2014 Annual Assessment Letter for Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220/2014001 and 05000410/2014001)(w/Inspection Plan)
ML15057A333
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 03/04/2015
From: Daniel Schroeder
Reactor Projects Branch 1
To: Orphanos P
Exelon Generation Co
Schroeder D
References
IR 2014001
Download: ML15057A333 (5)


Text

rch 4, 2015

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR NINE MILE POINT NUCLEAR STATION UNITS 1 AND 2 (REPORT 05000220/2014001 AND 05000410/2014001)

Dear Mr. Orphanos:

On February 12, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Nine Mile Point Nuclear Station (NMPNS) Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, NMPNS Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at NMPNS during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5262 with any questions you have regarding this letter.

Sincerely,

/RA/

Daniel L. Schroeder, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 50-220 and 50-410 License Nos. DPR-63 and NPF-69 Enclosure: NMPNS Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML15057A333 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ARosebrook/AAR DSchroeder/DLS DATE 02/19/15 02/19/15

Page 1 of 2 Nine Mile Point 02/26/2015 13:41:30 Inspection / Activity Plan Report 22 01/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 3/2EXAM - U1 INITIAL OL EXAM 4 1 02/02/2015 02/06/2015 U01905 FY15-NMP1 INITIAL OPERATOR LICENSING EXAM 1 03/02/2015 03/13/2015 U01905 FY15-NMP1 INITIAL OPERATOR LICENSING EXAM 7111108G - U1 INSERVICE INSPECTION 1 1 03/23/2015 03/27/2015 IP 7111108G Inservice Inspection Activities - BWR 71124 - RAD SAFETY INSPECTION 1 1, 2 03/30/2015 04/03/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/30/2015 04/03/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 03/30/2015 04/03/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/30/2015 04/03/2015 IP 71124.04 Occupational Dose Assessment 1, 2 03/30/2015 04/03/2015 IP 71151 Performance Indicator Verification 71124 - RAD SAFETY INSP 1 1, 2 05/11/2015 05/15/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 05/11/2015 05/15/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 05/11/2015 05/15/2015 IP 71124.04 Occupational Dose Assessment 71124.07 - RAD SAFETY INSPECTION 1 1, 2 06/01/2015 06/05/2015 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 06/01/2015 06/05/2015 IP 71151 Performance Indicator Verification TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 6 1, 2 06/22/2015 06/26/2015 IP 7111105T Fire Protection [Triennial]

1, 2 07/06/2015 07/10/2015 IP 7111105T Fire Protection [Triennial]

11/30EXM - U2 INITIAL OL EXAM 3 2 11/02/2015 11/06/2015 U01920 FY16-NMP2 INITIAL OPERATOR LICENSING EXAM 2 11/30/2015 12/04/2015 U01920 FY16-NMP2 INITIAL OPERATOR LICENSING EXAM 71124 - RAD SAFETY INSPECTION 1 1, 2 08/03/2015 08/07/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 08/03/2015 08/07/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 08/03/2015 08/07/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/03/2015 08/07/2015 IP 71124.04 Occupational Dose Assessment 71152B - PI&R - BIENNIAL 1 1, 2 08/10/2015 08/14/2015 IP 71152B Problem Identification and Resolution 1, 2 08/24/2015 08/28/2015 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Nine Mile Point 02/26/2015 13:41:30 Inspection / Activity Plan Report 22 01/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111111B - U2 REQUAL INSP WITH P/F RESULTS 2 2 10/19/2015 10/23/2015 IP 7111111B Licensed Operator Requalification Program EP - EP EXERCISE 5 1, 2 10/19/2015 10/23/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 1, 2 10/19/2015 10/23/2015 IP 7111408 Exercise Evaluation - Scenario Review RS1234PI - HP INSPECTION 1 1, 2 04/24/2016 04/28/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/24/2016 04/28/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/24/2016 04/28/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/24/2016 04/28/2016 IP 71124.04 Occupational Dose Assessment ISI - U2 INSERVICE INSPECTION 1 2 04/25/2016 04/29/2016 IP 7111108G Inservice Inspection Activities - BWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure