ML033560473

From kanterella
Jump to navigation Jump to search
Undated IR 05000400-02-011, on 12/20/2002, Carolina Power & Light Co., New Hill, North Carolina
ML033560473
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 11/28/2003
From: Ogle C
Division of Reactor Safety I
To: Scarola J
Carolina Power & Light Co
References
FOIA/PA-2003-0358 IR-02-011
Download: ML033560473 (32)


See also: IR 05000400/2002011

Text

Carolina Power & Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

Shearon Harris Nuclear Power Plant

P. 0. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT: SHEARON HARRIS NUCLEAR PLANT - NRC INSPECTION REPORT

50-400/02-11

Dear Mr. Scarola:

On December 20, 2002, the Nuclear Regulatory Commission (NRC) completed a triennial fire

protection inspection at your Shearon Harris Nuclear Plant. The enclosed integrated inspection

report documents the inspection findings which were discussed on that date with you and other

members of your staff.

The inspection examined the effectiveness of activities conducted under your license relating to

implementation of your NRC-approved fire protection program. The inspectors reviewed

selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, the inspectors identified eight issues of very low safety

significance (Green). Each of these issues was determined to involve a violation of NRC

requirements. However, because of their very low safety significance and because they have

been entered into your corrective action program, the NRC is treating these issues as Non-

Cited Violations (NCVs), in accordance with Section VI.A.1 of the NRC's Enforcement Policy.

In addition, since three of these findings are related to your corrective action for the previous

violation associated with the Thermo-Lag fire barrier assembly between the 'B' train switchgear

room/auxiliary control panel room and the A train cable spreading room, that violation will

remain open. If you deny any NCV in this report, you should provide a response with the basis

for your denial, within 30 days of the date of this inspection report, to the Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001; with copies to the

Regional Administrator, Region II; Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at

the Shearon Harris Nuclear Plant.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be publicly available in the NRC Public Document Room or from the Publicly

AY

CP&L 2

Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.pov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No.: 50-400

License No.: NPF-63

Enclosure: NRC Inspection Report 50-400/02-11

w/Attachment

cc wfencl:

Distribution w/encl:

PUBLIC

OFFICE RII:DRS RI1:DRS RII:DRS RII:DRP RII:DRS RII:DRS RII:DRP

SIGNATURE

NAME RSchin GWiseman PFillion RHagar SWalker DCPayne PFreddckson

DATE 1/_J2003 1J2003 1IJ2003

I/ 1IJ2O3 1LJ2003 1I.J2003 1LJ2003

E-MAIL COPY? YES NO YES NO

N S NO IYES N YES NO I YES NO

.PUBLIC DOCUMENT YES NO I I I I II

n.JrrI'.P.lA~l~ J Lr I - Pwh-

nrlJAUMDKIT r-'UADD -u.. I rDw

-

Vrrl%.,IL MMUrn .Uur I uUtoumaN I NAML; rM:\l1AHlrU-022 IaI .

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 50-400

License No.: NPF-63

Report No.: 50-400/02-11

Licensee: Carolina Power & Light (CP&L)

Facility: Shearon Harris Nuclear Plant

Location: 5413 Shearon Harris Road

New Hill, NC 27562

Dates: October 21 - 25, 2002 (Week 1)

November 4 - 8, 2002 (Week 2)

December 16 - 20, 2002 (Week 3)

Inspectors: P. Fillion, Reactor Inspector, Region II

R. Hagar, Resident Inspector, Shearon Harris (Week 3 only)

C. Payne, Fire Protection Team Leader, Region II (Week 3 only)

R. Schin, Senior Reactor Inspector, Region II (Lead Inspector)

S. Walker, Reactor Inspector (Week 3 only)

G. Wiseman, Senior Fire Protection Inspector, Region II (Weeks 1

&2)

Accompanying

Personnel: H. Christensen, Deputy Director, Division of Reactor

Safety, Region II (Week 3 only)

C. Ogle, Chief, Engineering Branch 1, Division of Reactor

Safety, Region II (Week 3 only)

N. Staples, Inspector Trainee, Region II (Weeks 1 & 2)

Approved by: Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000400-02-11; Carolina Power & Light; on 10/21/2002 - 12/20/2002, Shearon Harris

Nuclear Plant, Triennial Baseline Inspection of the Fire Protection Program.

The inspection was conducted by a team of regional inspectors and the Shearon Harris resident

inspector. Eight Green findings, each a Non-Cited Violation (NCV), were identified. The

significance of issues is indicated by their color (Green, White, Yellow, Red) using IMC 0609

"Significance Determination Process" (SDP). Findings for which the SDP does not apply may

be "Green" or be assigned a severity level after NRC management review. The NRC's program

for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.

Inspection Identified Findings

Cornerstones: Mitigating Systems and Initiating Events

Green. An NCV of Shearon Harris Operating License Condition (OLC) 2.F, Fire

Protection Program; and Technical Specification (TS) 6.8.1, Procedures and Programs,

was identified for failing to protect.equipment [motor-operated valve (MOV) 1CS-1 65,

volume control tank (VCT) outlet to charging/safety injection pumps (CSIPs)] from

maloperation due to a fire. Consequently, a fire in any of three different SSA areas of

the reactor auxiliary building (RAB) could result in a reactor coolant pump (RCP) seal

loss of coolant accident (LOCA) with no operable high pressure safety injection.

This finding had a credible impact on safety because it could result in a loss of

equipment that was relied upon for safe shutdown from a fire and could initiate a LOCA

event. However, the finding was of very low safety significance because of the low fire

initiation frequency and probability of spurious actuations, and the effectiveness of

automatic sprinklers, fire brigade, and remaining safe shutdown (SSD) equipment to

limit the effects of a fire and to shut down the nuclear reactor. Therefore, this finding is

characterized as Green (Section 1R05.03.b.1).

  • Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to protect equipment

[MOVs 1CS-169, CSIP suction cross-connect; 1CS-214, CSIP mini-flow isolation; 1CS-

218, CSIP discharge cross-connect; and 1CS-219, CSIP discharge cross-connect] from

maloperation due to a fire. Consequently, a fire in one SSA area of the RAB could

result in a loss of all charging and high pressure safety injection.

This finding had a credible impact on safety because it could result in a loss of

equipment that was relied upon for safe shutdown from a fire. However, the finding was

of very low safety significance because of the low fire initiation frequency and probability

of spurious actuations, and the effectiveness of automatic sprinklers, fire brigade, and

remaining SSD equipment to limit the effects of a fire and to shut down the nuclear

reactor. Therefore, this finding is characterized as Green (Section 1R05.03.b.2).

  • Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to protect equipment

[MOVs 1CS-1 66, VCT outlet to CSIPs; and 1CS-1 68, CSIP suction cross-connect] from

2

maloperation due to a fire. Consequently, a fire in one SSA area of the RAB could

result in a loss of all charging and high pressure safety injection.

This finding had a credible impact on safety because it could result in a loss of

equipment that was relied upon for safe shutdown from a fire. However, the finding was

of very low safety significance because of the low fire initiation frequency and probability

of spurious actuations, and the effectiveness of automatic sprinklers, fire brigade, and

remaining SSD equipment to limit the effects of a fire and to shut down the nuclear

reactor. Therefore, this finding is characterized as Green (Section 1R05.03.b.3).

  • Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to protect equipment

[MOVs 1CC-208, component cooling (CC) supply to RCP seals; and 1CC-251, CC

return from RCP seals] from maloperation due to a fire. Consequently, a fire in one

SSA area of the auxiliary building could potentially result in an RCP seal LOCA.

This finding had a credible impact on safety because it could result in a loss of

equipment that was relied upon for safe shutdown from a fire and could potentially

initiate a LOCA event. However, the finding was of very low safety significance because

of the low fire initiation frequency and probability of spurious actuations, and the

effectiveness of automatic sprinklers, fire brigade, and remaining SSD equipment to limit

the effects of a fire and to shut down the nuclear reactor. Therefore, this finding is

characterized as Green (Section 1R05.03.b.4).

  • Green. An NCV of TS 6.8.1 and OLC 2.F was identified for inadequate procedural

steps and for inadequate corrective action. For a fire in the new auxiliary control panel

(ACP) fire area, certain SSD procedure steps involved excessive challenges to

operators. There was not reasonable assurance that all NLOs could perform the steps

during a fire. Consequently, a fire in the ACP fire area could result in a loss of all

auxiliary feedwater (AFW). The licensee had added these inadequate procedure steps

during this inspection, as part of the corrective action for violation 50-400/02-08-01

regarding an inadequate fire barrier wall.

