IR 05000387/2025001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000387/2025001 and 05000388/2025001
ML25121A252
Person / Time
Site: Susquehanna  
Issue date: 05/12/2025
From: Sarah Elkhiamy
Division of Operating Reactors
To: Berryman B
Susquehanna
References
IR 2025001
Download: ML25121A252 (1)


Text

May 12, 2025

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -

INTEGRATED INSPECTION REPORT 05000387/2025001 AND 05000388/2025001

Dear Brad Berryman:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2. On April 3, 2025, the NRC inspectors discussed the results of this inspection with Doug LaMarca, Director - Strategic Planning, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Sarah H. Elkhiamy, Chief Operations Branch Division of Operating Reactor Safety

Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000387 and 05000388

License Numbers:

NPF-14 and NPF-22

Report Numbers:

05000387/2025001 and 05000388/2025001

Enterprise Identifier: I-2025-001-0050

Licensee:

Susquehanna Nuclear, LLC

Facility:

Susquehanna Steam Electric Station, Units 1 and 2

Location:

769 Salem Blvd., Berwick, PA

Inspection Dates:

January 1, 2025 to March 31, 2025

Inspectors:

J. England, Senior Resident Inspector

E. Brady, Resident Inspector

S. Haney, Senior Project Engineer

Approved By:

Sarah H. Elkhiamy, Chief

Operations Branch

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Susquehanna Steam Electric Station,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On March 6, 2025, the unit down powered to 85 percent for scram time testing. On March 7, 2025, the unit down powered to 60 percent for a rod sequence exchange and returned to rated thermal power on March 9, 2025.

The unit remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power. On January 9, 2025, the unit was down powered to 78 percent for a rod pattern adjustment and returned to rated thermal power on January 10, 2025. On January 16, 2025, the unit was down powered to 77 percent for a rod pattern adjustment and returned to rated thermal power on January 17, 2025. On February 7, 2025, the unit was down powered to 74 percent for a rod pattern adjustment and returned to rated thermal power on February 9, 2025. On February 14, 2025, the unit commenced coast down and shut down for a refueling outage on March 23, 2025, and remained shut down for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of hot weather for offsite power on March 11, 2025.

Impending Severe Weather (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather on January 16 and 17, 2025.

71111.04 - Equipment Alignment

Partial Walkdown (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 core spray division 1 on January 21, 2025
(2) Unit Common standby gas treatment during the week of February 10, 2025
(3) Unit Common emergency service water during the week of March 3, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection (IP Section 03.01) (4 Samples; 1 Partial)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 reactor building, 645-foot elevation, fire areas 1-1A, 1-1B, 1-1C, 1-1D, 1-1E, 1-1F, and 1-1G, on January 7, 2025 (2)

(Partial)

Unit Common control structure, 698-foot elevation, fire areas 0-24A, 0-24B, 0-24C, 0-24D, 0-24E, and 0-24G, on January 15, 2025

(3) Unit Common FLEX equipment building, emergency service water building, and residual heat removal service water building, 685-foot and 721-foot elevations, fire areas 0-51, 0-52, and 0-FS, on February 11, 2025
(4) Unit 2 reactor building, 779-foot elevation, fire areas 2-6A, 2-6B, 2-6C, and 2-6D, on February 12, 2025
(5) Unit 2 turbine building, 676-foot and 699-foot elevations, fire areas 2-32B, 2-32C, 2-32D, 2-32E, 2-32F, 2-32I, 2-33B, 2-33C, 2-33D, 2-33E, 2-33F, and 2-33G, on March 27, 2025

