S. Wastler Memo Technical Assistance Request - Review of Proposed Amendment to the Cooper Power Station Physical Security Plan (TAC L24478)
ML102850517
Person / Time
Site: Cooper  Entergy icon.png
Issue date: 10/07/2010
From: David Pstrak
NRC/NMSS/SFST/LID/RIOB
To: Wastler S
Division of Security Policy
Wharton L
References
TAC L24478
Download: ML102850517 (3)


Text

October 7, 2010 MEMORANDUM TO: Sandra Wastler, Chief Materials, Waste and International Security Branch Division of Security Policy Office of Nuclear Security and Incident Response FROM: David W. Pstrak, Chief /RA/

Rules, Inspection and Operations Branch Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards

SUBJECT:

TECHNICAL ASSISTANCE REQUEST - REVIEW OF PROPOSED AMENDMENT TO THE COOPER POWER STATION PHYSICAL SECURITY PLAN (TAC NO. L24478)

The Division of Spent Fuel Storage and Transportation (SFST), Office of Nuclear Material Safety and Safeguards (NMSS), requests technical assistance from the Division of Security Policy (DSP), Nuclear Security and Incident Response (NSIR), for the completion of the following project:

PROJECT: Review Nebraska Public Power Districts (NPPD) response to Order (EA 195) and the Cooper Power Station Independent Spent Fuel Storage Installation (ISFSI)

Physical Security Plan and verify implementation of the additional security measures.

DOCKET NO: 50-298, 72-66 TAC NO: L24478 REQUESTED ACTION: NMSS/SFST requests that NSIR/DSP review NPPDs response to the Security Order and the Cooper Power Station ISFSI Physical Security Plan. Prepare a memorandum documenting the results of NSIRs review.

S. Wastler Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.

Name of NSIR/DSP assigned Reviewer: _________________________________

NSIR/DSP Project Completion Date: _________________________________

NSIR/DSP Branch Chief Signature: _________________________________

Contact:

Raynard Wharton (301) 492-3316 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.

S. Wastler Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.

Name of NSIR/DSP assigned Reviewer: _________________________________

NSIR/DSP Project Completion Date: _________________________________

NSIR/DSP Branch Chief Signature: _________________________________

Contact:

Raynard Wharton (301) 492-3316 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.

Distribution: (w/o attachment) SFST r/f BWhite ADAMS: ML102850517 G:\SFST\Security - ICMS & Orders\TARs\Cooper TAR.doc OFC SFST SFST SFST NAME RWharton WWheatley DPstrak DATE 10/ 6/2010 10/ 07/2010 10/ 07 /2010 OFFICIAL RECORD COPY