This finding had a credible impact on safety because it could result in inability to operate

equipment that was relied upon for SSD from a fire. However, the finding was of very

low safety significance because of the low fire initiation frequency, fire brigade, and

remaining SSD equipment to limit the effects of a fire and to shut down the nuclear

reactor. Therefore, this finding is characterized as Green (Section 1R05.04.b.2).

  • Green. An NCV of TS 6.8.1 and OLC 2.F was identified for an inadequate procedure for

SSD from a fire and for inadequate corrective action. For a fire in certain SSA areas of

the RAB, including the new ACP fire area, there were too many SSD procedure

contingency actions to respond to potential spurious actuations for the one available

SSD NLO to perform all of them. Consequently, equipment that was relied on for SSD

may not be available. The licensee had added some of these procedure steps as part

of the corrective action for violation 50-400/02-08-01 regarding an inadequate fire

barrier wall.

This finding had a credible impact on safety because it could result in inability to prevent

an initiating event or to operate equipment that was relied upon for SSD from a fire.

3

However, the finding was of very low safety significance because of the low fire initiation

frequency, automatic sprinklers, fire brigade, and remaining SSD equipment to limit the

effects of a fire and to shut down the nuclear reactor. Therefore, this finding is

characterized as Green (Section 1R05.04.b.3).

Green. An NCV of TS 6.8.1 was identified for an inadequate procedure for SSD from a

fire. For a fire in two SSA areas of the RAB, the SSD procedure directed operators to

take CSIP suction from the boric acid tank (BAT) even if BAT level indication were lost.

However, the charging volume needed for reactor coolant system (RCS) cooldown

would have emptied the BAT and damaged the CSIP.

This finding had a credible impact on safety because it could result in loss of equipment

that was relied upon for SSD from a fire. However, the finding was of very low safety

significance because of the low fire initiation frequency, automatic sprinklers, fire

brigade, and remaining SSD equipment to limit the effects of a fire and to shut down the

nuclear reactor. Therefore, this finding is characterized as Green (Section 1R05.04.-).

Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to provide battery-

backed emergency lights for operators to perform actions for SSD from a fire and for

inadequate corrective action. For a fire in all of the areas inspected in the auxiliary

building, including the new ACP fire area; many SSD procedure operator action

locations did not have the required battery-backed emergency lights. The licensee had

added some of these procedure steps as part of the corrective action for violation 50-

400/02-08-01 regarding an inadequate fire barrier wall.

This finding has a credible impact on safety because it could result in increased risk of

operators failing to perform SSD actions in an accurate and timely manner. However,

the finding was of very low safety significance because operators had flashlights

available which would have enabled them to perform the actions. Therefore, this finding

is characterized as Green (Section 1R05.04.-).

Report Details

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 FIRE PROTECTION

.01 Systems Required To Achieve and Maintain Post-Fire SSD Circuit Analysis

a. Inspection Scope

The team evaluated the licensee's approved fire protection program (FPP) against

applicable requirements, including Operating License NFP-63, License Condition 2.F,

FPP; Branch Technical Position (BTP) Chemical Engineering Branch (CMEB) 9.5-1

(NUREG-0800), July 1981; related NRC Safety Evaluation Reports (SERs) in NUREG

1038, and plant Technical Specifications (TS). The team evaluated all areas of this

inspection, as documented below, against these requirements.

The team used the licensee's Individual Plant Examination for External Events (IPEEE)

and in-plant tours to select four risk significant fire areas/zones for inspection. The four

fire areas/zones selected were:

Fire Zone 1-A-4-CHLR; part of Fire Area 1-A-BAL-B:

This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It

was further subdivided in the licensee's Safe Shutdown Analysis (SSA) into SSA areas 1-

A-BAL-B-B1 [including the "A" chiller and motor-driven AFW pump flow control valves

(FCVs)] and 1-A-BAL-B-B2 [including the "B" chiller and turbine-driven TDAFW pump

FCVs]. A significant fire in either of these areas would require shutdown of the unit from

the main control room (MCR) and additional manual operator actions in various areas of

the plant.

  • Fire Zone 1-A-4-COM-E; part of Fire Area 1-A-BAL-B:

This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It

was further subdivided in the licensee's SSA to SSA areas 1-A-BAL-B-B4 (including

480V MCC 11B35-SB) and 1-A-BAL-B-B5 (including 480V MCC 1A35-SA). A significant

fire in either of these areas would require shutdown of the unit from the MCR and

additional manual operator actions in various areas of the plant.

  • Fire Area 1-A-EPA:

This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It

included electrical penetration room 'A'. A significant fire in this area would require

shutdown of the unit from the MCR and additional manual operator actions in various

areas of the plant.

  • Fire Area 1-A-BATB:

2

This fire zone was located on the 286 foot level (above ground level) of the auxiliary

building. It included the 'B' electrical battery room. A significant fire in this area would

require shutdown of the unit from the MCR and additional manual operator actions in

various areas of the plant.

The team reviewed the post-fire SSD capability and the fire protection features to verify

that at least one post-fire safe shutdown success path would be maintained free of fire

damage during a fire in any of the selected fire areas/zones. The team reviewed the

licensee's fire protection program, including the SSA and supporting calculations, to

determine the systems required to achieve post-fire SSD. The team also reviewed the

Safe Shutdown Equipment List, system flow diagrams, and the Fire Hazards Analysis

(FHA) in the Updated Final Safety Analysis Report (UFSAR) for each of the selected fire

areas to evaluate the completeness and adequacy of the SSD analysis and the systems

relied upon to mitigate fires in the selected fire areas. Specific licensee documents and

drawings reviewed during the inspection are listed in the Attachment.

b. Findings

The team found that the licensee's SSA method for dealing with problem cables (i.e.,

cables that were required for control room operation of SSD equipment during a fire in a

certain area but were not physically protected from that fire) was to primarily rely on

operator manual actions (e.g., locally open the breaker to an MOV and locally operate

the MOV using the handwheel). Only if no operator action could be found would the

licensee physically protect the cables. Consequently, the licensee had over 100 local

manual operator actions that they relied on for achieving hot shutdown conditions during

a fire. The licensee had not requested deviation approvals from the NRC for these

operator actions and had not verified or validated the operator actions to the extent that

would have been involved in NRC reviews of deviation requests. This SSD methodology

contributed to the findings and unresolved item (URI) that are described in the following

sections of this report.

.02 Fire Protection of SSD CaDability

a. Inspection Scope

The team reviewed UFSAR Section 9.5.1, Appendix 9.5A, Fire Hazards Analysis (FHA);

the FPP manual; and plant administrative fire prevention/combustible hazards-ignition

source control procedures. This review was to verify that the objectives established by

the NRC-approved FPP were satisfied. The team also toured the selected plant fire

areas observing the licensee's implementation of these procedures. The team also

reviewed the FPP transient combustible permit logs, and fire emergency/incident

investigation reports, for the years 2000-2002. Corrective action program Action

Requests (ARs) resulting from fire, smoke, sparks, arcing, and equipment overheating

incidents for the same period were also reviewed to assess the effectiveness of the fire

prevention program and to identify any maintenance or material condition problems

related to fire incidents.

3

The team reviewed flow diagrams and engineering calculations associated with the 'B'

battery room heating, ventilation, and air conditioning (HVAC) systems. This review was

done to verify that systems used to accomplish safe shutdown would not be inhibited by

a potential hydrogen gas fire in the 'B' battery room due to inoperable ventilation supply

and exhaust fans. The team also reviewed the TS LCO requirements for loss of

ventilation in the 'B' battery room to verify that appropriate timely actions were specified

to ensure that hydrogen gas concentrations generated by the station batteries remained

below explosive limits.

The team toured the plant's primary fire brigade staging and dress-out areas to assess

the condition of fire fighting and smoke control equipment. Fire brigade personal

protective equipment located in brigade staging area lockers was reviewed to evaluate

equipment accessibility and functionality. Additionally, the team examined whether

backup emergency lighting was provided for access pathways to and within the fire

brigade staging and dress-out areas in support of fire brigade operations should a power

failure occur during the fire emergency. The team also observed whether emergency

exit lighting was provided for personnel evacuation pathways to the outside exits as

identified in the National Fire Protection Association (NFPA) 101, Life Safety Code and

Occupational Safety and Health Administration (OSHA) Part 1910, Occupational Safety

and Health Standards. The adequacy of the fire brigade self-contained breathing

apparatus (SCBAs) was reviewed as well as the availability of supplemental breathing air

tanks.

Team members also toured the selected fire areas and compared the associated fire

pre-plans with as-built plant conditions. This was done to verify that they were consistent

with the fire protection features and potential fire conditions described in the UFSAR.

Additionally, the team reviewed drawings and engineering flood analysis associated with

the 261-foot elevation reactor auxiliary building floor and equipment drain system to verify

that those actions required for SSD would not be inhibited by fire suppression activities or

leakage from fire suppression systems.

