IR 05000397/1986038

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/86-38 on 861124-26 & 1215-19.No Violations Noted.Major Areas Inspected:Gaseous Waste Sys,Liquids & Liquid Wastes,Facilities & Equipment,Followup on IE Info Notices & Enforcement Items
ML20212J257
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/07/1987
From: Cillis M, Russell J, Yuhas G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20212J195 List:
References
50-397-86-38, IEIN-86-022, IEIN-86-023, IEIN-86-042, IEIN-86-043, IEIN-86-046, IEIN-86-086, IEIN-86-22, IEIN-86-23, IEIN-86-42, IEIN-86-43, IEIN-86-46, IEIN-86-86, NUDOCS 8701280119
Download: ML20212J257 (13)


Text

,

-

..

.

U. S. NUCLEAR REGULATORY COMMISSION

-

REGION V

-

,

,

Report No. 50-397/86-38-DocketNo.'b0-397 License No. NPF-21 Licensee:' Washington Public Power Supp'ly System P. O. Box 968 Richland,' Washington 99352'

.

>

Facility Name: Washington. Nuclear Project No. 2 (WNP-2)

Inspection at: WNP-2 Site, Benton County, Washington Inspection Conducted:

November, 4-26 and December 15-19, 1986 Inspectors:

.

m i

/. p-P)

M. p is, 5(nio R~adiation Specialist Date Signed

'

m

/ 7-17

.

J )krssell, Radiation ~ Specialist, C.H.P.

Date Signed

L_

-

Ov/ F/

G. Y@asT Chief D6th Signed Faci 1Riks Radiological Protection Section Approved By: [

kSw

\\/ 7/97 bT

)'. Vuh4s', Chief Fal.e~ Signed Facili%.'g) Radiological Protection Section Summary:

Inspection on November 24-26 and December 15-19, 1986 (Report No. 50-397/86-38)

Areas Inspected:

Routine unannounced inspection by regionally based inspectors of the licensee's gaseous waste systems, liquids and liquid wastes;

-facilities and equipment; including followup on IE Information Notices, enforcement items, Licensee Event Reports, and open items; and several tours of the licensee's facility.

Inspection modules 30703, 83724, 83726, 83727,

'84723, 84724, 92700, 92701, 92702, 92703, and 93702 were performed.

Results:

In the eight areas inspected, no violations or deviations were identified.

$h0b0$g, PDR t

-

'

..

.

'

t

.

DETAILS

-"

,

F 1)

Persons Contacted T

a)

WNP-2 Staff

-

+ C. Powers, Plant Manager

'

.

  • J. Baker, Assistant Plant Madager

+*R. Graybeal, Health Physics / Chemistry Manager

+*D. Larson, Manager of Radiological Programs and. Instrument Calibration

'

.-

"

-

+*L. Bradford, Health Physics Supervisor

,,

+ L. Morrison, Chemistry Supervisor

'

V. Shockley, Health Physics / Radiochemistry Support x

+*E. R. Ray, I&C Supervisor D. Bainard, Principal Engineer

-

+*D. Feldman, Plant QA Manager '

  • J. M. Graziani, Nuclear Safety Assurance Engineer

S. Lentho, Principal Engineer

,

  • J. Arbuckle, Performance Engineer M. Kippes, Principal Engineer

_

W. Holzendorf, Supervisor, Maintenance Services c

  • C. Van Hoff, Senior State Liaison T. Houchins, Audits Manager

+ A. David, Radiochemist

+ D. Bouchey, Support Services Manager

,

b)

U. S. Nuclear Regulatory Commission (NRC)

,

+*R. C. Barr, Resident Inspector

'

R. Dodds, Senior Resident Inspector c)

State of Washington, Energy Facilities Site Evaluation Council

\\*

+*R. Bidstrip, Health Physicist

  • Denotes those present at the exit interview on November 26, 1986.

+ Denotes those present at the exit interview on December 19, 1986.

In addition, the inspectors met with other memb'ers of the licensee's staff.

'

,

.

2)

Open Item Tracking System An attempt was made to use the licensee's open item and commitment tracking system to review the status of open items identified in paragraph 3, herein.

