of 0-4T-530C changes KSF status as follows:

4 Risk associated with B-Traln ECCS LRPM testing Performnance of 0-IT-530D changes KSF status as follows:

1' nfl 9

R128 Outage Schedule Safety Review results Work That Must Finish Before Lowering Refueling Pool Level Some FEGs and components must be returned to service prior to lowering refueling pool level. The following is a list of FEGs and components that must be returned to service to lower RFP level.

  • CVX02 - Low Pressure Letdown.

X CVX03 -Normal Charging Header.

  • CVX05 -RCP Seal Injection.
  • CVX06 -Auxiliary Charging Header.
  • CVX07 - Blender.
  • CVX08 - Emergency Boration Line.
  • The Sump B debris screen must be installed.
  • 4KVX1l - X04 Transformer work Reactor Reassembly 14 nf19

R128 Outage Schedule Safety Review results 4

RPsk 4

Risk 1.5 of 19

ueZa uurage ocneouLe bazecy treview resuics

6) Head Set to Enter Mode 5 Reduced Inventory and Mld-Loop Work That Must be Complete to Enter Reduced Inventory Some FEGs and components should be returned to service prior to entering into reduced inventory to achieve the greatest possible defense in depth.
  • 4KVXOI - X04 Low Voltage Station Auxiliary Transformer.
  • 13KVXOI - X03 High Voltage Station Auxiliary Transformer.
  • VNCCX52 - D Containment Fan Cooler Unit
  • The work associated with B-41 must be complete.

165nflq

R128 Outage Schedule Safety Review results A'

7) 5 to RCS Filled and Vented Fill & Vent Work That Will be Performed While The RCS Is In Mode 5 a SIAXI - High Head Safety Injection A-Train Filled and Intact, but not available.

This is required to perform the MOV testing of SI-00858A and D. THEN:

  • SIBXI - High Head Safety Injection B-Train Filled and Intact, but not available.

This is required to perform the MOV testing of SI-00858B and C.

Risks 17 nf 19

R128 Outage Schedule Safety Review results 4

CS Filled and Vented to Enter Mode4 Containment Recovery 1R nf 19

R128 Outage Schedule Safety Review results

9) Enter Mode4 to Enter Mode3 Risk During the plant recovery through Modes 3, (Hot Standby), 2, (Startup), and 1, (Power Operation), risk is evaluated using the On Line Safety Monitor. NP 10.3.6 is Dot in effect after the plant achieves Mode 3.
10) EnterMode 3 to Enter Mode2 Risk During the plant recovery through Modes 3, (Hot Standby), & 2, (Startup), and 1, (Power Operation), risk is evaluated using the On Line Safety Monitor. NP 10.3.6 is not in effect after the plant achieves Mode 3.
11) Enter Mode2 to On-Line Risk During the plant recovery through Modes 3, (Hot Standby), & 2, (Startup), and 1, (Power Operation), risk is evaluated using the On Line Safety Monitor. NP 10.3.6 is not in effect after the plant achieves Mode 3.

FinalOn-Line to Full Power Risk During the plant recovery through Modes 3, (Hot Standby), & 2, (Startup), and 1, (Power Operation), risk is evaluated using the On Line Safety Monitor. NP 10.3.6 is not in effect after the plant achieves Mode 3.