IR 05000410/1986041

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/86-41 on 860729-0801.No Violations Noted. Major Areas Inspected:Power Ascension Test Program Procedures,Surveillance Activities to Support Fuel Loads & QA Interfaces
ML17055C259
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 08/13/1986
From: Eselgroth P, Florek D, Joe Golla
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17055C257 List:
References
50-410-86-41, NUDOCS 8608260355
Download: ML17055C259 (16)


Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-410/86-41 Docket No.

50-410 License No.

CPPR-112 Licensee:

Nia ara Mohawk Power Cor oration 300 Erie Boulevard West S racuse New York 13202 Facility Name:

Nine Mile Point Nuclear Station Unit 2 Inspection At:

Scriba New York Inspection Conducted:

Jul

Au ust

1986 I

Inspectors:

Florek, ad Reactor Engineer olla, ctor Engin er date date Approved by:

P. Eselgrot

,

hief Test Program Section Operations ranch, DRS date Ins ection Summar

Ins ection on Jul 29 - Au ust

1986 Ins ection Re ort No. 50-410/86-41

~d:

R inspectors of the power ascension. test program procedures, surveillance activities to support initial fuel load, in office CILRT pre=operational test report review, gA interfaces, independent

'measurements and calculations and tours at the facility..

Resul ts:

No violations were identi fied.

NOTE:

For acronyms not defined refer to NUREG-0544, Handbook of Acronymns and Initialisms.

8608260355 860815 PDR

'ADQCK 05000410

PDR

DETAILS 1.

Persons Contacted Nia ara Mowhawk Power Cor oration NMPC and Contractors R. Abbott, Station Superintendent

"J.

Conway, Power Ascension Manager M. Coulomb, Operation Surveillance Coordinator

"W. Hansen, Manager Nuclear QA L. Lagoe, 18C Unit Supervisor D. Myers, Supervisor Planning and Scheduling J.

Robles GE Site Operations Manager R. Warren, Surveillance Coordinator

~I. Weakley, Special Projects

"P. Wielde, Supervisor, Surveillance QA U.S. Nuclear Re ulator Commission

~W. Cook, Senior Resident Inspector

  • T. Koshy, Reactor Engineer

"R. McBrearty, Reactor Engineer

  • W. Schmidt, Resident Inspector

"C, Woodard, Reactor Inspector

  • Denotes those present at exit meeting held on August 1, 1986.

2.

Power Ascension Test Pro ram 2.1 References Regulatory Guide 1.68, Revision 2, August, 1978

"Initial Test Programs for Water-Cooled Nuclear Power Plants".

ANSI N18.7-1976 "Administrative Controls and Quality Assurance for the Operational Phase of Nuclear Power Plants".

Nine Mile Point Unit 2 (NMP-2) Technical Specifications Final Draft, June 25, 1986.

NMP-2 Final Safety Analysis Report (FSAR), Chapter 14 "Initial Test Program".

NMP-2 Safety Evaluation Report.

2.2 Power Ascension Procedure Review

~Sco e

The inspector reviewed N2-SUT-3-0V, uel Load, Revision 0 Final draft dated July, 1986 and N2-SUT-25-HU, Main Steam Isolation Valves, Re vision 0 draft dated June, 1986 utilizing the attributes defined in Inspection Report 50-410/86-38, Section The inspector also reviewed the analysis performed by the licensee to support the test methodology specified in N2-SUT-16-HU, Selected Process Temperature and Water Level Measurements, and performed inde-pendent calculations using the licensee analysis equations to deter-mine if the test methodology in N2-SUT-16-HU was adequate.

Discussion The fuel load procedure reflected the comments generated by the licen-see review process and was consistent with the observations of the in-spector during inspection 50-410/86-38.

The procedure was in the final stages of the review process.

The methodology in N2-SUT-25-HU was acceptable.

The inspector performed independent calculations to access whether the methodology utilized in N2-SUT-16-HU to satisfy the reactor water level scale end point error acceptance criterion was sufficient.

The inspector concluded that for wide range water level indication, the methodology was acceptable but questioned the methodology for narrow range water level indications.

The inspector also questioned the ade-quacy of limiting the analysis performed to only one level indicator to justify the test methodology.

The licensee will perform analyses on additional level instruments using "as built" data to justify the methodology or modify the method as appropriate.

~Findin s

No violations were identified.

3.

Surveillance Activities to Su ort Initial Fuel Load

~Sco e

The inspector reviewed the licensee program for assuring that the plant will satisfy the technical specification surveillance requirements applic-able for the initial fuel load.

In addition, the inspector reviewed the interim surveillance procedures listed in Attachment 1 to determine if they will lead to a successful procedure to satisfy the Technical Specifi-cations (final draft dated June 25, 1986).

The following documents were reviewed:

NMP2 Surveillance Test Matrix dated July 25, 1986.

N2-SAP-R5 Interim Surveillance Procedures, Revision 1 dated April 21, 1986

'P-2.0 Production and Control of Procedures, Revision 5 dated June, 1986.

AP-8.2 Surveillance Testing and Inspection Program, Revision 2 dated July 10, 1986.

N2 Instrument Surveillance Procedures Index dated July 30, 1986.

NMPC Working Schedule Run dated July 30, 198 Discussion The inspector reviewed surveillance activities for the Operations and In-'trument and Control Departments.

These two departments are utilizing a method of interim surveillance procedures to develop workable final proce-dures prior to issuing final surveillance test procedures.

Other depart-ments utilize only final surveillance test procedures.

As of July 28, 1986, the licensee has identified 216 surveillance test procedures for all de-partments required for fuel load and 81 have been approved as final sur-veillance procedures.

The licensee approach is to use the interim surveillance procedure in the field and make changes necessary to make the procedure workable and capable of satisfying technical specification requirements.

The procedures and changes are controlled under N2-SAP-125 as part of the preoperational test program.

The interim surveillance procedure review process does not sati s-fy the review and approval process required by technical specification so that once a successful surveillance test is performed, the licensee will then use the interim surveillance procedure to prepar e a final version.

It will then be reviewed and approved as required per the Technical Specifica-tion 6.8.2 in ac-ordance with licensee administrative procedure AP-2.

This includes satisfying the SORC review function, gA review, ALARA review and Health Physics review as required and approval by the General Superintend-ent.

The licensee plans on using the results from the successful interim test however to satisfy surveillance test requirements if minor changes occur in the AP-2 review cycle.

The inspector was initially concerned that the licensee process would result in technical specification requirements being based on procedures not reviewed and approved as required per the technical specification.

Based on discussions with the Plant Superintend-ent, the licensee w'ill have AP-2 reviewed and approved final surveillance procedures to satisfy technical specification requirements prior to fuel load.

Department supervisors wi 11 be responsible to assure that the final surveillance procedure requirements are satisfied.

Thus based on these discussions, the inspector initial concerns were resolved.

At the exit the inspector reiterated that the licensee can only take credit for technical specification surveillance when an approved signed procedure by the General Superintendent exists.

The Department supervisors are then responsible to assure that data used to satisfy the surveillance require-ments of the final approved procedure, whether it is based on preoperation-al test results, interim surveillance procedure data or data gathered using the approved procedure, is appropriate for the plant condition.

However, for the purposes of determining when the surveillance test needs to be per-formed again, the actual performance date of the test should be utilized.

The inspector attempted to review the final surveillance test procedures for operations and I8C sur vei llances.

Copies of final surveillance test procedures for these groups were not yet distributed although eighteen I&C procedures were approved and signed on July 28, 1986.

The inspector

L

~,

did review final surveillance procedure N2-ISP-NMS-R202 Fixed Neutral Flux Response, Revision 0 dated July 28, 1986 and the associated interim sur-veillance test results.

The test data supported the surveillance test pro-cedure.

The inspector noted that the procedure covered all 6 Average Power Range Monitors and that the tests were performed on different dates.

The date included in the licensee's working schedule for the purposes of esta-blishing a reperformance date was the latest APRM test completion date rather than the earliest completed date.

The licensee I&C Unit Supervisor indicated that he would review the indicated dates for rescheduling sur-veillances to assure that the dates were compatible with the earliest com-pleted portion.

The i'nspector noted that the discrepancy was well within the 25% allowance identified in technical specifications.

The inspector review of the interim surveillance procedures of Attachment I noted that the procedures were acceptable for use as a basis to establish final surveillance procedures.

The inspector also reviewed the method to assure that the required surveil-lance tests were completed.

Each department is responsible for assuring its assigned surveillance tests are current.

The licensee utilizes a docu-ment Cold Functional Test N2-CFT-1 to list all survei llances required for Modes 4 and 5 and to sign off when they are complete as well as individual department tracking to assure assigned survei llances are completed.

In addition, the planning and scheduling department is in the process of finalizing a program to schedule surveillance tests based on test date completed and technical specification frequencies.

