JAFP-94-0252, Special Rept 94-001 Re Fire Barrier Penetration Seals Not Restored within TS Time Frame.Caused by Scope of Work in Steam Tunnel.Roving Fire Watch Posted in Recirculation Motor Generator Set Room & Floor Plugs Removed

From kanterella
(Redirected from JAFP-94-0252)
Jump to navigation Jump to search
Special Rept 94-001 Re Fire Barrier Penetration Seals Not Restored within TS Time Frame.Caused by Scope of Work in Steam Tunnel.Roving Fire Watch Posted in Recirculation Motor Generator Set Room & Floor Plugs Removed
ML20065R318
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/06/1994
From: Harry Salmon
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
94-001, 94-1, JAFP-94-0252, JAFP-94-252, NUDOCS 9405110034
Download: ML20065R318 (2)


Text

._

4 3 James A. FitzPatrick Nucisar Power Plant

,, P O. Box 41 Lycoming. New York 13093 315 342 3MO 0

& Authon,IWM ty Harry P. saimon, Jr.

nesident Manager thy 6,1994 JAFP-94-0252 United States Nuclear Regulatory Commission Document Control Desk Mail Station P1-137 Washington, D.C. 20555

SUBJECT:

DOCKET NO. 50-333 SPECIAL REPORT 94-001 NONFUNCTIONAL FIRE BARRIER PENETRATION SEAL

Dear Sir:

The New York Power Authority (NYPA) submits this special report in accordance with Technical Specification 3.12.F.2 and 6.9.B.2. The report describes fire barrier penetration seals which were not restored to functional status within a seven day period due to planned outage activities.

Introduction:

During the conduct of the Spring, 1994, Maintenance Outage, floor plugs in the Recirculation Motor Generator Set Room were removed to provide maintenance access to the Main Steam Line Tunnel located directly below this room. Although the Steam Tunnel is'also accessible from the Turbine Building, floor plug access is preferred for ALARA considerations.

The floor plugs functionally provide fire barrier protection between the Recirculation Motor Generator Set Room and the Steam Tunnel.

Action Taken:

On April 4, 1994, a roving fire watch was posted in the Recirculation Motor Generator Set Room and floor. plugs removed to provide maintenance access to the Main Steam Tunnel. On April 15, 1994,'the fire watch was upgraded to continuous when the installed smoke detection system was taken out of service for scheduled outage maintenance. The smoke detection system was restored and a roving fire watch pse on April 22, 1994.

940511oo34 940506 gDR ADOCK 05000333 ggjd pay &so /9'S ~" f

i o

SPECIAL REPORT 94-001 NONFUNCTIONAL FIRE BARRIER PENETRATION SEAL 4'

Page .

Fire watches, either roving or continuous, remained posted until the floor plugs were replaced on April 28, 1994. The plant was shutdown and in the cold condition with the mode switch in Refuel during the time the floor plugs were

. removed.

Cause:

The scope of work in the steam tunnel was such that it could not be completed within a seven day period. Because the steam plugs were removed for greater than seven days, the Technical Specification requires a special report.

If you have any questions concerning this matter, please contact Donald F. Simpson at (315) 349-6361.

Very truly yours, y a 5 HARRY P. SALMON, JR.