E-mail from Jacob Zimmerman, Bulletin 2001-01 Status ReportML022400781 |
Person / Time |
---|
Site: |
Beaver Valley, Millstone, Calvert Cliffs, Davis Besse, Salem, Oconee, Mcguire, Palisades, Palo Verde, Indian Point, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Watts Bar, Sequoyah, Byron, Arkansas Nuclear, Three Mile Island, Braidwood, Summer, Prairie Island, Seabrook, Surry, Turkey Point, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Robinson, South Texas, San Onofre, Cook, Comanche Peak, Fort Calhoun, McGuire ![Constellation icon.png](/w/images/b/be/Constellation_icon.png) |
---|
Issue date: |
01/18/2002 |
---|
From: |
Jacob Zimmerman Office of Nuclear Reactor Regulation |
---|
To: |
Borchardt R, Collins S, Jerrica Johnson, Sheron B Office of Nuclear Reactor Regulation |
---|
References |
---|
BL-01-001, FOIA/PA-2002-0229 |
Download: ML022400781 (10) |
|
Similar Documents at Beaver Valley, Millstone, Calvert Cliffs, Davis Besse, Salem, Oconee, Mcguire, Palisades, Palo Verde, Indian Point, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Watts Bar, Sequoyah, Byron, Arkansas Nuclear, Three Mile Island, Braidwood, Summer, Prairie Island, Seabrook, Surry, Turkey Point, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Robinson, South Texas, San Onofre, Cook, Comanche Peak, Fort Calhoun, McGuire |
---|
Category:E-Mail
MONTHYEARML24037A1902024-02-0505 February 2024 Acceptance of LAR 23-07 to Delete License Condition 14 ML24032A2442024-02-0101 February 2024 OEDO-24-00011 - 10 CFR 2.206 Petition Holtec Misuse Decommissioning Fund- Email to Petitioner ML24032A4702024-02-0101 February 2024 Change in Estimated Review Schedule Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML24033A2842024-01-30030 January 2024 Fyi/Review - Draft Environmental Assessment Regarding Proposed Exemption Request from Maine Yankee ISFSI IR 05000350/19680012024-01-30030 January 2024 639017-Suspension of Review of License Amendment Request Due to Lack of Significant Amounts of Information and Closure of Mail Control 639017 - License 50-35068-01 for Anchorage Radiation Oncology Management, Inc ML24029A2732024-01-29029 January 2024 NRC Consultation with Commonwealth of Pennsylvania Re Proposed NSHC for Susquehanna License Amendment Request ML24030A0672024-01-26026 January 2024 Email EA Fonsi Notice to Kewaunee Solutions for Exemptions on Site Restoration Activities ML24026A2922024-01-26026 January 2024 Request for Additional Information Regarding Limerick Digital Instrumentation and Controls License Amendment Request ML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML24026A2802024-01-25025 January 2024 Acceptance Review for Virgil C. Summer Relief Requests RR-5-V1, RR-5-V2, and RR-5-V3 (EPIDs L-2023-LLR-0067, L-2023-LLR-0068, and L-2023-LLR-0069) (Email) ML24040A1602024-01-25025 January 2024 Email; Cfleming, NCSU to Dhardesty, USNRC-NC State Pulstar License Renewal Approach from Nc State (Jan. 2024) ML24009A2302024-01-25025 January 2024 Transmittal Email for Verification of - a Version Shielding Topical Report ML24024A0202024-01-24024 January 2024 Correction to Safety Evaluation Associated Wit Amendment No. 288 - Revision to Applicability Term for RCS Heat-Up and Cooldown Pressure-Temperature Limitations Figures ML24025A0952024-01-24024 January 2024 Clarifications Related to the NRC Staff'S EA for Crystal River ML24024A0182024-01-24024 January 2024 LTR-23-0216-1 - (E-Mail) Turkey Point Nuclear Plant, Units 3 and 4 - 10 CFR 2.206 Petition -Turkey Point and PWR RPV Embrittlement E-Mail Closure Letter to Petitioner, January 23, 2024 ML24024A1372024-01-24024 January 2024 NRR E-mail Capture - Final Snsb RAI Regarding FitzPatrick Amendment to Modify Safety Relief Valves Setpoint Lower Tolerance ML24024A2452024-01-24024 January 2024 1/24/2024 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in SE for Amendment No. 288 - Revision to Applicability Term for RCS Heatup and Cooldown Pressure-Temperature Limitations Figures ML24023A6242024-01-23023 January 2024 NRR E-mail Capture - Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Preliminary Safety Analysis Report (PSAR) Section 4.3 Audit Question (4.3-25 on Material