~indincis No violations were identified.

Containment Inte rated Leak Rate Test Re ort Preview Sco e

The inspector reviewed the Summary Technical Report submitted to the NRC by the licensee entitled "Reactor Containment Building Integrated Leakage Rate Tests Types A, B, and C" dated April, 1986 to determine if the tests satisfied 10CFR50 Appendix J.

Discussion The Nine Mile Point 2 Preoperational Containment Integrated Leak Rate Test (CILRT) was conducted during the period April 10, 1986 to April 14, 1986.

It included a reduced pressure test run at 20 psig and a full (accident)

pressure test run at 40 psig.'ach test was run for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of data ob-servation with a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> temperature stabilization period before and a

hour period following data observation for the conduct of a superimposed

=

leakage verification tes Both tests were successful in that the containment leak rate demonstrated by each was within the'acceptance criteria delineated in 10CFR50 Section III.A.4.(b),(1)5(2) of Appendix J (See table below).

Each test was followed by a successful superimposed leakage verification test.

TEST PRESSURE (PSIG)

TEST METHOD AND TYPE OF ANALYSIS ACCEPTANCE CRITERIA (WT. %/DAY)

TEST RESULT (WT. %/DAY)

MUST BE LESS THAN ACCEPTANCE CRITERIA

20

40 ABSOLUTE METHOD OF MASS POINT ANALYSIS ABSOLUTE METHOD OF TOTAL TIME ANALYSIS ABSOLUTE METHOD OF MASS POINT ANALYSIS ABSOLUTE METHOD OF TOTAL TIME ANALYSIS 0.75 Lt OR 0.525 0.75 Lt OR 0.525 0.75 La OR 0.659 0.75 La OR 0.659 0.143 0.238 0.205 0.290

~Findin s

No violations were identified.

5.

555 The inspector discussed with the Supervisor QA Survei llances the QA in-volvement in the Power Ascension Test Program.

QA is reviewing all startup test (SUT) procedures in accordance with AP-2.

Inspector reviewed QA com-ment sheets for selected SUTs.

QA will also review all completed test re-sults.

QA plans to have at least

QA personnel on shift to witness start-up testing on an as run basis.

QA is notified when each SUT is performed as a prer equi site to each SUT to facilitate QA coverage.

The inspector reviewed the SUT procedure review guidance provided to the QA personnel and the checklist for completed test results evaluation.

The inspector also discussed whether QA review is provided for surveil-lances procedures.

QA review is required per the AP-2 for safety related surveillance procedures and is ongoing.

No acceptable conditions were noted in the QA involvemen L

~

Inde endent Measurements and Calculations During the test procedure review, the inspector performed independent cal-culations to justify the methodology used to perform end point error analy-sis on water level measurements.

The results are discussed in Section 2.2.

7.

Tours of the Facilit The inspector made several tours of various areas of the facility including the control structure, diesel generation building and turbine building to observe work in progress housekeeping, cleanliness and status of construc-tion.

No acceptable conditions were noted.

8.

Exit Interview At the conclusion of the site inspection on August 1,

1986, an exit inter-view was conducted with the licensee's senior site representatives (denoted in Section 1).

The findings were identified and previous inspection items were discussed.

At no time during this inspection was written inspection findings provided to the licensee by the inspector.

Based on the NRC Region I review of this report and discussions held with licensee representatives during this in-spection, it was determined that this report does not contain information subject to

CFR 2.790 restriction l P

ATTACHMENT 1 Interim Surveillance Procedures Reviewed:

N2-OSP-LOG-S001 N2-OSP-LOG-D001 N2-OSP-RMC-WQ002 N2-OSP-SLS-M001 N2-OSP-SLS-0001 N2"OSP-SLS-R001 N2-OSP-SLS-R002 Shift Checks, Revision 0 dated June 24, 1986.

Daily Checks, Revision 0 dated May 20, 1986.

Reactor Mode Switch Functional Test of Refueling Interlocks, Revision 0 dated April 9, 1985.

Standby Liquid Control Explosive Valve Continuity Check and Valve Lineup Verification.

Standby Liquid Control Pump, Check Valve and Relief Valve Test, Revision 1 dated June 9,

1986.

Standby Liquid Control Manual Initiation Actuation, Revision 1 dated May 20, 1986.

Standby Liquid Control Heat Traced Piping and Storage Tank Heater Operability Test, Revision

dated May 26, 198