Fire Brigade Drill Performance (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the on-site fire brigade training and performance during an unannounced fire drill on January 17, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Unit 2 control room during reactor shutdown on March 23 and 24, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training in the simulator on January 27, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Unit Common 'B' emergency diesel generator (EDG) mid-cycle outage starting February 3, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Unit Common 'C' EDG synchronous selector switch on March 10, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2 elevated risk during planned maintenance on division 2 core spray during the week of January 13, 2025
(2) Units 1 and 2 elevated risk due to planned maintenance of the 'A' EDG resulting in the 125-volt direct current battery chargers supplied by an alternate source during the week of February 24, 2025
(3) Unit 2 elevated risk during planned maintenance on reactor core isolation cooling during the week of March 10, 2025
(4) Unit 2 elevated risk during planned maintenance on the high-pressure coolant injection system during the week of March 17, 2025
(5) Unit 2 elevated risk during the refueling outage during the week of March 24, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1 start up from cycle 24 maintenance outage was not in compliance with EC-FUEL-1973 on January 15, 2025 (CR-2024-13422)
(2) Unit 2 foreign material in breaker cubicle on January 16, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated Unit 2 refueling outage 22 activities from March 4 to March 31, 2025. The inspectors completed sections a., b.1, b.2, c.3, c.4, c.6, c.7, c.9, and c.10.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (IP Section 03.01) (5 Samples)

(1) Unit 2 reactor water cleanup steam isolation following temperature switch replacement on January 23, 2025
(2) Unit Common 'C' EDG following synchroscope replacement on January 29, 2025
(3) Unit Common 'B' EDG post-maintenance test following mid-cycle overhaul on February 11, 2025
(4) Unit Common 125-volt direct current station batteries monthly and quarterly electrical parameter checks for Unit 2 following planned maintenance during the week of February 24, 2025
(5) Unit Common measure currents and perform voltage regulator checks after 'A' EDG linear reactor replacement on February 27, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) Unit 2 SO-249-007, Residual Heat Removal Logic System Functional Test (Div I),on February 3, 2025
(2) Unit 1 SO-193-001, Turbine Valve Cycling, on March 11, 2025
(3) Unit 2 SO-225-101, Long-Term Nitrogen Supply System Functional Test (A Header), on March 18, 2025
(4) Unit 2 SO-224-117, Division I Diesel Generator Loss of Coolant Accident Loss of Offsite Power Test (Infrequently Performed Test or Evolution), on March 27, 2025

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Unit 2 SE-259-150, Hydraulic Leak Test of Control Rod Drive Seismic Island Check, on March 31,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours (IP Section 02.01)===

(1) Unit 1 January 1, 2024 through December 31, 2024
(2) Unit 2 January 1, 2024 through December 31, 2024

IE03: Unplanned Power Changes per 7000 Critical Hours (IP Section 02.02) (2 Samples)

(1) Unit 1 January 1, 2024 through December 31, 2024
(2) Unit 2 January 1, 2024 through December 31, 2024

IE04: Unplanned Scrams with Complications (USwC) (IP Section 02.03) (2 Samples)

(1) Unit 1 January 1, 2024 through December 31, 2024
(2) Unit 2 January 1, 2024 through December 31, 2024

BI01: Reactor Coolant System Specific Activity (IP Section 02.10) (2 Samples)

(1) Unit 1 January 1, 2024 through December 31, 2024
(2) Unit 2 January 1, 2024 through December 31, 2024

BI02: Reactor Coolant System Leak Rate (IP Section 02.11) (2 Samples)

(1) Unit 1 January 1, 2024 through December 31, 2024
(2) Unit 2 January 1, 2024 through December 31, 2024

71152A - Annual Follow-up of Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (1 Partial)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)

(Partial)

The inspectors reviewed the completed corrective actions for CR-2024-13422, Startup from Unit 1 Cycle 24 Maintenance Outage Not in Compliance with Control Rod Drop

Analysis.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 3, 2025, the inspectors presented the integrated inspection results to Doug LaMarca, Director - Strategic Planning, and other members of the licensee staff.

