Report on the Status of Open TIAs Assigned to NRR
ML031770076
Person / Time
Site: Cooper, Prairie Island  Xcel Energy icon.png
Issue date: 06/26/2003
From: Pulsifer R
NRC/NRR/DLPM/LPD1
To: Zwolinski J
NRC/NRR/DLPM/LPD1
Pulsifer R M, NRR/DLPM, 415-3016
References
FOIA/PA-2005-0134
Download: ML031770076 (9)


Text

June 26, 2003 MEMORANDUM TO: John Zwolinski, Director Division of Licensing Project Management THRU: Cornelius F. Holden, Director /RA by REnnis for/

Project Directorate I Division of Licensing Project Management FROM: Robert M. Pulsifer, Project Manager, Section 2 /RA/

Project Directorate I Division of Licensing Project Management

SUBJECT:

REPORT ON THE STATUS OF OPEN TIAs ASSIGNED TO NRR The attached graph and tables give the status of open TIAs assigned to NRR as of May 31, 2003.

Since the last status report, one draft TIA was sent to a region, one draft TIA was returned from a region, one TIA was completed and one TIA was opened. Of the four open TIAs, the following divisions are the current action holder: DE - 2*, DSSA - 1*, and DLPM - 2.

There are no TIA draft responses that are presently late that affect TIA goals.

There are two TIA draft responses due within the next two months (up to 08/01/03) that affect TIA goals. (Cooper 2002-03 due 06/25/03** and Prairie Island 2001-10 due 08/1/03)

The TIA Office Instruction (COM-106, Rev. 1) was revised on December 24, 2002, to improve the timeliness for meeting the NRR goal by increasing management oversight.

    • Draft response sent to the region on 6/03/03.

Attachments: 1. Graph of TIA Status

2. Table 1 - Summary Data
3. Table 2 - Open TIAs Assigned to NRR (by plant name)
4. Table 3 - Closed TIAs Assigned to NRR - FY03 YTD (by TIA Number) cc w/atts: See next page

June 26, 2003 MEMORANDUM TO: John Zwolinski, Director Division of Licensing Project Management THRU: Cornelius F. Holden, Director /RA by REnnis/

Project Directorate I Division of Licensing Project Management FROM: Robert M. Pulsifer, Project Manager, Section 2 /RA/

Project Directorate I Division of Licensing Project Management

SUBJECT:

REPORT ON THE STATUS OF OPEN TIAs ASSIGNED TO NRR The attached graph and tables give the status of open TIAs assigned to NRR as of May 31, 2003.

Since the last status report, one draft TIA was sent to a region, one draft TIA was returned from a region, one TIA was completed and one TIA was opened. Of the four open TIAs, the following divisions are the current action holder: DE - 2*, DSSA - 1*, and DLPM - 2.

There are no TIA draft responses that are presently late that affect TIA goals.

There are two TIA draft responses due within the next two months (up to 08/01/03) that affect TIA goals. (Cooper 2002-03 due 06/25/03** and Prairie Island 2001-10 due 08/1/03)

The TIA Office Instruction (COM-106, Rev. 1) was revised on December 24, 2002, to improve the timeliness for meeting the NRR goal by increasing management oversight.

    • Draft response sent to the region on 6/03/03.

Attachments: 1. Graph of TIA Status

2. Table 1 - Summary Data
3. Table 2 - Open TIAs Assigned to NRR (by plant name)
4. Table 3 - Closed TIAs Assigned to NRR - FY03 YTD (by TIA Number) cc w/atts: See next page Accession Number: ML031770076 OFFICE PDI-2/PM PD/ PDI NAME RPulsifer REnnis for CHolden DATE 6/26/03 6/26/03 OFFICIAL RECORD COPY

Date: June 26, 2003

SUBJECT:

REPORT ON THE STATUS OF OPEN TIAs ASSIGNED TO NRR DISTRIBUTION:

PDI-2 R/F J. Wiggins, RI B. Platchek, RI R. Blough, RI W. Lanning, RI J. Barnes, RII V. McCree, RII L. Plisco, RII J. Caldwell, RIII R. Lanksbury, RIII G. Grant, RIII J. Grobe, RIII C. Pederson, RIII D. Chamberlain, RIV T.P. Gwynn, RIV A. Howell, RIV NRR BCs, SCs and PDs (by e-mail)

B. Boger D. Matthews M. Johnson C. Carpenter C. Grimes T. Marsh R. Perch J. Andersen R. Pulsifer B. Sheron C. Holden G. Dick M. Thadani J. Lamb J. Clifford

TABLE 1 -

SUMMARY

DATA FY2003 New TIAs Draft TIAs sent to Draft TIAs Closed TIAs Open Draft Late* Percent Region for review returned from (Final response TIAs By TIAs by Region issued) Original FY-03 Original Due (B) Due May 03 FY-03 May 03 FY-03 May 03 FY-03 May 03 FY-03 Date Date (A)** (A/A+B)

Region I 0 0 0 1 0 1 0 1 0 1 0 Region II 1 1 0 2 0 2 0 2 1 2 0 Region III 0 2 1 1 1 2 1 4 2 2 0 Region IV 0 0 0 0 0 0 0 0 1 0 0 Total 1 3 1 4 1 5 1 7 4 5 0 100%*

  • An NRR goal is to complete 80% by latest scheduled due date. TIA Office Instruction COM-106, Rev. 1, issued December 24, 2002 states, The TIA response date or scheduled due date is considered to be the date when the draft TIA response is provided to the requesting organization.
    • (A) is TIAs closed or draft sent by initial requested completion date.

OPEN TIAs ASSIGNED TO NRR (by Plant Name) Table 2 PLANT TIA # - TAC#/TITLE INITIAL CURRENT ACTION AGE SE STATUS/ BILLED MEMO AGREED AGREED HOLDER (mo's) EVAL. OTHER REMARKS TO DATE COMPL. COMPL INPUT DATE DATE DATE* (HRS)

BYRON Unit 1 2003-02 MB7378 - 04/01/03 04/01/03 DLPM 4 SRXB Working - TIA noted that if 415.6 01/28/03 Licensed power 06/06/03T EEIB more detailed review is limit 08/30/03T required once info is Subject to received from licensee the change agreed upon completion date may change. An RAI is being prepared.

COOPER 2002-03 MB5768 - 06/25/03** Draft sent DLPM 11 EEIB Working - Response 93 06/26/02 Potential USQ off- 06/03/03 received from EEIB on site power 4/28. Draft response to the region sent 6/3/03.

PRAIRIE 2001-10 MB2953 - Design 08/30/02 Draft sent EEIB 20 EEIB Working - Preliminary 161.5 ISLAND Unit 2 09/07/01 basis assumptions 08/30/02 response sent to licensee for EDG #6 Returned for comment. Licensee 10/04/02 responded by stating there Final is a potential backfit.

03/01/03T Package is under OGC 05/01/03T review.

08/01/03T TURKEY POINT 2003-03 MB8728/29 - 04/30/03 12/31/03T EEIB 1 EEIB Working 23 3&4 04/30/03 Review of SBO SXRB SXRB strategy/analysis Average 9 Average Hours 173.275 Age Billed (Months)

  • An NRR goal is to complete 80% by latest scheduled due date. TIA Office Instruction COM-106, Rev. 1, issued December 24, 2002 states, The TIA response date or scheduled due date is considered to be the date when the draft TIA response is provided to the requesting organization.
    • No due date requested by TIA.

TABLE 3 CLOSED TIAs ASSIGNED TO NRR - FY03 YTD (By TIA Number)

DATE OF DATE

  • INITIAL COMPLETED AGE HOURS TIA NO. TAC NO. REQUEST (w/i, due date) (Months) PLANT BILLED 2001-13 MB3023/24 09/28/01 Draft sent 17 Dresden 2 & 3 753.6 12/05/01 Returned 12/12/01 02/21/03C 2001-15 MB3603/04 12/12/01 01/13/03C 13 DC Cook 765.1 2002-01 MB5061 05/03/02 12/06/02C 7 Davis Besse 707.4 2002-02 MB5460 06/19/02 Draft sent 6 Ginna 242.2 12/12/02 Returned 12/17/02 12/30/02C 2002-04 MB6248/49 09/06/02 01/30/03C 5 Hatch 1 & 2 93.5 2002-05 MB6252/3/4 09/10/02 Draft sent 2 Oconee 1, 2, 3 60.5 10/15/02 Returned 10/16/02 10/29/02C 2003-01 MB7294/95 01/17/03 Draft sent 4 Prairie Island 1 & 2 49 05/01/03 Returned 05/12/03 05/27/03C Average Age 8 Average Hours Billed 381.61 (Months)

Note: Completion dates are within the original agreed-upon date unless otherwise noted.

  • An NRR goal is to complete 80% by latest scheduled due date. TIA Office Instruction COM-106, Rev. 1, issued December 24, 2002 states, The TIA response date or scheduled due date is considered to be the date when the draft TIA response is provided to the requesting organization.