RNP-RA/03-0085, June 2003 Monthly Operating Report for H. B. Robinson, Unit 2
ML031970441 | |
Person / Time | |
---|---|
Site: | Robinson |
Issue date: | 07/10/2003 |
From: | Baucom C Progress Energy Carolinas |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RNP-RA/03-0085, TRM 6.2, TS 5.6.4 | |
Download: ML031970441 (3) | |
Similar Documents at Robinson | |
---|---|
Category:Letter type:RNP
MONTHYEARRNP-RA/21-0035, Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-18018 February 2021
[Table view]Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/20-0234, Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks2020-07-23023 July 2020 Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks RNP-RA/20-0199, Registration of Use of Spent Fuel Casks2020-06-25025 June 2020 Registration of Use of Spent Fuel Casks RNP-RA/18-0063, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-11-29029 November 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal RNP-RA/18-0060, Transmittal of Core Operating Limits Report2018-10-17017 October 2018 Transmittal of Core Operating Limits Report RNP-RA/18-0050, Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change2018-08-0101 August 2018 Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change RNP-RA/18-0044, Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transform2018-07-11011 July 2018 Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/18-0039, Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis2018-06-27027 June 2018 Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis RNP-RA/18-0041, Independent Spent Fuel Storage Installation - Register as User for Cask2018-06-13013 June 2018 Independent Spent Fuel Storage Installation - Register as User for Cask RNP-RA/18-0036, Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ...2018-05-16016 May 2018 Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ... RNP-RA/18-0029, Submittal of 2017 Annual Radiological Environmental Operating Report2018-05-0808 May 2018 Submittal of 2017 Annual Radiological Environmental Operating Report RNP-RA/18-0031, (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 352018-04-23023 April 2018 (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 35 RNP-RA/18-0015, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program2018-04-16016 April 2018 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program RNP-RA/18-0024, Report of Changes Pursuant to 10 CFR 50.59(d)(2)2018-04-0202 April 2018 Report of Changes Pursuant to 10 CFR 50.59(d)(2) RNP-RA/18-0020, Notification of Change in Licensed Operator Status2018-02-20020 February 2018 Notification of Change in Licensed Operator Status RNP-RA/18-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2018-01-23023 January 2018 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/17-0085, Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2018-01-0808 January 2018 Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0086, Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses2017-12-14014 December 2017 Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses RNP-RA/17-0081, Submittal of Change in Licensed Operators Medical Status2017-12-11011 December 2017 Submittal of Change in Licensed Operators Medical Status RNP-RA/17-0079, Operator License Renewal Application2017-12-0707 December 2017 Operator License Renewal Application RNP-RA/17-0071, Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks2017-10-19019 October 2017 Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks RNP-RA/17-0068, Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-09-28028 September 2017 Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0037, License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers2017-09-27027 September 2017 License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/17-0043, Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-42017-09-22022 September 2017 Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-4 RNP-RA/17-0065, Refueling Outage 30 Steam Generator Tube Inspection Report2017-09-18018 September 2017 Refueling Outage 30 Steam Generator Tube Inspection Report RNP-RA/17-0060, Notification of Change in Licensed Operator Status2017-08-10010 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0058, Notification of Change in Licensed Operator Status2017-08-0303 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0055, Transmittal of Core Operating Limits Report for Cycle 312017-07-26026 July 2017 Transmittal of Core Operating Limits Report for Cycle 31 RNP-RA/17-0042, Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals2017-06-29029 June 2017 Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals RNP-RA/17-0051, Submittal of Nine Day Inservice Inspection Summary Report2017-06-29029 June 2017 Submittal of Nine Day Inservice Inspection Summary Report RNP-RA/17-0041, Transmittal of Technical Specifications Bases Revisions2017-05-23023 May 2017 Transmittal of Technical Specifications Bases Revisions RNP-RA/17-0038, (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report2017-05-0909 May 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report RNP-RA/17-0034, Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544)2017-05-0202 May 2017 Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) RNP-RA/17-0036, (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 342017-04-25025 April 