RNP-RA/02-0185, November 2002 Monthly Operating Report for H. B. Robinson, Unit 2

From kanterella
(Redirected from ML023510005)
Jump to navigation Jump to search
November 2002 Monthly Operating Report for H. B. Robinson, Unit 2
ML023510005
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/13/2002
From: Baucom C
Carolina Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/02-0185
Download: ML023510005 (3)


Text

" -- TS 5.6.4 TRM 6.2

ýn CP&L A Progress Energy Company Serial: RNP-RAI02-0185 DEC 1 3 2002 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 MONTHLY OPERATING REPORT Ladies and Gentlemen:

In accordance with the H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2, Technical Specifications (TS) Section 5.6.4, "Monthly Operating Reports," and HBRSEP, Unit No. 2, Technical Requirements Manual (TRM) Section 6.2, "Monthly Operating Report," Carolina Power & Light Company submits the enclosed report of operating statistics and shutdown experience for the month of November 2002.

If you have any questions concerning this matter, please contact me.

Sincerely, C. T. Baucom Supervisor - Licensing/Regulatory Programs CAC/cac Attachment c: NRC Resident Inspector, HBRSEP L. A. Reyes, NRC, Region II R. Subbaratnam, NRC, NRR Robinson Nuclear Plant 3581 West Entrance Road Hartsville SC29550

Attachment to Serial: .RNP-RA/02-0185 Page 1 of 2 MONTHLY OPERATING REPORT DOCKET NO. 050-0261 UNIT H. B. ROBINSON STEAM ELECTRIC PLANT (HBRSEP), UNIT NO. 2 DATE 12/02/02 COMPLETED BY TOM FREEMAN TELEPHONE (843) 857-1403 REPORTING PERIOD: NOVEMBER 2002

1. DESIGN ELECTRICAL RATING (NET MWE): 700.0
2. MAX DEPENDABLE CAPACITY (NET MWE): 683.0 THIS YR TO CUMULATIVE MONTH DATE
3. NUMBER OF HOURS REACTOR CRITICAL 431.60 7246.60 211054.19
4. HOURS GENERATOR ON LINE 401.00 7216.00 207734.26
5. UNIT RESERVE SHUTDOWN HOURS 0.00 0.00 23.20
6. NET ELEC. ENERGY GENERATED (MWH) 270465.00 5054030.00 135385379.00

Attachment to Serial: RNP-RA/02-0185 Page 2 of 2 DOCKET NO. 050-0261 UNIT NAME HBRSEP. UNIT NO. 2 DATE 12/02/02 COMPLETED BY TOM FREEMAN 'r TELEPHONE (843) 857-1403 REPORTING PERIOD: NOVEMBER 2002 No. Date Type Duration Reason' Method of Shutting Down Cause / Corrective Actions / Comments 2

F Forced (Hours) the Reactoror Reducing Power S, Scheduled 02.005 10/11/02 S 319 C 4 Shutdown for Refueling Outage 21.

02.006 11/24/02 S 7.25 B 1 The unit was off-line to repair a steam leak.

2 Reason: Method:

A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Continuation E-Operator Training & License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

The unit was returned to service at 2345 hours0.0271 days <br />0.651 hours <br />0.00388 weeks <br />8.922725e-4 months <br /> on November 13, 2002, to end Refueling Outage 21. There were no challenges to the pressurizer safety valves during the month.