The inspectors were not able to effectively use the licensee's computer tracking system because the information in the systems was not current,

,

.

.

-

-

- -

-

-

__

-

'

t

.

u

,

,

)

a

"

.some. items could not be traced and the categories of trackable items-in the system were limited.

c t

The above observations were discussed ~with-the licensee's staff and at the exit' interview. -The staff informed the' inspectors that an evaluation of the system,was currently in progress.

'

No violations or deviations were identified.

'

3)

FollowupofNiscellaneousItemsl Thestatus.ofNRCenforcementitehs,licenseeevaluationsofNRC Information Notices (ins) and Generic Letters, Licensee Event Reports, and inspector identified items was examined.

The examination disclosed the following:

,

,

'

A)

Enforcement Itcms 1) a(Closed) Enforcement Items 50-397/86-23-02: An examination was conducted and discussions were held with the, Supervisor of Maintenance Services to verify licensee corrective actions described in their timely response, dated August 20, 1986, for controlling, vacuum cleaners.

The examination also included a tour of the licensee's controlled tool crib and discussions with a' tool crib attendant.

Inspection report 50-397/86-23 identified that vacuum cleaners used for radiation protection purposes were not being maintained and controlled in accordance with licensee procedure PPM 10.1.20,. Vacuum Cleaner Control.

The licensee's corrective actions included:

Revision of PPM 10.1.20

Designation and tagging of vacuum cleaners as either wet or dry type Issue of vacuum cleaners from WNP-2 tool crib as controlled tools by trained personnel.

Instruction of all maintenance group and contractor personnel in the revised PPM 10.1.20.

During the tour of the tool crib, the inspectors noted that vacuum cleaners, numbers 16 and 17, were not appropriately tagged and that the tool crib attendant's knowledge of PPM 10.1.20 was marginal.

The above observations were brought to the attention of the Supervisor of Maintenance Services who took immediate action to tag the two vacuum cleaners.

The supervisor stated that the two vacuum cleaners had recently been returned to the tool crib from the decontamination facility.

He added that the units

.

~3

.

were wrapped in polyethylene bags while the other cleaners were-being tagged.

The supervisor added that t.ool crib attendants will_ba reinstructed in PPM'10.1.20 and that the additional training'of the staff would be documented.

The above observations were discussed at the exit interview.

The inspector stated that this item was closed in view of the immediate action taken by the Supervisor'of Maintenance Services (86-23-02).

2)

(Close'd) Enforcement Items 50-397/86-28-01, 50-397/86-28-02 and 50-397/86-28-03.

A similar examination was' conducted to verify corrective actions identified in the licensee's timely response, dated November 18, 1986, for controlling radiation and high radiation areas and for assuring appropriate surveys are :ade in accordance with the regulatory requirements prescribed in'10 CFR Part 20.201(b).

The examination, tours (see paragraph 4), discussions with the licensee's staff and a review of the proposed revision to licensee procedure PFM 11.2.24.1, Health Physics Work Routines, disclosed that licensee practices for controlling and maintaining such areas were consistent with the regulatory requirements prescribed in 10 CFR Parts 20.201, 10 CFR Part 20.203 and the Technical Specifications (TS), Section 6.12, High Radiation Areas.

The corrective actions for assuring compliance with the above requirements include:

~

More frequent plant _ tours and reviews of work areas by Health Physics Management, Foreman, and Technicians. The

'

results of Health Physics tours are documented and reviewed by Health Physics Management.

A change to PPM 11.2.24.1 specifying a requirement to survey and to check all occupied areas.

~

This matter is closed (86-28-01, 86-28-02 and 86-28-03).

3) -(Closed) Enforcement item 50-397/86-28-04.

This examination included verification of corrective actions prescribed in the same response as that to (1) and (2) above, for assuring that area, portable and airborne radiation monitoring equipment is

- properly controlled, calibrated and adjusted at specified periods to maintain its accuracy as required by Regulatory Guide 1.33 pursuant to TS, Section 6.8.1.

The corrective actions described in the licensee's response were discussed with the I&C Supervisor and Health Physics / Chemistry Manager.