The team reviewed the fire brigade response procedure, fire brigade organization, and

training and drill program administration procedures. Fire drill critiques of operating shifts

for the period of March 2001 through October 2002 were reviewed to verify that fire

brigade drills had been conducted in high fire risk plant areas. Fire brigade training/drill

records for 2002 were also reviewed to verify that the fire brigade personnel

qualifications, brigade drill response time, and brigade performance met the

requirements of the licensee's approved FPP. Additionally, the team observed a fire drill

to verify the licensee's implementation of the fire brigade organization, training, and drill

program administration procedures. The team observed the actions of the site fire

brigade, offsite fire department, and fire drill monitors; and attended the drill critique.

b. Findings

No findings of significance were identified.

.03 Post-Fire SSD Circuit Analysis

a. Inspection Scope

4

The team reviewed the adequacy of separation and fire barriers provided for the power

and control cabling of equipment relied on for SSD during a fire in any of the selected fire

areas/zones. On a sample basis, the team reviewed the SSA and the electrical

schematics for power and control circuits of SSD components, and looked for the

potential effects of open circuits, shorts to ground, and hot shorts. This review focused

on the cabling of selected components for the charging/safety injection system, AFW

system, and component cooling water (CC) system. The team traced the routing of

cables by using the cable schedule and conduit and tray drawings. Walkdowns were

performed to compare 1-hour and 3-hour barriers (conduit and tray fire barrier wraps) to

barriers indicated on the drawings. Circuit and cable routings were reviewed for the

following equipment: 1CS-169, CSIP suction cross connect MOV; 1CS-168, CSIP

suction cross connect MOV; 1CS-214, CSIP minimum flow MOV; 1CS-217, CSIP

discharge cross connect MOV; 1CS-218, CSIP discharge cross connect MOV; 1CS-219,

CSIP discharge cross connect MOV; 1CS-1 65, volume control tank (VCT) outlet MOV;

1CS-166, VCT outlet MOV; 1CS-278, boric acid tank (BAT) to CSIP MOV; BAT level

instrumentation; 1CC-207, CC supply to RCP seals MOV; 1CC-208, CC supply to RCP

seals MOV; 1CC-252, CC return from RCP seals MOV; 1CC-251, CC return from RCP

seals MOV; 1CC-249, CC return from RCP seals MOV; 1RC-117, pressurizer power-

operated relief valve (PORV) block valve; 1Sl-310, containment sump to 'A' RHR pump

MOV; 1SI-311, containment sump to 'B' RHR pump MOV; motor-driven AFW pump 1A;

motor-driven AFW pump 1B; and turbine-driven AFW pump.

The team also reviewed studies of overcurrent protection on both AC and DC systems to

identify whether fire induced faults could result in defeating the safe shutdown functions.

b. Findings

(1) MOV 1CS-1 65. VCT Outlet to CSIPs

Introduction

The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to protect equipment

[MOV 1CS-165] from maloperation due to a fire. Consequently, a fire in any of three

different areas of the auxiliary building could result in an RCP seal LOCA with no

operable high pressure safety injection.

Description

The team found that the control power cable for charging system MOV 1CS-1 65; which

was relied upon to remain open for SSD during a fire in SSA areas 1-A-BAL-B-B1 and 1-

A-BAL-B-B2, and in fire area 1-A-EPA; was routed through those areas with no fire

barrier. As a result, the control power cable for the MOV was vulnerable to fire-induced

hot shorts which could result in spurious valve operation. The lack of a required fire

barrier was not recognized in the SSA and no procedural guidance was included in AOP-

36, Safe Shutdown Following a Fire, Rev. 21, for operators to prevent maloperation of

1CS-165 prior to damage occurring to SSD equipment. Consequently, a fire in one of

the three SSA areas could cause 1CS-165 to spuriously close, isolate all CSIP suction

flowpaths, and immediately damage the operating SSD CSIP.

5

The SSD analysis for a fire in SSA areas 1-A-BAL-B-B1, 1-A-BAL-B2, or 1-A-EPA was to

rely on SSD Division 2 equipment. This included reliance on CSIP 'B' for RCS makeup

water, RCP seal cooling, reactivity control by boration, and high pressure safety injection.

The SSA assumed that CSIP 'A' was not assured to be unaffected by the fire and CSIP

'C' was not assured to be available. Consequently, a failure of CSIP 'B' could result in a

loss of all charging and high pressure safety injection. Also, for a fire in any of these

three SSA areas, CC flow to the RCP seals was not protected. The team found that the

control power cable to MOV 1CC-207, CC flow to RCP seals, was also routed through

the same three SSA areas in the same cable tray with the control power cable to 1CS-

165. AOP-36 included no operator action to prevent spurious operation of MOV 1CC-

207. Spurious closure of MOV 1CC-207 would stop all CC flow to the seals of all three

RCPs. Thus the potential consequences of a fire in any of the three SSA areas could be

an RCP seal LOCA with no charging or high pressure injection.

Also, the team found that the control power cables for MOVs 1CC-252, CC return from

RCP seals, and 1CC-249, CC return from RCP seals, were routed through SSA area 1-

A-BAL-B-B2 and could be affected by a fire in that area. AOP-36 included an operator

action to prevent spurious actuation of 1CC-252 for a fire in SSA area 1-A-BAL-B-B2.

That action included opening the breaker to MOV 1CC-252 on MCC 1El 2. However, the

SSD NLO would likely not be able to safely do that action during a fire in SSA area 1-A-

BAL-B-B2 because MCC 1El 2 was located in that SSA area. AOP-36 included no

operator action for 1CC-249. Spurious closure of 1CC-252 or 1CC-249 would stop all

CC flow to the RCP seals. The team noted that, while the operator action for 1CC-252

may not be needed for a fire in SSA area 1-A-BAL-B-B2 because the charging system

was supposed to provide RCP seal cooling, this inappropriate procedural action (sending

an operator into an area where there was a fire) could delay the SSD NLO from

performing other procedure actions that were required to achieve SSD.

In addition, the team found that modification ESR 01-00087, which was installed in

January 2002, had affected this condition and missed an opportunity to correct it. ESR

01-00087 changed the CSIP mini-flow path so that it would go to the VCT instead of

going directly to the CSIP suction. Prior to the ESR, if 1CS-1 65 spuriously closed, the

running CSIP would still have some suction although probably not enough to prevent

pump damage. After the ESR, if 1CS-165 spuriously closed, the running CSIP would

have no suction and CSIP failure would be more certain and more immediate. ESR 01-

00087 failed to recognize this effect and missed an opportunity to identify and correct the

condition.

Analysis

This finding had more than minor safety significance because it affected the Mitigating

Systems and Initiating Events objectives of the Reactor Safety Cornerstone. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences. It also affected the likelihood of occurrence of initiating

events that challenge critical safety functions. However, the finding was of very low

safety significance because of the low fire initiation frequency and probability of spurious

actuations, and the effectiveness of automatic sprinklers, fire brigade, and remaining

SSD equipment to limit the effects of a fire and to shut down the nuclear reactor.

Therefore, this finding is characterized as Green.

6

Enforcement

OLC 2.F. required that the licensee implement and maintain in effect all provisions of the

approved fire protection program as described in the Final Safety Analysis Report. The

UFSAR, Section 9.5.1, Fire Protection Program (FPP), stated that outside containment,

where cables or equipment (including associated non-essential circuits that could prevent

operation or cause maloperation due to hot shorts, open circuits, or shorts to ground) of

redundant safe shutdown divisions of systems necessary to achieve and maintain cold

shutdown conditions are located within the same fire area outside of primary

containment, one the redundant divisions must be ensured to be free of fire damage.

Section 9.5.1 further stated that if both divisions are located in the same fire area, then

one division is to be protected from fire damage by one of three methods: 1) a three-hour

fire barrier, 2) a one-hour fire barrier plus automatic detection and suppression, or 3) a

20-foot separation with no intervening combustibles and with automatic detection and

suppression.

TS 6.8.1 required procedures as recommended by Regulatory Guide (RG) 1.33 and

procedures for fire protection program implementation. RG 1.33 recommended

procedures for combating emergencies, including fires. The licensee's interpretation of

their fire protection program was that they could and would rely on operator actions in

place of physical protection of SSD equipment (see Section ___). However, the

licensee had failed to provide procedural guidance in AOP-36 for operators to prevent

maloperation of MOV lCS-165.

