IE Insp Rept 50-387/79-23 on 790620-22,0702-03,05-06 & 09.No Noncompliance Noted.Major Areas Inspected:Electrical Equipment Cable Installation & QA
ML17138A857
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 08/22/1979
From: Ebneter S, Finkel A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17138A856 List:
References
50-387-79-23, NUDOCS 7910160364
Download: ML17138A857 (4)


Text

U.S.

NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I Report No. 50-387/79-23 Docket No. 50-387 License No.

CPPR-101 Priority:

Category:

A Licensee:

Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsyl vania 18101 Facility'Name:

Susquehanna Steam Electric Station, Unit

Inspection at:

Berwick, Pennsylvania Inspection conducted:

June 20-22; July 2-3 and 5-6; Inspectors:

A. E. Finke Reactor Inspector Approved by:

+r~i %%4'

er, e

, Engsneersng Suppo

,

ection No. 2, RC&ES Branch Ins ection Summar

and July 9, 1979 ig" P-).>- p date signe r

Ins ection on June 20-22 Jul 2-3 and 5-6 and Jul 9,

1979 Re ort No. 50-387 79-23.

~AI:

R i, di p ti hy gi

d inspector

. to followup on outstanding items in the areas of electrical equipment, cable installation, and quality assurance.

'The inspection involved 33 inspector hours onsite by one regional based inspector.

Results:

Of the three areas inspected no items of noncompliance were identifie DETAILS 1..

Persons Contacted Penns lvania Power and Li ht Com an

"J. Green, Resident Nuclear QA Engineer

  • M. Gorski, Resident Engineer
  • R. Petrokonis, Construction Engineer R. Prego, Electrical Project QA Engineer Bechtel Cor oration M. Donat, Lead Electrical Field Project QC Engineer
  • H. Lilligh, Quality Assurance
  • W Movrer, Construction Supervisor
  • K. Stout, Quality Control J. O'ullivan, Assistant Project Field Engineer
  • Denotes those persons attending the exit interview.

2.

Licensee Action on Previous Ins ection Findin s (Closed)

Unresolved Item (387/79-14-05)

Deficiency Report Log Item 0092, cable installation in embedded raceways.

The licensee issued a stop work order on cable pulling until the requirements of their June 22, 1979 letter were complied with.

The inspector verified that the Prerequisite requirements of the June 22, 1979 letter were complied with by Bechtel.

(Closed) Infraction (387/79-11-01)

Failure to properly brush aluminum conductors immediately prior to installing crimp connectors.

The inspector verified, in discussions with the electrical craft termination 'personnel, that they have been re-instructed on the site requirements for electrical termination and read a

memo No.

187 on terminations dated April 24, 1979.

The inspector witnessed the installation of power terminations and verified that the electrical craft did follow the field instructions for making. termination.

Cable Instal 1 ation The inspector examined the cable. installation of conduit CIK033.

This was the fitst authori'zed cable pull in conduit since the stop work order was issued by the licensee.

Two additional cables were to be pulled into the conduit, but they were not able to be pulled through.

All cables were removed from the conduit in order to re-align the cable input and at that time a 12 conductor No.

AWG Cable No.

CKQG0304R was identified as being damaged.

The cable was put on NCR and a review of the problem is being performed by the licensee.

This matter is considered to be unresolved and will be examined during a subsequent inspection (387/79-23-01).

4.

Electric Motors and Valve 0 erations 5.

The inspector witnessed the installation of the RHR motors and four safety related electric valve operators.

The inspector reviewed'he applicable work procedures and inspection pro-cedures in the following area for the. above components:

Receipt, storage, handling, placing and installation of components and inplace inspection procedures.

The inspector verified that the requirements of the applicable specifications, quality control inspection reports (gCIR s)

and field,instructions were complied with.

No items of noncompliance were identified.

ualit Control Bechtel's quality control inspector verified that the cables being pulled into conduits were in accordance with the require-ments of procedure E-49 entitled "Conduit and Cable Tray Notes and Details".

The installation of cables were inspected in accordance with the requi'rements of guality Control Instructions (OCI) E-1.0, E-l.l and E-2.0 entitled "Installation/Inspection of Class lE Raceway".

The inspector witnessed the. cable pull.,in conduit ClK033 and verified that the electrical-crafts were following the latest instructions. and that the.guality Control.Inspector was per-forming the in process inspection as required by the above gCI' No,items of noncompliance were identified except as stated in Paragraph 3 of this report.

6.

Unresolved Items Unresolved items are matters about which more information is required in order to ascertain whether they are acceptable items, items. of noncompliance, or deviations.

Unresolved ttems disclosed during this inspection are discussed in Paragraph 3.

7.

Exit Interview The inspector.

met with licensee representatives (denoted in Paragraph 1} at the conclusion of the inspection on July 9, 1979.

The inspector summarized the purpose and scope of the findings.

The licensee acknowledged the inspector s findings.