Corrective actions included:

!

.

9-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ -. _

.

.

Health Physics personnel have assumed the responsibility via the licensee's Scheduled Maintenance System (SMS)

Tracking Program, to assure that such equipment'is either within current calibration or removed from service prior to'the' calibration due date.

Health Physics personnel have been instructed to tag instruments _"out of service" until they can.be removed.

. Health Physics personnel verified that the SMS and

'

Material' Equipment List (MEL) for health physics equipment were current.

Responsibility for input of the SMS and MEL data into the licensee's accountability system for health physics equipment has been assumed solely by the Health Physics staff.

The I&C-supervisor informed the inspectors that he was still in

'

the process of reviewing Inspection Report 50-397/86-28 and the

_

Quality Assurance report referenced in the inspection report to verify that corrective actions for preventing a recurrence of this ~' item are ' adequate. This matter is closed (86-28-04).

B)

' Inspector Identified Open Items 1)

,(Closed) Open Items 50-397/86-14-03 and 50-397/86-14-04.

These items were associated with the spread of contamination from the 606' level refueling cavity to the 572', 548', 522', 501' and

.

~471' levels of the reactor building.

The cause for the spread of contamination was investigated by the licensee's radiation protection staff pursuant to procedures HPD 3.1.19 and PPM

,

11.2.19.1.

An examination of the licensee's investigation disclosed that the problem was'two fold.

A health physics technician allowed maintenance workers to use a dust broom to clean highly contaminated surfaces in the refueling cavity and this was complicated by an inbalanced reactor building ventilation system.

The licensee's staff was not aware of the inbalanced ventilation Fyrtem.

t Corrective actions taken by the licensee's staff included:

Health physics personnel were instructed that dust brooms (foxtails) should not be used in high contamination areas.

The ventilation system was properly balanced and steps were taken to assure balancing is maintained by performing

'

checks prior to future refuelings.

  • Steps were being taken to assure that HEPA vacuums are made available during work evolutions.

L i

-

_

-

.

5

,

.

i

f The licensee's evaluation of this matter was documented on radiological occurrence report number 2-86-18, dated October 18, 1986.

This matter is closed (86-14-03 and 86-14-04).

2)

(0 pen) Open Item 50-397/86-14-06.

Inspection Report

50-397/86-14 identified that loose surface contamination was

spread via the equipment hatchway located between the 437' and

467' level of the Radwaste Building.

The spread occurred after

a recirculation pump was transferred into the decontamination

room via the equipment hatchway.

The cause for the spread was attributed to a poor seal (i.e.

tape) used to cover the gap in the hatchway joint.

The licensee's investigation concluded that the tape sealed

poly cover installed over the hatchway had been poorly

installed.

The inspectors were informed that the door had been

resealed and covered with herculite.

The licensee's staff

added that an evaluation is still underway to develop a

permanent seal for the equipment hatchway.

The inspectors

informed the licensee that this item would be examined during a

subsequent inspection (86-14-06).

?)

(Closed) Open Item 84-CS-08.

This item was related to a

potential ALARA problem with the routing of SP-1, Reactor

Coolant Sample (RCS) line, through non-radiation zones from the

501' level of the Reactor Building to a sample room on the 441'

level of the Turbine Building.

This item was brought to the

licensee's attention through the NRC's preoperational

inspection program.

From discussions held with the licensee's staff and by

personnel observations, the inspectors verified that the SP-1

sample line had-been rerouted to the sample room located on the

467' level of the Radwaste Building, thereby eliminating the

problem.

This matter is closed (84-CS-08).

4)

(Closed) Open Item 84-CS-09.

Technical Specifications, Section 4.11.1.1.1, requires that monthly and quarterly composite

samples of liquid releases be retained for analysis.

Open item

84-CS-09 identified that composite samples were missed on some

occasions.

The licensee's corrective actions for assuring that their

composite sampling program is consistent with the Technical

Specifications'was examined.

Discussions with the Chemistry

Supervisor disclosed that procedure PPM 7.4.11.1.1.1,

Determination of Radioactivity in Radioactive Liquid Waste, was

revised.