Degradation) ML24025A1792024-01-23023 January 2024 State Consultation Response e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment (License No. DPR-40, Docket No. 50-285) ML24024A2242024-01-22022 January 2024 State Consultation e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment- (License No. DPR-40, Docket No. 50-285) ML24022A2122024-01-22022 January 2024 NRR E-mail Capture - Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Preliminary Safety Analysis Report (PSAR) Section 4.3 Audit Questions (4.3-23 and 4.3-24 on Material Degradation) ML24025A0172024-01-22022 January 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Comanche Peak License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML24022A1822024-01-19019 January 2024 Acknowledgment - Reply to Notice of Violation - Carbon Asset Solutions ML24019A0742024-01-19019 January 2024 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML23320A1122024-01-18018 January 2024 NRC to Fws, Concurrence with Endangered Species Act Determinations for North Anna Power Station, Units 1 and 2, Subsequent License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML24017A1112024-01-17017 January 2024 NRR E-mail Capture - Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-529, Clarifyuse and Applicaion Rules, Revision 4 ML24017A2392024-01-17017 January 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Valve Testing Frequency Alternative VR-9 ML24017A3032024-01-17017 January 2024 NRR E-mail Capture - Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Preliminary Safety Analysis Report (PSAR) Section 4.3 Audit Questions (Related to Material Degradation) ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML24029A1132024-01-16016 January 2024 Notification of Inspection and Request for Information (Email) ML24016A0062024-01-15015 January 2024 Email Dated 1/15/24 from D. Bussman (Gns) to N. Garcia Santos (Nrc), Staggered Confinement RAIs for the Castor geo69 Storage Application (Docket No. 72-1052) ML24015A0112024-01-12012 January 2024 NRR E-mail Capture - Schedule Change for Washington State University (Wsu) License Amendment Request (LAR) Proposed Amendment 22 ML24012A1942024-01-12012 January 2024 Email Dated 1/12/24 from N. Garcia Santos (NRC) to D. Bussmann (Gns), Staggered Confinement RAIs for the Castor geo69 Storage Application (Docket No. 72-1052) 2024-02-05 The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Calvert Cliffs]] OR [[:Davis Besse]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Indian Point]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Watts Bar]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Seabrook]] OR [[:Surry]] OR [[:Turkey Point]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Robinson]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Fort Calhoun]] OR [[:McGuire]] </code>.
[Table view]The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Calvert Cliffs]] OR [[:Davis Besse]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Indian Point]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Watts Bar]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Seabrook]] OR [[:Surry]] OR [[:Turkey Point]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Robinson]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Fort Calhoun]] OR [[:McGuire]] </code>. Category:Status Report
MONTHYEARML23276A5942023-09-28028 September 2023 and Independent Spent Fuel Storage Installation - Supplement to Decommissioning Funding Status Reports ML22348A0872023-07-25025 July 2023 Enclosure - VEGP Unit 4 - 103g - Final Memorandum Table ML23202A2162023-07-21021 July 2023 Final Vogtle Unit 4 ITAAC Review Status Report ML23184A0372023-07-0303 July 2023 ITAAC Review Status Report 7-3-2023 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance ML23152A1302023-06-0101 June 2023 Vog 4 Dashboard 6-1-2023 ML23152A1292023-06-0101 June 2023 Icn Review Status VOG4 6-1-2023 WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) ML23093A0872023-04-0303 April 2023 ITAAC Review Status Report 04/03/2023 ML23093A0862023-04-0303 April 2023 Dashboard Report 4-3-2023 ML23090A2302023-03-31031 March 2023 NRC Decommissioning Funding Status