IR 05000387/1980011

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-387/80-11 & 50-388/80-07 on 800513-16.No Noncompliance Noted.Major Areas Inspected:Site Activities & Review of NRC Insp Status
ML17138B392
Person / Time
Site: Susquehanna  
Issue date: 06/02/1980
From: Durr J, Mcgaughy R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17138B391 List:
References
50-387-80-11, 50-388-80-07, 50-388-80-7, NUDOCS 8007170257
Download: ML17138B392 (3)


Text

3rddt U.S.

NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION ANO ENFORCEMENT Region I

.50-,387/80-11 II 3 II

. ~gg-388 dtl-bp 50-387 Oocket No.

50-388 CPPR-101 License No.

CPPR-102 Priority 50-387/B'ategory50-388/A Licensee:

Penns lvania Power and Li ht Company 2 North Ninth Street Al 1 entown, Pennsyl vania 18101 Facility Name:

Susquehanna Units 1 and

Inspection at:

Berwick, Pennsylvania Inspection conducted.

May 13-16, 1980 Inspectors:

J.

P. Durr, Reactor Inspector d te signed date signed Approved by: c84 PA R.

W. McGaugh g f, Projects Section, RC8ES Br'h6ch date signed date signed Ins ection Summar

Unit 1 Ins ection on Ma 13-16 '1980 Re ort No. 50-387 80-11 d:

gb I

b d

I

d d

I

,

d inspection of on-going site activities and review of NRC inspection status.

The inspection involved 15 inspector-hours on site by one NRC inspector.

Results:

No items of noncompliance were identified.

Unit 2 Ins ection on Ma 13-16, 1980 Re ort No. 50-388/80-07)

d:.

gd I

b d

p d

d I,

d inspection of on-going site activities and review'f NRC inspection status.

The inspection involved 15 inspector-hours on site by one NRC inspector.

Results:

No items of noncompliance were identified.

Region I Form 12 (Rev. April 77)

800 Viv02&

> <i')"

DETAILS 1.

Persons Contacted Penns lvania Power'and Li ht Com an

  • R. A. Beckley, Resident Nuclear guality Assurance Engineer (Acting)
  • S. L. Denson, Project Construction Manager
  • J.

D.. Murray, Construction Project Engineer

  • M. S. Gorski, Resident Engineer Bechtel Cor oration
  • G. Y. Cranston, Resident Project Engineer
  • M. A. Drucker, Lead guality Assurance Engineer
  • J. E. O'ullivan,, Assistant Project Field Engineer
  • K. G. Stout,: Project Field, guality Control Engineer
  • Denotes those persons. present at the exit interview.

2.

Plant Tour The inspector toured the Units No.

1 and 2 reactor building and control room observing work in-progress.

He examined equipment storage and main-tenance, quality control activities, in-progress nondestructive testing on piping welds, and electrical wiring activities such as wire pulling and-cable termination.

Craftsmen..were.

interviewed concerning the work they were performing.

No items of'noncompliance were identified.

3.

Plant Turnover Activities The construction resident and.'project inspectors jointly reviewed the status of the IE inspection program in preparation for the inspector'urnover.

The review included enforcement history, construction deficiency reports, inspection module status, and unresolved items.

4.

Exit Interview The inspector met with representatives of the licensee (denoted in paragraph 1) at the conclusion of the inspection on May 16, 1980..

He discussed the scope and.findings of the inspection.