Contrary to the above requirements, the licensee failed to protect MOV 1CS-165 from

maloperation due to a fire where it was relied on for SSD. Because the licensee entered

the finding into the corrective action program as AR 76260, this item is being treated as

an NCV in accordance with Section VI.A.1 of the NRC's Enforcement Policy. This item is

identified as NCV 50-400/02-11 -01, Failure to Protect MOV 1CS-1 65, VCT Outlet to

CSIPs, From Maloperation Due To a Fire.

(2) MOV 1CS-169. CSIP Suction Cross-connect: MOV JCS-214. CSIP Mini-flow Isolation:

MOV 1CS-218. CSIP Discharge Cross-connect: and MOV 1CS-219, CSIP Discharge

Cross-connect

Introduction

The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to protect equipment

[MOVs 1CS-169, 1CS-214, ICS-218, and i CS-219] from maloperation due to a fire.

Consequently, a fire in one SSA area of the auxiliary building could result in a loss of all

charging and high pressure safety injection.

Description

The team found that the control power cables for charging system MOVs 1CS-1 69, 1CS-

214, 1CS-218, and 1CS-219, which were relied upon to remain open for SSD during a

fire in SSA area 1-A-BAL-B-B5, were routed through that area with incomplete fire

barriers. The control cables were unprotected for about one foot above MCC 1-A35-SA

and inside the MCC.

7

This lack of required fire barriers was recognized in the SSA for 1CS-1 69, 1CS-214, and

1CS-218, and procedural guidance was included in AOP-36 for operators to prevent

maloperation of these valves. However, the procedural guidance was not adequate.

AOP-36 directed operators to go to MCC 1A35-SA and open the breakers for 1CS-169

and 1CS-214 to prevent spurious operation. However, operators would not be able to

safely do that because the actions were in the area of the fire that could cause the

spurious operation. AOP-36 directed operators to go to MCC 1B35-SB, in another room,

to open the breaker for 1CS-218. However, operators would not be able to do that

because the breaker for 1CS-218 was actually located on MCC 1A35-SA. The SSA had

not identified a need for operator action to prevent maloperation of 1CS-219 and AOP-36

included no action steps for that valve.

AOP-36 did include the following guideline for operators: "Monitor for spurious valve and

pump operation which may result in equipment damage (for example, CSIP suction

valves.)" The team noted that closure of a CSIP suction valve could result in pump

damage within seconds; before operators could respond to an annunciator, analyze the

condition, and take action to prevent pump damage. Another AOP-36 guideline was:

'When directed by the Unit Shift Supervisor, then shut down equipment and de-energize

electrical busses located within the fire area.' Operators stated that they would de-

energize MCC 1A35-SA if the fire brigade team leader or another operator told them that

the MCC was on fire or if they observed spurious actuations that could be initiating from

the MCC. However, the team noted that the fire brigade would not arrive and attack the

fire until about 20 minutes after the control room sounded the fire alarm, and spurious

actuations could occur well before that. By procedure, control room operators would

respond to a single fire detector annunciator by sending an NLO to verify that there was

a fire and that the fire was large enough to warrant sounding the fire alarm and calling

out the fire brigade. However, if the control room operators received annunciation from

two or more fire detectors, which would be very likely in the event of fire large enough to

present an operational safety concern, then they would not send an NLO but instead

would immediately sound the fire alarm and call out the fire brigade. So it was likely that

the first visual report on the fire would not be received in the control room until about 20

minutes after the fire alarm. By that time, the fire would have likely filled the room with

smoke so that the fire brigade would not be able to immediately identify if the MCC was

on fire.

The team concluded that it was unlikely that the control room would de-energize MCC

1A35-SA before spurious actuations could occur. Consequently, a fire in this area, near

or in MCC 1A35-SA, could cause any of the four MOVs to spuriously close. Closure of

1CS-214 would stop all mini-flow from all CSIPs. Closure of 1CS-218 or 1CS-219 would

stop charging flow from SSD CSIP 'B'. If such a loss of charging flow or CSIP mini-flow

occurred, operators would receive an alarm in the control room and would probably have

time to diagnose the condition and initiate recovery actions before CSIP damage

occurred. However, closure of 1CS-169 would stop all suction to SSD CSIP 'B' and

immediately damage the pump.

The SSD analysis for a fire in SSA area 1-A-BAL-B-B5 was to rely on SSD Division 2

equipment. This included reliance on CSIP 'B' for RCS makeup water, RCP seal cooling,

reactivity control by boration, and high pressure safety injection. CSIP 'A' was not

assured to be unaffected by the fire and CSIP 'C' was not assured to be available. The

8

team noted that MOVs powered from MCC 1A35-SA could affect CSIP 'A' and CSIP 'C'.

While the SSA did not assure that CC would be available, the team did not identify any

vulnerabilities of CC to a fire in this area. Consequently, the team concluded that the

potential consequences of a fire in SSA area 1-A-BAL-B5 could be a loss of all charging

and high pressure safety injection.

Analysis

This finding had more than minor safety significance because it affected the Mitigating

Systems objectives of the Reactor Safety Cornerstone. The finding affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences. However, the finding was of very low safety significance because of the

low fire initiation frequency and probability of spurious actuations, and the effectiveness

of automatic sprinklers, fire brigade, and remaining SSD equipment to limit the effects of

a fire and to shut down the nuclear reactor.

During the inspection, a question arose about whether a fire initiating inside an MCC

could credibly cause spurious actuations. A premise was that the power breaker to the

MCC would always trip before spurious actuations could occur. The team noted that the

frequency of a fire initiating inside an MCC was higher than the frequency of a fire

initiating just outside of an MCC, However, after further review, the team concluded that

the frequency for a fire starting outside or inside an MCC would still result in a very low

safety significance for the observed condition. Therefore, this finding is characterized as

Green.

Enforcement

As described in Section lA05.03.b.1 above, OLC 2.F. required that equipment relied

upon for SSD be physically protected against maloperation due to the fire. Also, TS 6.8.1 required procedures for implementing the fire protection program and for combating

fires.

Contrary to the above requirements, the licensee failed to protect MOVs 1CS-169,1CS-

214, 1CS-218, and 1CS-219 from maloperation due to a fire where they were relied on

for SSD. Because the licensee entered the finding into the corrective action program as

ARs 76260 and 80212, this item is being treated as an NCV in accordance with Section

VL.A.1 of the NRC's Enforcement Policy. This item is identified as NCV 50-400/02-11-03,

Failure to Protect Charging System MOVs I CS-169, 1CS-214,1 CS-218, and 1CS-219

From Maloperation Due To a Fire.

(3) MOV 1CS-1 66. VCT Outlet to CSIPs: MOV 1CS-1 68, CSIP Suction Cross-connect: and

MOV 1CS-217. CSIP Discharge Cross-connect

Introduction

The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to protect equipment

[MOVs 1CS-1 66, 1CS-1 68, and 1CS-217] from maloperation due to a fire.

Consequently, a fire in one SSA area of the auxiliary building could result in a loss of all

charging and high pressure safety injection.

9

Description

The team found that the control power cables for charging system MOVs 1CS-1 66,1 CS-

168, and 1CS-217, which were relied upon to remain open for SSD during a fire in SSA

area 1-A-BAL-B-B4, were routed through that area with incomplete fire barriers. The

control cable for MOV 1CS-166 was unprotected for about one foot above MCC 1B35-SB

and inside the MCC. The control power cables for MOVs 1CS-168 and 1CS-217 were

unprotected inside MCC 1B35-SB. This lack of required fire barriers was not recognized

in the SSA and no procedural guidance was included in AOP-36 for operators to prevent

or mitigate maloperation of these valves. Consequently, a fire in this area, near or in

MCC 1B35-SB, could cause 1CS-1 66 or 1CS-168 to spuriously close, which would stop

all suction to SSD CSIP 'A', and immediately damage the pump. If CSIP 'C' were aligned

to be used in place of CSIP 'A', then the fire could cause spurious closure of 1CS-217

and stop charging flow from CSIP C.

The SSD analysis for a fire in SSA area 1-A-BAL-B-B4 was to rely on SSD Division 1

equipment. This included reliance on CSIP 'A' for RCS makeup water, reactivity control

by boration, and high pressure safety injection. CSIP 'B' was not assured to be

unaffected by the fire and CSIP 'C' was not assured to be available. Also, when all three

CSIPs were available, the 'C' CSIP would be aligned to the 'B' train; and it would take

licensee personnel several hours to align the 'C' CSIP to the 'A' train. Consequently, a

failure of CSIP 'A' could result in a loss of all charging and high pressure safety injection.

If CSIP 'C' were aligned to be operating in place of CSIP 'A', and a maloperation of 1CS-

217 caused a loss of charging flow, operators would receive a loss of charging flow alarm

and would probably have time to diagnose and respond to the condition before the CSIP

was damaged.

