IR 05000387/2025001
| ML25121A252 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 05/12/2025 |
| From: | Sarah Elkhiamy Division of Operating Reactors |
| To: | Berryman B Susquehanna |
| References | |
| IR 2025001 | |
| Download: ML25121A252 (1) | |
Text
May 12, 2025
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -
INTEGRATED INSPECTION REPORT 05000387/2025001 AND 05000388/2025001
Dear Brad Berryman:
On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2. On April 3, 2025, the NRC inspectors discussed the results of this inspection with Doug LaMarca, Director - Strategic Planning, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Sarah H. Elkhiamy, Chief Operations Branch Division of Operating Reactor Safety
Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000387 and 05000388
License Numbers:
Report Numbers:
05000387/2025001 and 05000388/2025001
Enterprise Identifier: I-2025-001-0050
Licensee:
Susquehanna Nuclear, LLC
Facility:
Susquehanna Steam Electric Station, Units 1 and 2
Location:
769 Salem Blvd., Berwick, PA
Inspection Dates:
January 1, 2025 to March 31, 2025
Inspectors:
J. England, Senior Resident Inspector
E. Brady, Resident Inspector
S. Haney, Senior Project Engineer
Approved By:
Sarah H. Elkhiamy, Chief
Operations Branch
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Susquehanna Steam Electric Station,
Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at rated thermal power. On March 6, 2025, the unit down powered to 85 percent for scram time testing. On March 7, 2025, the unit down powered to 60 percent for a rod sequence exchange and returned to rated thermal power on March 9, 2025.
The unit remained at or near rated thermal power for the remainder of the inspection period.
Unit 2 began the inspection period at rated thermal power. On January 9, 2025, the unit was down powered to 78 percent for a rod pattern adjustment and returned to rated thermal power on January 10, 2025. On January 16, 2025, the unit was down powered to 77 percent for a rod pattern adjustment and returned to rated thermal power on January 17, 2025. On February 7, 2025, the unit was down powered to 74 percent for a rod pattern adjustment and returned to rated thermal power on February 9, 2025. On February 14, 2025, the unit commenced coast down and shut down for a refueling outage on March 23, 2025, and remained shut down for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of hot weather for offsite power on March 11, 2025.
Impending Severe Weather (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather on January 16 and 17, 2025.
71111.04 - Equipment Alignment
Partial Walkdown (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 core spray division 1 on January 21, 2025
- (2) Unit Common standby gas treatment during the week of February 10, 2025
- (3) Unit Common emergency service water during the week of March 3, 2025
71111.05 - Fire Protection
Fire Area Walkdown and Inspection (IP Section 03.01) (4 Samples; 1 Partial)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit 1 reactor building, 645-foot elevation, fire areas 1-1A, 1-1B, 1-1C, 1-1D, 1-1E, 1-1F, and 1-1G, on January 7, 2025 (2)
(Partial)
Unit Common control structure, 698-foot elevation, fire areas 0-24A, 0-24B, 0-24C, 0-24D, 0-24E, and 0-24G, on January 15, 2025
- (3) Unit Common FLEX equipment building, emergency service water building, and residual heat removal service water building, 685-foot and 721-foot elevations, fire areas 0-51, 0-52, and 0-FS, on February 11, 2025
- (4) Unit 2 reactor building, 779-foot elevation, fire areas 2-6A, 2-6B, 2-6C, and 2-6D, on February 12, 2025
- (5) Unit 2 turbine building, 676-foot and 699-foot elevations, fire areas 2-32B, 2-32C, 2-32D, 2-32E, 2-32F, 2-32I, 2-33B, 2-33C, 2-33D, 2-33E, 2-33F, and 2-33G, on March 27, 2025
Fire Brigade Drill Performance (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the on-site fire brigade training and performance during an unannounced fire drill on January 17, 2025.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Unit 2 control room during reactor shutdown on March 23 and 24, 2025.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator requalification training in the simulator on January 27, 2025.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Unit Common 'B' emergency diesel generator (EDG) mid-cycle outage starting February 3, 2025
Quality Control (IP Section 03.02) (1 Sample)
The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Unit Common 'C' EDG synchronous selector switch on March 10, 2025
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management (IP Section 03.01) (5 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit 2 elevated risk during planned maintenance on division 2 core spray during the week of January 13, 2025
- (2) Units 1 and 2 elevated risk due to planned maintenance of the 'A' EDG resulting in the 125-volt direct current battery chargers supplied by an alternate source during the week of February 24, 2025
- (3) Unit 2 elevated risk during planned maintenance on reactor core isolation cooling during the week of March 10, 2025
- (4) Unit 2 elevated risk during planned maintenance on the high-pressure coolant injection system during the week of March 17, 2025
- (5) Unit 2 elevated risk during the refueling outage during the week of March 24, 2025
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Unit 1 start up from cycle 24 maintenance outage was not in compliance with EC-FUEL-1973 on January 15, 2025 (CR-2024-13422)
- (2) Unit 2 foreign material in breaker cubicle on January 16, 2025
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage (IP Section 03.01) (1 Partial)
(1)
(Partial)
The inspectors evaluated Unit 2 refueling outage 22 activities from March 4 to March 31, 2025. The inspectors completed sections a., b.1, b.2, c.3, c.4, c.6, c.7, c.9, and c.10.
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (IP Section 03.01) (5 Samples)
- (1) Unit 2 reactor water cleanup steam isolation following temperature switch replacement on January 23, 2025
- (2) Unit Common 'C' EDG following synchroscope replacement on January 29, 2025
- (3) Unit Common 'B' EDG post-maintenance test following mid-cycle overhaul on February 11, 2025
- (4) Unit Common 125-volt direct current station batteries monthly and quarterly electrical parameter checks for Unit 2 following planned maintenance during the week of February 24, 2025
- (5) Unit Common measure currents and perform voltage regulator checks after 'A' EDG linear reactor replacement on February 27, 2025
Surveillance Testing (IP Section 03.01) (4 Samples)
- (1) Unit 2 SO-249-007, Residual Heat Removal Logic System Functional Test (Div I),on February 3, 2025
- (2) Unit 1 SO-193-001, Turbine Valve Cycling, on March 11, 2025
- (3) Unit 2 SO-225-101, Long-Term Nitrogen Supply System Functional Test (A Header), on March 18, 2025
- (4) Unit 2 SO-224-117, Division I Diesel Generator Loss of Coolant Accident Loss of Offsite Power Test (Infrequently Performed Test or Evolution), on March 27, 2025
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
- (1) Unit 2 SE-259-150, Hydraulic Leak Test of Control Rod Drive Seismic Island Check, on March 31,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours (IP Section 02.01)===
- (1) Unit 1 January 1, 2024 through December 31, 2024
- (2) Unit 2 January 1, 2024 through December 31, 2024
IE03: Unplanned Power Changes per 7000 Critical Hours (IP Section 02.02) (2 Samples)
- (1) Unit 1 January 1, 2024 through December 31, 2024
- (2) Unit 2 January 1, 2024 through December 31, 2024
IE04: Unplanned Scrams with Complications (USwC) (IP Section 02.03) (2 Samples)
- (1) Unit 1 January 1, 2024 through December 31, 2024
- (2) Unit 2 January 1, 2024 through December 31, 2024
BI01: Reactor Coolant System Specific Activity (IP Section 02.10) (2 Samples)
- (1) Unit 1 January 1, 2024 through December 31, 2024
- (2) Unit 2 January 1, 2024 through December 31, 2024
BI02: Reactor Coolant System Leak Rate (IP Section 02.11) (2 Samples)
- (1) Unit 1 January 1, 2024 through December 31, 2024
- (2) Unit 2 January 1, 2024 through December 31, 2024
71152A - Annual Follow-up of Problem Identification and Resolution
Annual Follow-up of Selected Issues (Section 03.03) (1 Partial)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
(1)
(Partial)
The inspectors reviewed the completed corrective actions for CR-2024-13422, Startup from Unit 1 Cycle 24 Maintenance Outage Not in Compliance with Control Rod Drop
Analysis.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 3, 2025, the inspectors presented the integrated inspection results to Doug LaMarca, Director - Strategic Planning, and other members of the licensee staff.
THIRD PARTY REVIEWS
The inspectors reviewed Institute of Nuclear Power Operations Continuum Site Visit Report dated June 2024 on January 22, 2025.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
OI-AD-029
Emergency Load Control
Revision 19
Corrective Action
Documents
Resulting from
Inspection
CR-2024-01145
CR-2025-01142
CR-2025-01143
CR-2025-01144
CR-2025-01146
CR-2025-02352
Drawings
E106216 Sheet 1
Susquehanna S.E.S. Common PI&D Emergency Service
Water System
Revision 52
E106680 Sheet 3
Susquehanna S.E.S. Common P&ID HVAC Control Diagram
Reactor Building Standby Gas Treatment System
Revision 35
E162640 Sheet 1
Susquehanna S.E.S. Unit 2 P&ID Emergency Service Water
System A Loop
Revision 51
Miscellaneous
CL-054-0012
Common ESW System
Revision 47
CL-054-0016
Unit 2 Emergency Service Water System
Revision 39
CL-070-0011
Common Standby Gas Treatment System
Revision 8
CL-070-0012
Standby Gas Treatment
Revision 11
CL-151-0012
Instruments
Unit 1 Core Spray System Div 1
Revision 16
CL-151-0012
Valves
Unit 1 Core Spray System Div 1
Revision 16
Calculations
EC-013-1913
PGCC Halon Systems for the Units 1 & 2 Upper & Lower
Relay Rooms
Revision 0
Licensing Topical Report Power Generation Control
Complex Design Criteria and Safety Evaluation
February
1979
SSES-FPRR
Susquehanna Steam Electric Station - Fire Protection
Review Report Section 6.2
Revision 28
Corrective Action
Documents
Resulting from
Inspection
AR-2025-02597
AR-2025-04821
CR-2025-02177
CR-2025-02262
CR-2025-03212
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CR-2025-04702
CR-2025-04829
Fire Plans
Flex Storage Building Fire Zone 0-FS, Elevation 721
Revision 0
Susquehanna S.E.S. Prefire Plan Unit 1 Control Structure
Revision 0
FP-1-ESSW-685
Susquehanna S.E.S. Prefire Plan Unit 1 Pump House -
Revision 0
FP-1-RB-645
Susquehanna S.E.S. Prefire Plan Unit 1 645
Revision 0
FP-2-RB-779
Susquehanna S.E.S. Prefire Plan Unit 2 779
Revision 0
FP-2-TB-676
Susquehanna S.E.S. Prefire Plan Unit 2 676
Revision 0
FP-2-TB-699
Susquehanna S.E.S. Prefire Plan Unit 2 699
Revision 0
Miscellaneous
Scenario U1LCR
Fire Unit #1 Lower Cable Spreading Room, Elevation 714'
Revision 2
71111.11Q Procedures
GO-200-004
Plant Shutdown to Minimum Power
Revision 88
GO-200-005
Plant Shutdown to Hot/Cold Shutdown
Revision 73
OP-293-002
Main Turbine Testing
Revision 56
Miscellaneous
285262
Receipt Inspection Report
10/13/2021
675791
Purchase Order
Revision 001
EDU-SWH-0023
Dedication Document
Revision 3
Procedures
NOSP-QA-303
Receipt Inspection
Revision 10
Work Orders
RTSV 2780208
Corrective Action
Documents
Resulting from
Inspection
CR-2025-00954
CR-2025-02731
CR-2025-04075
CR-2025-04392
Miscellaneous03-001 Outage
Offsite Power-
U222RIO
Offsite Power Feeds Protected During U222RIO
Revision 0
16-001 RHRSW
2A Pump-
U222RIO
Protected While 1A RHRSW Pump OOS
Revision 0
49-001-U1 RHR
FPC Assist-
U222RIO
Unit 1 DIV 1 FPC Assist
Revision 0
2-001-U2 HPCI
SOW Week of
3/17/25
Revision 0
2-001-U2 HPCI-
WK OF 3/10/25
Unit 2 HPCI Protected
Revision 0
M-2155
Susquehanna S.E.S. Unit 2 High-Pressure Coolant Injection
Revision 46
Procedures
NDAP-QA-0340
Protected Equipment Program
Revision 46
Corrective Action
Documents
CR-2024-13422
CR-2024-16975
Drawings
D107252 Sheet 21
Unit 2 Schematic Diagram 4.16KV Bus 2C Incoming Feeder
Breaker from Engineered Safeguard System ESS
Transformer 211
Revision 28
FF103090 Sheet
1958
Unit 2 Medium Voltage Switchgear Safeguard Connection
Diagram Unit 8 Bus 2C 2A20308
Revision 18
Engineering
Changes
EC-FUEL-1973
Unit 1 Cycle 24 RWM Sequence Configuration Changes
Revision 0
Procedures
RE-0TP-101
Control Rod Sequence Development and Controls
Revision 14
Corrective Action
Documents
Resulting from
Inspection
CR-2025-04356
CR-2025-04359
CR-2025-04362
CR-2025-04363
CR-2025-04366
CR-2025-04375
CR-2025-04376
CR-2024-04817
Procedures
IC-280-005
Installation and Removal of Temporary Unit 2 RPV
Shutdown Level Transmitter
Revision 7
NDAP-QA-0505
Crane, Hoist, and Rigging Process
Revision 48
Corrective Action
Documents
CR-2025-01225
CR-2025-01812
Corrective Action
Documents
Resulting from
Inspection
CR-2025-03974
CR-2025-04533
Drawings
FF110683 Sheet
2302
Schematic Wiring Diagram Valve Test Logic TB (EHC)
Revision 0
Procedures
SI-261-309
Quarterly Calibration of Reactor Water Clean-Up (RWCU)
Steam Leak Detection Logic B (Div. 2) Temperature
Channels
Revision 11
SM-202-001
25 Volt DC Station Batteries Monthly and Quarterly
Electrical Parameter Checks - Unit 2
Revision 24
SO-024-001B
Monthly Diesel Generator 'B' Operability Test
Revision 30
SO-193-001
Turbine Valve Cycling
Revision 59
SO-224-117
Unit 2 Division I Diesel Generator LOCA LOOP (Infrequently
Performed Test or Evolution)
Revision 9
SO-225-101
Long-Term Nitrogen Supply System Functional Test (A
Revision 4
SO-249-007
RHR Logic System Functional Test (Div 1) - Online (Partial)
Revision 7
Work Orders
PCWO 2345661-0
PCWO 2363336-4
PCWO 2771647-1
PCWO 2783650-0
RACT 2655198
RLWO 2784525
RLWO 2784526
RTSV 2627008
RTSV 2637300
RTSV 2767574
RTSV 2771607
RTSV 2771647-1
RTSV 2779484
71151
Corrective Action
Documents
DI-2024-00641
DI-2024-02046
DI-2024-03475
DI-2024-05806
DI-2024-05806
DI-2024-07751
DI-2024-09002
DI-2024-10154
DI-2024-11919
DI-2024-13029
DI-2024-14244
DI-2024-15840
DI-2025-00509
DPA-01-DI-2024-
00374
DPA-02-DI-2024-
00374
DPA-03-DI-2024-
00374
DPA-04-DI-2024-
00374
DPA-05-DI-2024-
00374
DPA-06-DI-2024-
00374
DPA-07-DI-2024-
00374
DPA-08-DI-2024-
00374
DPA-09-DI-2024-
00374
DPA-10-DI-2024-
00374
DPA-11-DI-2024-
00374
DPA-12-DI-2024-
00374
Miscellaneous
Regulatory Assessment Performance Indicator Guideline
Revision 8
Procedures
NDAP-QA-0737
Reactor Oversight Process (ROP) Performance Indicators
Revision 22
OI-AD-094
NRC Performance Indicator Monthly Update Reactor System
Total Leakage (RCSL)
Revision 10
Engineering
Changes
EC-FUEL-1971
Unit 1 Cycle Step Out
Revision 0
EC-FUEL-1973
Unit 1 Cycle 24 RWM Sequence Configuration Changes
Revisions 0,
1, and 2
Miscellaneous
NF-220
Technical Instructions - RWM Startup Sequence
Development
Revision 5
Procedures
GO-100-002
Plant Startup, Heatup, and Power Operation
Revision 128
RE-0TP-101
Control Rod Sequence Development and Controls
Revisions 14
and 15
SR-131-001
Validating Rod Worth Minimizer Sequences
Revision 10