IR 05000416/1985025

From kanterella
Jump to navigation Jump to search
Insp Rept 50-416/85-25 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Review of Completed Startup Tests
ML20133P214
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 07/25/1985
From: Burnett P, Jape F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20133P201 List:
References
50-416-85-25, NUDOCS 8508140213
Download: ML20133P214 (6)


Text

.

o UNIVFD STATES

[g>n Ric , o, NUCLEAR REGULATORY COMMisslON

  1. \. .

REGION 11 f. 7.l! ,

101 MARIETTA STREET, 'c ATL ANTA, GEORGI A 30323

% + .w... ]

Report No.: 50-416/85-25 Licensee: Mississippi Power And Light Company Jackson, MS 39205 Docket No.: 50-416 License No.: NPF-29 Facility Name: Grand Gulf 1 Inspect'on Conducted : uly 15 - 19, 1985 Inspector: h , jgene2v

~P~ T. Burnett

,26 8 /fW Date Signed Approved by: c b f zx /for go4 MJape,SectionChief Date" Signed Engineering Branch Division of Reactor Safety SUMMARY Scope: This routine, unannounced, inspection entailed 32 inspector-hours at the site in the of review of completed startup test Results: No violations or deviations were identifie PDR ADOCK 05000416 G PDR L

_

-

.

.

1 REPORT DETAILS 1 Licensee Employees Contacted

  • J. E. Cross, General Manager
  • C. R. Hutchinson, Manager, Plant Maintenance
  • R. F. Rogers, Technical Assistant l *J. D. Bailey, Compliance Coordinator '
  • J. Wright, Manager, Plant Operations ,
  • Cupstid, Start-up Supervisor /
  • W. P. Harris, Compliance Coordinator /
  • G. H. Davant, Startup Engineer ,'

Other licensee employees contacted included engineers, operators, and office personnel.

, NRC Resident Inspectors

! *R. Buthcher

  • J. Caldwell i
  • Attended exit interview Exit Interview i

The inspection scope and findings were summarized on July 19, 1985 with j those persons indicated in paragraph I above. (The actual presentation of the findings was given by another inspector.) No dissenting comments were received from the licensee. The licensee did not identify as proprietary any of the materials provided to or reviewed by the inspector l during this inspection.

a Licensee Action on Previous Enforcement Matters

Not inspected, j Unresolved Items Unresolved items were not identified during this inspectio . Plant Surveillance (71711) '

i The inspector toured the nuclear instrument back panels in the control room l i and the upper cable spreading room. The number of bypassed local - i range monitors (LPRMs) in each average power range monitor (APRM)channel power - l

'

was determined by observation of the status lights. The determination was l compared with records maintained in the control room by the licensee, and

!

was found to agree. No APRM had more than four LPRMs bypassed, nor were

<

more than two of the bypassed LPRMs in any APRM from the same string leve I i

_ _ _ _ _ _ _ _ - - - - . . , _ _ , _ _ _ _ _ _ _ - - . , . _ . , . , _ _ . _ ,_ __

. _ _ . - _ _ _ _ _ _ _ _

._

_ _ _ _ _ _ __

. 1

.

'

.

Since there are 22 LPRMs per APRM, with a minimum of five LPRMs at each level, all APRMs were operable. Technical specification table 3.3.1-1 defines an APRM as inoperable if there are less than two LPRM inputs per level or less than fourteen LPRM inputs per channe However, a total of 16 failed detectors with only 90 effective full-power days of operation projects to about 60 failures by the end of the current cycle, if the failures are proportional to time at power. The Technical Specifications would allow, at most, 64 failed detectors. The status of the LPRMs will be monitored during future inspection . Review of Completed Startup Tests (72532)

The following completed startup tests were reviewed to assure that the results had been reviewed and accepted by plant management, that the accep-tance criteria had been satisified, and that all test exceptions had been resolved or were being actively pursue Heatup Tests (1) 1-C51-SU-11-H (Revision 1), LPRM Calibration, could not be per-formed at heatup conditions because of insufficient neutron flu The test was actually performed at test condition 1 under test exception HU-6 Performance was on October 6-15, 1984. The results were accepted on November 1, 1984, with no open test exception (2) 1-C91-SU-13-H (Revision 1), Process Computer, was completed on October 27, 1984. The results were accepted with no open test exceptions on November 9, 198 (3) 1-821-SU-16-H (Revision 1), Selected Process Temperatures and Water Level Measurements, was performed on October 25-30, 198 l The results were accepted on February 16, 1984 with no open test j exceptions.

l (4) 1-000-SU-23-H (Revision 1), Feedwater System, was perfonned on November 4-8, 1983. The results were accepted on March 23, 1984 i

with no open test exception (5) 1-821-SU-25-H (Revision 1), Main Steam Isolation Valves, was l

'

performed over the period October 17, 1983 to March 21, 198 The results were accepted on April 13, 1985 by all but the plant i

manager, who did not sign the cover sheet until July 17, 1985, when the lack of signature was identified by the inspector. The failure to sign was a simple oversight. No exceptions to the test were open on April 13, 198 (6) 1-B21-SU-26-H (Revision 2), Relief Valves, was performed in the period September 26 to November 29, 1983. The results were accepted on February 16, 1984 with no open test exception _ - _ _ - ..

..

'

-

.