In addition, the team found that modification ESR 01-00087, which was installed in

January 2002, had affected the significance of the lack of protection for 1CS-166. As

described above for 1CS-1 68, ESR 01-00087 was a missed opportunity to identify and

correct the lack of protection for 1CS-1 66.

Analysis

This finding had more than minor safety significance because it affected the Mitigating

Systems objectives of the Reactor Safety Cornerstone. The finding affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences. However, the finding was of very low safety significance because of the

low fire initiation frequency and probability of spurious actuations, and the effectiveness

of automatic sprinklers, fire brigade, and remaining SSD equipment to limit the effects of

a fire and to shut down the nuclear reactor. Therefore, this finding is characterized as

Green.

Enforcement

As described in Section 1R05.03.b.1 above, OLC 2.F. required that equipment relied

upon for SSD be physically protected against maloperation due to the fire. Also, TS 6.8.1 required procedures for implementing the fire protection program and for combating

10

fires.

Contrary to the above requirements, the licensee failed to protect MOVs 1CS-1 66, 1CS-

168, and 1CS-217 from maloperation due to a fire where they were relied on for SSD.

Because the licensee entered the finding into the corrective action program as AR

76260, this item is being treated as an NCV in accordance with Section VI.A.1 of the

NRC's Enforcement Policy. This item is identified as NCV 50-400/02-11-04, Failure to

Protect Charging System MOVs 1CS-166, 1CS-168, and 1CS-217 From Maloperation

Due To a Fire.

(4) MOV 1CC-251. CC Return From RCP Seals:

and MOV 1CC-208. CC SuppIV To RCP Seals

Introduction

The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to protect equipment

[MOVs 1CC-251 and 1CC-208] from maloperation due to a fire. Consequently, a fire in

one SSA area of the auxiliary building could potentially result in an RCP seal LOCA.

Description

The team found that the control power cables for CC system MOVs 1CC-251 and 1CC-

208, which were relied upon to remain open for SSD during a fire in SSA area 1-A-BAL-

C, were routed through that area and into MCC 1B31 in that area with no fire barrier.

Fire area 1-A-BAL-C was located on the 286 foot level of the auxiliary building, above

electrical penetration room 'B'. This lack of required fire barriers and need for operator

actions was recognized in the SSA but no procedural guidance was included in AOP-36

for operators to prevent or mitigate maloperation of these valves. Consequently, a fire in

this area could cause I CC-251 or 1CC-208 to spuriously close, which would stop all CC

flow to the RCP seals.

The SSD analysis for a fire in area 1-A-BAL-C was to rely on SSD Division 1 equipment.

This included reliance on CC to cool the RCP seals. CSIP supply to the RCP seals was

not assured to be unaffected by the fire. Consequently, a loss of CC to the RCP seals

could potentially result in a loss of all RCP seal cooling which could in turn result in an

RCP seal failure and a LOCA.

Analysis

This finding had more than minor safety significance because it affected the Initiating

Events objective of the Reactor Safety Cornerstone. The finding affected the likelihood

of occurrence of initiating events that challenge critical safety functions. However, the

finding was of very low safety significance because of the low fire initiation frequency and

probability of spurious actuations, and the effectiveness of automatic sprinklers, fire

brigade, and remaining SSD equipment to limit the effects of a fire and to shut down the

nuclear reactor. Therefore, this finding is characterized as Green.

Enforcement

11

As described in Section 1R05.03.b.1 above, OLC 2.F. required that equipment relied

upon for SSD be physically protected against maloperation due to the fire. Also, TS 6.8.1 required procedures for implementing the fire protection program and for combating

fires.

Contrary to the above requirements, the licensee failed to protect MOVs 1CC-251 and

1CC-208 from maloperation due to a fire where they were relied on for SSD. Because

the licensee entered the condition into the corrective action program as AR 80089, this

item is being treated as an NCV in accordance with Section VL.A.1 of the NRC's

Enforcement Policy. This item is identified as NCV 50-400/02-11-02, Failure to Protect

MOVs 1CC-251 and 1CC-208, CC for RCP Seals, From Maloperation Due To a Fire.

.04 Operational Implementation of SSD Capability

a. Inspection Scope

The team reviewed and walked down the local manual actions, needed to achieve and

maintain hot shutdown, that were described in procedure AOP-036, Safe Shutdown

Following a Fire, Rev. 21, for fires in all of the selected areas/zones as described in

Section 1R05.01.a.

The team also followed up on open violation (VIO) 50-400/02-08-01, Failure to Implement

and Maintain NRC Approved Fire Protection Program Safe Shutdown System Separation

Requirements. That VIO and related White finding had been left open in IR 50-400/02-

08. In a supplement to that IR dated October 4, 2002, the NRC had stated that licensee

modifications had reduced the risk significance of the degraded Thermo-Lag barrier to

that of a Green finding. However, VIO 50-400/02-08-01 was left open pending further

NRC review of licensee corrective actions and the development of internal NRC

inspection guidance, related to use of local manual actions as opposed to one of the

protection methods identified in NRC Position C.5.b.(2) of Branch Technical Position

(BTP) CMEB 9.5-1. During this inspection, the team reviewed and walked down the local

manual actions, needed to achieve and maintain hot shutdown, that were proceduralized

by the licensee during this inspection in AOP-36, Rev. 24, for the new ACP room fire

area. The team performed these reviews and walkdowns using NRC inspection

guidance.

The team reviewed and walked down the manual actions described above to verify that:

  • The procedures used for SSD were available to the appropriate staff.
  • The procedures used for SSD were consistent with the SSA methodology and

assumptions and also were consistent with fire pre-plan procedures.

  • The actions were described in the fire-protection-related licensing-basis

documents.

  • The procedures were written so that operator actions could be correctly

performed within the times assumed in the SSA.

12

  • Personnel required to achieve and maintain the plant in hot shutdown condition

from the MCR could be provided from normal onsite staff, exclusive of the fire

brigade.

  • Operator and fire brigade staffing would be adequate to complete the required

manual actions.

  • Operators had sufficient access to the equipment to perform the required actions.

inhibited by smoke migration from one area to adjacent plant areas used to

accomplish SSD.

  • The training program for operators included appropriate lesson plans and job

performance measures (JPMs) for SSD activities.

b. Findings

(1) Reliance on Manual Actions In Place of Required Physical Separation or Protection

Introduction

The team identified a URI related to the licensee's reliance on manual actions in place of

the required physical separation or protection.

Description

The team found that the licensee routinely relied on manual actions in place of the

required physical separation or protection. For a fire in SSA areas 1-A-BAL-B-B1, -B2, -

B4, or -B5; AOP-36 included about 39 local manual operator actions to achieve and

maintain hot shutdown. For a fire in the new ACP room, fire area 1-A-ACP, AOP-36

included about 55 local manual operator actions to achieve and maintain hot shutdown.

The local manual actions for each of the areas reviewed are listed in Attachment 2 to this

report. The team assessed that an SSD NLO would reasonably be able to perform each

of the operator actions that were reviewed (except those that are identified below as

findings) during a fire. However, reliance on all of these manual actions in place of

physical separation or protection could increase the risk of failure of SSD equipment to

operate during a fire.

Analysis

This issue could have more than minor safety significance because it could affect the

Mitigating Systems objectives of the Reactor Safety Cornerstone. The issue could affect

the availability and reliability of systems that mitigate initiating events to preclude

undesirable consequences.

Enforcement

As stated in Section 1R05.03.b.1, OLC 2.F. and the licensee's approved FPP required

13

that if both divisions (that could be used for SSD) are located in the same fire area, then

one division is to be physically protected from fire damage by one of three approved

methods. The licensee's approved FPP did not provide for reliance on operator actions

in place of physical separation or protection of SSD equipment. However, the licensee's

incorrect interpretation of their fire protection program was that they could and would rely

on operator actions in place of physical separation or protection of SSD equipment,

without obtaining NRC approval for deviating from the requirements. Consequently, the

licensee had not requested NRC approval for reliance on any operator actions in place of

physical separation or protection.

Per current NRC inspection guidance, this issue will be identified as a URI, pending the

commission's acceptance of a proposed NRC staff initiative to change the related NRC

requirements. It will be identified as URI 50-400/02-11-05, Reliance on Manual Actions

in Place of Required Physical Separation or Protection.

(2) Fire SSD Operator Actions With Excessive Challenges

Introduction

The team identified an NCV of TS 6.8.1 and OLC 2.F for inadequate procedural steps

and for inadequate corrective action. For a fire in the new auxiliary control panel (ACP)

fire area, certain SSD procedure steps involved excessive challenges to operators.

There was not reasonable assurance that all NLOs could perform the steps during a fire.