The revision provides for retaining separate monthly

and quarterly samples.

Previously, only one sample was taken

and then split for the required composite sample.

The split

was not made on several occasions.

-

__

t

.

The inspector concluded that the change to PPM 7.4.11.1.1.1 was

adequate. This item is closed (84-CS-09).

5)

(Closed) Open Item 84-GY-01. WNP-2 letter to the NRC, SN

G02-83-1152, dated December 13, 1983, identified that sealants

(RTV silicone) would be used to complete the operational

testing of a Standby Gas Treatment system charcoal filter bed.

The letter stated that the reason for using the sealants was to

. fill the gaps created by welding the units perforated plates

used to contain the activated charcoal bed..The licensee's

report stated that the wolding had warped the plates.

Subsequent discussions with the NRC disclosed that the sealants

used were not as recommended in ANSI N509, Nuclear Power Plant

Air Cleaning Units, and< ANSI N510, Testing of Air Cleaning

Units.

Discussions held with the license.'s staff and a review o'f

l_icensee records revealed that the RTV sealant was removed, the

warped plates were repaired and the system was successfully

tested in accordance with ANSI N510.

This matter is closed

.(84-GY-01).

6)

(Closed) Open Item 50-397/86-14-05.

This item concerned the

health physics controls established for inspecting the "B"

recirculation pump during the recent refueling outage.

The licensee: performed a ' detailed evaluation of the health

physi.cs practices that'were implemented during the work.

The

evaluation, documented ~on WNP-2 interoffice memorandum dated

November 6, 1986, and Radiological Occurrence report, serial

number Z-86-023, was reviewed by the inspector.

,

The inspector concluded that the licensee's evaluation was

thorough and had addressed the concerns discussed in the

inspection report.

The licensee's corrective actions planned

for similar work appeared to be adequate.

This matter is

closed (86-14-05).

7)

(Closed) Open Item 85-CS-02.

An examination was conducted to

determine if the estimated error associated with the-

measurement of radioactive materials in effluents as determined

by the licensee was consistent with Regulatory Guide 1.21,

Measuring, Evaluating...in Liquid and Gaseous

Effluents from Light-Water-Cooled Nuclear Power Plants,

Paragraph C.11.(a).

Discussions with the Radiochemist and a review of a WNP-2

l

memorandum dated December 22, 1986, disclosed that the

licensee's error determinations are consistent with R.G. 1.21.

The licensee uses a two-sigma counting error in lieu of the

one-sigma recommended by R.G. 1.21.

This matter is closed

-

(85-CS-02).

-

3 -..

'

.

,

C)

' Licensee Event Report (LER)

~

(Closed) LER 85-58 (85-58-LO), dated' November 13, 1985, describes an

event in which the Standby Gas Treatment (SGT) Fan 182 stopped with

no annunciation in the control room and the backup fan failed to

start. This resulted in an uncontrolled release of primary

containment atmosphere to the secondary containment and,

subsequently, to the environment without treatment as required by

Technical Specifications.

Immediate corrective actions were taken to terminate the purge,

restart SGT-FN-182, and align the secondary containment purge.

Health physics personnel were contacted to perform surveys to

determine the extent of any possible releases. No abnormal levels

were encountered.

An investigation was conducted by the licensee's

engineering staff including troubleshooting of the systems control

circuitry.

A review of the LER, discus:, ions with the staff, a review of plant

Deficiency Report /Nonconformance Report (NCR 286-0348) dated August

15, 1986, and Maintenance Work Requests (MWR's) related to this

subject, identified.that the system relays were not wired per

drawing E-545, Sheet #3.

The engineering staff stated that this

would not have prevented the lead SGT fan from starting due to a

fail safe Z signal or manual start. -The engineers added that this

condition would not have prevented the lag SGT fan from sta'rting

after a fail safe Z signal condition and a lead fan failure.

The relay was subsequently wired in accordance with drawing E-545.

No repeat of the problem identified in the LER has occurred since

the relay was rewired.

This matter is closed (85-58-LO).

D)

Information Notices

Region V Inspection Report 50-397/86-10, paragraph 4, identifies the

-licens'ee's program for handling Information Notices (ins).

