U.
S.
NUCLEAR REGULATORY COMMISSION
REGION V
Report No.
Docket No.
License No.
Licensee:
50-397/87-07 50-397 NPF-21 Washington Public Power Supply System P.
0.
Box 968 Richland, Washington 99352 Facility Name:
Washington Nuclear Project No.
2 (WNP-2)
Meeting at:
WNP-2 Site near Richland, Washington Meeting Conducted:
Ma ch 20, 1987 Prepared by: M/
~ R. T./)odds, Senior Resident Inspector
/'pproved by:
'.
~
.m~l;.
P.
John's n, Chief Reactor,j'rojects Section
~Summar:
Date Signed 3/+7
$ 7 Date S gned A Management Meeting was held on March 20, 1987 to discuss the following topics:
1.
Review of Recent Operating Events/Performance Indicators 2.
Status of SALP Improvement Program 3.
Status of Corrective Actions in Response to the August 29, 1986 Enforcement Conference 4.-
Issues of Current NRC Interest Root Cause Assessment Procedure Compliance/Attention to Detail Control Room Annunciators Timeliness of Cycle 3 Reload Submittal to NRR 8704130169 870327 PDR ADOCK 05000397 G
DETAILS 1.
Mana ement Meetin Partici ants NRC Partici ants J.
B.
A.
E.
R.
T.
P.
H.
J.
0.
C. J.
Martin,'Regional Administrator Chaffee, Deputy Division Director Dodds, Senior Resident Inspector Johnson, Chief, Reactor Projects Section
Bradfute, Project Manager, NRR Bosted, Resident Inspector WPPSS Partici ants D.
W. Mazur, Managing Director J.
W.
Shannon, Deputy Managing Director R.
B. Glasscock, Director, Licensing and Assurance J.
P.
Burn, Director, Engineering C.
M. Powers, Plant Manager J.
W. Baker, Assistant Plant Manager R.
L. Corcoran, Operations Manager S.
L; McKay,'ssistant Operations Manager J.
D.
Harmon, Assistant Maintenance Manager M.
R. Wuestefeld, Reactor Systems Supervisor J.
T. Little, Planning/Scheduling Supervisor G.
D.
Bouchey, Support Services Manager C.
H.
McGilton, Operations Assurance Programs Manager M.
C. Bartlett, Plant equality Assurance Supervisor P.
L. Powell, Manager, WNP-2 Licensing Bonneville Power Administration W.
A.
Milbrot, Nuclear Engineer A. J.
Repacz, Nuclear Engineer 2.
Mana ement Meetin On March 20, 1987, a management meeting was held at the WNP-2 Plant site near Richland, Washington, with the individuals identified in paragraph
in attendance'.
The purpose of the meeting was to review items of mutual interest involving operation of the WNP-2 facility.
The meeting convened at 8:00 a.m.
After introductory remarks, Supply System representatives made presentations on the following subjects:
Performance Indicators/Review of Recent Operating Events Status of SALP Improvement Program
Update on Actions in Response to the August 28, 1986 Enforcement Conference Selected slides from the licensee's presentations are enclosed with this report.
During and following the licensee's presentations, NRC representatives commented on issues of cur rent NRC interest, including the following:
Root cause assessment Procedure compliance/attention to detail Control room annunciators Timeliness of the Cycle 3 reload licensing submittal Mr. Martin acknowledged the general satisfactory appearance of the plant and supporting operations and improvements observed in recent months.
He emphasized to the Supply System the need to be their own worst critic, particularly during event critiques.
He noted that formal procedures are needed that are clearly understood by those performing event assessments, and stated that what distinguishes superior performers from average performers is the thoroughness of their root cause analysis during post-trip reviews and nonconformance report/plant deficiency report (NCR/PDR) evaluations.
He stated that plant management should also continue to work at the reduction of deficient and unnecessary control room annunciators.
He observed that recent events show a need for management to emphasize procedural compliance for all levels of work.
Some of these recent events also indicate that valve control during short shutdowns needs additional attention.
In closing, Mr. Martin again emphasized the need to maintain a
self-critical attitude and active management involvement, and questioned whether the equality Assurance (gA) organization was being well used by management in aggressively evaluating the effectiveness of licensee programs and performance.
Mr. Mazur expressed confidence that the gA organization was being effectively utilized, and stated that this would be further assessed.
He also acknowledged other comments expressed by NRC representatives during the meeting and stated that the Supply System's goal is to do its job in a professional manner.
The meeting adjourned at 12: 10 p.m.
Enclosure:
Selected slides from the licensee's presentations
ENCLOSURE SELECTED SLIDES FROM LICENSEE'S PRESENTATIONS
MANAGEMENT CONFERENCE MARCH 20, 1987 - 8:00 A.M.
GSB CONFERENCE ROOM-AGENDA 10 Minutes 1)
Opening Remarks:
-J.
B. Martin, NRC Region V Administrator-D.
W. Mazur, Supply System Managing Director 45 Minutes 2)
Performance Indicators/
Review of Recent Operating Events J.
W. Baker/
M. R.. Wuestefeld 60 Minutes 3)
Status of SALP Improvement Program C.
M. Powers/
G.
D. Bouchey 45 Minutes 4)
Enforcement Conference Update C.
M. Powers/
C.
H. McGilton 30 Minutes 5)
Issues of Current NRC Interest:
-Procedural'ompliance/Attention to Detail-Control Room Annunciators-Timeliness of Cycle 3 Reload Submittal-Limitorque Valve Program J.
W. Baker, J.
W. Baker P.
L. Powell C.
M. Powers 15 Minutes 6)
Other Topics of Interest:
-INPO Evaluation Update J.
W. Baker 7)
Closing Remarks
,
PERFORMANCE INDICATORS o
Corporate Goals quarterly Report Card o
quarterly Departmental Reviews
- Assigned performance indicators o
Monthly Performance Indicator Report
V SIGNIFICANT EVENTS PERSPECTI VE o
SIGNIFICANT EVENT EXAMPLES o
HCR/PDR o
LER o
HPES Reports o
SIGNIFICANT EVEHT CATEGORIES o
Personnel Error o
Design Deficiency o
Equipment Fai lure o
Procedure Deficiency o
RESOLUTI ONS o
Short Tens o
Long Tens o
COHCLUSIOHS
RESOLUTIONS Short Term o
NCR/PDR proce'ss requires Plant Manager's review on all personnel error XCRs.
o Human Performance Evaluation System (HPES)
adopted at NP-2 and supported by a dedicated resource within XSAG.
o Assessment Program used to evaluate program effectiveness (NSAG).
o Management attention to personnel errors consistently focuses on progranmatic solutions to resolve.
o NCR/PDR procedure revised to strengthen Plant Procedures review.
o Scram Evaluation procedure requires Plant Procedures, review for root cause asses@sent.
o PN process revised to require cognizant departmental review for applicable procedures.
L~on Term o
Root Cause Analysis training included in the operator license requalification and SE/STA requalification training.
Plans for Plant personnel responsible for NCR/PDR processing to be trained to further improve event documentation and evaluatio ~ton Term (continued)
o Principle problem identification documents (NCR/PDR, SR and HPES reports),wi11 be categorized for potential generic and programnatic weaknesses.
o Compliance Group will use an SRO (currently a candidate) for NCR/PDR overview function.
o All unplanned RPS actuations will-be documented on a NCR.
o Continued involvement in the BMROG-SFRC Subcomnittee.
o
.
Improvement of PTL for conrritment tracking.
o Continued Plant Management Departmental Reviews.
CONCLUSIONS o
Management involvement.
o Sufficient process controls.
o Problems are being identified.
o Problems identified are solved.
o Solutions indicative of refinements to existing processes.
o Management caani tted to refining our processe SALP IMPROVEMENT PROGRAM o
SALP Report Review to Identify Issues o
Specific Action Plan Developed on Each Issue o
Status Update with Resident Inspector o
Action Plan Details for 11 Functional Areas:
o Operations o
Maintenance o
Surveillances o
Outage Performance o
Radiological Controls o
Fire Protection o
.Security and Safeguards o
equality Assurance and Administrative Con-trols o
Licensing Activities o
Training
ENFORCEMENT CONFERENCE UPDATE 1;
Enforcement Conference Issues o
Management Involvement in Activities o
Housekeeping Performance o
Fire Protection Control of Transient Combustibles o
Responsiveness to Identified Deficiencies o
guality Control Program for Corrective Maintenance Activities 2.
Actions Taken/Results Achieved o
Management Involvement:
Corporate Goals and Objec.tives established; Director-ate Reviews focused on performance conducted; and Corporate visibility/involvement in Plant activities increased.
Department Reviews on overall performance conducted; future Department Reviews focused on backlogs sched-uled.
Maintenance Department realigned to increase supervi-sion on work control functions.
Positiv'e feedback on effectiveness from guality As-surance and Nuclear, Safety Assurance Group.
Observation Program in-place with positive result ENFORCEMENT CONFERENCE UPDATE 2.
Actions Taken/Results Achieved (continued)
o Housekeeping:
Plant material condition has improved.
Area Coordinators who conduct weekly inspections in-place.
Shop discussions on expectations conducted; positive respohse from Staff.
Monthly inspections by Plant Management in-place.
Region V
Plant tours to Palo Verde, Diablo Canyon, and Trojan conducted.
Corporate management tours conducted.
o Fire Protection Transient Combustible Control:
- Reevaluation of program requirements completed; pro-cedural changes in-place.
- Shop;meetings to discuss expectations held.
Biweekly inspections by Fire Protection Engineers on-going; increased sensitivity to respond.
~
4 'IJ
ENFORCEMENT CONFERENCE UPDATE 2.
Actions Taken/Results Achieved (continued)
o M8TE and Tool Control:
Tool Crib now staffed 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />s/day.
Computerized control program in-place.
Administrative changes in-place.
Activities under single supervision.
Verification.- of M8TE inventory complete.
Compli'ance with program has exceeded expectations.
o Responsiveness to Identified Deficiencies:
Plant Quality Assurance organization has taken stronger position on adequacy and timeliness Plant Staff focusi ng more'ttention on defi cienci es; Multi-organizational responses are coordinated through Plant Manager's Office; Periodic status of deficiency responses conducted at Plant Manager's Staff Meetings; and Quarterly Quality Trend Reports indicate improved responsivenes QUALIT A
A CE P
G A I PROVE ENTS E
ORDNANCE FEEDBAC
ENHANCE QA SURVEILLANCE PROGRAM TO INCLUDE ROUTINE OBSERVATION OF MAINTENANCE WORK ACTIVITIES WITH IMMEDIATE FEEDBACK TO PERFORMERS AND SUPERVISION.
IMPLEMENT A MONITORING PROGRAM OF PLANT INITIATIVES AND IMPROVEMENT PROGRAMS TO PROVIDE DIRECT FEEDBACK TO PLANT MANAGEMENT ON EFFECTIVENESS.
PLANT OVERVIEW PLANT MANAGEMENT~
PROGRAM ~
IMPLEMENTATION ~
GOALS INITIATIVE QUALITY ASSURANCE PERFORMANCE HONITORING
WNP-2 PLANT QA EXISTING PROGRAM CONSISTS OF:
A PROGRAM OF PLANNED'ERIODIC'EVIEWS TO VERIFY AND ASSESS COMPLIANCE TO PROCEDURES AND PROVIDE FEEDBACK TO PLANT MANAGEMENT.
REVIEWS OF VARIOUS QUALITY DOCUMENTS INCLUDING PROCEDURES FOR INCLUSION OF BASE REGULATORY REQUIREMENTS AND LICENSING COMMITMENT WiNP-2 PLAt<T QA EXISTING PROGRAil CONSISTS OF:
A PROGRAM OF HARDWARf INSPECTIONS TO VERIFY COMPLIANCE TO INSTALLATION PROCEDURES AND DESIGN REQUIREMENTS.
OETAILfD INSPECTION PLANS FOR MODIFICATION ACTIYITIES ARE FORrlALLY-ESTABLISHED fQUIVER LENT TO CONSTRUCTION.
CORRECTXYE MAINTENANCE INSPECTIONS Ai.E RANDOM WITH LEVEL OF INSPECTION BASED OiN QUALXTATIVE ATTRIBUTfS.
u Rf VIEWS OF WORK DOCUMENTS TO DETERMINE QC INVOLVfMENT AND PLAN INSPECTION ACTIVITIES~
QUALITY ASSURANCE PROGRAM IMPROVEMENTS PLANT RESPONSIVENESS TO QA/QC CONCERNS:
REFORMAT MONTHLY REPORT TO HI-LITE QA/QC CONCERNS AND PROVIDE FOLLOWUP STATUS OF PREVIOUS CONCERNS TO PLANT i'lAi4AGEMEi'4T AND LICENSING>> ASSURANCE MAi4AGEMENT.
(9-15-do)
INCREASE i ICENSING AND ASSURANCE MANAGEMENT INVOLVEMENT IN DAILY HilP-2 PLANT QA ACTIVITIES.
(9-1-8o)
IMPROVE CO,'lMUi4.[CATIOl4S,BETWEEN PLANT 4N AND PLANT MANAGEMEi4T R" GARDING QA S JRVEILLANCE DEFICIENCIES ~
(9-lb-Uo)
QUALITY CONTROL PROGRAi'I Ii<PROVENENTS OEVEl OP A BASELINE Ci'1 INSPECTION PROGRAM FOR CRITICAL PLANT COMPONENTS
~
( 11-15-86)
REFINE INSPECTION ATTRIBUTES APPI.IED TO CORRECTIVE MAINTENANCE~
(2 YEAR PHASE-IN STARTING 2-1-87)
~
DEVELOP A SAMPLING INSPECTION PROGRAM FOR OTHER THAN CRITICAL COMPONENTS.
(FINALI7E BY 9"15 87)
PROVIDE INTERIM BASELIiVE INSPECTION AND ATTRIBUTES FOR CORRECTI'AINTENANCE.
( J-1-86)
~
ENHANCE EXISTING QUALITY CONTROL INSP ECTION PROGRAM FOR I'1PORTA(
PREVENTIVE MAINTENANCE.
("f-1-87)
C
~
IMPROVE EFFICIENCY ArJD EFFECTIVENESS OF THE QUALITY CONTROL GROUP BY SEPARATING INSPECTION PLANiNING AND MONITORING FROM INSPECTION PERFORMANCE.
(12-1-Qo)
PROCEDURAL COMPLIANCE o
Define What Procedural Commpliance is:
o Tour of Other Region V Plants; o
Discussions with NRC; o
Discussions with INPO; and o
SONGS Management Expectation Letter.
o Principle Elements:
o Are procedures usable and accurate?
o Do people know.how/when to use them?
o Are people using them?
o Are we close?
o Yes, at a program level.
o Yes, at a root cause evaluation level.
o Need to continually reemphasis at implementation level.
II
CONTROL ROON ANNUNCIATORS o
Is there a program?
Yes.
o Weekly Status (operator knowledge acceptable)
o Categorize Type o
Has there been improvement?
Yes.
o Prior to RF86A:
139 o
Currently:
o After RF87A:
Less than
o Could we do better?
Yes.
o Be more willing to work at power; o
Assign unique responsibility; o
Increase priority/provide additional resources; and o
Establish management's expectation for each categor RELOAD APPLICATION RELOAD SUBMITTAL TO t/RR (Late - due to fuel consumption rate changes
- SLO)
APRIL j., 5937 OUTAGE COMMENC E S APRIL.13, i.987 OUTAGE ENDS JUNE 3, 3987 ELAPSED TIME FOR l~ RR REVI EW AND APPROVALS
DAYS HRR PREFERS A MINIMUM OF 90 DAYS OTHER POTENTIAL IMPACTS INCLUDE!
O NRR REORGANIZATION EFFECTIVE APRIL "2y -"987
NRR OFFICE RELOCATION APPROXIMATELY STARTING IN JUNE 19S7
ABILITY OF ERR PROJECT NANAGER TO FOCUS STAFF S
ENERGIES ON THIS AS WELL AS 4'UMEROUS TECH SPEC, CHANGES REQUIRED TO BE APPROVED PRIOR TO STARTUPs
ACTIONS DESIRED BEFORE OUTAGE ( f/13/87)
SUBMITTED DAYS IN REVIEW 1:!ITH HRR
.1, FusEs 2s BRC TYPE TESTING SRV TOLERANCES SNUBBERS 5,
t)202 ANALYZER 6/13/85 1/31/86 7/10/86 12/12/86 3/14/86 669 437 277 122 395
LON PPESSURE TURBINE INSPECTION SCHEDULE 11/20/86 ACTIONS REQUIRED ~10ff. TO STARTUP (ASSUMING JUNE 3g 1987)
RELOAD SUBMITTAL
~4/1/87
2s
~'! IDE PLUNGE I,EUTRON f<ONITOR (ADD TO TECH SPECS s )
3 s STANDBY LIQUI D CONTROL 4,
TIP 11/18/86 1/6/o7 11/18/S6 197 197 5s SUPPRESSION POOL LEVEL NONITOR (DEFER TO P.-3)
3/12/87 6a
!'. I DE RANGE HEUTRON f ION ITOR (DEFER TO R-3)
3/10/87
L IMITORQUE VALVE PROGRAM o
WNP-2 has 147 safety-related Limitorque Motor Operated Valves (MOVs)
o We incorporated known industry problems with Limitorque's in our qualification program o
Our response to IE Notice 86-03 developed a detailed inspection program conducted during RF86A (April 1986)
o Minor discrepancies were corrected with engineered resolutions; results documented in LER 86-019 o
At the present time, all Limitorque issues resolved on all safety-related valves o
We are extending inspection program for remainder of Limitorque valves at WNP-2 (non-safety related)
o Our response to IE Bulletin 85-03 provides for:
MOVATS testing of specified valves within a two (2)
year schedule Long-term program directed at performance monitoring of safety-related valves Our program examined by Region with favorable feed-back