Consequently, a fire in the ACP fire area could result in a loss of all AFW. The licensee

had added these inadequate procedure steps during this inspection, as part of the

corrective action for violation 50-400/02-08-01.

Description

For a fire in Fire Area 1-A-ACP, AOP-36 steps 2.c and 14.a required the NLO to remove

fuses from transfer panel 1B. Completing these steps would include the following

challenges:

The subject transfer panel was physically located approximately 20 feet from the

ACP room door. With a fire in the ACP room, the area around the transfer panel

could become uninhabitable before the NLO could complete these steps,

because some smoke from the fire could enter the transfer panel area from

around the door while the door was closed, and because smoke would certainly

enter the transfer panel area when the door was opened by the fire brigade to

attack the fire.

  • To physically reach the subject fuses, the NLO would need to place his or her

entire body inside a cabinet with an opening that was approximately 15 inches

wide. Also, the inside of the cabinet included energized electrical components on

each side of the cabinet, with about 15 inches of width between them. The

licensee had not ensured that all NLOs were physically capable of safely entering

that cabinet - the team noted that some NLOs were more than 15 inches wide.

  • Because the subject fuses were located on a panel inside the cabinet and

14

approximately seven feet above floor level, all but the tallest NLOs would need to

use a narrow, custom-made wooden step-stool inside the cabinet to be able to

reach the fuses. The team noted that the location of the step-stool was not

controlled.

Because the subject fuses were also located behind a plexiglass fuse cover that

was held in place by small metal screws, the NLO would need to raise his or her

hands above the level of his or her head and use a metal screwdriver to remove

the fuse cover. The licensee had not ensured that all NLOs were physically

capable of completing this activity. Furthermore, because this activity involved

manipulating a metal screwdriver inside an energized electrical cabinet, the team

considered the activity to involve a personnel safety hazard.

  • To identify the correct fuses to be pulled, the NLO must first identify the cabinet in

which the fuses are located, and then identify the fuses themselves, within that

cabinet. The team observed that the subject cabinet was physically adjacent to

four identical cabinets, that these cabinets were not labeled on the side from

which the NLO would enter, and that the instructions in NLOP-036 did not identify

the subject cabinet. Furthermore, the team observed that the labels which

uniquely identified the subject fuses within the cabinet were difficult to see - they

were partially obscured by cables which had been landed on adjacent terminal

blocks.

The team considered that these challenges were excessive and that there was not

reasonable assurance that all NLOs would be able to perform the actions during a fire.

Consequently, operators would not able to start the turbine-driven AFW pump and the

AFW system could be inoperable. The team concluded that these procedure steps were

inadequate and that they represented inadequate corrective action for violation 50-

400/02-08-01.

Analysis

This finding had more than minor significance because it affected the Mitigating Systems

objectives of the Reactor Safety Cornerstone. The finding affected the availability and

reliability of systems that mitigate initiating events to prevent undesirable consequences.

However, the finding was of very low safety significance because of the low fire initiation

frequency, fire brigade, and remaining SSD equipment to limit the effects of a fire and to

shut down the nuclear reactor. Therefore, this finding is characterized as Green.

Enforcement

As described in Section 1R05.03.b.1 above, OLC 2.F required that equipment relied

upon for SSD be physically protected from the fire. Also, TS 6.8.1 required procedures

for implementing the fire protection program and for combating fires. In addition, OLC

2.F and the UFSAR, Section 9.5.1, FPP, included quality assurance requirements for fire

protection. The FPP stated that a QA program was being used to identify and rectify any

possible deficiencies in design, construction, and operation of the fire protection systems.

Contrary to the above requirements, the licensee failed to protect the turbine-driven EFW

15

pump from effects of a fire where it was relied on for SSD. In addition, the licensee's

corrective actions for a previous violation were inadequate. Because the licensee

entered the finding into the corrective action program as AR 80214, this item is being

treated as an NCV in accordance with Section VI.A.1 of the NRC's Enforcement Policy.

This item is identified as NCV 50-400/02-11-06, Fire SSD Operator Actions With

Excessive Challenges.

(3) Too Many SSD Actions for Operators to Perform

Introduction

The team identified an NCV of TS 6.8.1 and OLC 2.F for an inadequate procedure for

SSD from a fire and for inadequate corrective action. For a fire in certain SSA areas of

the RAB, including the new ACP fire area, there too many SSD procedure contingency

actions to respond to potential spurious actuations for the one available SSD NLO to

perform them all. Consequently, equipment that was relied on for SSD may not be

available. The licensee had added some of these procedure steps as part of the

corrective action for violation 50-400/02-08-01.

Descrintion

The team found that for each fire SSA area inspected, AOP-036 required operators to

complete a relatively large number of manual actions outside the main control room. The

team determined that the normal shift operating crew included four NLOs; three were

assigned to the fire brigade and one was assigned to be the SSD NLO. The local

manual operator actions required to achieve and maintain hot shutdown for each of the

fire areas inspected are listed in Attachment 1 to this report. The most demanding fire

areas were fire area 1-A-ACP, which included about 55 such actions, and fire area 1-A-

BAL-B, which included about 39 such actions.

Also, since the SSA did not ensure that offsite power would not be lost due to a fire in

any of the SSA areas inspected, operators were expected to be able to respond to a loss

of offsite power (LOOP) and reactor trip while performing the fire SSD actions. The team

noted that a LOOP or reactor trip could place even more demands on the one NLO who

was not fighting the fire.

The team found that while most of the manual actions in these SSA areas involved one-

time actions (like opening a breaker), others could require the NLO to monitor plant

conditions and make system adjustments over an extended period of time. The manual

actions which could require dedicated NLO attention, and thus possibly detract from the

successful and timely performance of subsequent required local manual operator

actions, included the following:

In Section 3.0 of AOP-036, which was to be performed for a fire in any of the SSA

areas inspected, Step 13.b(3) required the NLO to establish continuous

communications with the MCR, locally shut 1CS-228 to isolate the normal

charging flow control valve (FCV) and then to locally control charging flow by

throttling the bypass valve,1 CS-227. Both valves were in close proximity and

located in the scalloped area of the 248-ft level in the RAB. This area was

16

located in the radiation-controlled area (RCA) and radiation levels at these valves

were elevated but within 10 CFR 20 limits. A sound powered phone with a long

extension cord was located in the area to allow the NLO to wait in low dose areas

between valve manipulations if the NLO's radio was not functional. However,

local manual operator actions subsequent to this step could be adversely

impacted [e.g., Section 3.0, Step 14.b for locally responding to a failed open

steam generator power operated relief valve (PORV)].

In Attachment 1 of AOP-036, Step 13.c for fire area 1-A-ACP required the NLO to

locally operate a PORV on the C steam generator, to obtain and maintain the

desired RCS temperature. Because the unit would likely not be at steady state

when this action was undertaken, and because a fire in this area may complicate

operator efforts to stabilize the plant, the NLO who undertakes this action may be

required to monitor RCS temperature and make appropriate adjustments to the

PORV position almost continuously and for some time, until the plant is

reasonably stable.

In Attachment 1 of AOP-036, Step 14.b for fire area 1-A-ACP required the NLO to

throttle lAF-149 to maintain level in the C steam generator. For the same

reasons as described above, the NLO who undertakes this action may be

required to continue to monitor steam-generator level and make appropriate

adjustments to the position of 1AF-149 almost continuously and for some time,

until the plant is reasonably stable.

The team found that some of the required manual actions would be completed inside the

RCA, while others would be completed outside the RCA. The team also observed that

completing the manual actions in AOP-036, in the order in which they are described in

that procedure, would require the SSD NLO to enter and exit the RCA several times.

The team noted that:

  • some manual actions involved valves identified as potentially contaminated or

located in contamination areas,

  • radioactive radon gas can become associated with anyone who passes through

the RCA,

alarm, and

  • anyone who is in a portal monitor when it alarms must wait at the exit point for

health physics (HP) technicians to complete a detailed survey to determine the

true cause of the alarm, before proceeding.

The team noted that the licensee had no emergency dosimeters or rapid ingress/egress

procedures in place for use during plant emergency situations. The team therefore

considered that every time the SSD NLO exited the RCA, that NLO may experience a

portal-monitor alarm, and may therefore be forced to wait for HP technicians to arrive at

the exit and complete a detailed survey before proceeding. The team received a portal

monitor alarm on many occasions during this inspection. Operators stated that, if they

17

received such an alarm during a fire, they would wait for an HP technician before

proceeding to perform SSD actions.

The team considered that the manual actions in AOP-036 could not reasonably be

completed by the available staff, because:

  • the SSD NLO may be required to complete as many as 55 manual actions,
  • several manual actions require dedicated operator attention,
  • some of the manual actions could require a considerable amount of time to

complete,

  • some manual actions could be delayed by RCA portal-monitor alarms, and
  • only one NLO would have been available to complete all safe-shutdown manual

actions.

The team concluded that the SSD NLO may not be able to accomplish some required

manual actions in a timely manner. Consequently, some equipment relied on for SSD

may not be available. For example, the SSD NLO may not be able to respond to a failed

open steam generator PORV, locally throttle a sxteam generator PORV, or throttle AFW.

The team therefore considered AOP-36 to be inadequate.

Analysis

This finding had more than minor significance because it affected the Mitigating Systems

objectives of the Reactor Safety Cornerstone. The finding affected the availability and

reliability of systems that mitigate initiating events to prevent undesirable consequences.

However, the finding was of very low safety significance because of the low fire initiation

frequency, automatic sprinklers, fire brigade, and remaining SSD equipment to limit the

effects of a fire and to shut down the nuclear reactor. Therefore, this finding is

characterized as Green.

Enforcement

As described in Section 1R05.03.b.1 above, OLC 2.F required that equipment relied

upon for SSD be physically protected from the fire. Also, TS 6.8.1 required procedures

for implementing the fire protection program and for combating fires. In addition, OLC

2.F and the UFSAR, Section 9.5.1, FPP, included quality assurance requirements for fire

protection. The FPP stated that a QA program was being used to identify and rectify any

possible deficiencies in design, construction, and operation of the fire protection systems.

Contrary to the above requirements, the licensee failed to protect various equipment from

the effects of a fire where that equipment was relied on for SSD. In addition, the

licensee's corrective actions for a previous violation were inadequate. Because the

licensee entered the finding into the corrective action program as AR AR 80215, this item

is being treated as an NCV in accordance with Section VL.A.1 of the NRC's Enforcement

Policy. This item is identified as NCV 50-400/02-11-07, Too Many SSD Actions for

18

Operators to Perform

(4) Using the BAT Without Level Indication

Introduction

The team identified an NCV of TS 6.8.1 was identified for an inadequate procedure for

SSD from a fire. For a fire in SSA area 1-A-BAL-B, the SSD procedure directed

operators to take CSIP suction from the BAT even if BAT level indication were lost.

However, the charging volume needed for RCS cooldown would have emptied the BAT

and damaged the SSD CSIP.

Description

The team found that, for a fire in SSA area 1-A-BAL-B-B2 or -B3, near the BAT, AOP-36

directed operators to use the BAT as a suction source for the CSIPs even if the BAT

level indication was lost due to the fire. This alignment was to be used in preparation for

and during a cooldown of the RCS. However, the team analyzed that the charging

volume needed for RCS cooldown would have emptied the BAT and damaged the SSD

CSIP.

The SSA stated that, if BAT level indication was lost due to a fire, then the RWST was to

be used as a suction source for the CSIPs. However, this analysis was not implemented

in AOP-36. AOP-36 was inadequate because it failed to recognize that the charging

volume needed for RCS cooldown would have emptied the BAT and damaged the SSD

CSIP.

Analysis

This finding had more than minor significance because it affected the Mitigating Systems

objectives of the Reactor Safety Cornerstone. The finding affected the availability and

reliability of systems that mitigate initiating events to prevent undesirable consequences.

However, the finding was of very low safety significance because of the low fire initiation

frequency, automatic sprinklers, fire brigade, and remaining SSD equipment to limit the

effects of a fire and to shut down the nuclear reactor. Therefore, this finding is

characterized as Green.

Enforcement

As described in Section 1R05.03.b.1 above, OLC 2.F required that equipment relied

upon for SSD be physically protected from the fire. Also, TS 6.8.1 required procedures

for implementing the fire protection program and for combating fires.

Contrary to the above requirements, the licensee failed to protect the BAT level indication

from effects of a fire where it was relied on for SSD, and the AOP-36 reliance on using

the BAT without level indication was inadequate. Because the licensee entered the

finding into the corrective action program as AR 75065, this item is being treated as an

NCV in accordance with Section VI.A.1 of the NRC's Enforcement Policy. This item is

identified as NCV 50-400/02-11-08, Using the BAT Without Level Indication.

19

.05 Emergency Communications

a. Inspection Scope

The team reviewed the adequacy of the communication systems relied upon to

coordinate the shutdown of the unit and fire brigade duties, including the site paging

(PA), portable radio, and sound-powered phone systems. The team reviewed the

licensee's portable radio channel features to assess whether the system and its

repeaters were protected from exposure fire damage. During walkdowns of sections of

the post-fire SSD procedure, the team checked if adequate communications equipment

would be available for the personnel performing the procedure. The team also reviewed

the periodic testing of the site fire alarm and PA systems; maintenance checklists for the

sound-powered phone circuits and amplifiers; and inventory surveillance of post-fire SSD

operator equipment to assess whether the maintenance/surveillance test program for the

communications systems was sufficient to verify proper operation of the systems.

b. Findings

No findings of significance were identified.

.06 Emergency Lighting

a. Inspection Scope

The team reviewed the design and operation of the direct current (DC) emergency

lighting system self-contained, battery powered emergency lighting units (ELUs) as

described in UFSAR Sections 9.5.1 .2.2.e and 9.5.3. During plant walk downs of selected

areas where operators performed local manual actions defined in the post-fire SSD

procedure, the team inspected area ELUs for operability and checked the aiming of lamp

heads to determine if adequate illumination was available to correctly and safely perform

the actions required by the procedures. The team inspected emergency lighting features

along access and egress pathways used during SSD activities for adequacy and

personnel safety. The locations and identification numbers on the ELUs were compared

to design drawings to confirm the as-built configuration. The team also checked if these

battery power supplies were rated with at least an 8-hour capacity. In addition, the team

reviewed the manufacturer's information and the licensee's licensee periodic

maintenance tests to verify that the ELUs were properly designed and were being

maintained in an operable manner.

b. Findings

Introduction

A violation of OLC 2.F was identified for failure to provide fixed, self-contained lighting

with individual eight-hour-minimum battery power supplies in areas that must be manned

for safe shutdown.

Description

20

In the SSA areas in which the team walked down safe shutdown manual actions, the

team identified that the locations for local manual operator actions listed in Attachment 2

to this report would not be illuminated by fixed, self-contained lighting with individual

eight-hour-minimum battery power supplies.

The team observed that about 17 of the locations for local manual operator actions had

no emergency lighting, as identified in Attachment 2. The team also observed that many

more locations for local manual operator actions had fluorescent lights, that would be

powered by the safety-related emergency diesel generators, that could provide

emergency illumination. However, these lights did not meet the requirements for lights

with eight-hour batteries. These locations are separately identified in Attachment 2.

Also, the team noted that the licensee had not requested NRC exemptions from the

requirement to provide lights with eight-hour batteries.

The team also observed that all NLOs routinely carried flashlights and had access to

more flashlights that were stored in the auxiliary building. The team assessed that, by

using a flashlight, the SSD NLO would be able to perform the required actions but that

those actions would take more time to perform when relying on illumination by a flashlight

and could be less reliable.

Analysis

This finding had more than minor safety significance because it affected the Mitigating

Systems cornerstone. The finding affected the availability and reliability of systems that

mitigate initiating events to prevent undesirable consequences. However, the finding

was of very low safety significance because of the low fire initiation frequency and the

effectiveness of automatic sprinklers (in all but the ACP fire area), fire brigade, and

remaining SSD equipment to limit the effects of a fire and to shut down the nuclear

reactor. Therefore, this finding is characterized as Green.

Enforcement

OLC 2. F. and UFSAR Section 9.5.1 stated that BTP 9.5-1 was used in the design of the

fire protection program for safety-related systems and equipment and for other plant

areas containing fire hazards that could adversely affect safety-related systems. BTP

9.5-1, Section C.5.g, "Lighting and Communication," paragraph (1), required that fixed

self-contained lighting consisting of fluorescent or sealed-beam units with individual

eight-hour-minimum battery power supplies should be provided in areas that must be

manned for safe shutdown and for access and egress routes to and from all fire areas.

Contrary to the above requirements, the licensee failed to provide fixed self-contained

lighting consisting of fluorescent or sealed-beam units with individual eight-hour-minimum

battery power supplies in the location of the manual actions identified above and listed in

Attachment 3. Because The licensee entered this finding into the corrective action

program as AR 79047, this violation is being treated as an NCV in accordance with

Section VL.A of the NRC's Enforcement Policy. This item is identified as NCV 50-400/02-

11-09, Failure to Provide Required Emergency Lighting for SSD Operator Actions.