The

inspection report also identified that' improvements in timely IN

,

evaluation were'needed.

The inspectors determined the status of IN 86-22, 86-23, 86-42,

86-43, 86-46 and 86-86.

Licensee evaluations.of ins 86-22 and 86-86 were determined to be

consistent with the recommendations identified in the respective IN.

Licensee evaluations of the remaining ins were incomplete.

The

<

evaluation of IN 86-42 had not started even though it had been-

received by the licensee in June 1986.

Only partial evaluations of

IN 86-23, 86-43 and 86-46 have been completed even though the

licensee's Operating Experience Review (0ER) system had assigned an

evaluation completion date of November 21, 1986.

The licensee's Nuclear Safety Assurance Group (NSAG) engineer

responsible for assigning ins to the staff for evaluation informed

.

'

the inspectors that he intended to complete the evaluation of these

ins but had not had sufficient time to do so.

Further discussions with the NSAG engineer revealed that procedure

1.10.4, External Operating Experience Review, was being revised to

include provisions for assuring that evaluations of ins are more

timely.

The inspectors brought the above observations to the licensee's

attention at the exit interview.

The concern identified in

Inspection Report 50-397/86-10 for more timely evaluations of ins

was reiterated.

IN 86-22 and 86-86 are closed.

IN 86-23, 86-42,

86-43 and 86-46 are open.

E)

Generic Letters

(Closed) 85-08-R1 (Generic Letter 85-08, Revision 1).

Discussions

held with the Manager of Radiological Programs disclosed that the

licensee plans to implement the recommendations of Generic Letter 85-08, Rev. 1.

Implementation is expected to be complete by March

1, 1987.

This matter is closed (85-08-R1).

4)

Facility Tour

Several tours of the licensee's facilities were conducted by the NRC

inspectors =during the inspection period.

Independent radiation

measurements were performed by the inspectors with an Eberline, Model

R0-2 ion chamber survey ' meter, Serial No. 2694, due for calibration on

January 16, 1987.

The following observations were made:

A)'

The licensee's posting and labeling practices were consistent with

10 CFR Part 20.203, Caution Signs, Labels, Signals and Controls, and

10 CFR Part-19.11,' Posting of Notices to Workers.

Current copies

(i.e. 1985) of Form NRC-3 were provided to the licensee's staff to

replace the 1984 editions that were observed during the tour.

B)

A general improvement in housekeeping was noted in the areas toured.

C)

Observed radiation protection practices appeared to be consistent

with ALARA as defined in 10 CFR Part 20.1(c), Purpose.

D)

The inspcctors noted several Nuclear Measurement Corporation (NMC)

constant air monitors, located in the reactor building, did not

display any calibration labels.

The NMC units are routinely calibrated in accordance with licensee

procedures PPM 12.13.20, In Plant Air Particulate Monitor

Calibration and PPM 12.13.21, Calibration of Iodine Monitor NMC-54M.

A review of the procedures disclosed instructions are provided for

performing electronic and isotopic calibrations but no instructions

are included for calibrating the units flow rate measurement device

as recommended by Regulatory Guide 8.25, Calibration and Error

.

'

.

,

.

Limits of Air Sampling Instruments for Total Volume of Air Sampled.

The.I&C supervisor informed the inspectors that the flow rate

measurement devices are' calibrated by his staff at the same time the

isotopic calibration is performed.

The I&C supervisor stated that

procedures would be developed to include requirements for assuring

the flow rate measurement devices are calibrated.

The above observations were brought to the licensee's attention at

the exit interview.

The inspectors informed the licensee that this

item would be examined during a subsequent inspection (86-38-01).

E)

Excluding item 0 above, all other portable instruments used for air

sampling and radiation detection were in current calibration.

F)

The inspectors noted numerous process and effluent monitor racks had

no valve labels and some, whose valves had been labeled, from which

the labels had fallen.

Discussions with the licensee staff revealed

that a program to tag / label panels and instruments in the plant had

been instituted several years previously and that this program had

not yet been completed.

The inspectors noted to the staff that more

aggressive pursuit of this program's completion could eliminate the

,

potential for problems due to valve misalignments.