Report PLA-8049 L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports ML23090A0482023-03-31031 March 2023 (PBAPS) Unit 1 - Decommissioning Status Report - 2022 ML23090A1802023-03-31031 March 2023 GEH - Financial Assurance Status Reports RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports ML23089A3852023-03-30030 March 2023 Decommissioning Funding Status Report ML23089A3042023-03-30030 March 2023 Decommissioning Fund Status Report NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 ML23089A3722023-03-30030 March 2023 Decommissioning Funding Status Report CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report ML23094A1162023-03-30030 March 2023 Decommissioning Fund Status Report ML23089A3892023-03-30030 March 2023 (Vcsns), Unit 1 - Decommissioning Funding Status Report ML23089A3642023-03-30030 March 2023 Decommissioning Funding Status Report NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 ML23089A0622023-03-29029 March 2023 Financial Assurance for Decommissioning - 2023 Update ML23094A1272023-03-29029 March 2023 Independent Spent Fuel Storage Installation - 10 CFR 50.82(a)(8)(v and VII) and 10 CFR 72.30(c) Decommissioning Funding Status Report 2021 NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding ML23089A0762023-03-29029 March 2023 Decommissioning Funding Status Reports ML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report ML23080A2882023-03-21021 March 2023 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) Entergy Operations, Inc ML23086B3812023-03-15015 March 2023 Cimarron Monthly Status Teleconference Notes March 15, 2023 GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report ML23080A1112023-03-0606 March 2023 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML23068A0132023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-23-007, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-23-006, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML23060A0602023-03-0101 March 2023 Dashboard Report 3-1-2023 ML23060A0642023-03-0101 March 2023 ITAAC Review Status Report 3-1-2023 ND-23-0021, Nineteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2023-02-22022 February 2023 Nineteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML23045A0882023-02-14014 February 2023 3Q 2022 Performance Summary Vogtle Unit 4 ML23045A0072023-02-13013 February 2023 Archives 2023-09-28 The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Calvert Cliffs]] OR [[:Davis Besse]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Indian Point]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Watts Bar]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Seabrook]] OR [[:Surry]] OR [[:Turkey Point]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Robinson]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Fort Calhoun]] OR [[:McGuire]] </code>.
[Table view]The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Calvert Cliffs]] OR [[:Davis Besse]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Indian Point]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Watts Bar]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Seabrook]] OR [[:Surry]] OR [[:Turkey Point]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Robinson]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Fort Calhoun]] OR [[:McGuire]] </code>. |
Text
I Jacob Zimmerman - Bulletin 2001-01 Status Report .. ........
. ........... ......... .. .. .... ....... - - i- * - " P ag e 1 From: Jacob Zimmerman i To: Borchardt, Richard; Collins, Samuel; Johnson, Jon; Sheron, Brian Date: Fri, Jan 18, 2002 1:38 PM
Subject:
Bulletin 2001-01 Status Report The attached file contains the latest Status Report for Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles" as of this afternoon, January 18, 2002. Please note that updated information is in red (must be viewed in Word Perfect) and indicated by rev. bars. One major revision this week to include closeout letter status.
If you have any questions or comments, please email or call me. If you would like to be removed from distribution, please let me know.