THIRD PARTY REVIEWS

The inspectors reviewed Institute of Nuclear Power Operations Continuum Site Visit Report dated June 2024 on January 22, 2025.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

OI-AD-029

Emergency Load Control

Revision 19

71111.04

Corrective Action

Documents

Resulting from

Inspection

CR-2024-01145

CR-2025-01142

CR-2025-01143

CR-2025-01144

CR-2025-01146

CR-2025-02352

Drawings

E106216 Sheet 1

Susquehanna S.E.S. Common PI&D Emergency Service

Water System

Revision 52

E106680 Sheet 3

Susquehanna S.E.S. Common P&ID HVAC Control Diagram

Reactor Building Standby Gas Treatment System

Revision 35

E162640 Sheet 1

Susquehanna S.E.S. Unit 2 P&ID Emergency Service Water

System A Loop

Revision 51

Miscellaneous

CL-054-0012

Common ESW System

Revision 47

CL-054-0016

Unit 2 Emergency Service Water System

Revision 39

CL-070-0011

Common Standby Gas Treatment System

Revision 8

CL-070-0012

Standby Gas Treatment

Revision 11

CL-151-0012

Instruments

Unit 1 Core Spray System Div 1

Revision 16

CL-151-0012

Valves

Unit 1 Core Spray System Div 1

Revision 16

71111.05

Calculations

EC-013-1913

PGCC Halon Systems for the Units 1 & 2 Upper & Lower

Relay Rooms

Revision 0

NEDO-10466-A

Licensing Topical Report Power Generation Control

Complex Design Criteria and Safety Evaluation

February

1979

SSES-FPRR

Susquehanna Steam Electric Station - Fire Protection

Review Report Section 6.2

Revision 28

Corrective Action

Documents

Resulting from

Inspection

AR-2025-02597

AR-2025-04821

CR-2025-02177

CR-2025-02262

CR-2025-03212

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2025-04702

CR-2025-04829

Fire Plans

FP-013-382

Flex Storage Building Fire Zone 0-FS, Elevation 721

Revision 0

FP-013-CS

Susquehanna S.E.S. Prefire Plan Unit 1 Control Structure

Revision 0

FP-1-ESSW-685

Susquehanna S.E.S. Prefire Plan Unit 1 Pump House -

ESSW

Revision 0

FP-1-RB-645

Susquehanna S.E.S. Prefire Plan Unit 1 645

Revision 0

FP-2-RB-779

Susquehanna S.E.S. Prefire Plan Unit 2 779

Revision 0

FP-2-TB-676

Susquehanna S.E.S. Prefire Plan Unit 2 676

Revision 0

FP-2-TB-699

Susquehanna S.E.S. Prefire Plan Unit 2 699

Revision 0

Miscellaneous

Scenario U1LCR

Fire Unit #1 Lower Cable Spreading Room, Elevation 714'

Revision 2

71111.11Q Procedures

GO-200-004

Plant Shutdown to Minimum Power

Revision 88

GO-200-005

Plant Shutdown to Hot/Cold Shutdown

Revision 73

OP-293-002

Main Turbine Testing

Revision 56

71111.12

Miscellaneous

285262

Receipt Inspection Report

10/13/2021

675791

Purchase Order

Revision 001

EDU-SWH-0023

Dedication Document

Revision 3

Procedures

NOSP-QA-303

Receipt Inspection

Revision 10

Work Orders

RTSV 2780208

71111.13

Corrective Action

Documents

Resulting from

Inspection

CR-2025-00954

CR-2025-02731

CR-2025-04075

CR-2025-04392

Miscellaneous03-001 Outage

Offsite Power-

U222RIO

Offsite Power Feeds Protected During U222RIO

Revision 0

16-001 RHRSW

2A Pump-

U222RIO

Protected While 1A RHRSW Pump OOS

Revision 0

49-001-U1 RHR

FPC Assist-

U222RIO

Unit 1 DIV 1 FPC Assist

Revision 0

2-001-U2 HPCI

SOW Week of

3/17/25

Protected for Unit 2 HPCI SOW

Revision 0

2-001-U2 HPCI-

WK OF 3/10/25

Unit 2 HPCI Protected

Revision 0

M-2155

Susquehanna S.E.S. Unit 2 High-Pressure Coolant Injection

Revision 46

Procedures

NDAP-QA-0340

Protected Equipment Program

Revision 46

71111.15

Corrective Action

Documents

CR-2024-13422

CR-2024-16975

Drawings

D107252 Sheet 21

Unit 2 Schematic Diagram 4.16KV Bus 2C Incoming Feeder

Breaker from Engineered Safeguard System ESS

Transformer 211

Revision 28

FF103090 Sheet

1958

Unit 2 Medium Voltage Switchgear Safeguard Connection

Diagram Unit 8 Bus 2C 2A20308

Revision 18

Engineering

Changes

EC-FUEL-1973

Unit 1 Cycle 24 RWM Sequence Configuration Changes

Revision 0

Procedures

RE-0TP-101

Control Rod Sequence Development and Controls

Revision 14

71111.20

Corrective Action

Documents

Resulting from

Inspection

CR-2025-04356

CR-2025-04359

CR-2025-04362

CR-2025-04363

CR-2025-04366

CR-2025-04375

CR-2025-04376

CR-2024-04817

Procedures

IC-280-005

Installation and Removal of Temporary Unit 2 RPV

Shutdown Level Transmitter

Revision 7

NDAP-QA-0505

Crane, Hoist, and Rigging Process

Revision 48

71111.24

Corrective Action

Documents

CR-2025-01225

CR-2025-01812

Corrective Action

Documents

Resulting from

Inspection

CR-2025-03974

CR-2025-04533

Drawings

FF110683 Sheet

2302

Schematic Wiring Diagram Valve Test Logic TB (EHC)

Revision 0

Procedures

SI-261-309

Quarterly Calibration of Reactor Water Clean-Up (RWCU)

Steam Leak Detection Logic B (Div. 2) Temperature

Channels

Revision 11

SM-202-001

25 Volt DC Station Batteries Monthly and Quarterly

Electrical Parameter Checks - Unit 2

Revision 24

SO-024-001B

Monthly Diesel Generator 'B' Operability Test

Revision 30

SO-193-001

Turbine Valve Cycling

Revision 59

SO-224-117

Unit 2 Division I Diesel Generator LOCA LOOP (Infrequently

Performed Test or Evolution)

Revision 9

SO-225-101

Long-Term Nitrogen Supply System Functional Test (A

Header)

Revision 4

SO-249-007

RHR Logic System Functional Test (Div 1) - Online (Partial)

Revision 7

Work Orders

PCWO 2345661-0

PCWO 2363336-4

PCWO 2771647-1

PCWO 2783650-0

RACT 2655198

RLWO 2784525

RLWO 2784526

RTSV 2627008

RTSV 2637300

RTSV 2767574

RTSV 2771607

RTSV 2771647-1

RTSV 2779484

71151

Corrective Action

Documents

DI-2024-00641

DI-2024-02046

DI-2024-03475

DI-2024-05806

DI-2024-05806

DI-2024-07751

DI-2024-09002

DI-2024-10154

DI-2024-11919

DI-2024-13029

DI-2024-14244

DI-2024-15840

DI-2025-00509

DPA-01-DI-2024-

00374

DPA-02-DI-2024-

00374

DPA-03-DI-2024-

00374

DPA-04-DI-2024-

00374

DPA-05-DI-2024-

00374

DPA-06-DI-2024-

00374

DPA-07-DI-2024-

00374

DPA-08-DI-2024-

00374

DPA-09-DI-2024-

00374

DPA-10-DI-2024-

00374

DPA-11-DI-2024-

00374

DPA-12-DI-2024-

00374

Miscellaneous

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

Revision 8

Procedures

NDAP-QA-0737

Reactor Oversight Process (ROP) Performance Indicators

Revision 22

OI-AD-094

NRC Performance Indicator Monthly Update Reactor System

Total Leakage (RCSL)

Revision 10

71152A

Engineering

Changes

EC-FUEL-1971

Unit 1 Cycle Step Out

Revision 0

EC-FUEL-1973

Unit 1 Cycle 24 RWM Sequence Configuration Changes

Revisions 0,

1, and 2

Miscellaneous

NF-220

Technical Instructions - RWM Startup Sequence

Development

Revision 5

Procedures

GO-100-002

Plant Startup, Heatup, and Power Operation

Revision 128

RE-0TP-101

Control Rod Sequence Development and Controls

Revisions 14

and 15

SR-131-001

Validating Rod Worth Minimizer Sequences

Revision 10