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 34 RNP-RA/17-0031, Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 02017-04-20020 April 2017 Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 0 RNP-RA/17-0033, Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal2017-04-12012 April 2017 Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal RNP-RA/17-0014, Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0028, Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0021, Transmittal of Core Operating Limits Report2017-03-13013 March 2017 Transmittal of Core Operating Limits Report RNP-RA/17-0019, Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 22017-03-0808 March 2017 Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 2 RNP-RA/17-0015, Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/17-0016, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report2017-02-22022 February 2017 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report RNP-RA/17-0015, H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/16-0100, Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-2272017-01-24024 January 2017 Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-227 RNP-RA/16-0097, Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/20154052016-12-15015 December 2016 Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/2015405 RNP-RA/16-0089, Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2016-11-10010 November 2016 Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/16-0090, Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise2016-11-10010 November 2016 Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise RNP-RA/16-0087, Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-31031 October 2016 Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0078, Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-0505 October 2016 Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0079, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants.2016-10-0505 October 2016 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants. 2021-02-18 Category:License-Monthly Operating Report MONTHYEARRNP-RA/05-0035, March 2005 Monthly Operating Reports for H. B. Robinson Steam Electric Plant (Hbrsep), Unit No. 22005-04-11011 April 2005
[Table view]March 2005 Monthly Operating Reports for H. B. Robinson Steam Electric Plant (Hbrsep), Unit No. 2 RNP-RA/05-0025, February 2005 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 22005-03-10010 March 2005 February 2005 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 2 RNP-RA/05-0002, December 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 22005-01-0707 January 2005 December 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 2 RNP-RA/04-0149, November 2004 Monthly Operating Report for the H. B. Robinson, Unit 22004-12-0707 December 2004 November 2004 Monthly Operating Report for the H. B. Robinson, Unit 2 RNP-RA/04-0132, September 2004 Monthly Operating Report for H.B. Robinson, Unit 22004-10-11011 October 2004 September 2004 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/04-0117, August 2004 Monthly Operating Report for H B Robinson Steam Electric Plant Unit 22004-09-0303 September 2004 August 2004 Monthly Operating Report for H B Robinson Steam Electric Plant Unit 2 RNP-RA/04-0103, July 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit 22004-08-0404 August 2004 July 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit 2 RNP-RA/04-0087, June 2004 Monthly Operating Report for H. B. Robinson, Unit 22004-07-0808 July 2004 June 2004 Monthly Operating Report for H. B. Robinson, Unit 2 RNP-RA/04-0052, April 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 22004-05-11011 May 2004 April 2004 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit No. 2 RNP-RA/04-0041, March 2004 Monthly Operating Report for H.B. Robinson, Unit 22004-04-0505 April 2004 March 2004 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/04-0030, February 2004 Monthly Operating Report for H.B. Robinson, Unit 22004-03-0505 March 2004 February 2004 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/04-0020, January 2004 Monthly Operating Report for H.B. Robinson, Unit 22004-02-0505 February 2004 January 2004 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/04-0004, December 2003 Monthly Operating Report for H.B. Robinson, Unit 22004-01-0606 January 2004 December 2003 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/03-0155, November 2003 Monthly Operating Report for H.B. Robinson, Unit 22003-12-0909 December 2003 November 2003 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/03-0140, October 2003 Monthly Operating Report for H B Robinson Steam Electric Plant Unit 22003-11-0606 November 2003 October 2003 Monthly Operating Report for H B Robinson Steam Electric Plant Unit 2 RNP-RA/03-0132, September 2003 Monthly Operating Report for H. B. Robinson, Unit 22003-10-10010 October 2003 September 2003 Monthly Operating Report for H. B. Robinson, Unit 2 RNP-RA/03-0115, August 2003 Monthly Operating Report for H. B. Robinson, Unit 22003-09-0909 September 2003 August 2003 Monthly Operating Report for H. B. Robinson, Unit 2 RNP-RA/03-0105, July 2003 Monthly Operating Report for H.B. Robinson, Unit 22003-08-12012 August 2003 July 2003 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/03-0085, June 2003 Monthly Operating Report for H. B. Robinson, Unit 22003-07-10010 July 2003 June 2003 Monthly Operating Report for H. B. Robinson, Unit 2 RNP-RA/03-0079, May 2003 Monthly Operating Report for H.B. Robinson, Unit 22003-06-10010 June 2003 May 2003 Monthly Operating Report for H.B. Robinson, Unit 2 RNP-RA/03-0062, April 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No.22003-05-0606 May 2003 April 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No.2 RNP-RA/03-0042, March 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No. 22003-04-0404 April 2003 March 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No. 2 RNP-RA/03-0033, February 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 22003-03-0707 March 2003 February 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 2 RNP-RA/03-0021, January 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No. 22003-02-10010 February 2003 January 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No. 2 RNP-RA/03-0004, December 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 22003-01-10010 January 2003 December 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 2 RNP-RA/02-0185, November 2002 Monthly Operating Report for H. B. Robinson, Unit 22002-12-13013 December 2002 November 2002 Monthly Operating Report for H. B. Robinson, Unit 2 RNP-RA/02-0174, October 2002 Monthly Operating Report for H B Robinson Unit 22002-11-14014 November 2002 October 2002 Monthly Operating Report for H B Robinson Unit 2 RNP-RA/02-0153, September 2002 Monthly Operating Report for Robinson Unit 22002-10-0707 October 2002 September 2002 Monthly Operating Report for Robinson Unit 2 RNP-RA/02-0142, August 2002 Monthly Operating Report for H. B. Robinson Unit 22002-09-12012 September 2002 August 2002 Monthly Operating Report for H. B. Robinson Unit 2 RNP-RA/02-0119, July 2002 Monthly Operating Report for H. B. Robinson Unit 22002-08-13013 August 2002 July 2002 Monthly Operating Report for H. B. Robinson Unit 2 RNP-RA/02-0102, June 2002 Monthly Operating Report for H.B. Robinson Steam Electric Co., Unit 22002-07-10010 July 2002 June 2002 Monthly Operating Report for H.B. Robinson Steam Electric Co., Unit 2 RNP-RA/02-0088, May 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 22002-06-0505 June 2002 May 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 2 RNP-RA/02-0075, April 2002 Monthly Operating Report for H. B. Robinson Unit 22002-05-14014 May 2002 April 2002 Monthly Operating Report for H. B. Robinson Unit 2 RNP-RA/02-0050, March 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 22002-04-11011 April 2002 March 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 2 RNP-RA/02-0035, February 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 22002-03-11011 March 2002 February 2002 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit 2 RNP-RA/02-0019, January 2002 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit 22002-02-12012 February 2002 January 2002 Monthly Operating Report for H. B. Robinson Steam Electric Plant, Unit 2 RNP-RA/02-0001, December 2001 Monthly Operating Report for H. B. Robinson, Unit 22002-01-0707 January 2002 December 2001 Monthly Operating Report for H. B. Robinson, Unit 2 2005-04-11 |
Text
S 4-TS 5.6.4 TRM 6.2 aJ Progress Energy Serial: RNP-RA/03-0085 JUL 1 0 2003 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 MONTHLY OPERATING REPORT Ladies and Gentlemen:
In accordance with the H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2, Technical Specifications (TS) Section 5.6.4, "Monthly Operating Reports," and HBRSEP, Unit No. 2, Technical Requirements Manual (TRM) Section 6.2, "Monthly Operating Report," Progress Energy Carolinas, Inc., submits the attached report of operating statistics and shutdown experience for the month of June 2003.
If you have any questions concerning this matter, please contact me.
Sincerely, C. T. Baucom Supervisor - Licensing/Regblatory Programs N
CTB/jwv Attachment c: NRC Resident Inspector, HBRSEP L. A. Reyes, NRC, Region II C. P. Patel, NRC, NRR Progress Energy Carolinas. Inc.
Robinson Nuclear Plant 3581 West Entrance Road Hartsville, SC 29550
"'O
Attachment to Serial: RNP-RA/03-0085 Page 1 of 2 MONTHLY OPERATING REPORT DOCKET NO. 050-0261 UNIT H. B. ROBINSON STEAM ELECTRIC PLANT (HBRSEP). UNIT NO. 2 DATE 77/2003 COMPLETED BY TIM SURMA TELEPHONE (843) 857-1086 REPORTING PERIOD: JUNE 2003
- 1. DESIGN ELECTRICAL RATING (NET MWE): 765
- 2. MAX DEPENDABLE CAPACITY (NET MWE): 710 THIS YR TO MONTH DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR CRITICAL 720.00 4343.0 216140.99
- 4. HOURS GENERATOR ON LINE 720.00 4343.0 212821.26
- 5. UNIT RESERVE SHUTDOWN HOURS 0.00 0.00 23.20
- 6. NET ELEC. ENERGY GENERATED (MWH) 522429.00 3214138.00 139151596.00
Attachment to Serial: RNP-RA/03-0085 Page 2 of 2 DOCKET NO.50-026 UNrT NAME HBRSEP. UNIr NO.2 DATE 7/07/03 COMPLETED BY llM SlURMA TELEPHONE (843)857-1086 REPORTING PERIOD: JUNE 2003 No. Date Type Duration Reason1 Method of Shutting Down Cause / Corrective Actions / Comments F: Forced (Hours) the Reactor or Reducing Power 2 5: Scheduled I2 Reason: Method:
A-Equipment Failure (Explain) 1-Manual 6-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Continuation E-Operator Training &Ucense Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H-Other (Explain)
SUM MARY: The unit operated at approximately full power for the entire month.