Jake Zimmerman (301) 415-2426 CC: Adensam, Elinor; Bajwa, Satwant; Barrett, Richard; Bateman, Bill; Bearden, William; Berkow, Herbert; Black, Suzanne; Blough, A. Randolph; Brockman, Ken; Burkhart, Lawrence; Caldwell, James; Caniano, Roy; Casto, Charles; Chandler, Lawrence; Chokshi, Nilesh; Christensen, Harold; Chung, Jin; Clark, Robert; Clifford, James; Colburn, Timothy; Collins, Daniel; Collins, Elmo; Collins, Jay; Congel, Frank; Cowgill, Curtis; Crlenjak, Richard; Dembek, Stephen; Dyer, Jim; Edison, Gordon; Ellershaw, Lee; Eltawila, Farouk; Goshen, John; Grant, Geoffrey; Grobe, John; Gwynn, Pat; Hackett, Edwin; Harrison, John; Hiser, Allen; Holahan, Gary; Holian, Brian; Holmberg, Melvin; Howell, Art; Jacobson, John; Jaxheimer, Frederick; Lanning, Wayne; Laufer, Richard; Lee, Andrea; Lesser, Mark; Lew, David; Longo, Giovanna; Mallett, Bruce; Marsh, Tad; Marshall, Michael; Mayfield, Michael; McCree, Victor; Mendiola, Anthony; Merschoff, Ellis; Miller, Hubert J.; Modes, Michael; Monarque, Stephen Raul; Munday, Joel; Nelson (HQ-OE), David; Olshan, Leonard; Paulk, Chuck; Pickett, Douglas; Reckley, William; Reinhart, F. Mark; Reynolds, Steven; Richards, Stuart; Rogge, John; Sands, Stephen; Stang, John; Strosnider, Jack; Wert, Leonard; Wetzel, Beth; Wharton, L. Raynard; Wichman, Keith; Wiggins, James; Young, Mitzi; Zwolinski, John
Jacob Zimmerman 1 8-02BulletinSR.wpd. Page 1 PRE-DECISIONAL INFORM ON - NOT FOR PUBLIC DISCLOSURE STATUS REPORT BULLETIN 2001-01, CIRCUMFERENTIAL CRACKING OF REACTOR PRESSURE VESSEL HEAD PENETRATION NOZZLES PLANTS WITH REFUELING OUTAGES SPRING 2002 PLANTS WITH HIGH SUSCEPTIBILITY TO PRIMARY WATER STRESS CORROSION CRACKING (PWSCC) OR PRIOR VHP NOZZLE CRACKING Davis-Besse Licensee Plans/Commitments: The licensee plans to shutdown for their next refueling outage on February 16, 2002 and perform VHP nozzle inspections. The shutdown date of February 16, 2002, was docketed in a letter dated November 30, 2001.
Planned Meetings & Teleconferences: A public meeting with the licensee is scheduled for January 23, from 10:30 a.m. to 1:00 p.m. in room 0-7B4 to provide the licensee an opportunity to discuss their plans for the inspection, flaw evaluation, and repair (if necessary) of the VHP nozzles.
The staff is making plans to visit the site during the planned outage to observe inspections.
D. C. Cook, Unit 2 Licensee Plans/Commitments: The licensee plans to shutdown for their next refueling outage on January 19, 2002 and perform VHP nozzle inspections. The shutdown date of January 19, 2002, was docketed in a letter dated November 30, 2001.
Planned Meetings & Teleconferences: None planned prior to the outage.
The staff is making plans to visit the site during the planned outage to observe inspections.
Surry, Unit 2 Licensee Plans/Commitments: The licensee performed a visual examination at a mid-cycle outage in November, and does not plan to perform any inspection at the RFO scheduled to begin in March 2002.
Planned Meetings & Teleconferences: None needed.
PRE-DECISIONAL INFOR - NOT FOR PUBLIC DISCLOSURE i Jacob Zimmerman 18-02BulletinSR.wpd Page Page.22 PRE-DECISIONAL INFORM - NOT FOR PUBLIC DISCLOSURE Oconee, Unit 1 Licensee Plans/Commitments: The licensee will perform a qualified visual examination at the RFO scheduled to begin April 2002. Prior experience at this unit had one CRDM nozzle and 5 (out of 8) thermocouple nozzles with leakage and cracks. From the recent experience at Unit 3, additional leakage/cracking is anticipated.
Planned Meetings & Teleconferences: None planned prior to the outage.
PRE-DECISIONAL INF- NOT FOR PUBLIC DISCLOSURE Jacob Zimmerman 1 8-02BulletinSR.wpd Page 3.
PRE-DECISIONAL INFORMATION - T FOR PUBLIC DISCLOSURE PLANTS WITH MODERATE SUSCEPTIBILITY TO PWSCC Unless noted otherwise, these plants have committed to perform an inspection consistent with the discussion in Bulletin 2001-01 (an effective visual examination or better).
ANO, Unit 2 (April 2002)
Beaver Valley, Unit 2 (February 2002)
Calvert Cliffs, Unit 1 (February 2002)
Diablo Canyon, Unit 1 (May 2002)
Fort Calhoun (May 2002)
Ginna (March 2002)
Licensee Plans/Commitments: The licensee does not plan to perform any inspection at the next RFO, but has stated plans to replace the RPV head at the next RFO (fall 2003).
The staff is reviewing a submittal from the licensee justifying this plan, based on the results of (1) the previous eddy current testing performed in 1999, (2) the crack growth rate analysis developed by Structural Integrity Associates, and (3) the fact that Ginna reactor vessel head temperatures are significantly lower than plants which have seen cracking. The 1999 eddy current test indicated no through-wall cracks, and the crack growth rate analysis using linear elastic fracture mechanics indicated that for the most limiting case (180 degree flaw) the time to grow to the allowable flaw size of 300 degrees is greater than the operating time from the 1999 inspection until the fall 2003 outage when RG&E plans to replace the reactor vessel head. The licensee also indicated that by providing enhanced operator training related to medium break loss of coolant accident, the probabilistic safety assessment results indicated that the conditional core damage probability is equal to 2.252E-03.
Staff Position: The approach proposed by the licensee appears reasonable. The staff is completing its review of the licensee's submittal to determine the adequacy of the justification.
Planned Meetings & Teleconferences: None scheduled.
ACTION ITEM: The staff needs to complete its review of the licensee's justification.
PRE-DECISIONAL INFORM N FOR PUBLIC DISCLOSURE LJacob Zimmerman 1,8-02BulletinSR.wpd . . . . . . .. .- PageL PRE-DECISIONAL INFORMATION OT FOR PUBLIC DISCLOSURE Millstone, Unit 2 (February 2002)
Licensee Plans/Commitments: The licensee has committed to an inspection that will interrogate the nozzle base material and the weld material using a rotating UT transducer (this plant does not have thermal sleeves in its CRDM nozzles). The licensee is determining the "appropriate sample size of RVHPs necessary to inspect to assure that potential cracks are detected and repaired." (The licensee has concluded that a visual inspection is not viable at this time because of the contoured insulation, presence of asbestos, restricted access, and ALARA concerns.)
Staff Position: The staff has pursued inspection of 100% of VHP nozzles at all plants, an approach borne out by the findings at Crystal River 3 for example, where only 1 nozzle was found with cracking, but this one nozzle had a large circumferential flaw and numerous other through-wall flaws. Therefore, it isn't obvious how a sampling program (of less than 100% of the nozzles) can be demonstrated to meet the objectives of the inspection program intended by the Bulletin.
Planned Meetings & Teleconferences: A public meeting with the licensee is scheduled for January 24, from 9:00 a.m. to 11:30 a.m. in room 0-1084 to provide the licensee an opportunity to present their justification for sampling less than 100% of the nozzles.
ACTION ITEM: The licensee needs to provide justification for its sampling plan.
Palo Verde, Unit 2 (March 2002)
Licensee Plans/Commitments: From a letter dated December 6, 2001, and subsequent phone calls, the licensee appears to plan an inspection that will be effective in meeting the objectives of the Bulletin. However, the licensee has been reluctant to document a written commitment that provides a sufficient description of the scope (e.g., 100% of the nozzles) and intent (e.g., ECT, PT, or UT of the wetted surfaces) of the inspection.
Staff Position: The staff has requested that the licensee provide a written commitment that sufficiently describes the scope and intent of the inspection. The verbal description provided by the licensee is acceptable.
Planned Meetings & Teleconferences: None planned.
ACTION ITEM: The licensee needs to document a clarification of the scope and intent of their planned inspection.
PRE-DECISIONAL INFORM ON - NOT FOR PUBLIC DISCLOSURE
. . . . . . . . . . . . . .. .. . . .. . . . . . P a g e ,5 acob Zimmerman 1 8-02BulletinSR.wpd PRE-DECISIONAL INFORMATI - NOT FOR PUBLIC DISCLOSURE Point Beach, Unit 2 (April 2002)
Licensee Plans/Commitments: From a letter dated January 3, 2002, the licensee plans to remove the existing insulation and perform an "effective visual examination" of all VHP nozzles. The licensee will inspect both the removed insulation and the vessel head to identify evidence of leakage. Because of the probability of asbestos, abatement will be required during the removal process, which the licensee does not expect to interfere with the visual inspection.
Staff Position: The inspection planned by the licensee appears to be effective in meeting the objectives of the Bulletin. However, the staff has identified several issues that are needed to demonstrate sufficiency of the planned inspection.
Planned Meetings & Teleconferences: A teleconference was held January 17, 2002, with the licensee. The licensee is consulting with vendors to resolve issues associated with inspection techniques. The licensee plans to meet with the staff one month prior to their planned outage to discuss their finalized plans.