This observation was brought to licensee management attention at the

exit interview.

The inspectors informed the licensee that this item

would be examined during a subsequent inspection (86-38-02).

G)

During a tour of the Radwaste Building, the inspectors noted that

the building ventilation exhaust radiation monitor panel, WEA-SR-25,

had a low flow alarm.

The inspectors traced the sample lines and

found the cause to be an air leak in the particulate and iodine

sample cartridge. When the inspectors informed the licensee staff

of the problem, immediate action to replace and properly align the

cartridge eliminated the leak and the low flow alarm.

The licensee's staff informed the inspectors that there have

previously been leakage problems with the plant's particulate and

iodine sample cartridges, that the cartridges were very difficult to

remove and install and that the staff had, in previous years,

submitted a design change request on which no action had yet been

taken.

The inspectors noted that such problems can result in lost

or inaccurate sampling data from TS instrumentation.

This

observation was brought to the licensee's attention during the

inspection and at the exit interview.

The inspectors informed the

licensee that this item would be examined during a subsequent

inspection (86-38-03).

5)

Facilities and Equipment

A discussion was held with the Health Physics Support Supervisor to

determine whether any changes, additions or improvements of facilities

and equipment used for the radiation protection program were being

considered.

The supervisor informed the inspector that there were no

plans for adding to or modifying existing facilities.

The supervisor

-

p

-

-

.,

,

,

. -

3,

.

.

,

,

f*

loi

,'

_

,...

,

,

,

N

,y

a

j'

i

-,..

g

.,

^

c

said:some plans for improving the electro polisher decontamination system-

>

.

~-would be accomplished.

~

'

"

u-

,

'

"

=The supervisor.added that a freon decontamination unit and a_ waste b'ag

~

'

"

_

, monitoring system'had been approved for purchase and-that,an evaluation

of.available freon decontamination' units and of waste, bag monitoring

' systems Would'be accomplished before they are' purchased.

,

,

['

-

No. violations ~or deviations were-identified.

-

6)

. Liquids and Liquid Wastes

,

_

-A)

Audits' -

.

s-

.

.

Licensee audits. conducted in 1985 and'1986 pursuant to Technical

' '

-Specifications, Section 6.5.-2.8, Audits,-were. examined.

'

'

,

.

.

.

Audit report 85-327 addressed Technical Specification requirements

,

'

-,

.

'in the area ~of Radioactive Effluent Monitoring, Radiological.

'

M'

Environmental Monitoring Program and the Offsite Dose Calculation

'

Manual. The audit identified five deficiencies and seven concerns.

_

No Lviolations of theiregulatory requirements were identified.

All

'

'

deficiencies'and concerns were resolved in a timely manner.

,

'

^

/

Audit report 86-362 a'ddressed the licensee's Radiological Effluenti

Monitoring ~and the Radiological Environmental Monitoring Prog' ram.. A

<

' total of six deficiencies and twelve concerns were identified.

No

-

violations or deviations of the regulatory requirements.were

1 identifi.ed._ Approximately,90% of the deficiencies and concerns have

~

ebeen resolved.-

-"

. '

+

x '_,

a

,,

The inspector, concluded'th'at the audits were thorough and well-

'

,

.

Jdocumented. -

.

,

'

Novioiati

drdeviationswereidentified.

'

'

e

.

B).

Instrument 5 tion

'

.[,;

(,

F Rabioactivi fliquid effluent. monitoring instrumentation shown in ~.

'

Table 3.3.7.11-1.of,the Technical Specifications (TS) and in Table

e

11.'5-2'of the' Final Safety' Analysis Report (FSAR) was discussed with

~

'-

the Radiati.on Protec, tion and I&C staffs.

'

- e:

,

!

,-ThelinstrumentationidentifiedintheTSandFSARwasinspected

during the tour (see" paragraph 4) of the licensee!s facility.

t-

-

Additionally, related calibration records, surveillance procedures

and surveillance records for 1985 and 1986 were examined.