'

l

l (7) 1-G33-SU-70-H (Revision ~1), Reactor Water Cleanup System, was performed from September 26 to November 3,1983. The results were accepted on November 16, 1983 with no open exceptions to the tes (8) 1-M51-SU-72-H (Revision 1), Drywell Cooling System, was performed from September 26 to October 31, 1983, and the results were accepted on 15 November 1983 with no test exceptions ope (9) 1-000-SU-75-H (Revision 1), Cooling Water Systems, was performed over the period September 24 to November 2, 1983. The results were accepted on February 16, 1984 with no test exceptions open, Test Condition 3 (1) 1-C11-SU-05-3(Revision 1), Control Drive System, was performed on April 25-26, 1985. The results were accepted on April 27, 1985 with no exceptions. No rods exceeded the first line scram time limit in the table of acceptable scram times, hence no further evaluation of performance with respect to location was require (2) 1-C51-SU-11-3 (Revision 1), LPRM Calibration, was performed on February 6, 1985. The results were accepted on April 15, 1985 with no open exception (3) 1-C51-SU-12-3 (Revision 2), APRM Calibration, was performed on February 5-6, 1985 using 06-RE-1J11-V-0001 (Revision 23), Power Distribution. Limits Verification, for data collection. The results were accepted on April 9, 1985 with no exception (4) 1-C91-SU-13 2 3 (Revision 1), Process Computer, was performed on April 12, 1985, and the results were accepted on April 26, 1983 with no open exception (5) 1-821-SU-16-3 (Revision 2), Selecteo Process Temperatures and Water Level Measurements, was perforned between January 24 and April 19, 1985. The results were accepted' on April 26, 1985 with no open exception (6) 1-000-SU-18-3 (Revision 1), Core Power Distribution Limits, was performed on April 12, 1985. The total traveling incore probe (TIP) flux measurement uncertainty was 1.8%, well below the acceptance criterion limit of 6%. The results were accepted on April 26, 1985 with no open exception (7) 1-000-SU-19-3 (Revision 1), Core Performance, was performed on February 5, 1985 with no exceptions taken. The results were accepted on April 15, 1985.

l

,

>

> l

_______

-

.

(8) 1-N32-SU-22-3(Revision 1), Initial Pressure Controller, was performed between January 30 and April 6,1985. The results were approved on April 27, 1985 with no open exceptions. Testing related to automatic load following (ALF) was deleted as non essential, since use of the ALF feature is not anticipated in the near futur (9) 1-000-SU-23-3 (Revision 2), Feedwater System, was perfonned between February 6 and April 26, 1985. The results were accepted on April 27, 1985 with exception MP-77, a level 2 acceptance criterion unresolve The licensee has observed and made specific note that the response of the feedwater system to plant transients was slow leading to high vessel water level during power reductions. However, no corrective action was indicated. Resolution of feedwater system issues will be pursued during future inspection (10) 1-000-24-50-3 (Revision 1), Turbine Valve Surveillance, was performed on April 6-8, 1985. The results were accepted on

.

i April 26, 1985 with no open test exception !

(11) 1-B21-SU-25-3 (Revision 1), Main Steam Isolation Valves, was performed on April 1-26, 1985, with the results accepted on April 29, IC85 with no open exception (12) 1-000-SU-27-3 (Revision 2), Turbine Trip, was performed between April 24-27, 1985. The results were accepted on April 29, 1985 with two test exceptions still open. The exceptions, MP-117 and MP-118, affect only level 2 acceptance criteri (13) 1-B33-SU-29-3 (Revision 2), Recirculation Flow Control System, was

!

'

performed on April 8-27, 1985. Four test exceptions, MP-106, MP-107, MP-111, and MP-112, none of which address acceptance criteria, were still open when the test was accepted on April 29, 198 (14)1-B33-SU-30-3(Revision 2),ReactorRecirculationSystem,was performed between April 16 and 26, 1985. The results were accept-ed on April 29, 1985 with test exception MP-99 (a level 2 accep-tance criterion) still ope (15) 1-B33-SU-35-3 (Revision 1), Recirculation System Flow Calibration, was performed between February 6 and April 4,1985. The results were accepted on April 29, 1985 with no open test exception (16) 1-000-SU-75-3 (Revision 2), Cooling Water Systems, was performed on January 24-26, 1985, and the results were accepted on March 25, 1985. The test was performed without requiring a single test change or exceptio i

- .- .__ - -. = ...

.,

'

.

i No violations or deviations were identified in the review of the completed startup test procedures. The status of the review of the startup tests is shown in an attachment to this repor . Followup of Inspector-Identified Items (927901)

) (Closed) Inspector followup item 50-416/83-29-02, Remote shutdown crew initial positions. By permanent test change number 1, issued on June 15, 1984, to startup test procedure 1-000-SU-28-2, Shutdown from Outside the

. Main Control Room, the licensee removed the procedure step that dispatched i the test crew to the remote stations prior to initiating the test. With this change the test was initiated with the crew in the control room, satisfying the requirements of Regulatory Guide 1.68.2. Proper performance j of the test was witnessed during inspection 50-416/85-01.

j i

'}

!

I i

l

!

't i

. - - ,. -- , - - - , - . - . - , . . , . - - .r v. . , , - , s .,, - , . , - - . . , - - ,, ,