ACTION ITEM: The licensee needs to document their commitment to discuss their inspection plans with the staff one month prior to the planned outage.
Prairie Island, Unit 2 (January 2002)
Salem, Unit 2 (April 2002)
San Onofre, Unit 2 (May 2002)
Turkey Point, Unit 4 (March 2002)
Waterford Unit 3 (March 2002)
PRE-DECISIONAL INFORM ON - NOT FOR PUBLIC DISCLOSURE
-PageW 6 v,-" .Zimmerman- 01-18-02BuI.etinSR.w.. d Pae 6 PRE-DECISIONAL INFORMATI - NOT FOR PUBLIC DISCLOSURE CLOSEOUT LETTERS Closeout letters have been issued for 48 of the 69 affected units.
PLANTS WITH HIGH SUSCEPTIBILITY TO PWSCC OR PRIOR VHP NOZZLE CRACKING Plant Closeout Letter ANO-1
- D.C. Cook 2 01/14/02 North Anna 1 **
North Anna 2 **
Oconee 1
- Robinson 11/20/01 Surry 1 **
Surry2 **
TMI-1 01/03/02
- NRR/DE/EMCB review ongoing
- Licensee owes supplemental response PRE-DECISIONAL INFORM ION - NOT FOR PUBLIC DISCLOSURE Jacob Zimmerman 18-02Bu~letinSR.wpd Page7*
PRE-DECISIONAL INFORMATI -NOT FOR PUBLIC DISCLOSURE PLANTS WITH MODERATE SUSCEPTIBILITY TO PWSCC Plant Closeout Letter ANO-2 01/14/02 Beaver Valley 1 12/11/01 Beaver Valley 2 12/11/01 Calvert Cliffs 1 12/06/01 Calvert Cliffs 2 12/06/01 Crystal River 3 Diablo Canyon 1 Diablo Canyon 2
- Farley 1 11/08/01 Farley 2 11/08/01 Fort Calhoun 11/08/01 Ginna
- Kewaunee 11/14/01 Millstone 2 **
PRE-DECISIONAL INFOR ION - NOT FOR PUBLIC DISCLOSURE Jacob Zimmerman 18-02BulletinSR.wpd Page 8 PRE-DECISIONAL INFORMATION - NOT FOR PUBLIC DISCLOSURE Plant Closeout Letter Palo Verde 1 **
Palo Verde 2 **
Palo Verde 3 **
Point Beach 1 **
Point Beach 2 **
Prairie Island 1 11/08/01 Prairie Island 2 11/08/01 Salem 1 11/20/01 Salem 2 11/20/01 San Onofre 2 11/20/01 San Onofre 3 11/20/01 St. Lucie 1 11/09/01 St. Lucie 2 11/09/01 Turkey Point 3 11/14/01 Turkey Point 4 11/14/01 Waterford 3 11/23/01
- Closeout letter in process
- Licensee owes supplemental response PRE-DECISIONAL INFORMATION - NOT FOR PUBLIC DISCLOSURE I ,, 7i nmmrm n - ni -iq-r~li ltinqR wnd Page 9 LýT %,U .,
PRE-DECISIONAL INFORMATION - NOT FOR PUBLIC DISCLOSURE PLANTS WITH LOW SUSCEPTIBILITY TO PWSCC Plant Closeout Letter Braidwood 1 11/14/01 Braidwood 2 11/14/01 Byron 1 11/14/01 Byron 2 11/14/01 Callaway 11/14/01 Catawba 1 12/04/01 Catawba 2 12/04/01 Commanche Peak 1 11/19/01 Commanche Peak 2 11/19/01 DC Cook 1 01/14/02 McGuire 1 11/19/01 McGuire 2 11/19/01 Millstone 3 11/26/01 Palisades 11/08/01 Seabrook 12/03/01 Sequoyah 1 11/20/01 Sequoyah 2 11/20/01 Shearon Harris 12/20/01 South Texas 2 12/14/01 South Texas 1 12/14/01 Summer 12/03/01 Vogtle 1 11/07/01 Vogtle 2 11/07/01 Watts Bar 1 11/20/01 Wolf Creek 11/14/01 PRE-DECISIONAL INFORMATION - NOT FOR PUBLIC DISCLOSURE