-

s

,

I

^

iThe examination disclosed that the channel checks, channel

calibrations,-source checks and channel functional, tests prescribed

in Table.4.3.7.11-1 of the TS were performed at the frequencies

"

-

specified.

.

%

L

!

-

<

s

b

'

,

,

..,c

v

"

.

E

The inspector also verified that the method for. process ~and effluent

monitor setpoint determinations was established in accordance with

g

~ the 0.ffsite Dose Calculation, Manual and plant procedures.

,

No' violations or deviations were' identified.

.C)

Reactor' Coolant System - Chemistry

Surveillance procedures, established for assuring the chemistry of

the reactor coolant is maintained within the limits specified in

Table 3.4.4-1 of the TS,.were reviewed.

Selected surveillance

records were also reviewed.

The' inspector verified that the reactor coolant chloride,

conductivity and pH levels for the period of 1985 through 1986 were

maintained within the TS limits.

No violations or deviations were identified.

D)

Reactor Coolant - Specific Activity

l

The inspector discussed TS, Section 3/4.4.5, with the Chemistry

Supervisor and examined surveillance procedures and records

,

associated with the. licensee's primary coolant specific activity

l

[

sampling and analysis program.

Measurements and analyses were performed for gross beta and gamma

activity, Dose Equivalent Iodine-131 concentration, E-Bar

determination', isotopic analyses for iodine and isotopic analyses of

~

off gas.

The values were within the limits specified in the TS and

i

licensee procedures.

No violations or deviations were identified.

7)

Gaseous Waste Systems

A)

Audits

See Paragraph 6. of this report.

B)

. Changes

The inspectors reviewed current gaseous waste processing and

sampling equipment and procedures for both normal and emergency use.

No equipment changes were identified.

Procedure changes identified

were evaluated as to their safety significance and~did not appear to

constitute unreviewed safety questions.

Changes appeared to be

appropriately documented and reviewed.

~

No violations or deviations were identified.

~ C)'

Effluents

.

-

-

- _ _ _ _ _ _ _ _ _ - - _ _ _ _ - _ _ _

-

_

>

I

'

^

'

-

_

The inspectors examined the monthly and quarterly gaseous waste.

release reports, off-site dose. calculations for 1986 and the January

,'

to June 1986 Semiannual Effluent Release Report.

The inspectors

also examined software input precedures, computer code validation

practices, and code data manipulations for the licensee's

- meteorological and gaseous effluent dose estimation codes,- X0QD0Q

and GASPAR, respectively.

Discussions with the licensee staff indicated a difference in

interpret 6 tion of the TS 3/4.11.1 limits from that held by the NRC.

The staff, when questioned, interpreted,these as cumulative dose

rate limits which could be summed over extended periods rather than

instantaneous limits.

An examination of licensee instrument

setpoints and procedures revealed no improper instrument settings

had resulted from this misinterpretation but control' room

procedures, specifically PPM 4.602.A5-3.5,'did not provide

sufficient information for the staff to determine what actions-and

reports were_necessary when a plant stack high radiation alarm

annunciated and the potential for exceeding the TS limits existed.

The inspectors brought the above observations to the licensee's

attention at the exit interview.

The inspectors informed the

licensee that this item would be examined during a subsequcnt

inspection (86-38-04).

D)

Instrumentation

Gaseous waste monitoring instrumentation identified in Table 4.11-2

of the TS and in Table 11.5-1 of the FSAR was discussed with the

licensee and inspected during the tour.

Calibration records,

setpoint determination procedures and records, and surveillance

procedures and records were examined.

The calibrations and

surveillances appear to be performed at the required frequencies and

~

the procedures seemed adequate to accomplish the requirements of the

TS.

'

No violations or deviations were identified.

E)

Air Cleaning Systems

Records of in place HEPA filter and. iodine adsorber testing were

reviewed and procedures for these were discussed with the licensee

staff.

Records for required surveillances were also examined.

No violations or deviations were identified.

8)

Exit-Interview

t

The inspectors met with the individuals denoted in paragraph 1 at the

'

conclusion of the inspection on November 26 and December 19, 1986.

The

scope and findings of the inspection were summarized. The licensee wa:

informed that no violations or deviations had been identified.

-