21

.07 Cold Shutdown Repairs

a. Inspection Scope

The team reviewed existing procedures and examined plant equipment to establish that

the licensee had dedicated repair procedures, equipment, and materials to accomplish

repairs of damaged components required for cold shutdown, that these components

could be made operable, and that cold shutdown could be achieved within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The

team examined cold shutdown repair equipment and replacement electrical power and

control cables for systems needed to take the plant to cold shutdown following a large

fire. The team evaluated the estimated manpower and the time required to perform post-

fire repairs for reasonableness.

b. Findings

No findings of significance were identified.

.08 Fire Barriers and Fire Area/Zone/Room Penetration Seals

a. Inspection Scope

The team walked down the selected fire zones/areas to evaluate the adequacy of the fire

resistance of barrier enclosure walls, ceilings, floors, and cable protection. This

evaluation also included fire barrier penetration seals, fire doors, fire dampers, cable tray

fire stops, and fire barrier partitions to ensure that at least one train of SSD equipment

would be maintained free of fire damage from a single fire. The team observed the

material condition and configuration of the installed fire barrier features and also

reviewed construction details and supporting fire endurance tests for the installed fire

barrier features. The team compared the observed fire barrier penetration seal

configurations to the design drawings and tested configurations. The team also

compared the penetration seal ratings with the ratings of the barriers in which they were

installed. In addition, the team reviewed licensing documentation, engineering

evaluations of Generic Letter 86-10 fire barrier features, and NFPA code deviations to

verify that the fire barrier installations met design requirements and license commitments.

b. Findings

No findings of significance were identified.

.09 Fire Protection Systems, Features, and Equipment

a. Inspection Scone

The team reviewed flow diagrams, electrical schematic diagrams, periodic test

procedures, engineering technical evaluations for NFPA code deviations, operational

valve lineup procedures, and cable routing data for the power and control circuits of the

motor-driven fire pump, the diesel-driven fire pump, and the fire protection water supply

system yard mains. The review evaluated whether the common fire protection water

delivery and supply components could be damaged or inhibited by fire-induced failures of

22

electrical power supplies or control circuits and subsequent possible loss of fire water

supply to the plant. Additionally, team members walked down the fire protection water

supply system in selected fire areas to assess the adequacy of the system material

condition, consistency of the as-built configuration with engineering drawings, and

operability of the system in accordance with applicable administrative procedures and

NFPA standards.

The team examined the adequacy of installed fire protection features in accordance with

the fire area and system spatial separation and design requirements in BTP CMEB 9.5-1.

The team walked down accessible portions of the fire detection and alarm systems in

the selected fire areas to evaluate the engineering design and operation of the installed

configurations. The team also reviewed engineering drawings for fire detector spacing

and locations in the four selected fire areas for consistency with the licensee's fire

protection plan and the requirements in NFPA 72E.

The team also walked down the selected fire zones/areas with automatic sprinkler

suppression systems installed to assure proper type, placement and spacing of the

heads/nozzles and the lack of obstructions. The team examined vendor information,

engineering evaluations for NFPA code deviations, and design calculations to verify that

the required suppression system density for each protected area was available.

The team reviewed the adequacy of the design, installation and operation of the manual

suppression standpipe and fire hose system for the selected fire areas. The team

examined design calculations and evaluations to verify that the required fire hose water

flow and sprinkler system density for each protected area were available. The team

checked a sample of manual fire hose lengths to determine whether they would reach

the SSD equipment. Additionally, the team observed placement of the fire hoses and

extinguishers to assess consistency with the fire fighting pre-plan drawings.

b. Findings

No findings of significance were identified.

.10 Compensatory Measures

a. Inspection Scope

The team reviewed the licensee's Fire Protection System Engineering Status Reviews

which identified each fire protection system's performance problems and regulatory

issues. The team also reviewed the Fire Protection Out of Service Log generated for the

last 18 months and associated compensatory measures. The review was performed to

verify that the risk associated with removing fire protection and/or post-fire systems or

components was properly assessed and adequate compensatory measures were

implemented in accordance with the approved fire protection program.

b. Findings

No findings of significance were identified.

23

4. OTHER ACTIVITIES (OA)

40A2 Identification and Resolution of Problems

a. Inspection Scone

The team reviewed the corrective action program procedures and a selected sample of

condition reports associated with the Harris FPP to verify that the licensee had an

appropriate threshold for identifying issues. The team also reviewed licensee audits and

assessments of fire protection and safe shutdown. The team evaluated the

effectiveness of the corrective actions for the identified issues.

b. Findings

The team found that licensee corrective actions for violation 50-400/02-08-01 regarding

an inadequate fire barrier wall were inadequate, in that the licensee's corrective actions

for that violation contributed to three of the findings described above. However, because

the net effect of corrective actions completed to date have significantly reduced the

overall risk related to the finding, violation 50-400/02-08-01 is being closed at this time.

The team also found that licensee audits and self-assessments in the area of SSD were

weak. The audits and self-assessments had not identified the types of findings that this

inspection found. Contributing factors included a lack of attention to detail; for example,

not tracing cable routings or walking down operator actions as was done in this

inspection. In addition, the CP&L corporate Nuclear Assessment Section (NAS) audits of

fire protection at Shearon Harris did not look at SSD. A Peer Report included in the

November 2000 NAS audit of Shearon Harris fire protection stated: "Harris NAS Fire

Protection Program Audits of recent past have not included fire events safe shutdown

within the scope of the audits due to a reliance on engineering self-assessments. It is

the opinion of the auditor that the scope of future Harris NAS Fire Protection

assessments should include fire events safe'shutdown related documentation and

activities." However, the team noted that subsequent NAS audits of Harris fire

protection did not audit SSD.

The team noted that the licensee's initial corrective actions to the findings described in

this report were timely and responsive. The licensee revised SSD procedures three

times during the inspection, made a 10 CFR 50.72 report to the NRC, and stationed an

additional SSD NLO.

40A6 Meetings

Exit Meeting Summary

The team presented the inspection results to you and members of your staff at the

conclusion of the inspection on December 20, 2002. You acknowledged the findings

presented. Proprietary information is not included in this inspection report.

SUPPLEMENTAL INFORMATION

24

Partial List of Persons Contacted

Licensee

D. Baksa, Supervisor, Equipment Perfromance

J. Caves, Licensing Supervisor

R. Duncan, Director of Site Operations

M. Fletcher, Manager, Fire Protection Program

P. Fulford, Superintendent, Design Engineering

C. Georgeson, Supervisor, EI&C Design

W. Gregory, Operations Fire Protection Specialist

W. Gurganion, Manager, NAS

T. Hobbs, Manager, Operations

A. Khanpour, Manager, Engineering

F. Lane, Jr., Senior Nuclear Work Management Specialist

J. Laque, Manager, Maintenance

T. Morton, Site Services Manager

J. Scarola, Site Vice President

B. Waldrep, Plant General Manager

NRC

J. Brady, Senior Resident Inspector, Shearon Harris

H. Christensen, Deputy Director, Division of Reactor Safety (DRS), Region II (RII)

C. Ogle, Chief, Engineering Branch 1, DRS, Ril

Items Opened, Closed, and Discussed

ODened

50-400/02-11-01 NCV Failure to Protect Charging System MOV 1CS-1 65, VCT

Outlet to CSIPs, From Maloperation Due To a Fire (Section

1R05.03.b.1)

50-400/02-11-02 NCV Failure to Protect Component Cooling MOVs 1CC-251 and

1CC-208, CC for RCP Seals, From Maloperation Due To a

Fire (Section 1R05.03.b.2)

50-400/02-11-03 NCV Failure to Protect Charging System MOVs 1CS-169, 1CS-

214, 1CS-218, and 1CS-219 From Maloperation Due To a

Fire (Section 1R05.03.b.3)

50-400/02-11-04 NCV Failure to Protect Charging System MOVs 1CS-1 66, 1CS-

168, and 1CS-217 From Maloperation Due To a Fire

(Section 1R05.03.b.4)

50-400/02-11-05 URI Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire (Section 1R05.04.b.1)

25

50-400/02-11-06 NCV Fire SSD Operator Actions With Excessive Challenges

(Section 1R05.04.b.2)

50-400/02-11-07 NCV Too Many Fire SSD Actions for Operators to Perform

(Section 1R05.04.b.3)

50-400/02-11-08 NCV Using the Boric Acid Tank Without Level Indication (Section

1R05.04.b.4)

50-400/02-11-09 NCV Failure to Provide Required Emergency Lighting for SSD

Operator Actions (Section 1R05.06.b)

Closed

50-400/02-08-01 VIO Failure to Implement and Maintain NRC Approved Fire

Protection Program Safe Shutdown System Separation

Requirements (Section 40A2.b)

Discussed

None

26